Muskegon Central Dispatch 911 v. Tiburon, Inc.
Filing
OPINION filed : The decision of the district court is AFFIRMED, but remand the dispute to a new arbitrator, decision not for publication pursuant to local rule 206. Eric L. Clay and Jane Branstetter Stranch, Circuit Judges and Michael R. Barrett, (autjoring) U.S. District Judge for the Southern District of OH.
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 1
NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
File Name: 12a0133n.06
No. 09-2214
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
Feb 02, 2012
MUSKEGON CENTRAL DISPATCH 911,
LEONARD GREEN, Clerk
Plaintiff-Appellee,
v.
TIBURON, INC.,
FILED
ON APPEAL FROM THE UNITED
STATES DISTRICT COURT FOR THE
WESTERN DISTRICT OF MICHIGAN
Defendant-Appellant.
OPINION
BEFORE:
CLAY, and STRANCH, Circuit Judges; BARRETT, District Judge.*
BARRETT, District Judge. Plaintiff-Appellee Muskegon Central Dispatch 911 (“MCD”)
and Defendant-Appellant Tiburon, Inc. entered into an agreement to implement an integrated public
safety computer system. A dispute arose under the agreement, and the parties agreed to privately
arbitrate the matter. The arbitrator found that MCD did not properly terminate the contract and
awarded Tiburon damages and costs. MCD filed a complaint in state court seeking to vacate the
arbitration award. Following removal to federal court based on diversity of citizenship, the district
court concluded that the arbitrator exceeded his powers and vacated the award. For the reasons set
*
Honorable Michael R. Barrett, United States District Judge for the Southern District of Ohio, sitting by
designation.
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 2
No. 09-2214
forth below, we AFFIRM the district court’s decision vacating the award, but remand the dispute
to a new arbitrator.
STATEMENT OF FACTS
I.
Factual Background
MCD represents a consortium of Muskegon County, Michigan police, fire, and emergency
medical service agencies that share an emergency response system. Tiburon is a supplier of public
safety software systems. On December 30, 2003, MCD and Tiburon entered into a System
Implementation Agreement (“SIA”) under which Tiburon was to design, implement, and maintain
an integrated public safety computer system for MCD. (R. 28, Ex. A.) Under the SIA, contract
termination is either for cause or without cause:
13.1. Termination for Default. Subject to completion of the dispute resolution
procedures set forth in Section 12.1 hereof, in the event that either party hereto
materially defaults in the performance of any of its obligations hereunder, the other
party may, at its option, terminate this Agreement by providing the defaulting party
thirty (30) days’ prior written notice of termination delivered in accordance with
Section 34 hereof, which notice shall identify and describe with specificity the basis
for such termination. If, prior to the expiration of such notice period, the defaulting
party cures such default to the satisfaction of the non-defaulting party (as evidenced
by written notice delivered by the non-defaulting party in accordance with Section
34 hereof), termination shall not take place.
13.2. Termination Without Cause. [MCD] may terminate this Agreement without
cause by providing Tiburon at least thirty (30) days’ prior written notice of
termination delivered in accordance with Section 33 hereof.
The dispute resolution procedures (“DRP”) referenced in Section 13.1 are explained in
Section 12.1 of the SIA as follows:
12. Informal Dispute Resolution
-2-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 3
No. 09-2214
12.1. The parties to this Agreement shall exercise their best efforts to negotiate and
settle promptly any dispute that may arise with respect to this Agreement in
accordance with the provisions set forth in this Section 12.1.
(a) If either party (the “Disputing Party”) disputes any provision of this Agreement,
or the interpretation thereof, or any conduct by the other party under this Agreement,
that party shall bring the matter to the attention of the other party at the earliest
possible time in order to resolve such dispute.
(b) If such dispute is not resolved by the employees responsible for the subject matter
of the dispute within ten (10) business days, the Disputing Party shall deliver to the
first level of representatives below a written statement (a “Dispute Notice”)
describing the dispute in detail, including any time commitment and any fees or other
costs involved.
(c) Receipt by the first level of representatives of a Dispute Notice shall commence
a time period within which the respective representatives must exercise their best
effort to resolve the dispute. If the respective representatives cannot resolve the
dispute within the given time period, the dispute shall be escalated to the next higher
level of representatives in the sequence as set forth below.
(d) If the parties are unable to resolve the dispute in accordance with the escalation
procedures set forth below, the parties may assert their rights under this Agreement.
Escalation Timetable
(Business Days)
Tiburon
Representative
Client
Representative
0 to 5th
Project Manager
Project Manager
6th to 10th
Operations Manager
COPS Coordinating
Committee Chair1
11th to 15th
Executive Officer
Chairman of COPS Board
If a party terminates the SIA “without cause” under Section 13.2, the termination is
considered to be for “convenience” under Section 13.3(d). In the event of a termination for
convenience by MCD, the SIA provides that Tiburon is entitled to payment for:
1
The Central Operations Police Services (“COPS”) Board controls the MCD.
-3-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 4
No. 09-2214
all outstanding invoices submitted to [MCD] prior to the effective date of the
termination and for all costs and expenses incurred prior to the effective date of the
termination to the extent not invoiced prior to the effective date of the termination,
based upon Tiburon’s then-current labor rates.
In Section 13.5, the SIA also provides that “[t]he termination of this Agreement shall in no way
relieve either party from any obligations hereunder nor limit the rights and remedies of the other
party in any manner.”
MCD alleges that during the implementation of the system, Tiburon caused numerous delays
and failed to respond to concerns raised by David McCastle, MCD’s Executive Director. On July
19, 2006, McCastle sent an email to Tiburon’s Project Manager, Glenn Matsushima, and his
immediate supervisor, Darrell Richards. (R. 29, Ex. 25.) McCastle copied Tiburon’s President,
Gary Bunyard, and its Board Chairman, Brad Wiggins, on the e-mail, along with the COPS Board
of Directors. (Id.) In his email, McCastle detailed a number of concerns left unresolved by Tiburon.
(Id.) In response, Tiburon replaced Matsushima with Robert Towery, who was the fifth project
manager over the course of a two and a half year period.
MCD also alleges that there were problems with the actual functioning of the system. In an
internal email, Towery acknowledged as much, stating: “In reviewing the contract, we are clearly
in material default however, the client has not yet made this connection.” (R. 29, Ex. 32.)
On August 25, 2006, in a letter from counsel, MCD notified Tiburon that it was terminating
the SIA for cause, effective thirty days thereafter. (R. 29, Ex. 37.) Following the August 25, 2006
letter, there were a number of meetings and communications between the parties. Despite these
efforts, MCD reaffirmed its termination of the contract in a letter to Tiburon’s counsel dated
December 21, 2006. (R. 29, Ex. 40.)
-4-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 5
No. 09-2214
II.
Procedural Background
A.
Arbitration Proceedings
On February 28, 2007, Tiburon filed a demand for arbitration with the American Arbitration
Association. However, the parties subsequently agreed to privately arbitrate the dispute and entered
into an Agreement to Submit to Private Arbitration (“Arbitration Agreement”). (R. 28, Ex. B.)
In the arbitration proceedings, Tiburon filed a statement of claim asserting that MCD
terminated the SIA without cause pursuant to Section 13.2 and claiming damages of $456,662.97
pursuant to Section 13.3(d) of the SIA. (R. 1, Ex. B.) MCD denied liability and argued that it had
terminated the SIA for cause in the August 25, 2006 letter. MCD counterclaimed for breach of
contract in the amount of $516,104.03, plus costs and expenses.2 (Id., Ex. C ¶¶ 23, 28.) The
Arbitrator denied the parties’ cross-motions for summary disposition on MCD’s claim, finding the
existence of genuine issues of material fact regarding MCD’s compliance with the dispute resolution
procedures in the SIA. (R. 36, Ex. 45, at 6.)
The parties agreed to bifurcate the proceedings in order to present the liability issues first,
which would then be followed by evidence on damages. The hearing on liability consisted of twelve
days of testimony and presentation of evidence.
In his written opinion at the close of the liability phase, the arbitrator found that “[t]he
language of the SIA leaves no doubt that this dispute resolution process [in Section 12.1] was
2
MCD also asserts claims of common law fraud/misrepresentation; unfair and deceptive acts
under M.C.L. § 445.901, et. seq.; and a violation of the Magnuson-Moss Warranty Act, 15 U.S.C.
§ 2301, et seq. In a decision not before us, the Arbitrator granted summary disposition for Tiburon
on these other claims.
-5-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 6
No. 09-2214
intended as a condition precedent to the termination of the contract for cause.” (R. 1, Ex. D, at 3.)
The arbitrator found that the language of Section 12.1 was “generally clear and unambiguous,” but
did not “specifically identify which party has the responsibility to initiate the escalation procedures
contained in Section 12.1(d).” (Id. at 4.) The arbitrator reasoned that:
Section 12.1(a) requires that the Disputing Party “shall bring the matter to the
attention of the other party.” Thus, the Disputing Partly clearly has the obligation to
initiate the dispute resolution process. I conclude from a reading of Section 12.1 of
the SIA in context that the intent of the parties was to place the responsibility on the
Disputing Party not only to initiate the process, but to complete the process and bring
it to conclusion. That includes the initiation and conclusion of the escalation
procedures in Section 12.1(d).
(Id.) The arbitrator identified MCD as the Disputing Party. (Id.) The arbitrator found that the July
19, 2006 email sent by McCastle on behalf of MCD constituted a Dispute Notice under Section 12.1.
(Id. at 7.) After a review of the evidence, the arbitrator concluded MCD had not met the
requirements of the “Escalation Timetable” in Section 12.1(d). (Id. at 9.) Therefore, the arbitrator
concluded that MCD’s termination was for convenience under Section 13.2. (Id.)
On September 4 and 5, 2008, the arbitrator heard evidence on Tiburon’s claim for damages
under Section 13.3(d). The arbitrator concluded MCD owed $452,579, “together with interest
running at the statutory rate allowed under Michigan law, and taxable costs.”
MCD filed a complaint in the Muskegon County Circuit Court to vacate the arbitration
award. (R. 1, Ex. A2.) Tiburon then removed the action to the U.S. District Court for the Western
District of Michigan. (R. 1.) In cross-motions before the district court, MCD sought to vacate the
arbitration award, and Tiburon sought to have the award confirmed. (R. 27, 35.)
-6-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 7
No. 09-2214
B.
District Court Opinion
The district court found that in accordance with the Arbitration Agreement, the Michigan
Arbitration Act and Michigan Court Rules, not the Federal Arbitration Act, applied. Muskegon Cent.
Dispatch 911 v. Tiburon, Inc., 652 F. Supp. 2d 862, 867 (W.D. Mich. 2009). The district court
explained that under Michigan law, a court is required to vacate an arbitration award if “‘the
arbitrator exceeded his or her powers’” or “‘refused to hear evidence material to the controversy.’”
Id. (quoting M.C.R §§ 3.602(c), (d)). The district court applied the following standard under
Michigan law:
“Where it clearly appears on the face of the award or the reasons for the decision as
stated, being substantially a part of the award, that the arbitrators through an error in
law have been led to a wrong conclusion, and that, but for such error, a substantially
different award must have been made, the award and decision will be set aside.”
Id. (quoting Detroit Auto. Inter-Ins. Exch. v. Gavin, 331 N.W.2d 418, 430 (Mich. 1982)). The
district court concluded that MCD met this high standard and vacatur of the arbitration award was
appropriate.
The district court explained that there was “no basis in the language of the contract for the
Arbitrator to allocate responsibility for proceeding through the DRP to a single party.” Id. at 868.
The district court pointed out that the plain language of Section 12.1(d) contemplates mutuality of
obligation by referring to the parties in the plural: “‘[i]f the parties are unable to resolve the dispute
in accordance with the escalation procedures set forth below, the parties may assert their rights under
this Agreement.’” Id. The district court found “[i]n assigning the burden to only one party, the
Arbitrator read his own additional terms into the SIA.” Id. The district court explained that “[b]y
adding words to make the escalation process the obligation of just one party, rather than the mutual
-7-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 8
No. 09-2214
obligation the SIA describes; and by treating the DRP not merely as an exhaustion requirement, but
as a winner-take-all bet, the Arbitrator exceeded the scope of his authority.” Id. at 869.
The district court also found that the arbitrator exceeded the scope of his authority by reading
Section 13 as the mandatory and exclusive procedure for a party seeking breach of contract damages.
As the district court explained:
a decision by one party to terminate the contract does not automatically negate all
possible bases for contract liability generated before termination. Termination
generates one set of potential rights and liabilities for each party, but it does not
subsume all other possible claims the contracting parties may have against each
other. See Mead Corp. v. ABB Power Generation, Inc., 319 F.3d 790, 796 (6th Cir.
2003) (parties may invoke independent remedies to the extent not explicitly limited
by contract). Termination liability or its absence is just one aspect of the overall
contractual rights and liabilities of the parties.
Id. at 869–70. Accordingly, the district court issued an order vacating “the arbitral decisions on
liability, damages and costs” and remanding “to address issues submitted to the Arbitrator but not
resolved.” Id. at 870. The district court concluded that a remand to the same arbitrator was
appropriate. Id.
DISCUSSION
I.
Legal Standards
A.
Choice of Law
This case falls within the scope of the Federal Arbitration Act (“FAA”) because the
Arbitration Agreement, read together with the SIA, is a “contract evidencing a transaction involving
commerce.” 9 U.S.C. § 2. Although the FAA “governs all aspects of arbitration procedure and
preempts inconsistent state law[,]” Stout v. J.D. Byrider, 228 F.3d 709, 716 (6th Cir. 2000), where
“the parties have agreed to abide by state rules of arbitration, enforcing those rules according to the
-8-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 9
No. 09-2214
terms of the agreement is fully consistent with the goals of the FAA.” Volt Info. Scis., Inc. v. Bd. of
Trs. of Leland Stanford Junior Univ., 489 U.S. 468, 479 (1989); see also Ario v. Underwriting
Members of Syndicate 53 at Lloyds for 1998 Year of Account, 618 F.3d 277, 288–89 (3d Cir. 2010).
In making a choice of law determination, the central inquiry is whether the parties’ agreement
evinces an unambiguous intent to “predicate[] the court’s judicial action on the parties’ having
agreed to specific standards.” Hall Street Assoc., L.L.C. v. Mattel, Inc., 552 U.S. 576, 587 n.6
(2008); see also Mastrobuono v. Shearson Lehman Hutton, Inc., 514 U.S. 52, 66 (1995) (stating that
parties’ intent controls); Pub. Serv. Credit Union v. Ernest, 988 F.2d 627, 629 (6th Cir. 1993)
(finding that district court erroneously relied on FAA, where “both parties agreed that the Michigan
statute controlled their agreement” to arbitrate). Ambiguities are resolved in favor of the federal
standard. See E.E.O.C. v. Waffle House, Inc., 534 U.S. 279, 293 n.9 (2002).
In this case, the Arbitration Agreement evidences the unambiguous intent of the parties to
apply Michigan law in any subsequent appeal of the arbitration award. Paragraph 1 of the
Arbitration Agreement explicitly refers to the Michigan Arbitration Act in stating that disputes “shall
be submitted to final and binding arbitration in accordance with the provisions of this Submission
Agreement and pursuant to the provisions of MCL 600.5001-600.5035.” (R. 28, Ex. B ¶ 1.) The
Arbitration Agreement makes numerous other references to Michigan law, (id. ¶¶ 3 (applicable law
generally); 6 (disqualification); 9(h) (discovery)), and most notably, Paragraph 18 states that:
¶ 18. Award. . . . Judgment upon the [arbitration] decision may be entered in any
court that has jurisdiction over the parties, in accordance with the Michigan
Arbitration Act, being MCL 600.5001, et. seq. Appeals from the arbitration award
shall be conducted as provided for in MCL 600.5001, [et] seq. and MCR 3.602[.]
(Id.)
-9-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 10
No. 09-2214
Moreover, the Arbitration Agreement neither refers to the Federal Arbitration Act, nor
otherwise suggests that either party sought to “invoke[] the FAA in the arbitration agreement.” Uhl
v. Komatsu Forklift Co., Ltd., 512 F.3d 294, 303 (6th Cir. 2008) (concluding that federal law
governed, where the parties’ choice of law provision referenced both the state and federal arbitration
acts). To the contrary, Paragraphs 1 and 18 expressly incorporate the Michigan Arbitration Act into
the agreement, and Paragraph 18 provides that state law will govern entry of judgment by a court and
all appeals. See, e.g., Jacada (Europe), Ltd. v. Int’l Mktg. Strategies, Inc., 401 F.3d 701, 710 (6th
Cir. 2005) (concluding that a generic choice-of-law provision does not displace the federal standard
for vacating an arbitration award), abrogated on other grounds by Hall Street Assoc., 552 U.S. 576
(2008).
Accordingly, because the Arbitration Agreement unambiguously provides that the Michigan
Arbitration Act will govern subsequent proceedings, we find that the parties intended to displace the
federal standard and that Michigan law provides the legal standard.
B.
Standard of Review
When reviewing a district court’s decision to vacate an arbitration award, we review factual
findings for clear error and questions of law de novo. Green v. Ameritech Corp., 200 F.3d 967, 974
(6th Cir. 2000).
Under Michigan law, a court’s power to modify, correct, or vacate an arbitration award is
limited by the Michigan Court Rules. Gordon Sel-Way, Inc. v. Spence Bros., Inc., 475 N.W.2d 704,
709 (Mich. 1991). A court shall vacate an arbitration award if “(a) the award was procured by
corruption, fraud, or other undue means; (b) there was evident partiality by an arbitrator appointed
-10-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 11
No. 09-2214
as a neutral, corruption of an arbitrator, or misconduct prejudicing a party’s rights; (c) the arbitrator
exceeded his or her powers; or (d) the arbitrator refused to postpone the hearing on a showing of
sufficient cause, refused to hear evidence material to the controversy, or otherwise conducted the
hearing to prejudice substantially a party’s rights.” Mich. Ct. Rule § 3.602(J)(2). Michigan courts
have explained that “arbitrators can fairly be said to exceed their power whenever they act beyond
the material terms of the contract from which they primarily draw their authority, or in contravention
of controlling principles of law.” Gavin, 331 N.W.2d at 430; see also Gordon Sel-Way, 475 N.W.2d
at 709. Thus, “‘where it clearly appears on the face of the award or the reasons for the decision as
stated, being substantially a part of the award, that the arbitrators through an error in law have been
led to a wrong conclusion, and that, but for such error, a substantially different award must have been
made, the award and decision will be set aside.’” Gavin, 331 N.W.2d at 434 (alteration omitted)
(quoting Howe v. Patrons’ Mut. Fire Ins. Co. of Michigan, 185 N.W. 864, 867–68 (Mich. 1921)).
Michigan courts have explained that “[j]udicial review of an arbitrator’s decision is narrowly
circumscribed.” City of Ann Arbor v. Am. Fed’n of State, Cnty., & Mun. Emps. Local 369, 771
N.W.2d 843, 854 (Mich. Ct. App. 2009) (citing Police Officers Ass’n of Mich. v. Manistee Cnty.,
645 N.W.2d 713 (Mich. Ct. App. 2002)). Specifically, “[a] court may not review an arbitrator’s
factual findings or decision on the merits.” 771 N.W.2d at 854. A reviewing court is also prohibited
from engaging in contract interpretation, which is an issue for the arbitrator to determine. Id. (citing
Konal v. Forlini, 596 N.W.2d 630 (Mich. Ct. App. 1999)).
-11-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 12
No. 09-2214
II.
Analysis
Tiburon appeals the district court’s two holdings in support of vacatur, namely that the
Arbitrator exceeded his powers (1) by concluding MCD had the responsibility to escalate and
complete the DRP; and (2) by reading Section 13 as the exclusive remedy for breach of contract.
In support, Tiburon argues that a court may not interfere with the arbitrator’s judgment on procedural
issues. Tiburon maintains that the arbitrator decided, and the parties agreed, that the sequencing of
his decision on the issues presented was such that the arbitrator would only reach Tiburon’s alleged
breach of contract if the DRP completion issue was decided in MCD’s favor. Although procedural
issues are generally reserved for the arbitrator, Bennett v. Shearson Lehman-Am. Exp., Inc., 423
N.W.2d 911, 913 (Mich. Ct. App. 1987), MCD’s assignments of error are not properly characterized
as procedural matters beyond the scope of our review. For this reason, and as fully explained below,
we will affirm.
A.
Burden to Escalate under Section 12
Tiburon argues that the district court erred in ruling that the arbitrator had exceeded his
powers by concluding that under Section 12 of the SIA, MCD had the responsibility to escalate and
complete the DRP. Tiburon points out that the SIA was silent as to which party has the burden to
escalate and complete the DRP.
In addressing this argument, the district court applied reasoning found in the Michigan
Supreme Court’s decision in Detroit Automobile Inter-Insurance Exchange v. Gavin:
As Gavin points out, in agreeing to arbitration, the parties’ central focus is the benefit
of the bargain they entered-the substantive terms of the agreement-not process.
Where parties to a contract provide specifically for the use of arbitration to resolve
significant disputes, “it is clear that the primary concern of the parties is the
-12-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 13
No. 09-2214
enforcement of the terms of the agreement which they have made, securing to each
of them the benefits to which they are entitled under the applicable law, including
their own agreement.” Of secondary concern are the procedural mechanisms by
which disputes will be resolved. “The process of dispute resolution and the
procedural advantages of arbitration are the servants of the law governing the issues
in dispute, not the reverse.”
Muskegon Cent. Dispatch 911, 652 F. Supp. 2d at 867–68 (citations omitted). The district court
found that the reasoning in Gavin applies “not only to the ultimate arbitration process, but also to
the preliminary dispute resolution steps leading to the eventual arbitration.” Id. at 868. The district
court found that under Gavin, “the DRP of Section 12 imposes mutual obligations that are the
servant, not the master of the substantive contract obligations.” Id. (emphasis omitted).
The district court explained that incorporating mutual obligations to carry out the escalation
process makes practical sense:
The purpose of an escalation process such as the DRP is to resolve as many disputes
as possible on business terms, leaving only the most intractable and substantive
problems for arbitration. Business solutions by their nature require both parties to
engage and compromise. When one or both parties loses interest in or the ability to
reach a business solution, the practical value of the DRP is exhausted-it is no longer
a servant of the parties' mutual obligation to work for informal resolution.
Id. at 868. The district court noted that it was Tiburon that initiated the arbitration, and thus “[i]t
would be especially odd to penalize MCD for failing to exhaust informal means when Tiburon
actually initiated the arbitration process.” Id. at 868–69.
Tiburon argues that by engaging in this analysis, the district court was engaging in contract
interpretation, which is a duty reserved for the arbitrator. Tiburon would be correct if the SIA was
indeed silent as to which party has the responsibility to complete the escalation procedures.
However, as the district court explained, the plain language of the contract expressly refers to both
-13-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 14
No. 09-2214
parties: “[i]f the parties are unable to resolve the dispute in accordance with the escalation
procedures set forth below, the parties may assert their rights under this Agreement.” Id. at 868.
Any fair reading of the contract language makes it clear that the parties intended a mutual obligation
to carry out the escalation process. See Morley v. Auto. Club of Mich., 581 N.W.2d 237, 240–41
(Mich. 1998) (quoting Maclean v. Fitzsimons, 45 N.W. 145, 146 (Mich. 1890) (explaining rule that
“what is plainly implied from the language used in a written instrument is as much a part thereof as
if it was expressed therein”)). By ignoring this language, the arbitrator exceeded his power. See
Gavin, 331 N.W.2d at 430. Therefore, it was not error for the district court to vacate the award of
the arbitrator.
B.
Section 13 as Exclusive Remedy for Breach of Contract
The district court found that the arbitrator exceeded the scope of his authority by applying
Section 13 as the exclusive procedure for a party seeking breach of contract damages. Muskegon
Cent. Dispatch 911, 652 F. Supp. 2d at 869. As a result, the arbitrator never reached the merits of
MCD’s breach of contract claim. See id. at 868. Tiburon argues that MCD did not argue before the
arbitrator that its breach of contact claim should be decided independent of the issue of completion
of the DRP. Tiburon argues that this constituted a waiver of the issue. However, in the brief MCD
submitted during the damages phase of the arbitration proceedings, MCD stated:
Given the lack of any discussion in the Opinion regarding any breach of the SIA by
either party, MCD can only assume that the Arbitrator concluded that MCD waived
its right to sue for breach of contract by falling short of successfully invoking the
SIA’s termination for cause provision. MCD disagrees with this implied conclusion
and further disagrees that terminated the SIA “without cause,” but is nevertheless
proceeding to the hearing based on the belief that the Arbitrator's ruling has
foreclosed MCD’s opportunity to prove its damages.
-14-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 15
No. 09-2214
(R. 43, Ex. 1.)
After reviewing the record, the district court found that the Arbitrator was presented with the
issue of MCD’s breach of contract claim, but never reached the issue:
In neither his opinion on liability nor his opinion on damages did the Arbitrator
address the merits of MCD’s breach of contract claim. Indeed, the arbitrator never
made any findings on whether Tiburon breached its own contractual obligations, as
MCD claimed, and as Tiburon’s own project manager believed. Instead, the
Arbitrator treated what he found as MCD’s failure to comply with the DRP, coupled
with the termination provisions, as essentially a forfeiture of MCD’s right to assert
breach. The Arbitrator’s decision resulted in MCD losing entirely and Tiburon
winning entirely, without any finding on whether Tiburon was in material breach of
substantive obligations.
Muskegon Cent. Dispatch 911, 652 F. Supp. 2d at 866–67.
The district court correctly concluded that the Arbitrator’s decision resulted in a forfeiture
of MCD’s breach of contract claim. This result is contrary to Michigan law, which provides that
“where one party to a contract commits a material breach, the nonbreaching party is entitled to
terminate the contract.” Convergent Grp. Corp. v. Cnty. of Kent, 266 F. Supp. 2d 647, 657–58
(W.D. Mich. 2003) (citing Lynder v. S.S. Kresge Co., 45 N.W.2d 319, 325 (Mich. 1951)). Parties
are free to modify this rule by conditioning the right to terminate upon some condition precedent.
Id. at 658. However, as the district court noted, the parties in this instance did not do so. There was
no language in the SIA stating that Section 13 is the exclusive remedy for a party seeking breach of
contract damages. Cf. Short v. Hollingsworth, 289 N.W. 158, 159 (Mich. 1939) (holding that “[i]f
it appears to have been the intention that the remedy specified in the contract should be exclusive,
the rights of the parties will be controlled thereby”). Therefore, the district court did not err by
-15-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 16
No. 09-2214
vacating the award of the arbitrator and remanding the case to the arbitrator for decision on the
merits of MCD’s breach of contract claim.
C.
Arbitrator on Remand
The district court held that the Arbitrator originally selected by the parties is the appropriate
person to handle any further proceedings. We disagree.
The Michigan Court Rules permit a court to vacate an arbitration order and remand for
rehearing. Mich. Comp. Laws § 3.602(J). However, the functus officio doctrine provides the
circumstances in which remand to the original arbitrator, rather than a new arbitrator, is appropriate.
Green, 200 F.3d at 976–77.
The Latin term “functus officio” means that “having performed his or her office,” an official
is “without further authority or legal competence because the duties and functions of the original
commission have been fully accomplished.” Black’s Law Dictionary 743 (9th ed. 2009). “The
policy behind the doctrine is an unwillingness to permit one who is not a judicial officer and who
acts informally and sporadically, to re-examine a final decision which has already been rendered,
because of the potential evil of outside communication and unilateral influence which might affect
a new conclusion.” Oakwood Labs. v. Howrey Simon Arnold & White, LLP, 2007 WL 1544577, at
*2 (N.D. Ohio May 24, 2007) (internal citations omitted).
In general, “‘once an arbitrator has made and published a final award his authority is
exhausted and he is functus officio and can do nothing more in regard to the subject matter of the
arbitration.’” McClatchy Newspapers v. Cent. Valley Typographical Union, 686 F.2d 731, 734 (9th
Cir. 1982) (quoting La Vale Plaza, Inc. v. R.S. Noonan, Inc., 378 F.2d 569, 572 (3d Cir. 1967)); see
-16-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 17
No. 09-2214
also Beattie v. Autostyle Plastics, Inc., 552 N.W.2d 181, 184 (Mich. Ct. App. 1996) (recognizing the
doctrine of functus officio). This means that where a vacated arbitration award is remanded and
requires a reopening of the merits of a claim, remand to a new arbitrator is appropriate. Cf. Green,
200 F.3d at 977–78 (noting that if remand was warranted, remand would be to original arbitrator
because he would simply be completing his duties by clarifying his reasoning, not reopening the
merits of the case); M & C Corp. v. Erwin Behr GmbH & Co., 326 F.3d 772, 783 (6th Cir. 2003)
(remanding to original arbitrator is proper where arbitrator is not reopening the merits of a case).
However, there are exceptions to the functus officio doctrine that direct when remand to the
original arbitrator is appropriate: “(1) an‘arbitrator can correct a mistake which is apparent on the
face of his award’; (2) ‘where the award does not adjudicate an issue which has been submitted, then
as to such issue the arbitrator has not exhausted his function and it remains open to him for
subsequent determination’; and (3) ‘[w]here the award, although seemingly complete, leaves doubt
whether the submission has been fully executed, an ambiguity arises which the arbitrator is entitled
to clarify.’” Green, 200 F.3d at 977 (quoting La Vale Plaza, 378 F.2d at 573).
In the instant case, there are two reasons supporting our decision to vacate the award and
remand: (1) the Arbitrator exceeded his powers when he reviewed Tiburon’s contract claim and
decided that MCD had the burden to escalate, and (2) the Arbitrator was presented with MCD’s
contract claim but failed to review the merits of it.
We decide that Tiburon’s contract claim should be remanded to a new arbitrator. Where an
arbitration award is vacated because the arbitrator exceeded his or her powers, the Michigan Court
Rules grant the court discretion to remand to a new arbitrator or the original arbitrator. Mich. Comp.
-17-
Case: 09-2214
Document: 006111203666
Filed: 02/02/2012
Page: 18
No. 09-2214
Laws § 3.602(J)(4). Because the original arbitrator here would also be required to reopen the merits
of Tiburon’s contract claim, remand to the original arbitrator “implicate[s] . . . the concerns
underlying the functus officio doctrine.” Green, 200 F.3d at 978. Thus, a new arbitrator should
review Tiburon’s contract claims.
We decide that MCD’s contract claim should also be reviewed by the new arbitrator. The
original arbitrator, although presented with the MCD’s contract claim, did not review the merits of
it. Under the second exception to functus officio, we would normally remand the unreviewed claim
to the original arbitrator to give him the opportunity to review it for the first time and complete his
duty with respect to that claim. However, submitting Tiburon’s contract claim to a new arbitrator
and MCD’s contract claim to the original arbitrator would be inefficient. In the interest of fairness
and efficiency, we remand all claims to a new arbitrator.
CONCLUSION
For the foregoing reasons, we AFFIRM the decision of the district court, but remand the
dispute to a new arbitrator.
-18-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?