Christian et al v. Cotton States Mutual Insurance Company et al
Filing
47
MEMORANDUM OPINION. Signed by Judge L Scott Coogler on 5/29/2014. (KAM, )
FILED
2014 May-29 PM 03:52
U.S. DISTRICT COURT
N.D. OF ALABAMA
UNITED STATES DISTRICT COURT
FOR THE NORTHERN DISTRICT OF ALABAMA
WESTERN DIVISION
STANLEY R. CHRISTIAN, et al.,
Plaintiffs,
vs.
COUNTRY MUTUAL
INSURANCE COMPANY, et al.,
Defendants.
)
)
)
)
)
)
)
)
)
)
7:13-CV-0027-LSC
MEMORANDUM OF OPINION
Stanley R. Christian and his wife Nancy K. Jones-Christian (collectively,
“Plaintiffs”) brought this action against their insurance company and a group of
engineers and adjusters after their home was damaged by a tornado on April 27, 2011.
The only Defendant that remains in the action is Country Mutual Insurance Company
(“CMIC”), the successor in interest to Plaintiffs’ original home insurer, Cotton States
Mutual Insurance Company (“Cotton States”). Before the Court is CMIC’s motion
for partial summary judgment. (Doc. 36.) For the reasons stated below, the motion is
due to be granted in part and denied in part.
I. Factual Background
Plaintiffs own a home in Cottondale, Alabama, which they insured through
Page 1 of 14
CMIC.1 A tornado struck the area on April 27, 2011, damaging the home and causing
a tree to fall on the carport. Plaintiffs submitted a claim to CMIC for the damage to the
home.
After the house was damaged, Plaintiffs lived in it for about two weeks. They
used a generator during this time, and were told not to have their power turned back
on because the wires in the house had been stretched. It became unbearable to live in
the house without air conditioning. Since moving out of the house at issue, Plaintiffs
have lived in a camp house in Moundville, Alabama.
The first adjuster to examine Plaintiffs’ home was Michael Long (“Long”) of
Crawford and Company on May 2, 2011. He told Stanley Christian that the amount
of damage was greater than he was authorized to adjust. Long also told Plaintiffs that
they needed to have an engineer look at the house. Plaintiffs then retained Al Cabaniss
(“Cabaniss”), an engineer who performed an inspection on May 10, 2011. Stanley
Christian and Jeff Englebert (“Englebert”), the builder of Plaintiffs’ house, were
present for this inspection. On May 18, 2011, Brian Brady (“Brady”), a CMIC claims
representative who had been assigned to Plaintiffs’ claim, brought an engineer named
Robert Edmondson (“Edmondson”) to inspect the home. Stanley Christian testified
1
The parties use CMIC to refer to both the current defendant and its predecessor in
interest, Cotton States, and the Court will do the same.
Page 2 of 14
that Edmondson did a “pretty good job” of inspecting the house in a thorough,
professional manner. (Doc. 37-1 at 82.)
On May 20, 2011, before either Cabaniss or Edmondson issued the reports of
their inspections, Brady submitted a “Request for Authority” in the amount of
$50,000. The parties dispute the meaning of this request. Plaintiffs point out that
CMIC’s 30(b)(6) representative, Bradley McLaughlin, characterized the request as the
maximum amount that would be needed to cover Plaintiffs’ claims, regardless of the
details of the engineering report. CMIC notes, however, that McLaughlin also stated
that the request could have been resubmitted if the engineer had found that all of the
damage came from the tornado.
On May 21, 2011, Brady offered Plaintiffs the cash value of the damage to the
carport, a retaining wall, and a portion of the roof framing. Stanley Christian asked him
to delay payment until the submission of the engineering reports. Cabaniss and
Edmondson came to very different conclusions in their reports. Cabaniss believed that
the upper level house had shifted approximately two inches on the frame, and that
most of the brick and framing needed to be replaced. He concluded that it would be
more economically efficient to rebuild the house on the basement slab. Edmondson,
on the other hand, determined that much of the damage outside the carport area was
caused not by the tornado, but by settlement of the house.
Page 3 of 14
Using Edmondson’s report as a guide, CMIC issued Plaintiffs a check for
$32,302.89 on June 22, 2011. Five days later, Christian requested a reinspection.
Although CMIC sent out a new adjuster, the reinspection of the premises did not
occur until December 18, 2011. During the intervening period, Cabaniss prepared a
report that reiterated his conclusions, and Plaintiffs also hired Ron Martin (“Martin”)
to prepare a third engineer’s opinion. Martin concluded that all of the damage at issue
was caused by the tornado.
After reinspecting the house, Edmondson wrote a new report that addressed the
issues raised by Martin and Cabaniss, concluding again that the damage outside the
carport area was caused by settlement rather than wind. CMIC relied on this report
in denying coverage for this damage. Both Martin and Edmondson later issued further
reports in line with their first conclusions. The parties agree that settlement damage
is not covered by the policy.
Although some contents coverage and Alternative Living Expenses (“ALE”)
payments have been paid, the parties dispute whether further payments are due.
Plaintiffs claim additional ALE benefits incurred while living at their camp house.
CMIC contends that ALE expenses incurred after February 29, 2012 are not
reimbursable. It also argues that Plaintiffs’ failed to mitigate their damages with
respect to contents claims for items in the basement of the home. Plaintiffs have not
Page 4 of 14
repaired their home or moved back into it. Finally, Plaintiffs also seek damages for
mental anguish and distress caused by the damage to their home. Plaintiffs filed suit
in the Circuit Court of Tuscaloosa County on December 6, 2012, and Defendants
properly removed the case to this Court.
II. Standard of Review
Summary judgment is proper “if the movant shows that there is no genuine
dispute as to any material fact and the movant is entitled to judgment as a matter of
law.” Fed. R. Civ. P. 56(a). The party moving for summary judgment “always bears
the initial responsibility of informing the district court of the basis for its motion, and
identifying those portions of [the evidence] which it believes demonstrate the absence
of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986).
The movant can meet this burden by presenting evidence showing that there is no
genuine dispute of material fact, or by showing that the nonmoving party has failed to
present evidence in support of some element of its case on which it bears the ultimate
burden of proof. Celotex, 477 U.S. at 322-23. In evaluating the arguments of the
movant, the court must view the evidence in the light most favorable to the nonmoving
party. Mize v. Jefferson City Bd. of Educ., 93 F.3d 739, 742 (11th Cir. 1996).
Once the moving party has met his burden, Rule 56(e) “requires the nonmoving
party to go beyond the pleadings and by her own affidavits, or by the ‘depositions,
Page 5 of 14
answers to interrogatories, and admissions on file,’ designate ‘specific facts showing
that there is a genuine issue for trial.’” Celotex, 477 U.S. at 324 (quoting Fed. R. Civ.
P. 56(e)). “A factual dispute is genuine only if a ‘reasonable jury could return a verdict
for the nonmoving party.’” Info. Sys. & Networks Corp. v. City of Atlanta, 281 F.3d
1220, 1224 (11th Cir. 2002) (quoting United States v. Four Parcels of Real Property, 941
F.2d 1428, 1437 (11th Cir. 1991)).
III. Discussion
CMIC moves for summary judgment on Plaintiffs’ bad faith claim. In addition,
CMIC seeks summary judgment on the portion of Plaintiffs’ breach of contract claim
predicated on contents coverage and ALE benefits. Finally, CMIC also seeks to
preclude damages for mental anguish on the breach of contract claim.
A. Bad Faith
To survive summary judgment on a bad faith claim under Alabama law, a
Plaintiff must show substantial evidence of five elements: “(a) an insurance contract
between the parties and a breach thereof by the defendant; (b) an intentional refusal
to pay the insured’s claim; (c) the absence of any reasonably legitimate or arguable
reason for that refusal (the absence of a debatable reason); (d) the insurer’s actual
knowledge of the absence of any legitimate or arguable reason; (e) if the intentional
failure to determine the existence of a lawful basis is relied upon, the plaintiff must
Page 6 of 14
prove the insurer’s intentional failure to determine whether there is a legitimate or
arguable reason to refuse to pay the claim.” State Farm Fire and Cas. Co. v. Brechbill,
2013 WL 5394444 at *8 (Ala. Sept. 27, 2013).
The Brechbill Court made it clear that bad faith exists as a single tort, and that
there are two potential methods to prove such a claim. Id. at *8-*9. The “normal”
method of proving the claim requires not only that the plaintiff prove the first four
elements, but also that the underlying breach of contract claim be so strong that the
plaintiff is entitled to a preverdict judgment as a matter of law. Shelter Mut. Ins. Co. v.
Barton, 822 So. 2d 1149, 1155 (Ala. 2001). Here, Plaintiffs do not contend that they are
entitled to judgment as a matter of law on the breach of contract claim. Therefore,
they seek to prove the tort of bad faith through the “abnormal” method, which does
not require such a preverdict judgment. White v. State Farm Fire & Cas. Co., 953 So.
2d 340, 348 (Ala. 2006).
In order to prove the abnormal case, the plaintiff must show that the insurer (1)
intentionally or recklessly failed to investigate the plaintiff’s claim; (2) intentionally
or recklessly failed to properly subject the plaintiff’s claim to a cognitive evaluation or
review; (3) created its own debatable reason for denying the plaintiff’s claim; or (4)
relied on an ambiguous portion of the policy as a lawful basis to deny the plaintiff’s
claim.” State Farm Fire & Cas. Co. v. Slade, 747 So. 2d 293, 306-07. In addition to
Page 7 of 14
proving one of these four elements, however, the plaintiff must also demonstrate that
the insurer lacked a debatable reason to deny the claim. Brechbill, 2013 WL 5394444
at *9. Failure to prove this element is fatal to the claim, because “[o]f course, if a
lawful basis for denial actually exists, the insurer, as a matter of law, cannot be held
liable in an action based upon the tort of bad faith.” Gulf Atl. Life Ins. Co. v. Barnes,
405 So. 2d 916, 924 (Ala. 1981).
Here, the Edmondson engineering reports gave State Farm a debatable reason
to deny the claim. See National Sec. Fire & Cas. Co. v. Bowen, 417 So. 2d 179, 185 (Ala.
1982) (finding that investigative report gave insurer “ample debatable reason” to deny
claim). State Farm requested three separate reports from its engineer, and these
reports found that significant portions of the damage to the house were not caused by
the tornado. In addition, State Farm’s engineer considered reports made by
independent engineers retained by Plaintiffs and even reinspected the house in light
of their findings. Although Plaintiffs dispute Edmondson’s conclusions, Stanley
Christian conceded in deposition that the engineer did a thorough inspection, and
Plaintiffs do not contend that he manufactured or planted evidence to defeat the claim.
See Adams v. Auto-Owners Ins. Co., 655 So. 2d 969, 971-72 (Ala. 1995). Nor do Plaintiffs
claim that the damage should have been covered if it was not caused by wind; both
parties agree that State Farm had no obligation to pay for damage caused by settling,
Page 8 of 14
normal wear and tear, or defective workmanship. Thus, once it had obtained the
Edmondson reports, State Farm had a debatable reason for its partial denial of
Plaintiffs’ claim.
Plaintiffs, however, argue that CMIC committed bad faith by denying the claim
before it received Edmondson’s first engineering report. An insurance company’s
decision to deny a claim must be based on the information before it at the time. Aetna
Life Ins. Co. v. Lavoie, 505 So. 2d 1050, 1053 (Ala. 1987). Before Edmondson’s report
was issued, CMIC adjuster Brian Brady filed a Request for Authority for $50,000 on
May 18, 2011. Although it was possible for Brady to ask for more money if the
engineering report had concluded that the whole house suffered tornado damage, this
request would not cover the total reconstruction of Plaintiffs’ home recommended by
Al Cabaniss. On May 21, 2011, Brady offered Plaintiffs the actual cash value of the
undisputed repairs to the carport and roof framing (“the carport damage”). Stanley
Christian then asked CMIC to wait until it received the engineering reports to issue
payment. Plaintiffs’ expert Gary Augustine opines that the request for authority and
offer to repair the carport damage together mean that CMIC’s denial of the
Christians’ claim for total loss of the home occurred on May 20 or 21, 2011.2
2
CMIC has filed a motion to disqualify Mr. Augustine. (Doc. 43). The Court does not rule
on this motion herein, but examines Mr. Augustine’s testimony in light of the fact that only
evidence that can be reduced to admissible form may be considered on summary judgment. Kidd
Page 9 of 14
It is not fully clear whether Plaintiffs argue that these actions constituted an
express denial or a constructive denial. However, they provide no argument as to how
the Request for Authority, which was not communicated to Plaintiffs, and the offer to
pay for a portion of the damage can constitute an express denial of the claim for the
rest of the house. Augustine characterized the actions as a constructive denial in his
deposition. He did not, however, opine concerning the legal standard of what
constitutes a constructive denial in Alabama. Alabama law specifically provides two
ways for a Plaintiff to demonstrate a constructive denial: “(1) by showing that the
passage of time is so great that the delay alone creates a denial; or (2) by showing
sufficient delay in payment coupled with some wrongful intent by the insurance
company.” Congress Life Ins. Co. v. Barstow, 799 So. 2d 931, 938 (Ala. 2001).
Either of these methods requires a showing of delay, which Plaintiffs cannot
meet in this case. Plaintiffs’ home was damaged on April 27, 2011, and the supposed
constructive denial came less than a month later, within three days of the first
engineering inspection of the home. Plaintiffs make no argument that this brief delay
was unreasonable. In Barstow, the Alabama Supreme Court held that a six week
“passage of time, by itself, is not so great that it amounts to a denial.” Id.; see also Ins.
v. Mando American Corp., 731 F.3d 1196, 1207 (11th Cir. 2013).
Page 10 of 14
Co. Of N. Amer. v. Citizensbank of Thomasville, 491 So. 2d 880, 883 (Ala. 1986) (finding
constructive denial at the end of 24-month period). The delay between the storm
damage on April 27, 2011, and the receipt of Edmondson’s report on June 7, 2011, is
simply insufficient to constitute a constructive denial under Alabama law. No
reasonable jury could find that CMIC denied Plaintiffs’ claim without a debatable
reason to do so, making summary judgment on the bad faith claim proper.
B. ALE and Contents Claims
Plaintiffs bring breach of contract claims regarding the policy’s contents and
Additional Living Expenses coverages. A breach of contract claim demands proof of
the following elements: (1) a valid contract binding the parties; (2) Plaintiffs’
performance under the contract; (3) Defendant’s nonperformance; and (4) damages.
Barstow, 799 So. 2d at 937. The second and third element appear to be at issue in this
case. CMIC paid some ALE and contents benefits, but additional claims remain
disputed.
Plaintiffs sent three letters to CMIC in April of 2012 regarding additional living
expenses and contents damage. The letters included specific calculations and receipts
for certain living expenses, and generally described “everything in the basement of the
home” as being ruined by mildew. CMIC moves for summary judgment on these
claims. CMIC states that it has paid all the ALE claims covered by the policy but does
Page 11 of 14
not explain why any of the receipts submitted with these letters should not be paid.3
Thus, CMIC has failed to meet its burden of showing the Court that it is entitled to
judgment as a matter of law on this issue. Summary judgment on the ALE claim is due
to be denied.
CMIC also argues that it paid all of Plaintiffs’ contents claims. In deposition,
Stanley Christian acknowledged that he submitted some claims to CMIC and that they
were paid. He does not state that all his claims were paid. Plaintiffs now claim that
mold and mildew ruined objects that were not damaged in the original tornado event.
CMIC, while denying these claims, does not appear to argue that these items are not
covered by the policy. Rather they claim that a storage shed would have been provided
for these items if Plaintiffs had asked for one. A genuine factual dispute exists as to
whether Plaintiffs could and should have mitigated their damages to the basement
content. Therefore, summary judgment on the contents claim is due to be denied.
C. Mental Anguish Damages
Alabama law allows a plaintiff to recover for mental anguish damages in a breach
of contract action when “the contractual duties imposed by this contract are so
coupled with matters of mental solicitude . . . that a breach of that duty will necessarily
3
In its reply brief, CMIC states that the ALE claim is due to be limited to the receipts
submitted in the April 24 letter, but makes no argument as to why this is the case. (Doc. 44 at 17).
Page 12 of 14
or reasonably result in mental anguish.” Ind. Fire Ins. Co. v. Lunsford, 621 So. 2d 977,
979 (Ala. 1993). A contract to build or insure a home can meet this standard. Id.; B &
M Homes Inc. v. Hogan, 376 So. 2d 667, 671 (Ala. 1979). To recover damages for mental
anguish, the Plaintiff must demonstrate that the breach of the contract could
“reasonably be seen to affect the solicitude and well-being” of the contracting party.
Orkin Exterminating Co., Inc. v. Donavan, 519 So. 2d 1330, 1333 (Ala. 1988).
The Alabama Supreme Court has never required that the breach render the
house uninhabitable, though it did note that a contract for termite protection “affects
the habitability of a house.” Id. A contract for home insurance can also affect
habitability, and a factual dispute exists over whether the damage in this case affected
the home’s habitability. Furthermore, in Lunsford, the plaintiffs recovered mental
anguish damages after a windstorm destroyed an awning, with no indication that this
damage rendered the home uninhabitable. 621 So. 2d at 979. In this case, a reasonable
jury could find a breach of contract by CMIC that affected Plaintiffs’ “solicitude and
well being.” Donavan, 519 So. 2d at 1333. Therefore, summary judgment is
inappropriate and due to be denied.
IV. Conclusion
Because Plaintiffs cannot demonstrate the absence of a debatable reason for
CMIC to deny their claim, summary judgment is due to be granted on their bad faith
Page 13 of 14
claim. Summary judgment is due to be denied on Plaintiffs’ claims for ALE and
contents coverage, as well as their claim for mental anguish damages. A separate order
will be entered.
Done this 29th day of May 2014.
L. SCOTT COOGLER
UNITED STATES DISTRICT JUDGE
174310
Page 14 of 14
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?