Razorback Concrete Company v. Dement Construction Company
Filing
OPINION FILED - THE COURT: DIANA E. MURPHY, MICHAEL J. MELLOY and RAYMOND W. GRUENDER. Roger L. Wollman, Authoring Judge (PUBLISHED) [3939382] [11-3499]
United States Court of Appeals
For the Eighth Circuit
___________________________
No. 11-3499
___________________________
Razorback Concrete Company
lllllllllllllllllllll Plaintiff - Appellant
v.
Dement Construction Company, LLC
lllllllllllllllllllll Defendant - Appellee
____________
Appeal from United States District Court
for the Eastern District of Arkansas - Jonesboro
____________
Submitted: April 19, 2012
Filed: August 6, 2012
____________
Before MURPHY, MELLOY, and GRUENDER, Circuit Judges.
____________
GRUENDER, Circuit Judge.
Razorback Concrete Company (“Razorback”) sued Dement Construction
Company (“Dement”) for breach of contract and fraud based on disputes over
performance of a concrete supply contract. The district court1 granted summary
1
The Honorable Susan Webber Wright, United States District Judge for the
Eastern District of Arkansas.
Appellate Case: 11-3499
Page: 1
Date Filed: 08/06/2012 Entry ID: 3939382
judgment to Dement on the fraud claim and partial summary judgment to Dement as
to the measure of damages for the breach of contract claim, holding that Razorback
was not entitled to recover damages under a lost profits theory. After obtaining a
judgment on the contract claim that it deems inadequate, Razorback appeals the
grants of summary judgment. We affirm.
I.
BACKGROUND2
Dement was the prime contractor on a bridge construction project, and
Razorback was its concrete provider. Pursuant to a written contract requiring
payment by Dement within thirty days of receiving monthly statements, Razorback
was to supply concrete that met the requisite strength level for the bridge. However,
some of the concrete failed strength tests after a specified twenty-eight-day interval
(occurrences the parties describe as “low breaks”). As a result, Dement had to allow
extra time for the concrete to strengthen to an acceptable level for the project.
Dement sent a letter to Razorback on April 4, 2007 noting that the project had a time
charge of $5,000 for each day that it took Dement to complete the project and that
Dement considered “that thirty (30) days of time charged for [Razorback’s] account
would be equitable.” Razorback responded in writing that the concrete was not
substandard, but rather that the tests—which were not conducted by
Razorback—were flawed. Additionally, Razorback inquired of Dement
whether it is your intention to attempt to set off payments due
[Razorback] for future deliveries of concrete with your claim for
damages. . . . [U]nless we are told to the contrary, [Razorback] will
assume that you will pay for material as it is delivered to the site. If this
assumption is unwarranted you need to say so, because [Razorback] will
2
The facts in this opinion are stated in the light most favorable to Razorback,
the party resisting the grant of summary judgment. See Smith v. Arrington Oil & Gas,
Inc., 664 F.3d 1208, 1212 (8th Cir. 2012).
-2-
Appellate Case: 11-3499
Page: 2
Date Filed: 08/06/2012 Entry ID: 3939382
rely upon your failure to correct this assumption in order to make future
deliveries of concrete to the site.
After receiving no response from Dement, Razorback wrote another letter on May 8
stating that it would rely on Dement’s failure to respond as a representation that no
amount due Razorback would be withheld as an offset. Razorback also stated that
should Dement later try to offset moneys due Razorback, Razorback would have
claims for breach of contract, fraud, deceit, and misrepresentation.
Dement responded on May 9 that, to Dement’s knowledge, there were no more
low breaks after Razorback had changed its mix design for the concrete. It also noted
that it had never intended “to unilaterally deduct monies due Razorback based on this
issue” and that it would continue to pay all invoices in a timely manner. In reliance
on Dement’s assurances, Razorback continued to supply concrete to Dement.
On May 18, Dement learned that concrete used in a “critical zone” of what it
described as “probably the most critical pier in the structure” had substandard
strength-test results. Furthermore, Dement was informed on June 8 that the Federal
Highway Administration (“FHWA”) might require concrete to be replaced if a low
break were to occur in a certain area of the construction. According to Razorback,
Dement’s payments in June and August withheld some of the amount owed for
delivered concrete and Dement stopped making any payments after August 2007. In
light of what it viewed as a breach of contract by Dement, Razorback terminated the
contract and refused to supply any additional concrete.
In its suit against Dement, Razorback asserted that it was entitled to $318,767,
representing lost profits that it would have earned by supplying concrete for the
remainder of the project. Razorback also asserted that Dement was liable for fraud
because it withheld payments after promising Razorback that it would not. The
district court granted summary judgment to Dement as to Razorback’s fraud claim,
-3-
Appellate Case: 11-3499
Page: 3
Date Filed: 08/06/2012 Entry ID: 3939382
holding that Razorback’s evidence was insufficient for a reasonable jury to find fraud.
The district court granted partial summary judgment to Dement on the issue of lost
profits as the measure of damages on Razorback’s breach of contract claim because
Razorback’s evidence did not create a material question of fact regarding whether
Razorback was entitled to that measure of damages under the Uniform Commercial
Code (“U.C.C.”). The case proceeded to trial on the remaining breach of contract
claim, and Razorback obtained a jury verdict in its favor. Razorback now appeals the
grants of summary judgment as to the fraud claim and the lost profits measure of
damages on the contract claim.
II.
DISCUSSION
“As a federal court sitting in diversity jurisdiction, we apply the law that the
forum state would apply.” Winthrop Res. Corp. v. Stanley Works, 259 F.3d 901, 904
(8th Cir. 2001). Because the district court determined that Arkansas law governs and
the parties did not appeal that determination, we too will apply Arkansas law. See
Lackawanna Chapter of the Ry. & Locomotive Historical Soc’y, Inc. v. St. Louis
Cnty., Mo., 497 F.3d 832, 835 (8th Cir. 2007). “If the Supreme Court of [Arkansas]
has not addressed an issue, we must predict how the court would rule . . . .” Eubank
v. Kan. City Power & Light Co., 626 F.3d 424, 427 (8th Cir. 2010).
We review de novo a district court’s grant of summary judgment and its
interpretation of state law. Best Buy Stores, L.P. v. Benderson-Wainberg Assocs.,
L.P., 668 F.3d 1019, 1026 (8th Cir. 2012). “Summary judgment is appropriate when,
viewing the record in the light most favorable to the nonmoving party, there are no
genuine issues of material fact and the moving party is entitled to judgment as a
matter of law.” Smith v. Arrington Oil & Gas, Inc., 664 F.3d 1208, 1212 (8th Cir.
2012). As the moving party, Dement bore “the initial responsibility of informing the
district court of the basis for its motion” and needed to identify “those portions of [the
record] . . . which it believes demonstrate the absence of a genuine issue of material
-4-
Appellate Case: 11-3499
Page: 4
Date Filed: 08/06/2012 Entry ID: 3939382
fact.” Torgerson v. City of Rochester, 643 F.3d 1031, 1042 (8th Cir.) (en banc)
(alterations in original) (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986)),
cert. denied, 565 U.S. ---, 132 S. Ct. 513 (2011). If Dement met this burden,
Razorback needed to submit “evidentiary materials that set out specific facts showing
that there is a genuine issue for trial.” Id. Razorback needed to “do more than simply
show that there is some metaphysical doubt as to the material facts . . . .” Id.
A.
Fraud Claim
Under Arkansas law, fraud consists of the following five elements: (1) “a false
representation of a material fact,” (2) “knowledge that the representation is false or
that there is insufficient evidence upon which to make the representation,” (3) “intent
to induce action or inaction in reliance upon the representation,” (4) “justifiable
reliance on the representation,” and (5) “damage suffered as a result of the
representation.” Bomar v. Moser, 251 S.W.3d 234, 241 (Ark. 2007). “Fraud is never
presumed, but must be affirmatively proved, and the burden of proving fraud is upon
the party who alleges it and relies on it.” Interstate Freeway Servs., Inc. v. Houser,
835 S.W.2d 872, 873 (Ark. 1992). “An action for fraud or deceit may not be
predicated on representations relating solely to future events. However, this rule is
inapplicable if the person making the representation or prediction knows it to be false
at the time it is made.” Goforth v. Smith, 991 S.W.2d 579, 586 (Ark. 1999) (internal
citation omitted). “While fraud may be established by circumstantial evidence, the
circumstances must be so strong and well connected as to clearly show fraud.”
Fowler v. SmithKline Beecham Clinical Labs., Inc., 225 F.3d 1013, 1016 (8th Cir.
2000) (quoting Allred v. Demuth, 890 S.W.2d 578, 580 (Ark. 1994)).
This case turns on whether Razorback produced sufficient evidence to create
a genuine issue of material fact regarding whether Dement, at the time it assured
Razorback that it would not withhold payments (a statement relating solely to future
events), knew that the representation was false. See Goforth, 991 S.W.2d at 586.
-5-
Appellate Case: 11-3499
Page: 5
Date Filed: 08/06/2012 Entry ID: 3939382
Razorback asserts that when Dement assured Razorback in May 2007 that it would
not withhold payments, Dement already intended to withhold future payments. In
support, Razorback claims that Dement began withholding payments in June 2007
even though there were no problems with the concrete and that nothing, except
perhaps testing procedures, had changed from the time of Dement’s promise. The
record demonstrates, however, that Dement learned consequential news between the
time that it made the assurance to Razorback and the time that it began withholding
payments. First, Dement learned that concrete used in what it claims was probably
the most critical pier in the structure had substandard strength-test results. Second,
Dement learned that there was no guarantee that the FHWA would allow certain
concrete to remain in place in the event of a low break. In September 2007, Dement
wrote to Razorback stating that removal and replacement of the concrete, if necessary,
would cost approximately $420,000 to $840,000 and that, in an effort to resolve the
matter without withholding payments from Razorback, Dement would accept a letter
of credit for the estimated amount of the repair. Dement then stated that it would
release the letter of credit if the issue was resolved without requiring repairs. In
opposition to this undisputed evidence that Dement’s decision to withhold payments
was based on the intervening information, Razorback fails to cite any evidence
suggesting that Dement’s decision to withhold payments beginning in June 2007 was
reached by the time of its initial assurance of continued payments in May 2007.3
3
Instead, Razorback suggests that Dement’s explanation is not to be trusted by
arguing that Dement demonstrated a lack of candor by claiming in its April 2007
letter “that the negative test[] results caused a delay of 30 days” because Charles
Capps, Dement’s vice president, admitted at his deposition that he “pulled the 30 day
figure out of the air.” However, rather than stating as fact that there was a delay of
thirty days, the letter merely said “[w]e feel that thirty (30) days of time charged for
your account would be equitable.” Moreover, Capps testified at his deposition that
there was probably more than a thirty-day delay attributable to Razorback. This
testimony does not show that Dement is not credible, and it does not raise a material
question of fact regarding whether Dement knew that its representation about future
payments was false at the time of the representation.
-6-
Appellate Case: 11-3499
Page: 6
Date Filed: 08/06/2012 Entry ID: 3939382
Given Razorback’s failure to identify any evidence creating a genuine issue of
material fact regarding whether Dement knew its assurance that it would not withhold
payments was false at the time the statement was made, the district court did not err
by granting summary judgment in favor of Dement on Razorback’s fraud claim.
B.
Lost Profits Measure of Damages
When Razorback filed suit against Dement, it requested “the monies it is owed”
as damages for its breach of contract claim. However, Razorback conceded at oral
argument that it was clear from its subsequent computation of damages, submitted in
accordance with Federal Rule of Civil Procedure (“FRCP”) 26, that it was seeking
lost profits under Arkansas Code Annotated (“ACA”) section 4-2-708(2), the analog
of U.C.C. section 2-708(2), although it did not include a specific citation to section
4-2-708(2). While section 4-2-708(1) provides a measure of compensatory damages
to an injured seller—the difference between the unpaid contract price and the market
price—premised on the seller’s ability to resell the same goods at market price,
section 4-2-708(2) provides for lost profits damages but only to sellers who can show
that the section 4-2-708(1) damages are inadequate to place them in as good a
position as performance by the buyer would have.4 One way to make this showing
4
Section 4-2-708 provides:
(1) Subject to subsection (2) and to the provisions of this chapter with
respect to proof of market price (§ 4-2-723), the measure of damages for
non-acceptance or repudiation by the buyer is the difference between the
market price at the time and place for tender and the unpaid contract
price together with any incidental damages provided in this chapter
(§ 4-2-710), but less expenses saved in consequence of the buyer's
breach.
(2) If the measure of damages provided in subsection (1) is inadequate
to put the seller in as good a position as performance would have done
-7-
Appellate Case: 11-3499
Page: 7
Date Filed: 08/06/2012 Entry ID: 3939382
is for the seller to prove it “has the capacity to perform the contract which was
breached as well as other potential contracts, due to their unlimited resources or
production capacity.” Bill’s Coal Co. v. Bd. of Pub. Utils., 887 F.2d 242, 245 (10th
Cir. 1989). Such a seller is commonly referred to as a “lost volume seller.” See id.
The district court ruled in favor of Dement because it concluded that Razorback’s
evidence did not create a genuine question of material fact regarding whether
Razorback was a lost volume seller or whether damages under section 4-2-708(1)
were otherwise inadequate.5
On appeal, Razorback first argues that the trial court acted sua sponte in ruling
that Razorback was not a lost volume seller because Dement never argued that
Razorback was not a lost volume seller or that Razorback failed to mitigate its
damages. Thus, Razorback claims that it did not have the opportunity to present
evidence and argument regarding these issues. The record belies this argument.
After Razorback’s FRCP 26 damages calculation made clear that it was seeking lost
profits, Dement, in seeking summary judgment, made multiple arguments claiming
that Razorback was not entitled to lost profits, including that “[t]he U.C.C. does not
permit a seller to recover consequential damages such as lost profits” and that
Razorback’s claim for lost profits was speculative. Razorback opposed summary
then the measure of damages is the profit (including reasonable
overhead) which the seller would have made from full performance by
the buyer, together with any incidental damages provided in this chapter
(§ 4-2-710), due allowance for costs reasonably incurred and due credit
for payments or proceeds of resale.
Ark. Code Ann. § 4-2-708.
5
Because Razorback does not provide any developed argument that it is entitled
to lost profits under a different provision of the Arkansas code, we address its
argument that it is entitled to lost profits by examining ACA section 4-2-708(2).
Furthermore, we assume without deciding that the facts of this case constitute “nonacceptance or repudiation” by Dement. See Ark. Code Ann. § 4-2-708(1).
-8-
Appellate Case: 11-3499
Page: 8
Date Filed: 08/06/2012 Entry ID: 3939382
judgment by quoting section 4-2-708(2) in support of its position that a seller can
recover lost profits under the U.C.C. and asserting that its lost profits—which it
calculated as the contract price minus the cost of performance—were not speculative.
Razorback further asserted that “to the extent that [Dement] may be arguing that
Razorback [could not] have supplied concrete on other jobs if it had continued
supplying concrete on the Dement job, . . . Razorback’s high-capacity plants
permitted Razorback to meet all the requirements of the Dement job as well as being
able to supply concrete on other jobs.” Thus, we conclude that the issue was properly
before the district court.
Razorback next argues that the issue of whether it was a lost volume seller
would only be relevant if Dement had argued that Razorback failed to mitigate its
damages. We disagree. Section 2-708(2) generally is interpreted as placing upon the
seller the burden of demonstrating that it should be compensated as a lost volume
seller if that is a theory by which the seller seeks to show that damages under section
2-708(1) are inadequate. See, e.g., Bill’s Coal Co., 887 F.2d at 245 (“Sellers have the
burden of proving that they are lost volume sellers . . . .”); R.E. Davis Chem. Corp.
v. Diasonics, Inc., 826 F.2d 678, 684 (7th Cir. 1987) (“Diasonics must establish, not
only that it had the capacity to produce the breached unit in addition to the unit
resold, but also that it would have been profitable for it to have produced and sold
both. Diasonics carries the burden of establishing these facts because the burden of
proof is generally on the party claiming injury to establish the amount of its damages
. . . .”). Finding no Arkansas law addressing this question directly, we predict
Arkansas likewise would place this burden upon the seller claiming damages. See
Marine Servs. Unlimited, Inc. v. Rakes, 918 S.W.2d 132, 136 (Ark. 1996) (“The
burden of proving damages rests on the party claiming them and the proof must
consist of facts, not speculation.”). At the summary judgment stage, Razorback had
the burden of identifying facts that at least created a genuine issue of material fact
regarding whether Razorback was eligible to recover under ACA section 4-2-708(2).
To meet this burden, Razorback needed to provide the district court with sufficient
-9-
Appellate Case: 11-3499
Page: 9
Date Filed: 08/06/2012 Entry ID: 3939382
proof as to why the damages under subsection (1) were inadequate. Nothing in
section 4-2-708 conditions this burden on whether the buyer asserted a failure to
mitigate damages.
Razorback next argues that the district court erred by concluding that no
reasonable jury could find that Razorback was a lost volume seller. Again, we
disagree. The testimony of Razorback’s general manager, Keith Wetsell, shows that
Razorback would have had a limited capacity to perform other contracts if Dement
had not breached. According to Wetsell, Razorback “probably turned away or didn’t
bid [on] some work that had come along during the time we were doing the Dement
project . . . because we knew we were kind of at maximum peak there with their job.”
Although Wetsell later indicated that Razorback “could have done plenty of other
work” if the opportunity were there, he specified that it would have had to be a size
that Razorback could handle. Given this testimony that Razorback was operating at
near peak capacity, the absence of contrary evidence indicating that Wetsell
understated Razorback’s capacity to supply concrete, and the lack of evidence
regarding whether the additional jobs that Razorback took after ending its
relationship with Dement were of a size it could have handled if it were still
supplying Dement under the contract, the district court did not err in determining that
Razorback failed to create a genuine issue of fact as to its status as a lost volume
seller. See Bill’s Coal Co., 887 F.2d at 245.
Finally, Razorback contends that it is entitled to lost profits under Arkansas law
based on Capital Steel Co. v. Foster & Creighton Co., 574 S.W.2d 256 (Ark. 1978),
where the court affirmed a jury’s award of lost profits to a supplier. There are many
obstacles, however, to applying Capital Steel to this case. First, the court held that
the breaching buyer forfeited its argument that a jury instruction premised on what
is now ACA section 4-2-708(2) was “an incorrect declaration of the law” because its
objection to the instruction was not sufficiently specific. Id. at 259. Second, the
court held that what is now section 4-2-708(1) was not applicable because Capital
-10-
Appellate Case: 11-3499
Page: 10
Date Filed: 08/06/2012 Entry ID: 3939382
Steel could not have tendered actual performance. Id. Notably, Razorback did not
argue that it could not have tendered actual performance. Finally, the court held that
once the instruction on damages under section 4-2-708(2) went to the jury, it was not
outside the realm of the jury’s competence, based on the evidence presented at trial,
to find that Capital Steel “may have been in a position to make a profit on two
transactions instead of one.” See id. at 260. Here, Razorback did not provide
evidence from which a reasonable jury could conclude that Razorback was in a
similar position because it did not show that it had the capacity to complete profitably
the project for Dement plus any of the other jobs that it acquired after ending its
relationship with Dement.
We conclude that Razorback failed to supply evidence creating a fact issue
regarding whether it was a lost volume seller or whether the damages provided for
under section 4-2-708(1) were otherwise inadequate and that such evidence was
necessary for Razorback to show successfully that lost profits under section 4-2708(2) were potentially appropriate. Therefore, the district court did not err by
granting partial summary judgment to Dement on Razorback’s claim for lost profits
under section 4-2-708(2).
III.
CONCLUSION
For the foregoing reasons, we affirm.
______________________________
-11-
Appellate Case: 11-3499
Page: 11
Date Filed: 08/06/2012 Entry ID: 3939382
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?