Bonn Operating Company v. Devon Energy Production Co.
Filing
Bonn Operating Company v. Devon Energy Production Co.
Doc. 0
Case: 09-11040
Document: 00511189903
Page: 1
Date Filed: 07/30/2010
IN THE UNITED STATES COURT OF APPEALS United States Court of Appeals FOR THE FIFTH CIRCUIT Fifth Circuit FILED
July 30, 2010 N o . 09-11040 Lyle W. Cayce Clerk
B O N N OPERATING COMPANY P la in t iff- Appellant v. D E V O N ENERGY PRODUCTION COMPANY, L.P. D e fe n d a n t -Appellee
A p p e a l from the United States District Court for the Northern District of Texas
B e fo r e HIGGINBOTHAM, DAVIS and BENAVIDES, Circuit Judges. W . EUGENE DAVIS, Circuit Judge: B o n n Operating Company ("Bonn") appeals the district court's grant of s u m m a r y judgment in favor of Devon Operating Company ("Devon") on issues a r is in g out of the joint operating agreement governing their relationship. The p la in language of the agreement and the undisputed facts do not support Bonn's c h a lle n g e s to that judgment. Accordingly, we affirm. I. B o n n Operating Company ("Bonn") and Devon Energy Production C o m p a n y ("Devon") are co-working interest owners in oil and gas leases in W y o m in g . Under a Form 610 Model Form Operating Agreement-1956 executed
Dockets.Justia.com
Case: 09-11040
Document: 00511189903
Page: 2
Date Filed: 07/30/2010
No. 09-11040 b y the parties' predecessors-in-interest ("JOA"), Devon is the operator of the le a s e s and Bonn is a non-operating working interest owner. Under the terms of the operating agreement, if a party desires to drill a w e ll it "may give the other party written notice of the proposed operation" with s p e c ifie d information. Upon receipt of notice, the other parties to the JOA have 3 0 days to elect whether they will participate in the operation. Declining to p a r tic ip a t e or failing to make an election causes a party to be a non-consenting p a r ty . Consenting parties bear the cost and risk of drilling. Non-consenting p a r tie s avoid those risks, but are subject to a penalty. Under the penalty p r o v is io n , consenting parties are entitled to the non-consenting party's share of a n y production from the well until their proceeds equal the cost of 100% of the n o n -c o n s e n t in g party's share of certain costs (such as the cost to operate the w e ll) and 300% of other costs (such as the cost to drill and complete the well b e fo r e it becomes operational and producing). Although the JOA provision regarding operations is written in terms of s e n d in g notice of proposed operations, Devon sent Bonn notice by letter dated F e b r u a r y 12, 2003, that the Marquis Federal 15W-12 well had been drilled and c o m p le t e d . Bonn was aware that the completion was successful, but elected not t o participate by notifying Devon in writing on the ballot that it "elect[ed] to go n o n -c o n s e n t on this well." The cost of the well was $135,139.38, of which Bonn's s h a r e was 50% or $67,569.69. The non-consent penalty charged to Bonn was $ 1 0 5 ,4 9 1 .3 3 . Bonn filed suit against Devon in October 2006 alleging breach of contract a n d contending that Devon improperly charged it with non-consent penalties r e la t e d to the Marquis Federal well. Bonn also contends that Devon failed to t im e ly ballot Bonn regarding the Marquis Federal 15W-12 well and that Devon fa ile d to pay interest on sums due to it pursuant to a Wyoming statute.
2
Case: 09-11040
Document: 00511189903
Page: 3
Date Filed: 07/30/2010
No. 09-11040 B o n n and Devon filed competing motions for summary judgment on the b r e a c h of contract claim. In its orders on these motions, the district court made r u lin g s concerning the appropriate choice of law and concluded that Devon did n o t breach the JOA by failing to give notice prior to the time the well was drilled a n d completed. It also found that Bonn waived any claims related to late b a llo t in g by Devon. Finally, the district court held that Devon did not
im p r o p e r ly charge penalties to Bonn. The parties subsequently executed a Settlement Agreement and Mutual R e le a s e , by which they released each other from the remaining claims in the la w s u it not resolved by the court's orders on the motions for summary judgment. The parties filed a joint motion to dismiss those claims and Bonn timely a p p e a le d the court's orders. II. B o n n argues first that Devon improperly charged contractual penalties r e la t e d to costs incurred before drilling and after completion of the well, contrary t o the terms of the JOA. Devon acknowledged charging Bonn's interest in v a r io u s wells with penalties both prior to spudding and subsequent to the r e le a s e of the drilling and completion rig, but argues that those charges are p r o p e r under the terms of the JOA. Although the parties disagree as to whether t h e charges were proper, both agree that the JOA and the attached Accounting P r o c e d u r e s in Exhibit C govern the issue. Paragraph 12 of the JOA details the non-consent penalty. It states that t h e non-consenting party is deemed to have relinquished its interest in the well " [u ]p o n commencement of operations for the drilling, reworking, deepening or p lu g g in g back of any such well" until such time as payout. Case law is clear that " c o m m e n c e m e n t of operations" for the drilling of a well occurs before the well is spu dded.
3
Case: 09-11040
Document: 00511189903
Page: 4
Date Filed: 07/30/2010
No. 09-11040 V a r io u s activities preliminary to actual drilling have been held to r e p r e s e n t commencement of operations. To mark commencement of o p e r a tio n s , actual drilling is unnecessary. See Petersen v. Robinson O il & Gas Co., 356 S.W.2d 217, 220 (Tex. Civ. App.-Houston 1962, n o writ). D o r s e tt v. Valence Operating Co., 111 S.W.3d 224, 230 (Tex. App. 2003), reversed o n other grounds in Valence Operating Co. v. Dorsett, 164 S.W.3d 656 (Tex. 2 0 0 5 ). Dorsett specifically rejected the suggestion that operations are not
c o m m e n c e d until the well is spudded. Id. P a y o u t is defined in the JOA as the time when the proceeds from the well e q u a l 100% of the non-consenting party's share of certain costs and 300% of the n o n -c o n s e n t in g party's share of drilling costs. Payout is thus determined by the a c c o u n t in g records for the well. It is not tied to any operational milestone, like c o m p le tio n . Accordingly Devon states that it properly charged Bonn for
p e n a lt ie s from the date it commenced operations on the well until payout. We agree. B o n n argues that the proper time period for accumulation of penalty costs is from the date the well is spudded (the drill bit pierces the surface of the earth) u n t il completion (or commencement of production). Bonn bases its argument on a misreading of the Accounting Procedures in Exhibit C to the JOA. Section III o f the Exhibit deals with the application of Indirect Charges or overhead to p a r tic u la r wells. Paragraph III.2. allows Devon to charge overhead to a well at a fixed monthly rate per well. The drilling overhead rate, which varies
d e p e n d in g on the depth of the well, applies during the drilling of the well. A d iffe r e n t rate applies during production. Paragraph III.4., the provision relied o n by Bonn, states when the different rates apply. The drilling overhead rate " s h a ll begin on the date each well is spudded and terminate on the date the d r illin g or completion rig is released." However, this time limitation applies only 4
Case: 09-11040
Document: 00511189903
Page: 5
Date Filed: 07/30/2010
No. 09-11040 t o indirect charges for overhead. It does not limit Devon's ability to charge nonc o n s e n tin g parties for all direct costs, and associated penalties, applicable to a w e ll pursuant to the terms of Paragraph 12 of the JOA. Bonn's argument is w it h o u t merit. III. In addition to alleging that Devon charged costs to its account for an im p r o p e r period, Bonn argued that no penalties should be owed at all because o f improper balloting for the Marquis Federal well. Devon drilled and completed t h e Marquis Federal well prior to sending notice of operations or intent to drill t o Bonn. Bonn responded to the notice by stating in writing "we elect to go nonc o n s e n t on this well." Bonn argues that because notice was sent after the well w a s drilled it was improper and the JOA penalty provisions do not apply. The d is t r ic t court found that Devon did not breach the JOA by balloting Bonn after t h e well was drilled, that Bonn was not damaged as a result of the late ballot, t h a t the non-consent penalties applied because Bonn elected to go non-consent, a n d that Bonn is estopped from claiming that the expenses incurred on the well b e fo r e the ballot are not properly chargeable. We agree. S e c t io n 12 of the JOA does clearly speak in terms of proposed operations in d ic a tin g that the notice should be sent prior to operations being commenced.
any party or parties wishing to drill, rework, deepen or plug back s u c h a well may give the other party written notice of the proposed o p e r a t io n , specifying the work to be performed, the location, p r o p o s e d depth, objective formation and the estimated cost of the o p e r a tio n . The party receiving such notice shall have thirty (30) d a y s . . . within which to notify the party wishing to do the work w h e t h e r they elect to participate in the cost of the proposed o p e r a tio n .
5
Case: 09-11040
Document: 00511189903
Page: 6
Date Filed: 07/30/2010
No. 09-11040 H o w e v e r , the Texas Supreme Court has held that this language in a JOA does n o t forbid the operator from commencing work before the end of the 30-day n o tic e period. In Valence Operating Co. v. Dorsett, 164 S.W.3d 656 (Tex. 2005), the o p e r a t o r sent notice of a proposed operation but commenced drilling before the 3 0 -d a y period to elect to participate expired. The non-operator argued that this fa ilu r e constituted a breach of contract and therefore prevented enforcement of t h e non-consent penalty. The operator, Valence, argued that the operator can c o m m e n c e work on the proposed operation during the notice period or even b e fo r e the 30-day notice period begins. The Texas Supreme Court agreed with V a le n c e that the JOA "places no temporal limitation on Valence's ability to c o m m e n c e work on proposed projects." After citing the provision that is
s u b s t a n t ia lly similar to the one in this case, the Texas Supreme Court stated This plain language in the Agreement describes Dorsett's right to r e c e iv e notice of proposed operations and to elect to participate in t h o s e operations. It places no restrictions on when Valence may c o m m e n c e drilling or preparations for drilling. .... I n short, the thirty-day notice period sets a deadline for Dorsett to d e c id e whether to participate in proposed operations. Nothing in the la n g u a g e of the Agreement forbids the operator from commencing w o r k before the end of the notice period. Id. at 662-663. Unlike in Dorsett, in this case that operations were essentially completed b e fo r e Devon sent the notice of operations to Bonn. However, that fact actually w o r k s in favor of Bonn. It had the opportunity to decide its participation in the w e ll after the majority of the risk associated with drilling had been determined. Bonn knew that the well was completed and successfully producing. As stated
6
Case: 09-11040
Document: 00511189903
Page: 7
Date Filed: 07/30/2010
No. 09-11040 in Valence, early commencement does not harm the non-operators. It simply p la c e s greater risk on the operator that the cost of the operation will fall entirely o n him. Id. at 663. In addition, Aaron Cawley, Bonn's managing partner, a c k n o w le d g e d that the JOA contains no provision requiring balloting prior to d r illin g and also stated that Bonn suffered no damage as a result of Devon's o p e r a t io n s before balloting Bonn. With full knowledge of the costs of the well and its successful completion, B o n n elected to go non-consent. Cawley acknowledged that this election was c le a r ly pursuant to the terms of the JOA. These facts establish waiver. "Under T e x a s law, the elements of waiver are (1) an existing right, benefit, or a d v a n t a g e ; (2) actual or constructive knowledge of its existence; and (3) actual in t e n t to relinquish that right." GP Plastics Corp. v. Interboro Packaging Corp., 1 0 8 Fed. Appx. 832, 836 (5th Cir. 2004). The district court did not err in
c o n c lu d in g that Bonn waived any rights, if any exist, related to Devon's late b a llo t in g . IV. The final issue Bonn raises in this case relates to the appropriate choice o f law for determining the interest rate to apply to the payment of proceeds. The d is t r ic t court analyzed choice of law and determined that Oklahoma law supplies t h e interest rate. This rate only applies if any damages are assessed. Because o f our disposition of the issues above, there are no damages on which to calculate in t e r e s t and this issue is moot. V. For the foregoing reasons, we affirm the judgment of the district court. AFFIRMED.
7
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?