The City of Eufaula, Alabama et al v. Alabama Department of Transportation et al
Filing
37
OPINION. Signed by Honorable Judge Myron H. Thompson on 12/29/14. (djy, )
IN THE DISTRICT COURT OF THE UNITED STATES FOR THE
MIDDLE DISTRICT OF ALABAMA, NORTHERN DIVISION
THE CITY OF EUFAULA,
ALABAMA; EUFAULA HERITAGE
ASSOCIATION; ALABAMA TRUST
FOR HISTORIC PRESERVATION;
and NATIONAL TRUST FOR
HISTORIC PRESERVATION,
)
)
)
)
)
)
)
Plaintiffs,
)
)
v.
)
)
ALABAMA DEPARTMENT OF
)
TRANSPORTATION; JOHN R.
)
COOPER, as Director of the )
Alabama Department of
)
Transportation; FEDERAL
)
HIGHWAY ADMINISTRATION;
)
and MARK BARTLETT, as
)
Division Administrator of )
the Federal Highway
)
Administration,
)
)
Defendants.
)
CIVIL ACTION NO.
2:14cv1206-MHT
(WO)
OPINION
This case involves a challenge to the widening from
two lanes to four lanes of a road in Eufaula, Alabama’s
historic district.
The plaintiffs are the City of Eufaula and three
historic preservation groups,1 and the defendants are
the
Alabama
Department
of
Transportation
and
its
director, as well as the Federal Highway Administration
and its division administrator.2
The plaintiffs assert
that the defendants violated § 4(f) of the Department
of Transportation Act (49 U.S.C. § 303),3 § 106 of the
National Historic Preservation Act (16 U.S.C. § 470f),
and the National Environmental Policy Act, also known
as NEPA (42 U.S.C. §§ 4321 et seq.). The court has
federal-question
§ 1331.
jurisdiction
pursuant
to
28
U.S.C.
The case where is now before this court on the
plaintiffs’ motion for a temporary-restraining order.
1. The historic preservation groups are the Eufaula
Heritage
Association,
Alabama
Trust
for
Historic
Preservation, and the National Trust for Historic
Preservation.
2. The director of the Alabama Department of
Transportation is John R. Cooper.
The division
administrator of the Federal Highway Administration is
Mark Bartlett.
3. Essentially identical provisions are contained
in § 18(a) of the Federal-Aid Highway Act (23 U.S.C.
§ 138), and the plaintiffs also cite to this statute.
2
Based
on
the
evidence
and
argument
submitted
as
of
December 22, 2014, the motion will be denied.
I.
LEGAL STANDARD
In a motion for a temporary-restraining order or
preliminary injunction, the moving party must show “(1)
a substantial likelihood of success on the merits of
the
underlying
case,
(2)
the
movant
will
suffer
irreparable harm in the absence of an injunction, (3)
the harm suffered by the movant in the absence of an
injunction
would
exceed
the
harm
suffered
by
the
opposing party if the injunction issued, and (4) an
injunction
would
not
disserve
the
public
interest.”
Grizzle v. Kemp, 634 F.3d 1314, 1320 (11th Cir. 2011)
(internal quotation marks omitted).
II. BACKGROUND
This case arises out of the proposed widening of a
0.8 mile stretch of an Alabama road by the Alabama
Department of Transportation.
3
The
street
at
issue--North
Eufaula
Avenue--is
located in Eufaula, Alabama, in the southeast part of
the State.
It currently is a two-lane road running
through an historic district of town, with old houses
lining each side and a 30-50 foot median of billowing
trees that overhang the street.
The street is featured
in the Alabama Scenic Byway Program, which received
some federal funding, and is a major source of tourism
income for the city.
The
street
is
also
part
of
Highway
thoroughfare along the eastern side of
runs to the beach in Florida.
431,
a
Alabama that
Although the highway was
originally two lanes, other parts have been widened in
the
past
several
decades.
Segments
of
the
highway
north and south of Eufaula were authorized for widening
from
two
to
four
lanes
in
1981,
with
construction
taking place over the following 15 years.
Both of
those projects used federal money and complied with
federal requirements.
Overall, the federal government
has contributed $ 47 million on 57 different projects
4
for repair and widening parts of the highway in the
county
in
which
Eufaula
is
located.
Although
federal-review documents for these projects noted that
they were part of the State’s long-term plan for a
four-lane corridor through eastern Alabama, the federal
government did not fund or approve of the North Eufaula
widening in any previous review.
While much of
North
Eufaula
this highway
Avenue
remains
now has four
two
lanes,
lanes,
creating
congestion and safety concerns according to the State.
In 2005, the State first tried to solve this problem by
proposing a bypass around Eufaula.
For this bypass,
the Federal Highway Administration completed a study on
the environmental impact of the bypass and approved a
request from the Alabama Department of Transportation
to purchase real estate for the bypass.
was
never
constructed
due,
in
part,
This bypass
to
local
opposition.
Earlier this year, the State again decided to widen
the 0.8 mile stretch at issue.
5
It decided to use only
state funds on the project so that it could move “more
quickly”
and
“more
efficiently.”
The
State
began
meetings on the issue with the community starting last
spring and made a final decision sometime this fall.
The project was released for bidding on December 5,
2014, and the State signed a contract for construction
on December 10.
Several days after the project was released for
bidding, the plaintiffs brought this suit on December
8, 2014, requesting a temporary-restraining order to
prevent
the
construction
on
North
Eufaula
Avenue.
Shortly after that, the parties held an on-the-record
conference call with the court on December 9, 2014,
where the defendants agreed to delay groundbreaking for
several weeks until the parties could submit briefs and
the court could consider the arguments.
III. DISCUSSION
The defendants allege that the plaintiffs do not
meet
any
of
the
requirements
6
for
a
temporary-restraining order.
Because the court finds
that there is not a substantial likelihood of success
on the merits, it need not address the other elements.
The crux of the plaintiffs’ argument is that the
Alabama Department of Transportation and the Federal
Highway Administration violated federal law by failing
to follow procedural protections required under NEPA,
the
National
Department
federal
of
Historic
Preservation
Transportation
governments
respond
Act.
Act,
The
that
and
the
state
and
these
federal
protections do not apply because the widening project
at issue was never a federal project and thus did not
have to meet federal requirements.
NEPA’s
procedural
protections
apply
to
“major
Federal actions significantly affecting the quality of
the
human
Federal
environment
regulations
....”
elaborate
42
U.S.C.
that,
§ 4332(C).
“Major
Federal
action includes actions with effects that may be major
and which are potentially subject to Federal control
and responsibility.”
40 C.F.R. § 1508.18.
7
They can
“include
new
projects
and
and
continuing
programs
activities,
entirely
or
including
partly
financed,
assisted, conducted, regulated, or approved by federal
agencies.”
40
C.F.R.
§ 1508.18(a).
As
40
C.F.R
§ 1508.18 makes clear, “major federal actions need not
be federally funded to invoke NEPA requirements.”
Sw.
Williamson Cnty. Cmty. Ass’n, Inc. v. Slater, 243 F.3d
270, 279 (6th Cir. 2001) (cases cited).
“In effect,
major federal action means that the federal government
has actual power to control the project.” Ross v. Fed.
Highway Admin., 162 F.3d 1046, 1051 (10th Cir. 1998)
(internal quotation marks omitted).
Particularly in cases where the project at issue is
not
federally
funded,
“[n]o
litmus
test
exists
determine what constitutes major Federal action.”
to
Save
Barton Creek Ass’n v. Fed. Highway Admin. (FHWA), 950
F.2d 1129, 1134 (5th Cir. 1992) (internal quotation
marks omitted); see also Ross, 162 F.3d at 1053 (“We do
not,
however,
define
the
precise
point
at
which
a
federal project becomes immutably federal for purposes
8
of NEPA compliance.”).
“situation-specific
and
Rather, the test requires a
fact-intensive
analysis.”
Slater, 243 F.3d at 281.4
This fact-intensive analysis often comes down to a
framing exercise.
In such cases, the plaintiffs will
claim that the road in question--which is only using
state
funds--has
been
“federalized”
because
it
is
actually part of a much larger project that the federal
government has helped plan, execute, and fund.
The
States, on the other hand, will contend that the road
constitutes
a
discrete
entity,
separate
from
other
state roads that took federal money or accepted federal
help.
Although case law takes this framing exercise on
a case-by-case basis, this court can discern several
4. All parties agree that the “major federal
action” test under NEPA can also be used to evaluate
whether the protections in the National Historic
Preservation Act and the Department of Transportation
Act are triggered. Pl. Supp. Br. in Support of Mot. for
TRO and/or Prelim. Inj. (doc. no. 34) at 3 n.3; State
Def. Opp. to Pl. Request for Inj. Relief (doc. no. 35)
at 17; Fed. Def. Mem. in Opp. to Pl. Mot. for a TRO or
Prelim. Inj. (doc. no. 36) at 8-10.
9
circumstantial factors that indicate which frame is the
correct one.
First, courts look to pretext--that is, whether a
State labels something as a purely state project after
facing
federal
study.
rejection
in
the
environmental-impact
In Ross, for example, the Kansas Department of
Transportation was completing a road through a major
city.
162 F.3d at 1048-53.
It asked the federal
government to segment the project into four pieces and
submitted
environmental-impact
While
Highway
the
statements
Administration
for
each.
the
first
approved
three legs, there was deadlock on the environmental
impact of the fourth segment.
Out of frustration, the
state government declared that the last leg would be a
state
project
After
a
and
challenge,
proceeded
the
towards
court
halted
construction.
the
State’s
construction, holding that the State cannot “withdraw a
portion
of
consideration
the
with
project
the
from
resulting
federal
of
avoiding
compliance with federal environmental laws.”
Id. at
10
effect
funding
1053; see also Scottsdale Mall v. Indiana, 549 F.2d
484,
487-89
(7th
Cir.
1977)
(rejecting
a
State’s
argument that a segment of a proposed bypass was not a
major
federal
action
where
the
State
submitted
an
environmental-impact statement, the federal government
approved
and
attempted
to
then
backtracked,
continue
the
and
project
the
using
State
only
then
state
funds); but see Slater, 243 F.3d at 284 n.14 (finding
the project was not a major federal action even though
the State had previously applied for federal interstate
status but then withdrew the application because it did
not want to comply with NEPA).
Pretext in cases like
Scottsdale Mall and Ross is a strong indicator of a
major federal action because the State’s submission of
an impact study to get federal funds for a part of a
project comes close to an admission that even the State
sees the project as federal in character.
Pretext is not present in this case.
Alabama did
not apply for federal funds and then decide against
using
them
once
the
federal
11
government
expressed
reservations about its environmental-impact statement.
Unlike
Ross
and
Scottsdale
Mall,
the
State
never
submitted statements to the federal government or asked
for
federal
funds
for
this
portion
of
the
highway.
Admittedly, the State’s explanations that it did not
want to get involved in the federal process do suggest
it
wanted
to
avoid
federal-environmental
standards.
However, a State is free to build a road using its own
funds under state requirements.
(“The
authorization
of
the
23 U.S.C. § 145(a)
appropriation
of
Federal
funds or their availability for expenditure under this
chapter
shall
in
no
way
infringe
on
the
sovereign
rights of the States to determine which projects shall
be federally financed.”).
The pretext problem arises
only when States obviously tip their hand that they
believe
a
road
is
part
of
a
federal
project
by
submitting an environmental impact statement and then
insist it is a state project after failing the federal
standards.
12
Second,
indicator
of
while
a
pretext
major
might
federal
be
action,
the
the
simplest
degree
of
federal involvement in a project is the most common.
The federal government can be involved in a number of
stages in a highway-development project including “the
programming, location, design, preliminary engineering,
and right of way acquisition stages.”
Scottsdale Mall,
549 F.2d at 489. For example, in Scottsdale Mall, the
court found a segment of a larger project was a major
federal action when the federal government approved the
design plans, spent over $ 150,000 for an engineering
study on the segment, and was scheduled to be acquired
using federal money.
549 F.2d at 487-89; see also
Slater, 243 F.3d at 275 n.6, 281-86 (finding that a
road was not a major federal action even though the
federal government approved places where the new road
would
cross
federal
highways
and
funded
planning
programs on the traffic in the area as well as an air
quality study); Ross, 162 F.3d at 1048 (noting that
“local, state and federal officials began planning the
13
trafficway
as
a
jointly
funded
federal-aid
highway
project”) Thompson v. Fugate, 347 F. Supp. 120, 123-24
(E.D.
Va.
1972)
(Merhige,
J.)
(concluding
that
a
segment of a bypass around Richmond was a major federal
project,
in
part,
because
the
federal
government
approved the location of the entire bypass).
Here, the federal government did not approve the
location, conduct an engineering study, plan with the
State, or exercise other forms of control over the 0.8
mile stretch.
Similar to Slater, it did fund small
projects, such as the Alabama Scenic Byway Program, but
funding
a
small
tourist
federal
government
program
control.
does
The
not
lack
equate
of
to
federal
involvement on this stretch weighs against this being a
major federal action.
As the plaintiffs point out, however, the federal
government
did
potential bypass
fund
an
environmental
study
of
a
around Eufaula about a decade ago.
The bypass would have served at least one of the same
purposes as the widening of North Eufaula Avenue--to
14
decrease congestion and improve safety on the highway.
Contrary
to
the
defendants’
arguments,
the
court
believes this bypass is relevant to show some federal
involvement.
funds
for
Indeed, if a State proposed using federal
a
project,
environmental-impact
received
study,
and
then
a
negative
simply
proposed
building a new road, ten feet away, with only state
money,
it
likely
would
be
a
major
That, though, is not the case here.
federal
action.
The State proposed
the bypass ten years ago, and it was defeated because
of
local
opposition
environmental
rather
impact.
than
Just
concerns
because
the
over
the
federal
government once offered to fund a segment of a highway
does not mean that an alternative plan, proposed ten
years
later,
especially
constitutes
when
there
a
is
major
minimal
federal
action,
federal-government
involvement in the new plan.
The third, and final, factor is whether the segment
at issue forms part of a larger coherent project.
A
coherent project could be based on the type of project,
15
such as building a major bypass around a city.
See
Scottsdale Mall, 549 F.2d at 486; Fugate, 347 F. Supp.
at 122-24.
It could be based on direct funding for the
entire project from the federal government.
162
F.3d
at
1052
(noting
that
the
See Ross,
entire
project,
including the segment at issue, was funded by a single
grant from Congress as a demonstration project).
it
could
projects
be
based
are
on
how
designed
or
close
in
time
approved.
Or,
different
See,
e.g.,
Scottsdale Mall, 549 F.2d at 486 (all parts of the
bypass were planned at the same time even though the
construction of the segment at issue faced a seven to
eight year delay due the environmental impact study);
Fugate, 347 F. Supp. at 123 (segments approved within a
two-year
period).
The
underlying
idea
is
that
the
project was conceptualized as a single unit rather than
a series of discrete projects.
Based on the current evidence, this factor does not
support
granting
plaintiffs.
the
relief
requested
by
the
The widening of Highway 431 does have some
16
features of a coherent plan. On earlier projects the
federal government funded along Highway 431, federal
reviews noted that the widening was part of a larger
project for a four-lane corridor along the eastern part
of Alabama down to the beach in Florida.
The federal
government contributed funds to widen the highway north
of Eufaula in the 1960s and 1990s and south of Eufaula
in the 1960s, 1980s, and early 1990s.
$ 50
million
over
four
decades
It spent around
on
widening
repairing the highways in Eufaula’s county.
and
At the
same time, this project is more discrete than those
found to be major federal projects in other cases.
It
did not receive a single source of funding at one time,
but has been funded in parts.
These discrete parts
have also occurred over nearly four decades rather than
within a short time span. It is also not a bypass or a
wholly
new
project,
but
rather
improvements
on
an
existing road.
Weighing
convinced
these
this
0.8
three
mile
factors,
stretch
17
the
is
a
court
is
not
major
federal
project. There is no evidence of pretext by the State
nor has there been federal involvement at any point
over this project.
that
the
widening
Although there are some indications
of
Highway
431
was
a
coherent
project, others indicators, including the four decade
time span, suggest otherwise.
Taken together, these
factors do not show that the federal government has
“actual power to control the project.” Ross, 162 F.3d
at 1051 (internal quotation marks omitted).
The
plaintiffs
also
contend
that
to
allow
this
project to go forward would present an impermissible
fait accompli.
Even if the federal government does not
have control over the project, the plaintiffs argue,
the project becomes a major federal action because it
“restrict[s] or limit[s] the federal decision-makers’
choice of reasonable alternatives when granting federal
approvals for highway construction.”
at 281-82.
Slater, 243 F.3d
The concern in cases applying this theory
is that a federal agency might face such a degree of
public pressure from a state-sponsored building project
18
already underway that it cannot make a reasoned and
independent decision on the federal proposal.
280-81 (collecting cases).
Id. at
For example, in Maryland
Conservation Council, Inc. v. Gilchrist, 808 F.2d 1039,
1041 (4th Cir. 1986), Maryland wanted to build a new
highway running through a state park with federal money
although
an
environmental-protection
organization
argued that upgrading existing highways would serve the
same purpose and limit any impact.
Before the federal
government
study,
completed
its
impact
the
State
allowed construction on the new highway on either side
of
the
state
government
park
to
to
approve
put
pressure
the
on
project.
the
federal
After
the
environmental organization moved for an injunction, the
Gilchrist
federal
court
action
found
and
that
granted
the
the
highway
was
injunction,
a
major
holding
that, “Nonfederal actors may not be permitted to evade
NEPA by completing a project without an [impact study]
and then presenting the responsible federal agency with
a fait accompli.”
Id. at 1042.
19
The plaintiffs contend that allowing the State to
widen
North
government
Eufaula
in
a
Avenue
similar
would
situation
put
as
the
in
federal
Gilchrist
because it would have “no alternative means to connect
the existing four lane termini of U.S. 431 through a
project
that
is
less
otherwise preferable.”
7.
environmentally
damaging
or
Pl. Supp. Br. (doc. no. 34) at
The court is not persuaded.
The theory articulated
in Gilchrist applies when a project is up for approval
by a federal agency and a state or city government
attempts to influence the result through speeding up
construction and spending a lot of money on other parts
of
the
project
that
will
be
proverbial
“roads
to
nowhere” should the federal government deny approval.
Unlike Gilchrist, the question in this case is whether
any federal agency has to grant approval for the state
project.
government
The State is not arguing that the federal
should
approve
its
widening
project;
instead, it is contending that the federal government
20
has no role to play at all.5
North
Eufaula
project,
the
Avenue
is
plaintiffs
Because the widening of
likely
do
not
not
a
have
major
a
federal
substantial
likelihood of succeeding on the merits.
***
The
States
court
should
is
sympathetic
not
be
environmental regulation.
able
to
concerns
to
skirt
that
the
federal
Nevertheless, a State can
choose to use state funds to improve a road, even if
the reason is that the State has less regard for the
environment in relation to development.
Under federal
5.
Because the court finds that there is not a
major federal action, it need not decide whether there
has
been
improper
segmentation
by
the
federal
government. See Barton Creek, 950 F.2d at 1139
(collecting cases); Macht v. Skinner, 916 F.2d 13, 16
n.4 (D.C. Cir. 1990) (“Unless a project involves a
major federal action, NEPA does not apply.
The
segmentation cases are distinguishable because they
involve the question of whether a federal project has
been illegally segmented to avoid compliance with
NEPA.”) (emphasis in original), abrogated on other
grounds by Karst Envtl. Educ. & Prot., Inc. v. E.P.A.,
475 F.3d 1291, 1297 (D.C. Cir. 2007).
21
law, a problem arises only if the State takes advantage
of federal planning, expertise, or money and then tries
to avoid federal requirements.
That does not appear to
be the case here.
Also, the plaintiffs present a strong argument that
this
historic
area
should
not
be
put
in
jeopardy.
However, in view of the fact that this is not a federal
project, this is a local concern.
It should thus be
resolved at the local level--that is, between the State
of Alabama and the City of Eufaula.
An appropriate order will be entered separately.
DONE, this the 29th day of December, 2014.
/s/ Myron H. Thompson___
UNITED STATES DISTRICT JUDGE
22
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?