The City of Eufaula, Alabama et al v. Alabama Department of Transportation et al
Filing
50
OPINION. Signed by Honorable Judge Myron H. Thompson on 1/29/2015. (dmn, )
IN THE DISTRICT COURT OF THE UNITED STATES FOR THE
MIDDLE DISTRICT OF ALABAMA, NORTHERN DIVISION
EUFAULA HERITAGE
ASSOCIATION, et al.,
)
)
)
)
)
)
)
)
)
)
)
Plaintiffs,
v.
ALABAMA DEPARTMENT OF
TRANSPORTATION, et al.,
Defendants.
CIVIL ACTION NO.
2:14cv1206-MHT
(WO)
OPINION
Previously,
the
court
denied
a
motion
for
a
temporary-restraining order (TRO) to stop the widening
of a road, from two to four lanes, in the historic
district of the City of Eufaula, Alabama.
City of
Eufaula, Ala. v. Alabama Dep’t of Transp., --- F. Supp.
3d
----,
2014
WL
(Thompson, J.).
7369783,
at
*1
(M.D.
Ala.
2014)
This case is now before the court on
two other motions: a motion for preliminary injunction
and an alternative motion for
appeal.
As
injunction,
which
an injunction pending
explained
below,
seeks
same
the
the
relief
preliminary
as
the
TRO
motion
did,
will
be
denied
as
will
the
motion
for
injunction pending appeal.
I.
The
plaintiffs
BACKGROUND
are
three
historic-preservation
groups,1 and the defendants are the Alabama Department
of
Transportation
Federal
Highway
administrator.2
defendants
and
its
director,
Administration
The
violated
§
plaintiffs
4(f)
of
and
as
well
its
assert
the
as
the
division
that
Department
the
of
Transportation Act (49 U.S.C. § 303),3 § 106 of the
National Historic Preservation Act (16 U.S.C. § 470f),
1. The historic preservation groups are the Eufaula
Heritage
Association,
Alabama
Trust
for
Historic
Preservation, and the National Trust for Historic
Preservation.
The City of Eufaula was originally a
plaintiff as well, but is no longer a party to the
case.
2. The director of the Alabama Department of
Transportation is John R. Cooper.
The division
administrator of the Federal Highway Administration is
Mark Bartlett.
3. Essentially identical provisions are contained
in § 18(a) of the Federal-Aid Highway Act, 23 U.S.C.
§ 138, and the plaintiffs also cite to this statute.
2
and the National Environmental Policy Act, also known
as “NEPA” (42 U.S.C. §§ 4321 et seq.).
The court has
federal-question
to
jurisdiction
pursuant
28
U.S.C.
§ 1331.
This case arises out of the proposed widening of a
0.8-mile
stretch
Department
of
here--North
Alabama.
of
an
Alabama
Transportation.
Eufaula
road
The
Avenue--is
by
the
street
located
in
Alabama
at
issue
Eufaula,
It currently has two lanes and runs through a
historic district, with old houses lining each side and
a 30-50 foot median of billowing trees that overhang
the street.
The street is featured in the Alabama
Scenic
Program,
Byway
which
received
some
federal
funding, and is a major source of tourism income for
the city.
In addition, the State received a federal
grant for landscaping the street in the early 1990s and
for repaving in the last five years.
The
street
is
also
part
of
Highway
431,
a
thoroughfare along the eastern side of Alabama that
runs to the beach in Florida.
Although the highway was
originally two lanes, other parts have been widened in
3
the past several decades.
The segments of the highway
north and south of Eufaula were authorized for widening
from two to four lanes from the 1960s to the mid-1990s,
with
construction
period.
complied
taking
place
throughout
this
time
Both of those projects used federal money and
with
federal
requirements.
Overall,
the
federal government has contributed $ 47 million on 57
different projects for repair and widening parts of the
highway
Although
in
the
county
federal-review
in
which
documents
Eufaula
for
is
located.
these
projects
noted that they were part of the State’s long-term plan
for a four-lane corridor through eastern Alabama, the
federal government did not fund or approve of the North
Eufaula widening in any previous review.
While much of this highway is now four lanes, North
Eufaula Avenue remains two lanes, creating congestion
and safety concerns, according to the State.
In 2005,
the State tried to solve this problem by proposing a
6.8-mile
bypass
around
Eufaula.
The
bypass
was
estimated to cost somewhere between $ 40 million and
$ 120
million
and
to
take
4
around
three
years
for
construction.4
For this bypass, the Federal Highway
Administration completed a study on the environmental
impact of the bypass and approved a request from the
Alabama Department of Transportation to purchase real
estate
for
the
bypass.
After
the
federal
study,
4. In a 2014 presentation, the Alabama Department
of Transportation stated that the current estimated
cost for the bypass was $ 120 million.
See “US 431
Eufaula, Alabama” Presentation (doc. no. 3-18) at 2.
However, the environmental assessment submitted to the
federal government when the bypass was being considered
estimated that the “proposed improvements” would cost
$ 41.8 million. See Environmental Assessment (doc. no.
36-2) at 4. The reason for this large discrepancy is
unclear, as inflation likely does not account for the
300 % increase in costs. As to construction time, the
State contends that the bypass “would not be available
for use for another 10-15 years.” State Def. Opp. to
Prel. Inj. and Request for Inj. Pending Appeal (doc.
no. 45) at 7.
However, the environmental assessment
estimated that “project construction will last for
approximately 30-40 months.” Environmental Assessment
(doc. no. 36-2) at 21. Perhaps “project construction”
does not include the time it would take to acquire the
necessary land, but again the court is unsure how to
reconcile
the
three-year
time
frame
in
the
environmental assessment with the 10-15 year estimate
presented to the court now.
5
however,
the
Department
withdrew
the
bypass
project
primarily based on cost concerns.5
Almost a decade later and earlier this year, the
State decided to address the problem by widening North
Eufaula.
It decided to use only state funds on the
project so that it could move “more quickly” and “more
efficiently.”
with
the
The State began meetings on the issue
community
starting
last
final decision sometime this fall.
spring
and
made
a
The project was
released for bidding on December 5, 2014, and the State
signed a contract for construction on December 10.
The
5. In its earlier opinion, the court stated that
“the bypass was never constructed due, in part, to
local
opposition.”
Eufaula,
--F.
Supp.
3d
at ----, 2014 WL 7369783, at *2.
As the plaintiffs
point
out,
that
characterization
was
incorrect.
Although the Transportation Department has noted that
the bypass “was very unpopular due to traffic bypassing
the business district” and noise concerns, “US 431
Eufaula, Alabama” Presentation (doc. no. 3-18) at 2, it
has
definitively
stated
that
“[d]ue
to
funding
limitations project work ceased.” Id. Moreover, after
the Transportation Department withdrew the project, the
Eufaula City Council still supported it.
See Eufaula
City Council Resolution 13-2005 (doc. no. 40-1) at 1.
6
Transportation
Department
estimates
that
the
project
will cost slightly more than one million dollars.
Several days after the project was released for
bidding, the plaintiffs brought this suit, requesting a
TRO
or,
prevent
alternatively,
the
a
preliminary
construction
on
North
injunction
Eufaula
to
Avenue.
After briefing from both sides, the court denied the
motion for a TRO.
Eufaula, --- F. Supp. 3d at --, 2014
WL 7369783, at *1.
motion
for
a
alternative,
The plaintiffs now renew their
preliminary
request
an
injunction
injunction
or,
pending
in
the
appeal.
These motions are now before the court.
II. DISCUSSION
The
court
will
first
address
the
motion
for
a
preliminary injunction and then move to the motion for
injunction pending appeal.
A. Motion for Preliminary Injunction
In
a
motion
for
a
preliminary
injunction,
the
moving party must show “(1) a substantial likelihood of
7
success on the merits of the underlying case, (2) the
movant will suffer irreparable harm in the absence of
an injunction, (3) the harm suffered by the movant in
the
absence
suffered
of
by
an
the
injunction
opposing
would
party
exceed
if
the
the
harm
injunction
issued, and (4) an injunction would not disserve the
public interest.”
Grizzle v. Kemp, 634 F.3d 1314, 1320
(11th Cir. 2011) (internal quotation marks omitted).
The defendants allege that the plaintiffs do not
meet
any
injunction.
of
the
requirements
for
a
preliminary
For the same reasons articulated in the
TRO opinion, the plaintiffs have failed to demonstrate
a substantial likelihood of success on the merits, and
the court therefore denies the motion for a preliminary
injunction.
Although the court stands on its earlier
reasoning--and
conjunction
several
that
with
additional
this
opinion
should
one--the
issues.
court
First,
it
be
read
will
in
address
briefly
will
address the Federal Highway Administration’s argument
that
the
court
should
have
denied
relief
on
jurisdictional grounds before reaching its three-factor
8
analysis.
issues
Next, the court will turn to the following
raised
by
the
plaintiffs:
whether
the
court
should have applied segmentation analysis; whether the
court’s pretext analysis was too narrow; whether the
court should have held that the bypass was a functional
equivalent of the current widening and therefore the
widening
was
a
major
federal
action;
and
finally
whether the court underestimated the federal role in
the widening of North Eufaula Avenue.
The court will
take each argument in turn.
i.
Jurisdiction
Although it agrees with the court’s conclusion on
the TRO, the Highway Administration argues that the
court erred in its legal approach by proceeding to its
three-factor
analysis
even
though
there
was
no
federal-agency action.
The court does not understand the Administration’s
argument.
The court agrees that it lacks jurisdiction
if
is
there
three-factor
no
federal-agency
analysis
was
9
the
action.
court’s
But
the
method
for
determining whether federal-agency action existed--that
is, whether the 0.8-mile stretch that used state funds
was ‘federalized’ due to related federal work on the
same
highway.6
invites
the
Put
court
to
differently,
the
Administration
presuppose
the
answer
engaging in the analysis.
before
The court declines such an
invitation.7
6. All of the cases cited by the Highway
Administration engage in this same analysis.
See
Rattlesnake Coal. v. U.S. E.P.A., 509 F.3d 1095, 1101
(9th Cir. 2007) (determining whether level of federal
involvement
in
local
project
gave
the
federal
decision-makers power or control over the project);
Coal. for Underground Expansion v. Mineta, 333 F.3d
193, 196 (D.C. Cir. 2003) (analyzing whether future
federal funding “federalizes” a city’s metro system
built with solely state funds); Pres. Pittsburgh v.
Conturo, 2011 WL 4025731, at *5 (W.D. Pa. 2011)
(Cercone, J.) (holding that there was “not requisite
involvement in the project by a federal agency” to
require an impact statement).
7.
To the extent that the defendants are arguing
that the lack of federal planning or funding is
dispositive, the court rejects this rigid test as well.
Granted, the court does give weight to the fact that
both the federal and state governments viewed this as a
local, rather than federal, issue as well as to the
Highway Administration’s interpretation of its own
regulations as applied to this case.
(continued...)
10
ii. Segmentation Analysis
The plaintiffs argue that the court should have
applied
segmentation
analysis
three-factor analysis.
in
addition
to
the
The court disagrees.
As discussed in the TRO opinion, NEPA procedural
protections
apply
significantly
to
“major
affecting
environment....”
the
Federal
quality
of
actions
the
human
42 U.S.C. § 4332(c).
The question is
how to define “major federal action.”
In the earlier
opinion,
the
court
used
three
factors
to
evaluate
whether there was enough federal involvement for the
project
to
be
a
major
federal
action.
It
concluded
there was no federal action and that NEPA, therefore,
Nevertheless,
courts
must
still
be
wary
of
situations where the federal government may turn a
blind eye to federal projects or where States evade
federal standards. Other circumstantial evidence can
uncover these scenarios.
For example, a State could
tacitly admit a project is a major federal action by
submitting an environmental impact statement, even if
the federal government does not act on it.
Or, as
discussed
below,
a
State
could
build
a
functional-equivalent
to
an
acknowledged
federal
project to avoid addressing environmental concerns.
While neither of these scenarios is the case here, the
court refuses to endorse a bright-line rule that would
allow States to evade federal regulations.
11
did not apply.
Eufaula, --- F. Supp. 3d. at ----, 2014
WL 7369783, at *6.
The plaintiffs argue that the court
erred by failing to use segmentation analysis as an
alternative
actually
test
a
for
major
segmentation
test
whether
federal
might
a
state
action.
be
a
project
Although
helpful
proxy
in
is
the
some
cases for determining the level of federal involvement,
the court affirms its position that segmentation is not
a
required
test
for
determining
whether
there
is
a
major federal action.
Federal
regulations
note
that,
“Major
Federal
action includes actions with effects that may be major
and which are potentially subject to Federal control
and
responsibility.”
discussed
action
can
in
the
exist
federal funding.
40
earlier
even
C.F.R.
opinion,
where
a
§ 1508.18.
a
State
major
does
As
federal
not
use
Eufaula, --- F. Supp. 3d at ----,
2014 WL 7369783, at *2.
This brings up the question in
dispute here: What can a district court look to in
order to determine whether something is a major federal
12
action, when the presence of federal funding does not
serve as an easy signal?
The animating concern underlying this question is
that a State might use federal resources for a project
and
then
avoid
the
accompanying
federal
rules
by
reclassifying a part of the project that might not pass
muster under those rules.
also
concerned
that
Correlatively, the court is
the
federal
government
might
improperly allow the State to do this.
Although there is no “litmus test” to address this
concern,
the
court
identified
three
circumstantial
factors that help reach the underlying question: the
presence of pretext, the degree of federal involvement,
and whether the project was part of a larger, coherent
project.
Id. at *3-*5.
After analyzing these factors,
the court determined that the widening of North Eufaula
Avenue was not a major federal action.
The
plaintiffs
insist,
however,
Id.
that
the
court
should not have stopped with that analysis and instead
was
required
to
apply
an
13
alternative
‘segmentation
test’ that the plaintiffs take from NEPA implementing
regulations.
This segmentation test states:
“In
order
to
ensure
meaningful
evaluation of alternatives and to
avoid commitments to transportation
improvements before they are fully
evaluated, the action evaluated in
each [environmental impact statement]
or finding of no significant impact
(FONSI) shall:
(1) Connect logical termini and be of
sufficient
length
to
address
environmental
matters
on
a
broad
scope;
(2)
Have
independent
utility
or
independent
significance,
i.e.,
be
usable and be a reasonable expenditure
even if no additional transportation
improvements in the area are made; and
(3) Not restrict
alternatives
for
foreseeable
improvements.”
23 C.F.R. § 771.111.
consideration of
other
reasonably
transportation
The Courts of Appeals are split
on whether this test should be applied in this context.
Compare Save Barton Creek Ass’n v. Fed. Highway Admin.
(FHWA),
950
F.2d
(noting
that,
action,
these
1129,
“absent
1140
a
[§ 771.111]
n.15
finding
criteria
14
(5th
of
do
Cir.
major
not
1992)
federal
apply.”);
Macht v. Skinner, 916 F.2d 13, 16 n.4 (D.C. Cir. 1990)
(“Because we hold that the Light Rail Project does not
involve
‘major
whether
the
Maryland's
federal
district
action,’
court
segmentation
of
we
do
not
correctly
the
Project
decide
held
was
that
proper.
Unless a project involves major federal action, NEPA
does
not
apply.
The
segmentation
cases
are
distinguishable because they involve the question of
whether a federal project has been illegally segmented
to avoid compliance with NEPA.”8), abrogated on other
grounds by Karst Envtl. Educ. & Prot., Inc. v. E.P.A.,
475
F.3d
1291,
1297
(D.C.
Cir.
2007),
with
Sw.
Williamson Cnty. Cmty. Ass'n, Inc. v. Slater, 243 F.3d
270,
286
n.17
‘segmentation
(6th
test’
Cir.
was
2001)
an
(noting
alternative
that
test
the
to
determine whether something is a major federal action);
8. The plaintiffs contend that Macht, when read in
context, does not preclude the use of the segmentation
test to determine whether something is a federal
project.
The language, however, seems clear that the
segmentation test is a different test that occurs only
after a court has determined whether a project is a
major federal action.
15
Vill. of Los Ranchos de Albuquerque v. Barnhart, 906
F.2d 1477, 1482 (10th Cir. 1990) (using segmentation
test in addition to degree of federal involvement to
determine whether project was a major federal action).
The Eleventh Circuit has yet to rule on this issue.
This court agrees with the Fifth and D.C. Circuits
that
the
segmentation
test
is
required
only
if
court already has found a major federal action.
the
The
court reaches this conclusion for two main reasons.
First, the plain language of § 771.111 suggests that
segmentation is a test for federal agencies to ensure
they
conduct
a
“meaningful”
and
“full[]”
evaluation
after they have authority and control over a project
rather than a test to establish their authority and
control requiring an evaluation in the first place. In
other
words,
without
the
requisite
authority
and
control for a major federal action, there is no project
for the federal government to segment, and, “[i]f there
has been no segmentation, there, a fortiori, can have
been no unlawful segmentation.” Brewery Dist. Soc’y v.
16
Fed. Highway Admin., 221 F. Supp. 2d 902, 914 (S.D.
Ohio 2002) (Marbley, J.).
Second, the segmentation test does not reach the
heart of the issue of whether there is enough federal
involvement
to
control
responsibility
or
establish
the
potential
over
a
for
project.
federal
See
40
C.F.R. § 1508.18 (specifically defining major federal
action). None of the three factors in the segmentation
test
addresses
whether
there
was
federal
planning,
help, or money involved in a project. Although courts
could
use
the
circumstantial
‘segmentation
factor,
the
test’
test
does
as
another
not--on
its
own--indicate levels of federal control as required by
the definition of major federal action.
Third, the plaintiffs insist that the court must
use the segmentation test, but they do not state why it
must be used; they merely note that some other courts,
outside the Eleventh Circuit, have employed it.
The
court is not convinced that § 771.111 was meant to lay
out
a
mandatory
test
for
17
the
question
of
whether
something is a major federal action, and is not bound
to use the test under precedent.
Moreover, even if the
court were to
apply the
§ 771.111 segmentation test, the test weighs against
granting the plaintiffs relief.
whether
the
project
The first factor is
connects
“logical
termini.”
However, “where the highway segments in question, are
not running between cities, but rather running through
one city, logical termini are not so easily determined
by
a
court.”
Moreland,
637
Piedmont
F.2d
430,
Heights
440
Civic
(5th
Club,
Cir.
Unit
Inc.
B
v.
Feb.
1981).9 Instead, as the plaintiffs suggest, “[t]he more
important inquiry in such a situation is whether the
projects have independent utility.”
Id.
As such, the
court turns to independent utility.
9. The Eleventh Circuit has adopted as precedent
all decisions of the former Fifth Circuit rendered
prior to October 1, 1981, and all Former Fifth Circuit
Unit B and non-unit decisions rendered after October 1,
1981. See Stein v. Reynolds Secur., Inc., 667 F.2d 33,
34 (11th Cir. 1982); Bonner v. City of Prichard, 661
F.2d 1206, 1207 (11th Cir. 1981) (en banc).
18
The plaintiffs argue that there is no independent
utility because the widening of North Eufaula merely
facilitates
However,
highway
movement
compelled
“it
traffic
is
the
inherent
network
in
along
that
many
in
each
no
the
very
segment
others;
aggregation,
Highway
if
such
project
enjoy independent utility.”
431
corridor.
concept
will
be
benefits
said
inquiry
is
to
Coal. on Sensible Transp.,
Inc. v. Dole, 826 F.2d 60, 69 (D.C. Cir. 1987).
correct
a
facilitate
mutual
could
of
whether
the
“project
The
serves
a
significant purpose even if the other related projects,
the other segments, are not built for a long time or
perhaps not at all.”
Save Barton Creek, 950 F.2d at
1141.
Here, the widening of North Eufaula Avenue serves
an independent purpose. It alleviates safety problems
for
motorists
Furthermore,
undertaking
and
the
the
emergency-response
Transportation
North
Eufaula
vehicles.
Department
widening
project
is
more
than a decade after the major widening projects to its
north and south.
The fact that the Eufaula widening
19
was
“not
projects
built
suggests
for
a
that
long
the
time”
three
after
the
projects,
other
although
related, served independent purposes at the time the
State decided to construct them.
See Piedmont Heights,
637 F.2d at 441.
Last, the plaintiffs contend that the project would
“restrict
consideration
reasonably
foreseeable
because
would
it
make
of
alternatives
transportation
federal
for
other
improvements”
involvement
in
other
related projects, such as the bypass, irrelevant.
23
C.F.R.
As
§ 771.111(f)(3).
The
court
disagrees.
explained in detail below, the bypass and the widening
of North Eufaula are vastly different projects in terms
of their cost and timeframe for completion.
Committing
one million dollars to the widening of North Eufaula
does
not
foreclose
the
construction
of
a
65-mile-per-hour bypass in the future.10
10. To the extent that the plaintiffs contend that
the North Eufaula widening restricts consideration of
alternatives by presenting a fait accompli to the
Highway
Administration,
the
court
considered
and
rejected that argument in its previous opinion.
See
(continued...)
20
In sum, the court holds that the segmentation test
is not required by law and of little help in this case.
Moreover,
even
if
the
test
were
required,
the
plaintiffs still would not meet their burden of proving
a substantial likelihood of success on the merits.
iii. Pretext
The plaintiffs next argue that the court’s test for
pretext is too narrow.
Specifically, the court defined
pretext in its TRO opinion as when a State submits an
impact study to the federal government, later withdraws
the
study
out
of
concern
it
will
fail
federal
standards, and then claims it will use only state money
for a purely state project. See Eufaula, --- F. Supp.
3d at ----, 2014 WL 7369783, at *3.
The plaintiffs
argue that requiring the submission of an impact study
for pretext is “bizarre [because] ... it would allow
state agencies to assert the exact same pretext that
would otherwise be unlawful, if they have the foresight
Eufaula, --- F. Supp. 3d at ----, 2014 WL 7369783, at
*5-*6.
21
to
assert
process.”
the
pretext
sufficiently
early
in
the
Pl. Mem. in Support of Mot. for Prelim. Inj.
and Request for Inj. Pending Appeal (doc. no. 40) at 5.
While
the
argument,
the
court
understands
plaintiffs
miss
with the “pretext” factor.
the
the
plaintiffs’
court’s
intention
The court’s point was that,
when a State applies for a federal impact study and
then later withdraws the application, the application
approaches
a
tacit
admission
that
the
federal
government has potential control or responsibility over
the
project,
and
the
withdrawal
of
the
application
suggests that the State may be trying to avoid federal
oversight.
The
court
was
not
implying
that
this
particular set of circumstances must be present for a
finding of a major federal action or that a State that
does not submit an impact statement can avoid scrutiny.
As with discussions of pretext in other situations, the
court lists pretext as a factor because it is an easy
sign that something is amiss.
However, just as the
absence of a racial slur in a workplace does not end a
question
of
racial
discrimination,
22
the
lack
of
the
submission of an impact study does not end the question
whether the State is truly engaged in a major federal
action here. Indeed, the two other factors identified
by the court also help to ferret out whether the State
is
taking
federal
resources
without
submitting
to
federal regulation.
Further, the court does not mean to suggest that
the only way to prove pretext is to show the submission
and withdrawal of an application for a federal impact
study.
In
a
sense,
all
factors
in
the
major-federal-action test examine whether the labelling
of a project as a state, rather than federal, project
was
“pretextual.”
appropriate
label
With
for
this
this
in
court’s
mind,
“pretext”
a
more
factor
might be something akin to “tacit admission.”
iv. Bypass as Functional Equivalent
The plaintiffs next argue that, because the bypass
would
have
served
the
same
function
as
the
current
widening proposal and was planned using federal money,
23
the widening, like the bypass, should be characterized
as a federal project.
For
this
functional-equivalent
theory,
the
plaintiffs rely primarily on Brewery District Soc’y v.
Fed. Highway Admin., 211 F. Supp. 2d 902 (S.D. Ohio
2002)
(Marbley,
Columbus,
Ohio,
J.).
In
proposed
that
case,
plans
for
the
an
city
of
interchange
project, which both parties agreed was a major federal
project.
Id. at 904.
The problem, according to the
plaintiffs, was that the city withdrew a connector that
was part of this interchange and instead proposed to
use its own funds to build an alternative connector
with
the
same
purpose--but
in
a
different
location--that ran through a historic district.
904-905.11
Because
it
replaced
a
similar
Id. at
federal
project, the plaintiffs in that case claimed that the
alternative
route
should
be
subject
to
federal
11.
These
facts
were
presented
at
the
summary-judgment phase. The district court later found
that the original connector was not part of the major
federal action.
See Brewery Dist. Soc’y v. Fed.
Highway Admin., 150 Fed. App’x 502, 504 (6th Cir. 2005)
(affirming district court’s finding).
24
procedural protections
even though the city was not
using federal funds to construct this alternative.
Faced with this novel situation, the court held
that a road could be ‘federalized’ based on it being
the functional equivalent of a previous federal project
with
the
same
primary
purpose.
In
reaching
this
decision, the court first articulated two poles of this
situation:
“Considering the hypothetical example
of the City canceling [the original
segment] and then seeking to use its
own funds to construct, in the same
time-frame as was contemplated for
[the original segment], a road of
quality and dimensions identical to
[original segment], with the only
difference between the two being that
the ‘new’ road is at all points two
feet to the east of the course set for
[the
original
segment],
it
seems
apparent that de minimis alterations
to the ‘old’ federal plan cannot be
enough
to
insulate
an
otherwise
‘federalized’ project from judicial
review. At the same time, it is
obvious that the City could terminate
[the original segment] and then, ten
years down the road, use its own funds
to construct a road unrelated to [the
original
segment]
in
purpose
or
location.”
25
Id. at 916.
For the more difficult cases falling in
between these two poles, like the case before it, the
court
looked
to
the
primary
purpose,
the
levels
of
accessibility, the capacity, and the timing of the two
roads.
Id.12
12. The court elaborated:
“Where the ‘federalized’ road to be built is
not
functionally
identical
to
the
road
contemplated in the federal project, but is
designed to serve the same purpose as the road
it is replacing, is compliance with 49 U.S.C.
§ 303(a) and 16 U.S.C. § 470 required? This
Court finds, based upon the language and
purpose of those two statutes, that the answer
must be yes, with the following caveats:
1. fulfilling the role of the canceled
federal project segment must be the
primary purpose of the ‘federalized’
road (a question of fact); and
2. in order to succeed, the plaintiff
must at least establish a prima facie
case
of
‘functional
replacement,’
consisting of evidence tending to
show:
a. the termini of the ‘federalized’
road are close enough to the termini
of
the
canceled
federal
project
segment to provide similar levels of
accessibility;
(continued...)
26
As
a
threshold,
this
court
finds
the
functional-equivalent test helpful in determining the
degree
of
federal
involvement.
See
Eufaula,
Supp. 3d, at ----, 2014 WL 7369783, at *4.
the
Highway
Administration
functional-equivalent
mean meritless.
test
as
--- F.
Although
criticizes
novel,
novel
does
the
not
Indeed, the Administration would be
hard pressed to maintain that a new project occurring
“in the same time frame,” having the same “quality and
dimensions,” and having the same purpose as an original
b. the capacity of the ‘federalized’
road is approximately that of the
canceled federal project segment;
c.
the
construction
of
the
‘federalized’ road is not so remote in
time from that contemplated for the
canceled federal project segment that
it could realistically have become
necessary due to new traffic patterns;
and
d. the utility of the ‘major federal
project’ of which the canceled project
segment was a part is substantially
enhanced by the construction of the
‘federalized’ road.”
Brewery Dist. Soc'y, 211 F. Supp. 2d at 916-17.
27
federal project becomes de-federalized if moved “two
feet to the east.”
Brewery Dist. Soc’y, 211 F. Supp.
2d at 916.13 Such a position would invite States to
flaunt federal environmental regulations with an easy
loophole.
Applying the above analysis, the court finds the
widening
of
North
Eufaula
equivalent of the bypass.
is
not
the
functional
Granted, the projects are
similar in that both would ensure that traffic moves
more
quickly
and
safely
current bottleneck.
on
Highway
431
through
the
But, the similarities stop there.
13. The plaintiffs contend that the court focused
too heavily on the location of the alternate route to
the exclusion of other factors in its earlier opinion.
See Eufaula, --- F. Supp. 3d, at ----, 2014 WL 7369783,
at *4 (providing example where a State built a
replacement road to a federal project 10 feet from the
original site).
This was not the court’s intention.
As explained above, multiple factors should play into
this analysis, such as the function of the new project,
the location, and the time between the old project and
the new one.
However, the court rejects the
plaintiffs’ argument that location (and by implication,
time frame) should not be used because it would require
the court to decide on a “magic distance” or magic time
period. Courts often use standards rather than precise
rules, especially considering questions that have no
“litmus test” to reach a decision.
See Save Barton
Creek, 950 F.2d at 1134.
28
As the Alabama Transportation Department points out,
the State designed the bypass to start at the outskirts
of the city and allow motorists to drive at speeds of
around 65 miles per hour around the city.
The State
envisioned it as a multi-year project that would cost
at
least
in
the
tens
of
millions
of
dollars.
In
contrast, the widening of North Eufaula would enlarge a
road through the downtown area of Eufaula, in which
motorists
will
speed limits.
likely
be
constrained
to
much
lower
The State estimates the widening will
take several months at most and cost around one million
dollars.
These projects do not have the same time
frame, quality, dimensions, or location. Moreover, most
importantly, there has been a decade time span between
the
two
projects.
“[L]ater
replacement
construction,
locally initiated and financed [cannot] be considered a
federal project merely because it will relieve some of
the
same
have.”
congestion
that
the
[original
road]
would
Brewery Dist. Soc’y, 150 Fed. App’x at 504
(affirming
lower
court)
(internal
omitted).
29
quotation
marks
v.
Federal Role on North Eufaula Avenue
The plaintiffs last argue that this court failed to
recognize
the
extensive
federal
influence
on
the
project.
First,
they
argue
that
the
State
used
federal
government funds to widen roads to the north and south
of
Eufaula,
thereby
current route.
creating
the
bottleneck
in
the
The court addressed this argument in
the previous opinion.
Although the roads around the
0.8-mile stretch were built using federal dollars, they
were widened and approved over a series of decades.
Additionally, as discussed in the earlier opinion, the
fait
accompli
argument
does
not
apply
here.
Eufaula, --- F. Supp. 3d at ----, 2014 WL 7369783, at
*5-*6.
Second, they argue that the design of the road was
a direct consequence of the State’s having followed
federal highway standards.
Both sides agree that the
Transportation Department used the American Association
of State Highway and Transportation Officials standards
30
as guidance to designing the widening.
contend
that,
because
the
highway
is
strategic highway corridor network, it
these standards under federal law.
The plaintiffs
part
of
the
had to apply
Even if this were
true--which the State disputes--it cannot be that every
project on Highway 431 (and a large number of highways
running through the country) is federalized because it
is part of the strategic highway corridor network.
Cf.
Dec. of Mark D. Bartlett (doc. no. 36-4) at ¶¶ 7-16
(noting that the States “construct, own, operate, and
maintain
highways
without
including Highway 431).
federal
involvement,”
Indeed, a number projects on
Highway 431 previously have been completed using solely
state funds.
Dec. of Ronald L. Baldwin (doc. no. 35-1)
at ¶¶ 26-27.
Last, the plaintiffs note that the segment at issue
received federal grants for landscaping and paving in
the
last
several
scenic-byways grant.
years,
in
addition
to
the
These grants do not mean that the
project to widen the road was a federal project.
A
State can make improvements using only state funds to a
31
road originally built with federal dollars, and vice
versa.
Maintenance projects do not equate to federal
control of larger actions.
B. Motion for Injunction Pending Appeal
In
the
injunction,
event
the
the
court
plaintiffs
denies
a
an
request
preliminary
injunction
pending appeal under Federal Rule of Civil Procedure
62(c).
The rule states in relevant part:
“While an appeal is pending from an
interlocutory order or final judgment
that grants, dissolves, or denies an
injunction, the court may suspend,
modify,
restore,
or
grant
an
injunction on terms for bond or other
terms that secure the opposing party's
rights.”
Fed. R. Civ. Proc. 62(c) (emphasis added).
language
of
the
rule
requires
that
“an
The plain
appeal
is
pending”; because the plaintiffs have not filed such an
appeal, the court denies its request for an injunction
pending appeal.
Even if an appeal were pending, the court would
deny
an
injunction
pending
32
appeal.
An
injunction
pending
an
appeal
is
an
“extraordinary
remedy.”
Touchston v. McDermott, 234 F.3d 1130, 1132 (11th Cir.
2000).
Four factors inform the decision: “(1) whether
the stay applicant has made a strong showing that he is
likely
to
succeed
on
the
merits;
(2)
whether
the
applicant will be irreparably injured absent a stay;
(3) whether issuance of the stay will substantially
injure the other parties interested in the proceeding;
and
(4)
Holder,
where
556
the
U.S.
public
418,
interest
434
(2009)
lies.”
Nken
v.
(citing
Hilton
v.
Braunskill, 481 U.S. 770, 776 (1987)).14
traditional
stay
factors
contemplate
“Since the
individualized
judgments in each case, the formula cannot be reduced
to a set of rigid rules.”
Hilton, 481 U.S. at 777.
Nevertheless, “the first two factors ... are the most
14.
As the Supreme Court has noted, “[t]here is
substantial overlap between these and the factors
governing preliminary injunctions, not because the two
are one and the same, but because similar concerns
arise whenever a court order may allow or disallow
anticipated action before the legality of that action
has been conclusively determined.”
Nken, 556 U.S. at
434 (internal citations omitted). As discussed below,
the only discernable different for applying the factors
is that the stay is not as rigid a set of rules.
33
critical” and “it is not enough that the chance of
success
on
the
merits
be
better
than
negligible.”
Nken, 556 U.S. at 434; see also Veasey v. Perry, 135 S.
Ct. 9, 10 (2014) (Ginsburg, J. dissenting) (dissenting
because the court
factors
of
irreparable
strayed from its traditional stay
likelihood
harm
of
when
success
on
rejecting
the
a
merits
stay
in
and
an
election-law case).
The court would deny the injunction pending appeal
for
the
same
reason
it
now
denies
the
preliminary
injunction--the plaintiffs have not shown a likelihood
of success on the merits.
Even with the plaintiffs’
additional briefing, the court remains convinced that
“this is a local concern” rather than a federal project
and “should be resolved at the local level--that is,
between the State of Alabama and the City of Eufaula.”
Eufaula, --- F. Supp. 3d at ----, 2014 WL 7369783, at
*6.15
15.
As
to
the
other
“critical
factor”
of
irreparable harm, the court, based on the current
record, is not convinced that the plaintiffs have
(continued...)
34
***
For the foregoing reasons, the court will deny the
plaintiffs’ motions for a preliminary injunction and
injunction pending appeal. An appropriate order will be
entered.
DONE, this the 29th day of January, 2015.
/s/ Myron H. Thompson____
UNITED STATES DISTRICT JUDGE
carried the day. The plaintiffs’ experts contend that
taking three feet off of both sides of the median will
lead to a decline of tree growth and the potential
death of many of the trees. See Dec. of George Barker
(doc. no. 3-35) at ¶¶ 19-26; Dec. of Arthur Chappelka
(doc. no. 3-36) at ¶¶ 11-15. Although the defendants’
arborist agrees that some newer trees close to the curb
may die or need to be relocated, the arborist contends
that the remaining trees will fill in the open canopy
space and might actually become healthier from the
removal of some trees.
Arborist’s Report (doc. no.
35-1) at 51. The arborist also did not predict damage
to the interior trees from pruning the roots that
extent to areas of construction. Id. at 50. For the
court, this expert dispute is in equipoise on the
current record; because the plaintiffs bear the burden
of proof, the court finds that the plaintiffs would
also not meet their burden on irreparable harm.
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?