Berg et al v. Honeywell International, Inc. et al
Filing
320
ORDER: re Cross Motions for Summary Judgment. Signed by Judge Sharon L. Gleason on 12/29/2016. (AEM, CHAMBERS STAFF)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF ALASKA
UNITED STATES OF AMERICA,
EX REL, THOMAS A. BERG, TIMOTHY
A. BERG, RYNE J. LINEHAN, NAYER M.
MAHMOUD, and STANLEY E. SMITH,
Plaintiffs,
v.
HONEYWELL INTERNATIONAL, INC.,
and HONEYWELL, INC.,
Case No. 3:07-cv-00215-SLG
Defendants.
ORDER RE CROSS MOTIONS FOR SUMMARY JUDGMENT
Before the Court are Defendants’ Motion for Summary Judgment at Docket 220
and Relators’ Motion for Partial Summary Judgment at Docket 225. The motions have
been fully briefed; 1 oral argument was held on October 17, 2016. 2
This is the third time the Court has addressed dispositive motions in this case.
The Ninth Circuit has twice sent this case back to the district court following orders
granting motions to dismiss based solely on the allegations pled by Relators. 3
In
contrast to the prior motions to dismiss, the motions before the Court at this juncture are
motions for summary judgment; the Court’s disposition of these motions is based on its
review of the extensive submissions of the parties regarding these motions, which
1
See Docket 222 (Defs.’ Mem.); Docket 303-1 (Relators’ Unredacted Opp.); Docket 258 (Defs.’
Reply); Docket 302-1 (Relators’ Corrected Mem.); Docket 238 (Defs.’ Opp.); Docket 276
(Relators’ Corrected Reply). Relators also filed a Notice of Supplemental Authority at Docket
292.
2
See Docket 287 (Hr’g Mins.); Docket 296 (Hr’g Tr.).
3
See 580 Fed. App’x 559 (9th Cir. 2014); 502 Fed. App’x 674 (9th Cir. 2012).
consists of thousands of pages of documentary evidence and excerpts from over a
dozen depositions.
BACKGROUND
In the late 1990s the Army sought to privatize the utilities at U.S. Army
installations. 4 Simultaneously, but as a separate initiative, the Army endeavored to
increase the energy efficiency of its buildings and facilities. 5
In 1986, Congress
authorized government agencies to enter into Energy Savings Performance Contracts
(“ESPC”), whereby the agency could use the savings from an efficiency upgrade to pay
for that upgrade. 6 Pursuant to this law, a private contractor would install and maintain
Energy Cost Savings Measures (“ECSM”), finance their installation, and receive
compensation from the government for years into the future based on verified savings
from the measures it had installed. 7 By statute, payments to a contractor in a given
year cannot exceed “the amount that the agency would have paid for utilities without an
[ESPC]” during that year. 8 Federal law also requires that the contract “provide for a
guarantee of savings to the agency.” 9 It is these types of contracts that underlie this
case.
4
Docket 319-1 at 4.
5
Docket 223-18 at 2.
6
Docket 223-18 at 2; 42 U.S.C. § 8287 et seq.
7
See Docket 223-18 at 2.
8
42 U.S.C. § 8287(a)(2)(B).
9
Id.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 2 of 37
As part of the privatization initiative, beginning in 1999 the Fort Richardson Army
base in Anchorage, Alaska (“FRA”) contemplated shutting down its central heating and
power plant (“CHPP”) and instead buying its electricity from a commercial provider. 10 At
around the same time, FRA reached out to Honeywell, Inc. to explore options for
improving its buildings’ energy efficiency. 11
Honeywell had previously entered a
contract with the U.S. Army making it the contractor for ESPCs for an extendable five
year term. 12
Under that “umbrella” Indefinite-Delivery Indefinite-Quantity contract
(“IDIQ”), Honeywell could propose ESPCs that the government could accept by issuing
a “Task Order” under the IDIQ. 13 In 2000, Honeywell proposed two ESPCs—referred to
as Proposal #3 and Proposal #4—to improve FRA’s energy efficiency. 14 It developed
these proposals with the understanding that FRA planned to cease generating its own
electricity and would instead buy its electricity from a third-party provider. 15 Honeywell’s
proposals included estimates of the costs of installation, the current costs of electricity
and heating for the base, and the projected costs of electricity and heating after the
10
Docket 319-1 at 4 (Paul Knauff Aug. 21, 2002 Information Paper).
11
Docket 223-18 at 6 (Col. Mark C. Nelson Mem.).
12
See Docket 225-1 (IDIQ) at 1–3.
13
Docket 225-1 at 3, 103–04 (ordering clause).
14
See Docket 225-5 (Proposal #3); Docket 265-5 (Proposal #4). The two proposals were
similar in their recommended improvements, but each concerned a distinct group of buildings on
FRA.
15
See Docket 223-18 at 56 (Nov. 29, 1999 email from Suzanne Wunsch) (inquiring whether
FRA intended to close CHPP); Docket 265-10 (Jan. 6, 2000 IST Presentation) at 13 (stating
Honeywell’s assumption that FRA would “convert from central to distributed heating); Docket
265-12 (Feb. 29, 2000 IST Presentation) at 12 (identifying increased electrical costs from
shutting CHPP); Docket 265-12 at 14 (identifying ancillary savings from shutting down CHPP).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 3 of 37
efficiency measures had been installed and the CHPP shuttered. Honeywell prepared
detailed calculations setting out how it arrived at its estimates, which it shared with both
FRA personnel and Army Corps of Engineers staff in Huntsville, Alabama. 16
As the proposals were developed, there were extensive discussions between
Honeywell’s engineers and the engineers at Huntsville about the basis and
reasonableness of certain calculations.
multilateral meetings and exchanges.
Over time, these issues were resolved in
Honeywell submitted several revised drafts
containing certain amended calculations during the course of these discussions. 17
Ultimately, the Army accepted Honeywell’s proposals for FRA in late 2000; Proposal #3
became formalized as Task Order 8 and Proposal #4 became formalized as Task Order
9. 18
Over the next few years, questions arose as to whether FRA could pay the
contract amounts because its actual savings were less than projected. 19 Because the
statute authorizing ESPCs limits payments to actual savings, Army lawyers were
concerned that making the payments would violate the Anti-Deficiency Act. 20
Honeywell and the government renegotiated and combined the two task orders in
2003. 21 Honeywell received its first payments thereafter, pursuant to the renegotiated
16
See, e.g., Docket 241-30 at 32–36; Docket 223-22 at 4–10; Docket 223-23 at 10–34.
17
See, e.g., Docket 241-26 at 9–34; Docket 223-2 at 32–35.
18
Docket 225-2 at 1–3; Docket 225-3 at 1–3.
19
See Docket 319-3 at 2.
20
See, e.g., Docket 223-38 at 45 (Simmons Mem.). See 31 U.S.C. § 1341.
21
Docket 223-42 at 2–20; see also Docket 265-21 (Bridgeman Dep.) at 3. This renegotiated
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 4 of 37
contract. 22
After unsuccessfully pursuing internal channels, 23 Relators initiated this
action in 2007, alleging that in 2000 Honeywell fraudulently obtained Task Orders 8 and
9. According to Relators, this initial fraud also induced the government to enter the
2003 modification and thus, Relators allege, the government’s payments pursuant to
that modification were fraudulently induced in violation of the FCA. 24
DISCUSSION
I. Jurisdiction
The Court has jurisdiction pursuant to 28 U.S.C. § 1331 because Plaintiffs’
claims arise under the False Claims Act, 31 U.S.C. § 3729 et seq.
II. Standard for Summary Judgment
Federal Rule of Civil Procedure 56(a) directs a court to “grant summary judgment
if the movant shows that there is no genuine dispute as to any material fact and the
movant is entitled to judgment as a matter of law.” The burden of showing the absence
of a genuine dispute of material fact initially lies with the moving party. 25 If the moving
party meets this burden, the non-moving party must present specific factual evidence
demonstrating the existence of a genuine issue of fact. 26 The non-moving party may
contract is referred to as “Mod II.” It combined the two task orders into a single contract.
Honeywell and the government had previously modified Task Order 8 to adjust the buildings
within its scope. See Docket 223-41 at 14 (documenting “modification 01”).
22
See Docket 223-45 at 2.
23
See, e.g., Docket 223-45 at 4–5.
24
See Docket 1. The operative complaint for purposes of these motions is the Second
Amended Complaint (SAC) at Docket 101, filed Aug. 13, 2014.
25
Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986).
26
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248–49 (1986).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 5 of 37
not rely on mere allegations or denials.
Rather, that party must demonstrate that
enough evidence supports the alleged factual dispute to require a finder of fact to make
a determination at trial between the parties’ differing versions of the truth. 27
When considering a motion for summary judgment, a court views the facts in the
light most favorable to the non-moving party and draws “all justifiable inferences” in the
non-moving party’s favor. 28 When faced with cross-motions for summary judgment, the
court “review[s] each separately, giving the non-movant for each motion the benefit of
all reasonable inferences.” 29 To reach the level of a genuine dispute, the evidence must
be such “that a reasonable jury could return a verdict for the non-moving party.” 30 If the
evidence provided by the non-moving party is “merely colorable” or “not significantly
probative,” summary judgment is appropriate. 31
To prevail on summary judgment, Relators must show that there is no genuine
dispute of material fact as to each element of their claim and that they are entitled to
judgment as a matter of law based on those undisputed facts. 32 But for Honeywell to
prevail, it must show only that there is no genuine dispute as to any material fact with
27
Id. (citing First National Bank of Arizona v. Cities Service Co., 391 U.S. 253 (1968)).
28
Id. at 255 (citing Adickes v. S.H. Kress & Co., 398 U.S. 144, 158–59 (1970)).
29
Flores v. City of San Gabriel, 824 F.3d 890, 897 (9th Cir. 2016) (citing Ctr. for Bio-Ethical
Reform, Inc. v. L.A. Cnty. Sheriff Dep’t, 533 F.3d 780, 786 (9th Cir. 2008)).
30
Anderson, 477 U.S. at 248.
31
Id. at 249.
32
Plaintiffs do not seek summary judgment on damages, but damages are not an element of an
FCA claim. See United States ex rel. Hagood v. Sonoma Cnty. Water Agency, 929 F.2d 1416,
1421 (9th Cir. 1991) (citing Rex Trailer Co. v. United States, 350 U.S. 148, 152–53 & n.5
(1956)).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 6 of 37
regard to any one element of each of Relators’ claims, and that it is entitled to judgment
as a matter of law on that element. And because Relators bear the burden of proof at
trial, Honeywell may prevail at summary judgment if it shows that “there is an absence
of evidence to support [Relators’] case.”33 If Honeywell meets that burden, the burden
then shifts to Relators “to designate specific facts demonstrating the existence of
genuine issues for trial.” 34 For that reason, the Court will first address Honeywell’s
motion; for if Honeywell can show that Relators lack evidence to prove any one element
of each of their claims even when adopting all justifiable inferences in favor of Relators,
then Relators’ motion necessarily fails.
III. Summary of Claims
This case arises in the context of a complex statutory, regulatory, and contractual
framework. For clarity, the Court will summarize Relators’ theories before addressing
the pending motions.
Relators seek to impose FCA liability based on a fraud-in-the-inducement
theory. 35 Such a claim requires a showing that (1) Honeywell made a promise to the
government that was false when made; (2) Honeywell knew the promise was false
when made; (3) Honeywell’s promise was material to the government’s decision to
award Honeywell the ESPCs at FRA in 2000, and the subsequent modification in 2003;
and (4) there was a request for the government to pay out money or forfeit money
33
In re Oracle Corp. Sec. Litig., 627 F.3d 376, 387 (9th Cir. 2010).
34
Id.
35
See Docket 101 (SAC) at ¶¶ 1–3; Docket 225 at 37 (“Relators’ claims are grounded on a
fraud in the inducement theory of liability.”).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 7 of 37
due. 36 Relators’ basic claim is that in 2000 Honeywell promised the Army that it would
produce certain savings through the ESPCs, that these savings promises were false,
and that Honeywell knew they were false at the time the promises were made. 37
Relators then contend that Honeywell knew that once the promised savings failed to
materialize the government would renegotiate the contracts rather than pay the roughly
$50 million termination fee, and that thus the payments under the renegotiated contract
were induced by the original fraud. 38
As Relators themselves explain, the “savings guarantee” is derived from an
equation. 39
The task orders disclose that the equation, calculations, and data
underlying the “savings” guarantee are provided in the “back-up data.”40 In essence,
the “savings guarantee,” as reported in the task orders, was the difference between the
“baseline” and the projected future costs: the “A” in A = B – C. Relators’ argument is
that the baseline “B” was false, and that the projected costs “C” was false, and that
Honeywell knew this to be so.
36
Relators have alleged four different falsehoods in
See United States ex rel. Hendow v Univ. of Phoenix, 461 F.3d 1166, 1174 (9th Cir. 2006).
37
See Docket 101 (Second Amended Complaint (“SAC”)) at ¶¶ 43, 74; Docket 302-1 (Relators’
Mot.) at 2 (“Honeywell obtained [the contracts] . . . through a materially false guarantee of costof-energy savings . . . .”).
38
See Docket 303-1 (Relators’ Unredacted Opp.) at 45.
39
See Docket 303-1 at 27–28.
40
Docket 225-2 at 9 (Task Order 8); Docket 225-3 at 9 (Task Order 9). Honeywell’s 30(b)(6)
witness testified that the “back-up data” referred to the proposals. See Docket 265-19 (Rogan
Dep.) at 3.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 8 of 37
support of their claim that Honeywell artificially inflated the baseline costs and artificially
deflated post-project costs. 41
First, Relators assert that Honeywell “added future non-actual costs of electricity
to the baseline”42 and that Honeywell “improperly use[d] the future commercial cost of
purchasing electricity as the pre-contract/pre-project cost of electricity energy
baseline.” 43 As discussed at greater length below, Honeywell calculated the baseline as
if FRA had already begun purchasing electricity commercially, even though the CHPP
had not yet shut down when the proposals were drafted and the task orders issued in
2000.
Second, Relators now claim in their summary judgment briefing (although so far
as the Court can discern, this allegation does not appear in their Second Amended
Complaint (“SAC”)), that the “cost of energy savings guarantee [in the task orders] is
demonstrably false as it excludes, for the post-project heat costs, the post-project/postcontract condition heat load costs for process loads and domestic hot water.” 44
Third, Relators contend that Honeywell’s “proposal documents knowingly and
fraudulently and falsely represented that normal Department of Energy infiltration
factors had been used,” but Honeywell had instead used an infiltration value that was
41
Relators’ SAC contains additional allegations of improper baseline and costs calculations,
see, e.g., Docket 101 at ¶ 25 (allegations of false weather data), but they have not advanced
those allegations at this stage in the proceedings. In their opposition to Honeywell’s motion,
Relators revive one allegation made in the SAC that was not raised in their own motion: that
Honeywell misled the government as to the contract’s legality. See Docket 101 at ¶ 72; Docket
303-1 (Relators’ Opp.) at 13. That claim is discussed infra, section V.B.
42
Docket 101 at ¶ 33.
43
Docket 302-1 at 3.
44
Docket 225 at 4.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 9 of 37
“only two thirds of the ‘tight’ construction value.” Relators maintain that the use of the
wrong infiltration value resulted in “a significant understatement of defendants’ postproject infiltration heat load requirement and grossly inflated energy savings.” 45
Fourth, Relators claim that Honeywell “failed to allow for adjustment of the
baseline for buildings that were to be demolished” and that this resulted in an improper
allocation of savings between Phase 1 and Phase 2 of the project. 46
Defendants argue that Relators have not and cannot produce any evidence that
Honeywell “knowingly” made any false statements to the government, and that therefore
Honeywell is entitled to summary judgment. 47 With regard to the particular assertions of
allegedly false statements, Honeywell contends that Relators’ claims fail for the
independent reason that Honeywell fully disclosed all of the relevant facts and
assumptions in its proposals to the government.
The Court will address each of
Relator’s four specific allegations in turn, but will first address the legal significance of
the government’s knowledge of Honeywell’s calculations and data inputs in this False
Claims Act proceeding.
45
Docket 101 at ¶ 24; Docket 302-1 at 4; see also Docket 101 at ¶ 79(A).
46
Docket 302-1 at 4; see also Docket 101 at ¶ 79(D). The project was divided into two phases.
See Docket 223-22 at 6. “Phase 1” was “Proposal #3” and became Task Order 8. “Phase 2”
was “Proposal #4” and became Task Order 9.
47
See Docket 222 at 33–34.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 10 of 37
IV. The Government Knowledge “Defense” 48
Honeywell contends that one reason Relators cannot prevail in this action is
because Honeywell indisputably made extensive disclosures to the government about
its underlying calculations and data inputs. Honeywell argues that because of these
disclosures, Relators cannot show that Honeywell made knowingly false statements to
the government. 49 According to Honeywell, the government’s “knowledge of the facts
underlying the alleged fraud negates the elements of knowledge and falsity.” 50 Relators
first counter that government knowledge “is irrelevant because Honeywell has admitted
that it actually knew there would be no savings before it submitted the two false task
order savings guarantees.” 51 Relators also argue that “Honeywell failed to make full
disclosure of the relevant information to the relevant government officials.” 52
The Court rejects the premise underlying Relators’ first argument as unsupported
by the record. There is no evidence in the record to support Relators’ assertion that
Honeywell knew there would be no savings from its proposed ECSMs. That assertion
48
The Ninth Circuit rejected Honeywell’s efforts to assert a government knowledge defense at
the motion to dismiss stage, noting that “[t]he possibility that Honeywell may prevail at a later
stage of this litigation under the so-called government knowledge defense to FCA liability does
not support the conclusion that the Relators’ complaint cannot be saved by an amendment. . . .
[That ‘defense’] is therefore appropriate ‘at the summary judgment stage or after trial.’” Berg v.
Honeywell Int’l, Inc., 580 Fed. App’x 559, 560 (9th Cir. 2014) (quoting United States ex rel.
Butler v. Hughes Helicopters, Inc., 71 F.3d 321, 327 (9th Cir. 1995)). As the proceedings have
now advanced to summary judgment, it is now appropriate to consider the government
knowledge “defense” and the extensive evidence in the record related to that defense.
49
See Docket 222 at 36–37.
50
Docket 258 at 10.
51
Docket 303-1 at 33.
52
Docket 303-1 at 37.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 11 of 37
rests on the deposition testimony of Suzanne Wunsch, a Honeywell employee involved
in the contract negotiations with the government in 2000. 53 Although Ms. Wunsch did
testify that “everyone knew” that “it would cost the government more for heat and
electricity after the plant was closed than it was before,”54 she also said that that was
exactly what Honeywell told the government: “[T]hese slides show the government that
although there will be savings generated, they will be paying more when they close the
plant.”55 This second statement underscores the fact that Ms. Wunsch understood
Honeywell’s “savings guarantee” to be based on assumed parameters—one of which
was that as a result of the CHPP closure FRA was going to pay more for electricity
whether or not it accepted Honeywell’s proposed ESPCs. Accordingly, Ms. Wunsch
testified that Honeywell was “directed” to show the Army “what will it look like when the
plant is closed.” 56 These statements reflect Ms. Wunsch’s belief that both Honeywell
and the government were well aware that the privatization of FRA’s electricity supply
would have a negative impact on FRA’s electricity costs.
Ms. Wunsch’s comment
reflects her understanding that Honeywell’s proposals were distinct from, and yet
incorporated, FRA’s plans to privatize its electricity supply. Honeywell’s calculations of
savings was determined within the context of FRA’s independent plan to buy electricity
53
See Docket 302-1 (Relators’ Mot.) at 18. Ms. Wunsch now goes by Ms. Johnson, but
consistent with the documents in evidence and the parties’ briefing, the Court will refer to her as
Ms. Wunsch.
54
See Docket 265-18 (Wunsch Dep.) at 5.
55
Docket 265-18 at 4.
56
Docket 265-18 at 4. There is a dispute as to whether the Army actually directed Honeywell to
make such an assumption, but as explained below, that dispute is immaterial. See infra note 96
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 12 of 37
from a commercial source. 57 No reasonable jury could conclude that her statements
reflect an admission that Honeywell knew that its baseline, its projected costs, or its
“savings guarantee” were “false” within the meaning of the FCA.
Plaintiffs correctly observe that the Ninth Circuit has held that the fact that the
“relevant government officials know of [a statement’s] falsity is not in itself a defense.”58
But the Ninth Circuit has also repeatedly recognized that “knowledge possessed by
officials of the United States may be highly relevant” at trial or at the summary judgment
stage. 59 Government knowledge may be “highly relevant” to two elements of an FCA
claim.
First, government knowledge may be used to rebut the necessary scienter: If the
contractor “so completely cooperated and shared all information” with the government,
then the contractor “did not ‘knowingly’ submit false claims.”60 In United States ex rel.
Butler v. Hughes Helicopters, the relator alleged that the contractor selling helicopters to
the Army had falsely certified compliance with agreed-upon testing parameters. The
contract called for certain testing procedures, but prior to testing the contractor
“prepared Test Plans for the Army’s approval” that “did not include all of the testing
57
See infra note 99 and sources cited therein.
58
See United States ex rel. Hagood v. Sonoma Cnty. Water Agency (Hagood I), 929 F.2d 1416,
1421 (9th Cir. 1991) (citing United States v. Ehrlich, 643 F.2d 634, 638–39 (9th Cir. 1981)).
59
Id. at 1421.
60
United States ex rel. Butler v. Hughes Helicopters, Inc., 71 F.3d 321, 327 (9th Cir. 1995); see
also Hooper v. Lockheed Martin Corp., 688 F.3d 1037, 1051 (9th Cir. 2012); Wang v. FMC
Corp., 975 F.2d 1412, 1421 (9th Cir. 1995), abrogated on other grounds, United States ex rel.
Hartpence v. Kinetic Concepts, Inc., 792 F.3d 1121 (9th Cir. 2015).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 13 of 37
referred to in the contract documents.”61
The Army’s technical representatives
nonetheless recommended approval of the test plans, and the contracting officers
signed off on them, apparently in recognition that less extensive testing was warranted
“because of [the Army’s] decision to speed up production.” 62
When the contractor
delivered the helicopters, it signed forms “which stated that the helicopters conformed to
contract.”63 In affirming a directed verdict for the defendant–contractor on the relator’s
FCA claims, the Ninth Circuit assumed that the contractor’s statements were “false,”64
but nonetheless concluded that the extent of the government’s knowledge negated a
finding that there had been a “knowing” submission of a false claim. As one example in
that case, the contractor had represented that “pattern tests of the pilot’s radio were
done at 10 to 12 nautical miles,” but they had actually been done at closer distances.
As to that example, the Ninth Circuit held that because “the Army knew that the
summary statement of the distances at which the pattern tests were conducted was not
strictly accurate as to all the tests,” and because “this discrepancy was the subject of
dialogue between the Army and MDHC” the “only reasonable conclusion is that this was
not a ‘knowingly’ false statement, as the noncomplying tests were known to and
approved by the Army.” 65
61
Butler, 71 F.3d at 324.
62
Id.
63
Id.
64
Id. at 327.
65
Id. at 328.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 14 of 37
Similarly, in Hooper v. Lockheed Martin Corp., the relator alleged that the
contractor had used “defective testing procedures.” 66
The district court granted
summary judgment to the contractor after concluding “that there was no evidence of
fraud in the testing because the Air Force was aware of and approved Lockheed’s
testing methods, even if the tests were not done in the order specified in the
contracts.”67
The Ninth Circuit affirmed, holding that “where Lockheed submitted
overwhelming evidence that it . . . disclosed to the Air Force its testing procedures,” the
FCA claim necessarily fails because the relator could not show that “Lockheed
‘knowingly’ submitted a false claim.” 68 Thus, Ninth Circuit authority establishes that the
fact that a contractor has been open and candid with the government about the facts
underlying its statements to the government can be used to show that the contractor did
not have the requisite scienter.
Second, government knowledge may “show that the contract has been modified
or that its intent has been clarified, and therefore that the claim submitted by the
contractor was not ‘false.’” 69 As the Seventh Circuit has stated, “[i]f the government
knows and approves of the particulars of a claim for payment before that claim is
presented, the presenter cannot be said to have knowingly presented a fraudulent or
false claim. In such a case, the government’s knowledge effectively negates the fraud
66
688 F.3d 1037, 1050 (9th Cir. 2012).
67
Id. at 1050–51.
68
Id. at 1051.
69
United States ex rel. Kreindler & Kreindler v. United Techs. Corp., 985 F.2d 1148, 1157 (2d
Cir. 1993).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 15 of 37
or falsity required by the FCA.” 70 In this context, government knowledge is used not to
rebut an inference of scienter, but rather to define the scope of the statement which is
alleged to be false.
Several district courts have taken the same view, recognizing that the context of
a statement can negate its apparent falsity. Thus, the district court in Butler found that
the relator “did not provide legally sufficient evidence that, given the nature of the
relationship between [the contractor] and the Army, any statements or claims made by
[the contractor] were ‘false or fraudulent.’” 71 And in Boisjoly v. Morton Thiokol, Inc., the
district court examined the “close interplay” between the contractor and the government,
and concluded that, given the government’s detailed knowledge of the very defects that
the relator alleged gave rise to an FCA claim, the relator could not prove “the element of
falsity or fraud required.” 72
In affirming the district court’s directed verdict in Butler, the Ninth Circuit applied
this same logic. In that case, the contractor had submitted a report that concluded that
the helicopter radios “have been successfully demonstrated and are ready for
production.” But in fact the radios had failed to meet certain contractual specifications.
The Ninth Circuit held that because “the failure to meet specifications was detailed
elsewhere in the report,” the “generalized statement with added details was not the type
70
United States ex rel. Durcholz v. FKW Inc., 189 F.3d 542, 545 (7th Cir. 1999); see also United
States ex rel. Burlbaw v. Orenduff, 548 F.3d 931, 952 n.19 (10th Cir. 2008).
71
1993 WL 841192 at *14 (C.D. Cal. Aug. 25, 1993) (granting directed verdict for defendant),
aff’d 71 F.3d 321 (9th Cir. 1995).
72
706 F. Supp. 795, 809–10 (D. Utah 1988). Boisjoly arose in the context of a motion to
dismiss. While the Ninth Circuit has rejected attempts to employ government knowledge at that
stage, it has characterized Boisjoly as “defensible on its facts.” Hagood I, 929 F.2d at 1421.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 16 of 37
of [false] representation required by the statute.” 73 Thus, the additional details provided
in the report warranted the directed verdict for the contractor despite the conclusion’s
guarantees because no reasonable jury could conclude that a false statement had been
made.
Honeywell maintains that the government’s knowledge in this case is relevant for
both of the reasons discussed above.
It contends that its open and collaborative
discussions with government officials and the wide-ranging disclosures prior to the
finalizing of the task orders defeat any claim that Honeywell knowingly made any false
statement. And Honeywell claims that its wide-ranging disclosures negate any claim
that its statements were false. 74
The Court will address the applicability of the
government’s knowledge in each of these two contexts for each of the Relators’ specific
claims as necessary.
V. Specific Claims
A. Baseline Inclusion of Future Non-Actual Costs of Electricity
Both the parties principally focus on Relators’ first claim: that Honeywell
misrepresented projected savings by assessing the baseline as though FRA were
already purchasing electricity on the commercial market. 75 The timing of the knowledge
is critical: an FCA claim requires a false statement that is known to be false at the time
the statement is made. 76 Thus, for the asserted savings to be an actionable claim that
73
Butler, 71 F.3d at 328.
74
See Docket 258 at 10.
75
See, e.g., Docket 222 (Honeywell’s Mem.) at 13–18; Docket 302-1 (Relators’ Mem.) at 9–14.
76
United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1174 (9th Cir. 2006) (quoting
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 17 of 37
survives summary judgment, there must be some evidence that Honeywell knew in
2000 that the savings it was projecting were inaccurate. 77
But Relators have not presented any evidence that Honeywell possessed such
knowledge at the time of the initial contracting in 2000.
As discussed above, Ms.
Wunsch’s statement that “everyone knew” that shutting down the CHPP would increase
electricity costs does not establish that Honeywell knew its baseline was improper. 78
And Honeywell executive Steve Craig’s statement in 2006 that Honeywell knew “from
the very beginning” that the project would not save energy 79 was wholly unrelated to the
accuracy of the baseline. 80 As discussed in greater detail below, Mr. Craig’s statement,
in its full context and drawing all reasonable inferences in Relators’ favor, was not that
Honeywell knew there would not be any savings as a result of its energy savings
measures, but rather that Honeywell knew there would not be any savings if certain
actions were not taken to improve infiltration rates. 81 Finally, Relators suggest that
Honeywell’s expertise in ESPC contracts warrants an inference that it “knew” its
United States ex rel. Hopper v. Anton, 91 F.3d 1261, 1267 (9th Cir. 1996)).
77
Some evidence suggests that there actually were substantial energy savings as a result of the
ESPCs. See, e.g., Docket 223-50 at 21–23 (Simmons June 27, 2008 Mem.). But whether
savings were in fact realized from the project does not impact whether there was fraud in the
inducement, and the Court need not decide the issue.
78
See supra section IV.
79
See Docket 53-1 (Berg Decl.) at 22, ¶ 44.
80
See Docket 259-1 at 94 (Berg Dep.) (“As far as I know, as far as I can recollect, the telephone
conference centered on heating and not on electrical.”).
81
See infra section V.C.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 18 of 37
baseline was “improper.” 82
But Honeywell’s expertise is not sufficient evidence to
establish knowing fraud under the False Claims Act. 83
Moreover, in this case Honeywell did not simply present a conclusory savings
number to the government. Rather, Honeywell provided extensive calculations to the
government supporting its projected savings; and the government, after substantial
discussion with Honeywell, approved those calculations. The Court has reconstructed
the following approximation of these calculations from the proposal documents:
First, Honeywell assessed FRA’s energy usage based on fiscal years 1998 and
1999. 84 At that time, most of FRA’s heat and electricity was being provided by the
CHPP. The CHPP was a cogeneration plant, meaning that it burned fuel to produce
steam; the steam first turned turbines to generate electricity and was then routed
throughout the base to heat the buildings. Honeywell then calculated the total cost of
fuel to produce all of the steam. 85 In consultation with Army personnel, Honeywell
allocated the cost of generating the steam between electricity generation and heat
production. 86 This provided a cost for heat and a separate cost for electricity. 87
82
See, e.g., Docket 302-1 at 15–16, 21–22.
83
Cf. Hopper, 91 F.3d at 1268 (“Hopper argues that past regulatory noncompliance creates an
inference that the School District lied when certifying future compliance. This is not sufficient
evidence to establish knowing fraud under the [False Claims] Act.”).
84
See, e.g., Docket 265-5 at 39.
85
See Docket 265-5 at 150 (Proposal #4).
86
This percentage varied throughout the various proposals, apparently based on input from
FRA employees. See Docket 265-5 at 147 (“Plant Steam to Heating was recalculated using the
formula provided by DPW.”).
87
In Proposal #4, Honeywell estimated this cost at $2,300,582 per year for electricity and at
$2,214,681 for heat. Docket 265-5 at 150–51. In Proposal #3, Honeywell had estimated
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 19 of 37
Honeywell’s proposals for Task Orders 8 and 9 each contained two proposed
Energy Cost Savings Measures (ECSMs). First, Honeywell would install high-efficiency
natural gas furnaces in each building and eliminate reliance on the CHPP for heating. 88
Honeywell estimated the cost of heating the buildings using the new furnaces, and
presented the energy savings from that ECSM as the difference between that cost and
the portion of steam costs that Honeywell had allocated to heating the buildings using
the CHPP. 89 Second, Honeywell proposed installing “building management and control
systems” that accounted for building occupancy by reducing heat supply during off-peak
hours and optimized hot water systems. 90
For these measures, Honeywell used
computer modeling software to project the energy consumption for each building with
and without the control measures. 91 The reported energy savings was the difference
between those two numbers. Combined, these two ECSMs were expected to produce
$464,239 in annual heat energy savings for Task Order 8 and $580,689 for Task Order
9. 92
$2,329,158 for electricity and $2,288,850 for heat. Docket 223-22 at 6.
88
Docket 265-2 at 23 (Proposal #3).
89
See Docket 265-2 at 27. The project was divided into two phases, with one-half of the heat
costs assigned to each phase. See Docket 223-22 at 6.
90
See Docket 223-20 at 161.
91
Docket 223-20 at 163.
92
See Docket 225-2 (Task Order 8) at 9; Docket 225-3 (Task Order 9) at 9. Task Order 8’s
savings are the sum of the savings from each proposed ECSM, $235,709 for the first, Docket
223-20 at 28, and $228,530 for the second, Docket 223-20 at 164. Task Order 9’s savings are
the sum of the savings from each ECSM, $522,941 for the first, Docket 265-5 at 54, and
$57,748 for the second, Docket 223-26 at 46. Task Order 9 included additional “electric
savings” of $245,681. Honeywell disclosed these savings separately, and reported that “These
savings are a result of a phone conversation with Mr. Paul Knauff [an FRA employee] on
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 20 of 37
Thus, the savings that Honeywell presented were the results of the underlying
calculations it disclosed: the difference between the cost associated with heating the
buildings using the CHPP and the cost to heat the buildings after the CHPP was shut
down. Honeywell was transparent about how it reached its numbers.
Of course, there was an additional consequence to shutting down the CHPP.
Once the CHPP was shut down, FRA would need to purchase electricity from another
source.
Relators’ claim is that Honeywell’s projected savings number was “false”
because Honeywell “improperly us[ed] the future commercial cost of purchasing
electricity as the pre-contract/pre-project cost of electricity energy baseline.”93 Relators
point to Honeywell’s “Fuel Sensitivity Analysis,” a spreadsheet that shows the dollar
value of the heat savings projected for Task Order 8, which is identical to the dollar
value of the total savings projected in Task Order 8. 94 According to Relators, this
“conclusively proves that for the cost of energy savings in Task Order 8 . . . Honeywell
only conducted a cost of energy savings regarding heat.”95 In essence, Relators argue
that Honeywell should have deducted the increased costs of purchasing electricity from
November 8, 2000.” Docket 265-5 at 54; see also Docket 265-5 at 153 (explaining the
calculations for these savings). This item of the savings calculation is not directly at issue in this
case, though it is discussed in more detail below. The total savings projected for Task Order 9
was the sum of these three numbers, $826,370. There is a $2,000 discrepancy in the projected
savings in the issued task order, see Docket 225-3 at 9 (estimating $828,370), but that
discrepancy may be the result of an amendment to the estimated savings from the second
ECSM: The estimates for the first were updated at some point, compare Docket 223-25 at 5,
with Docket 265-5 at 54, but the Court was unable to locate in the record any corresponding
update for the second ECSM estimates.
93
Docket 302-1 at 3.
94
Compare Docket 265-1 (Fuel Sensitivity Analysis) at 1, with Docket 225-2 (Task Order 8) at 9.
95
Docket 302-1 at 35.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 21 of 37
any energy savings number.
Honeywell does not dispute the contention that Task
Order 8 contained only heat savings, but instead counters that it was transparent not
only with regard to how it calculated savings, which looked only at heat costs, but also
with regard to the fact that it was not including the increased costs of electricity. 96
As Honeywell disclosed during a presentation with Army staff in February 2000
(several months before the task orders were issued), purchasing electricity
commercially would cost more money than producing it at the CHPP.
In that
presentation, Honeywell indicated that the then-current costs associated with generating
electricity at the CHPP were $3,652,591 per year, and that the cost to buy the same
amount of electricity commercially would be $4,544,027 per year. In bold letters at the
bottom of that slide, Honeywell indicated “Net Electric Cost Increase $891,437.”97 And
on the next slide, Honeywell showed how it intended to calculate the “Baseline Energy
Costs.” The baseline would include the total energy costs associated with running the
96
Relators identify a genuine dispute of fact as to whether Paul Knauff, an FRA employee,
instructed Honeywell to account for the increased costs of electricity in this matter. See Docket
241 (Relators’ Opp.) at 18–19; Docket 241-5 (Knauff Dep.) at 3. Paul Knauff’s own deposition
testimony directly contradicts Honeywell’s 30(b)(6) witness, Richard Rogan. See Docket 241-1
(Rogan Dep.) at 2–3. Separate evidence might also support Honeywell’s version of events if
this case went to trial: an Army Audit Agency interview from 2003 indicates that Paul Knauff
recalled that “electricity was never included in the project” and that “Honeywell briefed that
information upfront when the project first started.” Docket 319-2 at 5. But this statement is
ambiguous as to what it meant that “electricity was never included,” and the Court assumes, as
it must for purposes of this motion, that Mr. Knauff was not referring to the baseline. While such
an instruction would have bolstered Honeywell’s reliance on the government knowledge to
defeat Relators’ claims, it is not necessary to it. The Court assumes for purposes of this motion
that Mr. Knauff did not so instruct Honeywell, but the fact turns out to be immaterial: As the
discussion in this section shows, Honeywell’s repeated disclosures informed the government
exactly how Honeywell was calculating the baseline and the savings, and so its reason for doing
so in the first instance does not affect whether its baseline was “false” or whether any falsity was
known to Honeywell at the time.
97
Docket 265-12 at 12 (Feb. 29, 2000 IST Meeting Powerpoint).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 22 of 37
CHPP in the past, the projected increase in costs when electricity was purchased, and
the additional costs of the electricity that FRA was already purchasing. This gave the
“Total Annual Baseline Energy Costs” of $8,378,738. 98 Thus, in February 2000, over
six months before the first contract was formalized, Honeywell was clearly including the
increased electrical costs of purchasing electricity in its electricity baseline, thereby
indicating to the government that its energy savings calculations would not account for
those increased costs. 99
When Honeywell submitted its formal proposals in July 2000 (Proposal #3) and
November 2000 (Proposal #4), it again indicated that the electricity baseline would be
“adjusted” to account for the increased costs of purchasing electricity. Honeywell first
calculated, “per the monthly plant operating reports,” the CHPP’s electrical production in
megawatt-hours per year.
It then added the electricity that FRA was currently
purchasing to estimate CHPP’s total electricity requirement. Then, under the bolded
subtitle “Electrical Baseline Adjustment,” Honeywell calculated how much it would cost
98
Docket 265-12 at 13.
99
As a consequence of this adjustment, the baseline was calculated as if FRA had stopped
using the CHPP to produce electricity, but was still using it to produce heat. Thus, the ESPCs
could account for the ancillary savings from shutting down the CHPP, such as avoided labor and
maintenance costs, even though it did not account for the increased cost of electricity.
Honeywell may have concluded that FRA was planning exactly this, since the privatization
efforts were distinct from the ESPC. See Docket 225-8 (AAA Lessons Learned) at 13 (noting
that FRA personnel “were under the impression the Army was getting out of the utility business,
no matter what the cost, whether by privatizing or by the use of [ESPCs]”); Docket 223-41 at 7
(Charles Baus March 29, 2000 email) (discussing electrical privatization); Docket 223-38 at 44
(Simmons April 10, 2003 Mem.) (“USARAK [U.S. Army, Alaska] was proceeding with the
understanding that the electrical system was going to be privatized.”); Docket 319-2 at 2 (“At the
time the project started, it was understood that electricity was to be purchased.”); Docket 319-2
at 6 (“The intent of the ESPC was not to replace the power plant, but to replace the steam
distribution system.”).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 23 of 37
to purchase the same amount of electricity commercially. 100
The record also demonstrates that Honeywell knew that the government also
knew about the electrical baseline adjustment. As part of the ESPC process, Honeywell
submitted its calculations to the Army Corps of Engineers for review and approval. Tim
Brown, one of the Army engineers reviewing the proposal documents, specifically
commented to Honeywell with regard to the Electrical Baseline Adjustment that “[t]he
analysis should include supportive information to demonstrate the actual electrical
charges after the CH&PP is shut down.” 101
Relators argue that other parts of Honeywell’s savings calculations show that it
was misleading the government with regard to how it calculated the electricity costs.
They note that one component of the savings guarantee for Task Order 9 was the
“electrical savings” from shutting down the CHPP: The CHPP itself required electricity to
power lights and various mechanical components in the CHPP building, and shutting it
down would eliminate those requirements, reducing FRA’s total electricity demand. 102
In evaluating these savings, Honeywell used the then-current costs to provide that
electricity—the cost of generating the electricity using the CHPP—instead of the
projected commercial rate.
Relators argue that this fact demonstrates that the
government believed baseline costs would be calculated using the CHPP’s cost-to-
100
Docket 265-5 at 42; see also 225-5 at 5.
101
Docket 223-2 at 33–34.
102
See supra note 92. This component is not directly at issue, and is distinct from the electrical
baseline adjustment.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 24 of 37
generate, rather than the commercial cost-to-buy. 103 But the parties do not dispute that
this specific component of the proposal was added at the behest of Paul Knauff, an FRA
employee. 104 Thus, whichever rate should have been used for this calculation, the fact
that the Army personnel requested use of the CHPP’s cost-to-generate rate negates
Relators’ assertion that Honeywell made a knowingly false statement to the government
when it incorporated this request.
The Court agrees with Honeywell that, as a matter of law, its extensive
disclosures to the government prior to the task orders’ finalization preclude Relators’
FCA claim. 105 First, the stated energy savings were clearly calculated and identified as
heat energy savings only. Those numbers did not become “false” merely because they
excluded electricity costs. 106 The savings estimates were the result of clearly disclosed
mathematical equations that did not even purport to include electricity costs. Because
Honeywell disclosed the assumptions and math underlying its estimates, its statements
in that regard were not “false” within the meaning of the False Claims Act. 107
103
See Docket 302-1 at 13.
104
See Docket 265-5 at 54; see also Docket 265-5 at 153 (explaining the calculations for these
savings). Cf. supra note 96 (detailing a dispute regarding a different instruction Honeywell
contends Paul Knauff gave).
105
Relators have focused substantial briefing on whether the baseline was permissible or proper
under the applicable statutes and regulations. But FCA liability does not attach to mere
regulatory violations. See United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166,
1171 (9th Cir. 2006). Thus, the Court need not decide whether or not the applicable regulations
allowed an ESPC to account for the electricity costs in the manner these ones did. See also
infra Part IV.
106
Relators also argue that these numbers were inaccurate for other distinct reasons. The
Court addresses these allegations in the pages below.
107
Cf. United States ex rel. Butler v. Hughes Helicopters, Inc., 71 F.3d 321, 328 (9th Cir. 1995)
(holding that “a generalized statement with added details was not the type of representation
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 25 of 37
Moreover, Honeywell’s repeated disclosures to the government about the
“Electrical Baseline Adjustment” preclude a finding that any statement in that regard
was known to be false by Honeywell when made. 108
Honeywell informed the
government that it would cost more to buy electricity than to produce it. It disclosed the
basis for its energy savings calculations which clearly did not account for the increased
electricity costs. It communicated the electrical baseline adjustment to the government
in both its formal proposals and in its less formal presentations. It received comments
from government employees about its adjustment calculations. Honeywell “completely
cooperated and shared all information” with the government, and thus “the Army knew”
that the increased electrical costs were not accounted for and this fact “was the subject
of dialogue between the Army and [Honeywell].”
Therefore, the “only reasonable
conclusion is that this was not a ‘knowingly’ false statement, as the [calculations] were
known to and approved by the Army.” 109
In light of the lack of evidence that Honeywell had any knowledge that the
baseline was improper, and in light of the overwhelming evidence that Honeywell fully
disclosed the baseline adjustment and the fact that its energy savings calculations did
not account for the increased costs of electricity, the Court finds that there is no genuine
dispute as to any material fact with regard to either the “falsity” of Honeywell’s savings
required by the statute”).
108
Contemporaneous emails between Honeywell employees also rebut any suggestion that
Honeywell “knew” the baseline to be “false.” In March 2000, Honeywell’s Charles Baus emailed
other Honeywell employees working on the FRA project, and stated that “we will be using the
MLP Rate #760 to determine the baseline electric rate. Again, the philosophy being that the
electric system ‘privatization’ is proceeding without us and this is what they will be paying.”
Docket 223-41 at 7.
109
Butler, 71 F.3d at 327–28.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 26 of 37
estimates or Honeywell’s knowledge of any alleged falsity. Accordingly, Honeywell is
entitled to judgment as a matter of law on this claim. FCA liability cannot be premised
on Honeywell’s electrical baseline adjustment.
B. Heat Costs
Relators assert that Honeywell “improperly omitted the process loads and
domestic hot water loads from the post-project heat costs.”110 Honeywell responds that
the omission of process loads “was fully disclosed to the Government in the proposal
documents.” 111 But whether or not Honeywell fully disclosed this omission, Relators
have not answered Honeywell’s assertion that there is no evidence that the omission
was made “knowingly.” While Relators present evidence to demonstrate that these
numbers were omitted, 112 Relators offer only a bare unsupported assertion that this
omission was intentional. 113
Relators suggest that Honeywell can be charged with “knowingly” submitting
false claims because it failed to use due diligence to verify its submissions. But this
argument fails for two reasons. First, Relators have not proffered any evidence that
Honeywell did not use due diligence; they do not discuss at all what processes
110
Docket 302-1 at 23.
111
Docket 238 at 29.
112
See, e.g., Docket 302-1 at 38. The extent to which such an omission was wrongful is
disputed. Compare Docket 238 (Honeywell Opp.) at 29 (“Relators’ own expert agrees . . . that
ESPC baseline calculations should never include process loads.”), with Docket 302-1 at 36
(arguing that “Honeywell dropped the post-retrofit domestic hot water and process loads” in an
attempt “to yield the false energy savings guarantee”).
113
See Docket 302-1 at 39 (“Honeywell’s various and creative methods in cherry-picking values
and strategically inserting or deleting them from baseline calculations was conscious and
deliberate.”).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 27 of 37
Honeywell used (or did not use) to verify the submissions. They only repeatedly state
what they view as mistakes in Honeywell’s calculations. But if the fact of a mistake was
sufficient to charge a sophisticated contractor with knowledge of that mistake, then the
“knowingly” element of the False Claims Act would be vitiated entirely: every mistake
that a contractor made in submitting claims would be transformed into a lie. This is
plainly not the law, as “the common failings of engineers and other scientists are not
culpable under the Act.” 114
Second, and more fundamentally, Relators’ argument rests on an apparent
misreading of United States v. United Health Insurance Company. 115 In that case,
health insurers participated in a government program that paid the insurers a certain
amount for each insured, based on the assessed “risk” associated with that patient.
Because that risk—and accordingly the amount paid—was based on the number and
types of diagnoses for each patient, an insurer received more money from the
government for “sicker” patients than for healthier ones.
The insurers allegedly
implemented an internal program whereby they verified the diagnosis codes entered for
each patient, but only corrected the codes when they had understated the diagnosis,
and ignored diagnosing errors that overstated a patient’s diagnosis. Over time, the
insurers’ patients appeared much sicker than they actually were, because only
underdiagnoses were being corrected. 116
114
United States ex rel. Anderson v. N. Telecom, Inc., 52 F.3d 810, 815 (9th Cir. 1995) (quoting
Wang v. FMC Corp., 975 F.2d 1412, 1421 (9th Cir. 1992)).
115
See Docket 302-1 at 39 (citing United States v. United Health Insurance Co., 2016 WL
7378731 at *2 (9th Cir. Aug. 10, 2016), as amended on denial of r’hrg en banc).
116
See 2016 WL 7378731 at *2.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 28 of 37
In reversing a district court’s grant of the health insurers’ motion to dismiss, the
Ninth Circuit concluded that the alleged “one-sided retrospective review” was not a good
faith attempt to verify the accuracy of the diagnosis codes, and thus, if the allegations
were true, the insurers had falsely certified to the government that its submissions were
“accurate, complete and truthful” based on the “best knowledge, information, and belief”
of the insurers. 117 But the relevant regulations did not require the insurers to implement
a retrospective review at all; they merely required that, if the insurers did implement a
retrospective review, it be carried out in good faith. 118 And so the only requirement that
United Health Insurance imposes is that if a contractor implements a submittal review
process, it may not review their submittals in bad faith.
Here, Relators have not produced any evidence from which a jury could
reasonably infer that Honeywell had implemented a one-sided review that was designed
to correct only certain errors. Even assuming that the omission of the process and hotwater loads was an error, the fact that an error occurred, standing alone, does not
establish that Honeywell “knowingly” committed the error, even under a “reckless
disregard” standard. Honeywell has met its burden of “showing . . . that there is an
absence of evidence to support [Relators’] case,” and it is accordingly entitled to
judgment as a matter of law on this claim. 119
117
United Healthcare, 2016 WL 7378731 at *9.
118
See United Healthcare, 2016 WL 7378731 at *4.
119
Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 29 of 37
C. Infiltration Rates 120
Relators alleged in their SAC that Honeywell “deliberately overwrote” software
distributed by the Department of Energy (“DOE”) for calculating a structure’s passive
heating loss. 121 After this Court granted Honeywell’s second motion to dismiss, 122 the
Ninth Circuit reversed and remanded, finding that Relators’ proposed SAC properly pled
a fraud-in-the-inducement FCA claim.
The Ninth Circuit specifically noted Relators’
allegation that Honeywell had “falsified its estimates . . . by overwriting Department of
Energy software to include non-standard values for heat infiltration.” 123 In their motion
for summary judgment, however, Relators present no evidence to support this
allegation. While there is evidence suggesting that Honeywell did in fact use infiltration
rates lower than those recommended by DOE, 124 Relators have produced no evidence
that Honeywell “overwrote” the software. Instead, Relators now assert that Honeywell
used artificially low projected infiltration rates for FRA’s buildings, and that “Honeywell
knew that the true infiltration rates for the buildings would result in a larger postinstallation consumption of gas than the erroneous infiltration rates it had used for its
guarantee of savings.” 125
120
Infiltration rates refer to the “flow rate of outside air into a building” and are a measurement of
heating efficiency. See Docket 222 (Honeywell’s Mem.) at 39.
121
Docket 101 at ¶ 79(A).
122
See Docket 84.
123
See Berg v. Honeywell Intern., Inc., 580 Fed. App’x 559, 559–60 (9th Cir. 2014).
124
See, e.g., Docket 101-2 (EMP2 Audit) at 44.
125
Docket 302-1 at 31.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 30 of 37
As part of its contract proposals, Honeywell estimated the infiltration rates that
would exist during the period of contract performance. These infiltration rates were
used to project the costs of providing gas heat to each building. 126 In its proposals,
Honeywell used values between 0.15 and 0.3 ACH as the projected infiltration rates. 127
Honeywell later characterized these projections as “aggressive,” 128 and some of them
do seem lower than DOE suggests should be used. 129 But an FCA claim requires not
only a false statement, but also a showing that the defendant knew the statement to be
false when it was made. Whether a projection—even an aggressive projection—of
future infiltration rates could be “false” when made presents a conceptual conundrum.
Relators cite to no evidence in the record upon which a reasonable jury could find that
Honeywell knew its infiltration rate projections were false statements when it made
them.
Relators also alleged in their SAC that Honeywell had misrepresented an
infiltration rate of 0.15 as a “normal” rate. 130 At his deposition, Timothy Berg, one of the
relators and an FRA employee, explained that he based this assertion on surveying
forms completed by Honeywell personnel that were submitted with the contract
126
See Docket 223-61 (Berg Dep.) at 27–29.
127
E.g., Docket 223-23 at 11. “ACH” refers to “air changes per hour,” reflecting the insulation
effectiveness of a building.
128
Docket 265-16 (Honeywell Executive Briefing Powerpoint) at 4.
129
See Docket 223-54 (DOE Manual) at 25 (recommending rates of 0.3 ACH for “tightly
constructed buildings”).
130
Docket 101 at ¶ 24 (“The proposal documents knowingly and fraudulently and falsely
represented that normal Department of Energy infiltration factors had been used.”)
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 31 of 37
proposals. 131 Those forms indicated that the buildings had “normal” infiltration rates. 132
But as Mr. Berg testified, that assessment reflected “the surveyor’s interpretation of how
they would rate this building” at the time of the survey, before the project had begun.133
Thus, the forms did not indicate that the projected 0.15 ACH infiltration rates were
“normal,” but that the buildings’ preexisting infiltration rates were normal. In any event,
in their summary judgment briefing, Relators no longer press the assertion that
Honeywell misrepresented a 0.15 ACH infiltration rate as “normal.”
Relators instead now argue that Honeywell knew that the 0.15 ACH infiltration
rates were impossible to achieve. They base this claim on comments that Steve Craig,
a Honeywell executive, made during a July 25, 2006 conference call, six years after the
task orders were issued. According to Relator Berg’s recollection in 2010, during that
2006 conference call Mr. Craig “told everyone present that Honeywell knew the project
would never save energy and was not viable from the very beginning.” 134 Mr. Berg’s
declaration, and the Relators in their briefing, also point to a memorandum written by
Randy Tyler, a government employee, two weeks after the July 2006 call. But that
contemporaneous memorandum is at odds with Mr. Berg’s later recollection. In Mr.
Tyler’s memorandum, he posits that Mr. Craig “stated that the reason the energy saving
for the project could not be realized was because of the infiltration and that this was due
to the building heating system controls and the occupants opening windows and doors
131
See Docket 223-61 (Berg Dep.) at 28–29.
132
See, e.g., Docket 223-27 at 7.
133
Docket 223-61 at 28.
134
Docket 53-1 (Berg Decl.) at 22, ¶ 44.
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 32 of 37
in the buildings.” 135 According to Mr. Tyler, Mr. Craig contended that the government
had agreed to take certain measures to improve the infiltration rates, and that “without
this work, this project was not a viable project.” 136
Relators also cite to Mr. Smith’s declaration to support this claim. 137 But Mr.
Smith’s recollection does not offer additional support for Relators’ assertion as to
Honeywell’s knowledge and beliefs in 2000. For Mr. Smith’s declaration states only that
in 2006 Mr. Craig “admitted that the project would not save energy or money”; it does
not suggest that Mr. Craig said anything regarding what Honeywell knew or believed in
2000. 138
Although the Court views the evidence in the light most favorable to Relators and
draws all reasonable inferences in their favor, those “inferences are limited to those
upon which a reasonable jury might return a verdict.” 139 Mr. Craig’s full statement does
not support Relators’ supposition that Honeywell knew the infiltration rates were “false”
in 2000. At most, the evidence suggests that attaining the infiltration rates Honeywell
projected was essential to achieving savings, and those infiltration rate projections were
not realized. It may be that Honeywell later blamed this failure on the government, but
whether responsibility for attaining the infiltration rates belonged to Honeywell or to the
135
Docket 53-21 (Tyler Aug 7, 2006 Mem.) at 2–3.
136
Docket 53-21 at 3 (emphasis added).
137
See Docket 302-1 at 31–32.
138
Docket 52 (Smith Decl.) at 13, ¶ 30.
139
United States ex rel. Anderson v. N. Telecom, Inc., 52 F.3d 810, 815 (9th Cir. 1995) (citing
T.W. Elec. Servs. Inc. v. Pac. Elec. Contractors Ass’n, 809 F.2d 626, 630–31 (9th Cir. 1987)).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 33 of 37
government is simply irrelevant to whether the projection of low infiltration rates was
knowingly false when it was made in 2000. Optimism, even ill-founded optimism, does
not render a statement false. 140
Mr. Berg’s 2010 declaration is at odds with the extensive contemporaneous
documentary evidence and is unsupported by any other evidence. It omits the essential
context of Mr. Craig’s 2006 statement—that the projected savings were conditioned on
actions Honeywell believed the government would take—context that the Tyler
memorandum provides. The Court finds that the declaration is insufficient to permit “a
fair-minded jury [to] return a verdict for the plaintiff” on this claim, and that Honeywell is
therefore entitled to judgment as a matter of law with regard to the infiltration claim. 141
Honeywell also argues that it is entitled to summary judgment on this claim
because it disclosed the infiltration rates it projected to the government. 142 But because
the Court concludes that there is insufficient evidence to permit a reasonable jury to find
the infiltration rates were knowingly false, it need not address whether any disclosure to
the government of these rates also obviates any assertion that they were knowingly
false.
140
See, e.g., N. Telecom, 52 F.3d at 815 (“[P]roof of mistakes ‘is not evidence that one is a
cheat,’ and ‘the common failings of engineers and other scientists are not culpable under the
Act.’” (quoting Wang v. FMC Corp., 975 F.2d 1412, 1420–21 (9th Cir. 1992)).
141
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252 (1986)).
142
See Docket 222 at 39–40; Docket 223-28 at 7 (Proposal #4); Docket 265-20 (Dalsfoist Dep.)
at 7 (“The infiltration rates were provided to us.”).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 34 of 37
D. Adjustment for Destruction of Buildings
Relators assert that “Honeywell failed to allow for adjustment of the baseline for
buildings that were to be demolished.” 143 Whether or not this is true, Relators do not
allege, much less present evidence to support, that Honeywell did this “knowingly.” 144
That is, although Relators allege that Honeywell made an error in calculating the
baseline, they have not presented any evidence to demonstrate that any such error was
intentional or “knowing.” The FCA does not impose liability for “innocent mistakes” or
“mere negligent misrepresentations.” 145
Without such evidence, no reasonable jury
could conclude that the omission was done “knowingly.”
IV. Relators’ Opposition
Although Relators do not press the theory in their own motion for summary
judgment, in their opposition to Honeywell’s motion they revive their claim that
Honeywell misrepresented the contracts as “legal” under the relevant ESPC statutes
and regulations. 146 But a legal assertion of this type cannot form the basis of an FCA
claim. While a false promise to comply with statutory or regulatory requirements might
be sufficient to support an FCA claim, 147 Honeywell’s proffered view of the legality of a
143
Docket 302-1 at 4.
144
Relators’ briefing does not meaningfully address this issue, referencing the omission only in
a few parentheticals. See Docket 302-1 at 32, 34. Relators do not raise the issue again in their
reply or their opposition to Honeywell’s summary judgment motion.
145
United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1174 (9th Cir. 2006)
(quoting United States ex rel. Hopper v. Anton, 91 F.3d 1261, 1267 (9th Cir. 1996)); see also N.
Telecom, 52 F.3d at 815.
146
See Docket 303-1 at 13.
147
E.g., United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1174–75 (9th Cir.
2006) (finding a plausible FCA claim premised on knowingly false assurances that the
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 35 of 37
contract is entirely different. For any such legal assertion is not a promise or statement
of fact at all, so much as it is an opinion.
Taking a position on a “disputed legal
issue . . . is not enough to support a reasonable inference that [the claim] was false
within the meaning of the False Claims Act.” 148
The government is just as well-situated (indeed, perhaps better situated) to
assess the legality of government contracting in the complex world of the AntiDeficiency Act and appropriations. 149 Because legal opinions can reasonably vary, they
generally cannot constitute a “false” statement for purposes of the FCA. The Court
“need not decide whether the defendants correctly interpreted [the applicable statutes]
since a statement that a defendant makes based on a reasonable interpretation of a
statute cannot support a claim under the FCA if there is no authoritative contrary
interpretation of that statute.” 150
Accordingly, Honeywell is entitled to summary
judgment on such a claim if Relators intended to raise it.
CONCLUSION
Upon review of the extensive exhibits and portions thereof cited by the parties,
and drawing all reasonable inferences in Relators’ favor, the Court concludes that
Defendants have met their burden to show that there is no genuine dispute as to any
material fact and that Defendants are entitled to judgment as a matter of law.
As
contractor would follow the law).
148
Hagood II, 81 F.3d at 1477 (emphasis in original).
149
See United States ex rel. Becker v. Westinghouse Savannah River Co., 305 F.3d 284, 288
(4th Cir. 2002) (noting that the government “had at least as much knowledge” as the contractordefendant “regarding Congressional authority for the [challenged conduct]”).
150
United States ex rel. Hixson v. Health Mgmt. Sys., Inc., 613 F.3d 1186, 1190 (8th Cir. 2010).
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 36 of 37
detailed above, Relators have not presented sufficient evidence from which a
reasonable jury could return a verdict in their favor. Defendants have demonstrated that
Relators cannot show that a triable issue exists as to whether Honeywell made a false
statement in 2000 which it knew to be false at that time. For this reason, Honeywell is
entitled to summary judgment on Relators’ fraud-in-the-inducement claim. Because the
Court grants summary judgment to Defendants, it will deny Relators’ motion for partial
summary judgment.
Therefore, IT IS ORDERED that Defendants’ Motion for Summary Judgment at
Docket 220 is GRANTED. Relators’ Motion for Partial Summary Judgment at Docket
225 is DENIED.
All other pending motions are DENIED as moot. The final pretrial conference
scheduled for January 9, 2017 and the trial scheduled to commence January 23, 2017
are VACATED. The Clerk of Court is directed to enter a judgment accordingly.
DATED this 29th day of December, 2016 at Anchorage, Alaska.
/s/ Sharon L. Gleason
UNITED STATES DISTRICT JUDGE
Case No. 3:07-cv-00215-SLG, United States ex rel. Berg et al. v. Honeywell Int’l, Inc. et al.
Order re Cross Motions for Summary Judgment
Page 37 of 37
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?