Design Trend International Interiors, Ltd. v. Cathay Enterprises, Inc.
Filing
69
ORDER granting in part and denying in part 32 Cathay's Motion for Rehearing. IT IS FURTHER ORDERED that 30 Judgment is VACATED. The reference to the bankruptcy court of case number 2:04-ap-01085-RTB is WITHDRAWN pursuant to 28 U.S.C. § 157(d) for purposes of making additional findings of fact and conclusions of law. IT IS FURTHER ORDERED that the parties shall appear for oral argument on Thursday, November 3, 2011, at 10:00 a.m., at the Sandra Day OConnor U.S. Courthouse, Courtroom 504, 401 W. Washington Street, Phoenix, Arizona. Signed by Judge Neil V Wake on 10/5/11.(LSP)
1
WO
2
3
4
5
6
IN THE UNITED STATES DISTRICT COURT
7
FOR THE DISTRICT OF ARIZONA
8
9
Design Trend International Interiors, Ltd.,
an Arizona corporation,
10
ORDER
Appellant,
11
vs.
12
Cathay Enterprises,
corporation,
No. CV-10-01079-PHX-NVW
13
Inc.,
an
Arizona
Appellee.
14
15
16
Before the Court is Cathay’s “Motion for Rehearing” (Doc. 32). For the reasons
17
stated below, this motion is granted in part and denied in part, and the judgment will be
18
vacated.
19
I.
LEGAL STANDARD
20
Cathay’s motion for rehearing is effectively a motion to reconsider the March 29,
21
2011 Order. A motion to reconsider requires “a showing of manifest error or a showing
22
of new facts or legal authority that could not have been brought to [the Court’s] attention
23
earlier with reasonable diligence.” LRCiv 7.2(g)(1).
24
II.
ISSUES THAT DO NOT MERIT RECONSIDERATION
25
A.
Election of Remedies
26
Cathay principally argues against this Court’s conclusion that Cathay elected to
27
permit Design Trend to continue performing the contract. Design Trend made this
28
election-of-remedies argument in its opening appeal brief: “The consequence of Cathay’s
1
acceptance of Design Trend’s performance under Arizona law is that Cathay waived any
2
breach. It is fundamental that Cathay could not continue to accept Design Trend’s
3
performance and also refuse to make payment.” (Design Trend Br. 23; Doc. 18 at 29.)
4
Cathay argued in response, “There is substantial evidence supporting [the bankruptcy
5
court’s] finding that Cathay did not waive Design Trend’s untimely performance.”
6
(Cathay Br. 21; Doc. 23 at 21.)
7
8
9
10
11
12
13
14
15
16
This Court recognized that “the bankruptcy court did not express any finding
about waiver,” but because “the parties argue as if it did” and
because the bankruptcy court could not have ruled in favor of
Cathay without rejecting Design Trend’s waiver theory [i.e.,
election of remedies], the Court will infer a no-waiver finding
[i.e., a finding that Cathay did not elect performance over
damages] and review it accordingly. See Vance v. Am.
Hawaii Cruises, Inc., 789 F.2d 790, 792–93 (9th Cir. 1986)
(reviewing court may imply findings that necessarily flow
lower court’s explicit findings); Carr v. Yokohama Specie
Bank, Ltd., 200 F.2d 251, 255 (9th Cir. 1953) (“Nor is it
necessary that the trial court make findings asserting the
negative of each issue of fact raised. It is sufficient if the
special affirmative facts found by the court, construed as a
whole, negat[e] each rejected contention.”).
(Doc. 29 at 12–13.)
17
Cathay now argues that this Court could not legitimately reach this conclusion
18
because Design Trend did not present an election-of-remedies argument until Design
19
Trend appealed to this Court.
20
argument by not raising it first with the bankruptcy court.
Therefore, says Cathay, Design Trend waived the
21
This challenge lacks merit because Cathay, ironically, has waived it. Design
22
Trend unequivocally raised an election-of-remedies argument in its opening appeal brief.
23
If Cathay wanted to object that Design Trend had not raised that argument below, it
24
should have done so in its response brief. Instead, it attacked the argument on its merits.
25
This Court was therefore entitled to assume that Design Trend had presented an election-
26
of-remedies argument below. If that assumption was erroneous, Cathay bears the blame
27
and cannot now unravel the Court’s analysis on this basis.
28
-2
1
In any event, although the bankruptcy court did not express any finding regarding
2
election of remedies, the issue permeates the record, including the bankruptcy court’s
3
conclusion: “[Design Trend] breached its amended construction contract with [Cathay]
4
by not completing its work on the project timely per the schedule agreed to by the parties;
5
and [Design Trend] did not complete its work within a reasonable period of time in any
6
event.” (Design Trend Tr. 260.) Mention of “reasonable period of time” is an element of
7
the election-of-remedies principle. See, e.g., Joseph M. Perillo, Calamari and Perillo on
8
Contracts § 11.33 (6th ed. 2009) (“If . . . the owner allows the contractor to continue and
9
the contractor subsequently finishes within a reasonable time from the time of the
10
election, the owner must pay the price but is still entitled to damages for partial breach
11
because of the late completion.”).
12
In addition, the bankruptcy court’s various statements about Design Trend’s
13
choice not to pursue an unjust enrichment claim show that the bankruptcy court
14
understood the election-of-remedies consequences of its ruling. The bankruptcy court
15
knew that it was excusing Cathay from payment for completed work because Design
16
Trend delayed completion so long that it supposedly amounted to a material breach.
17
Thus, the bankruptcy court knew that it was foreclosing Design Trend’s normal route for
18
getting paid — i.e., as a matter of contract, Cathay having elected to permit Design Trend
19
to finish the job — and leaving Design Trend to an equitable fallback. In short, whether
20
or not Design Trend specifically raised an election-of-remedies argument below, the
21
bankruptcy court understood and considered it. Accordingly, it was not error for this
22
Court to review the argument.
23
B.
24
Cathay not only challenges the appropriateness of reviewing the election-of-
25
26
27
28
Cathay Elected Performance
remedies argument, but also this Court’s ultimate disposition. Cathay claims that
[i]t is in the public interest for citizens to be able to go to the
Registrar to compel a licensed contractor to correct work
which fails to meet the minimum workmanship standards
without fear of waving substantive legal rights. The Court’s
-3
ruling would have a chilling effect on the use of the
Registrar’s enforcement mechanisms by treating recourse to
the Registrar as an election of remedies.
1
2
3
(Doc. 32 at 8–9.)
4
Cathay’s public policy concerns are misdirected. It has long been the public
5
policy of Arizona contract law, and of Anglo-American contract law generally, that
6
contracting parties get either the performance for which they contracted or damages. If a
7
party gets performance but it comes late, the party can normally sue for damages
8
foreseeably caused by the delay (although Cathay contracted away that right in this case).
9
But the party cannot accept performance and refuse to pay for that performance.
10
Cathay’s argument endangers these principles.
Cathay would give property
11
owners an incentive to look for workmanship violations and withhold payment while
12
complaining to the Registrar. If the Registrar sustains those complaints, the property
13
owner pays nothing more to the contractor, even if the contractor fixes the workmanship
14
violations.
15
C.
“Within a Reasonable Time”
16
Cathay also challenges this Court’s conclusion that the bankruptcy court clearly
17
erred in concluding that Design Trend did not complete its work within a reasonable
18
period of time from the time Cathay elected to permit performance. Cathay has offered
19
no new argument or evidence here, and no reconsideration is warranted.
20
D.
Contract Price
21
Cathay next asks this Court to backtrack on its damages calculation because,
22
Cathay argues, the contract price of $1,209,737.45 (as renegotiated in July 2001) cannot
23
be established by collateral estoppel.
24
contract price as $1,209,737.45 in their “Findings of Fact,” Cathay claims that these
25
findings do not have collateral estoppel effect because the issue of contract price was not
26
actually litigated.
Although two Registrar ALJs described the
27
Even if the Registrar proceedings did not establish the contract price, it would
28
have been clear error for the bankruptcy judge to conclude that the renegotiated contract
-4
1
price was anything other than $1,209,737.45.
Cathay twice represented the
2
$1,209,737.45 figure to the Registrar, the Registrar twice accepted that figure, and
3
Cathay never sought to correct it. Cf. Hawkins v. State, 183 Ariz. 100, 104, 900 P.2d
4
1236, 1240 (Ct. App. 1995) (“Arizona case law also makes clear that the failure to seek
5
judicial review of an administrative order precludes attacking the order by means of a
6
separate complaint.” (internal quotation marks omitted)). Further, several other exhibits
7
admitted at trial confirm that Cathay knew that the contract price was $1,209,737.45.
8
(See, e.g., Doc. 45 at 38, 40, 48, 74 (statements by Cathay or its principal acknowledging
9
that the parties modified the contract price to $1,209,737.45 in July 2001).)
10
Cathay nonetheless insists that $1,209,737.45 cannot possibly be the correct
11
contract price because it does not add up correctly when one assumes a cost-plus-9%
12
structure, which it believes it was promised.
13
concluded that Cathay’s contract with Design Trend was a fixed price contract, not a
14
cost-plus contract. This obsession with obtaining the right markup, irrespective of the
15
final price, is baffling. Cathay was not misled as to the final price it would be required to
16
pay. Cathay seems to acknowledge this, but also appears to insist that it did not get the
17
benefit of its bargain unless the final price equals cost-plus-9%. Again, however, Cathay
18
did not bargain for cost-plus-9%. Although Design Trend may have used that as a method
19
of calculating the fixed price, nothing in Cathay’s contracts with Design Trend mention a
20
cost-plus structure, much less guarantee that the fixed price would equal cost-plus-9%.
But the bankruptcy court correctly
21
E.
Affirmative Defenses
22
Cathay argues that the bankruptcy court’s ruling obviated the need to address its
23
affirmative defenses of mistake and unconscionability.
Given that this Court has
24
reversed the bankruptcy court, Cathay requests an opportunity to argue those affirmative
25
defenses.
26
The affirmative defenses Cathay relies on are mistake and unconscionability.
27
(Doc. 32 at 15–16.) These “defenses” simply restate Cathay’s untenable cost-plus theory.
28
(See Cathay Enterprises Inc.’s Post-Trial Memorandum, No. 2:04-ap-01085-RTB (Bankr.
-5
1
D. Ariz.), Doc. 114 at 13–16.) Accordingly, there is no need for further proceedings
2
regarding Cathay’s mistake and unconscionability defenses.
3
F.
Offsets for Subcontractor Payments
4
Cathay claims it still deserves “offsets for several subcontractors which Cathay
5
had to pay because Design Trend refused.” (Doc. 57 at 9.) The Court already awarded a
6
$36,199.58 offset (see Doc. 29 at 15:14–20) — which was the total offset Cathay asked
7
for from the bankruptcy court, at least with respect to payments made to Design Trend’s
8
subcontractors (see Cathay Enterprises Inc.’s Post-Trial Memorandum, No. 2:04-ap-
9
01085-RTB (Bankr. D. Ariz.), Doc. 114 at 7). Cathay therefore has nothing more to
10
claim in terms of payments it made to subcontractors.
11
III.
ISSUES THAT MAY MERIT RECONSIDERATION
12
A.
“Items that Were Never Provided to Cathay”
13
Cathay claims that Design Trend did not provide certain items that it had promised
14
to provide, including headboards, toasters, end tables, vanity lights, and various other
15
items. Cathay bought these items itself for $20,801.65. (Doc. 57 at 15–16.) Cathay
16
claims this amount as an offset. The briefs currently before the Court do not suffice to
17
resolve this issue. Additional findings and conclusions are therefore necessary.
18
B.
19
This Court awarded Design Trend principal damages of $184,830.07 — the
20
amount Cathay had yet to pay on its reduced obligation of $1,209,737.45, minus certain
21
offsets. The Court also concluded that Cathay is responsible for sales tax on that amount
22
at 4.875%, for a total of $9,010.47. Cathay argues that this award of sales tax allows
23
Design Trend to have its cake and eat it too. If the parties originally agreed to a fixed
24
price of $1,277,000 inclusive of sales tax (as Design Trend claims), then why is the
25
reduced fixed price of $1,209,737.45 exclusive of sales tax? To this, Design Trend
26
responds,
27
28
Sales Tax
The revised budget clearly shows that the $1.209 million
figure only included sales tax through April 2001. . . . [T]he
revised contract price of $1.209 million was conditioned on
-6
[Cathay] securing the tax waiver for the balance of the
reduced tax yet to be paid. If [it] failed to obtain the waiver,
[it] had to pay that additional sales tax as would any other
customer.
1
2
3
4
5
6
(Doc. 44 at 15.) That contention is not clearly established by the record. Accordingly,
additional findings of fact are necessary to determine whether Cathay is liable for the
$9,010.47 in sales tax.1
C.
Procedure for Reconsideration
7
Cathay’s motion for reconsideration will be granted as to the $20,801.65 in items
8
Cathay allegedly had to buy when Design Trend did not supply them, and the $9,010.47
9
in sales tax. The Court will withdraw the bankruptcy court reference, see 28 U.S.C.
10
§ 157(d), and hear oral argument on these two issues. Oral argument should address both
11
the merits of these issues as well as whether Design Trend would simply prefer to
12
conclude these proceedings by permitting the Court to reduce the judgment by
13
$29,812.12.
14
If oral argument is not sufficient to resolve these issues, the Court will establish a
15
briefing schedule, with the goal of additional findings and conclusions, but based solely
16
on testimony and exhibits admitted at trial.2 This procedure will speed up the resolution
17
of this dispute which has now been in litigation for ten years.
18
IT IS THEREFORE ORDERED that Cathay’s “Motion for Rehearing” (Doc. 32)
19
is GRANTED with respect to items Cathay allegedly had to buy when Design Trend did
20
not supply them, and with respect to sales tax, and otherwise DENIED.
21
22
23
24
25
26
27
1
If Design Trend’s tax-waiver argument is correct, Design Trend would
theoretically be entitled to more sales tax. Cathay paid Design Trend $200,000 after
April 2001. This $200,000 was therefore exclusive of sales tax. However, when the
Court calculated sales tax, it assumed that Cathay did not owe any tax on that $200,000
payment. Had the Court been informed otherwise, the amount would have increased to
$18,760.47 ($384,830.07 * 0.04875). But Design Trend has not advanced this argument
here, and the Court deems it waived.
2
The Court has conferred with Judge Baum, and he agrees to this procedure.
28
-7
1
IT IS FURTHER ORDERED that the Judgment (Doc. 30) is VACATED.
2
IT IS FURTHER ORDERED that the reference to the bankruptcy court of case
3
number 2:04-ap-01085-RTB is WITHDRAWN pursuant to 28 U.S.C. § 157(d) for
4
purposes of making additional findings of fact and conclusions of law.
5
IT IS FURTHER ORDERED that the parties shall appear for oral argument on
6
Thursday, November 3, 2011, at 10:00 a.m., at the Sandra Day O’Connor U.S.
7
Courthouse, Courtroom 504, 401 W. Washington Street, Phoenix, Arizona.
8
Dated this 5th day of October, 2011.
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?