ORDER denying 169 B&L's motion for leave to file third-party complaint for contribution. IT IS FURTHER ORDERED GRANTING B&L's 171 motion for leave to file an amended answer that asserts a new statute of limitations affirmative defense. The Clerk of Court shall file B&L's lodged proposed amended answer. (Doc. 171-1.) Signed by Senior Judge Stephen M McNamee on 1/24/2014. (ALS)

Download PDF
1 WO 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE DISTRICT OF ARIZONA 8 9 Knight Transportation, Inc., et al., 10 Plaintiffs, 11 vs. 12 Baldwin & Lyons, Inc., et al., 13 Defendants. 14 ) ) ) ) ) ) ) ) ) ) ) No. CV-10-1835-PHX-SMM ORDER 15 Pending before the Court is Defendants Baldwin & Lyons, Inc., et al. (“B&L’s”) 16 motion for leave to file third-party complaint for contribution. (Doc. 169.) B&L has lodged 17 their proposed third-party complaint with the Court. (Doc. 169-1.) Also pending is B&L’s 18 motion for leave to file an amended answer that includes a new affirmative defense. (Doc. 19 171.) B&L has lodged their proposed amended answer. (Doc. 171-1.) Both motions are 20 fully briefed. (Docs. 176-78, 180-81.) The Court will deny B&L’s motion for leave to file 21 a third-party complaint for contribution and grant B&L’s motion for leave to file an amended 22 answer that includes a statute of limitations affirmative defense.1 23 Background 24 In 2001, B&L and Plaintiffs Knight Transportation, Inc., et al. (“Knight”) entered into 25 a contractual relationship (“Claims Contract”) in which B&L agreed to administer the 26 27 28 1 B&L has requested oral argument. The Court will not set oral argument on these motions because based on the submitted legal memoranda, oral argument would not aid the Court’s decisional process. See e.g., Partridge v. Reich, 141 F.3d 920, 926 (9th Cir. 1998). 1 work-related injury claims of Knight. (Doc. 1-1 at 47-48.) B&L submits that from August 2 1, 2001, until about February 1, 2009, B&L handled all work-related injury claims that 3 Knight referred to B&L for handling. (Doc. 76 at 11.) Subsequently, in July 2010, Knight 4 filed suit alleging that B&L negligently handled its worker’s compensation claims; Knight 5 contends that 92 of the 1,873 claims referred to B&L over the course of their relationship 6 were mishandled in some fashion. (Doc. 67, Doc. 82 at 2.) 7 With regard to at least 15 of the 92 claims at issue, B&L hired Third Party 8 Administrators (“instate TPAs”), Crawford & Company (“Crawford”) and/or CorVel 9 Corporation and CorVel Enterprise Comp., Inc. (collectively “CorVel”) to adjust those 10 claims. (Doc. 169 at 2.) Using the opinions and calculations of Knight’s expert’s, B&L 11 alleges that the 15 claims adjusted by Crawford and CorVel amount to over $1.6 million of 12 Knight’s alleged damages. 13 On March 4, 2011, the Court issued its case management order stating that “[t]he 14 deadline for joining parties, amending pleadings, and filing supplemental pleadings is 60 15 days from the date of this Order.” (Doc. 19.) The resulting deadline for joining parties and 16 amending pleadings was May 3, 2011. On March 16, 2012, the Court granted leave and 17 Knight filed an amended complaint. (Docs. 66, 67.) On April 20, 2012, B&L filed its 18 answer to the amended complaint. (Doc. 76.) Since the Court’s initial case management 19 order, the case management deadlines have been extended five times. (Docs. 50, 62, 73, 123, 20 165.) The current discovery cut-off deadline is August 8, 2014. 21 Standard of Review 22 Amending Case Management Deadlines 23 Once the court files its pretrial case management order pursuant to Federal Rule of 24 Civil Procedure 16 establishing a timetable for amending pleadings, Rule 16 standards 25 control any modification. See Johnson v. Mammoth Recreations, Inc., 975 F.2d 604, 607-08 26 (9th Cir. 1992). The case management schedule shall not be modified except by leave of 27 court upon a showing of good cause. Fed. R. Civ. P. 16(b)(4). The good cause standard 28 primarily considers the diligence of the party seeking the amendment. See Johnson, 975 F.2d -2- 1 at 609. The court may modify the pretrial schedule if amendment cannot reasonably be 2 sought despite the diligence of the party seeking the modification. Id. 3 Rule 15 Amendment 4 A party seeking to amend its pleading must both establish good cause for modifying 5 the case management schedule and demonstrate that amendment of pleadings is proper under 6 Fed. R. Civ. P. 15. See id. at 608. Under Rule 15, although leave to amend “shall be freely 7 given when justice so requires,” it “is not to be granted automatically.” Zivkovic v. Southern 8 California Edison Co., 302 F.3d 1080, 1087 (9th Cir. 2002) (citing Jackson v. Bank of 9 Hawaii, 902 F.2d 1385, 1387 (9th Cir. 1990)). The court may deny a motion for leave to 10 amend if permitting an amendment would, among other things, cause an undue delay in the 11 litigation or prejudice the opposing party. See Jackson, 902 F.2d at 1387; see also Solomon 12 v. North Am. Life & Cas. Ins. Co., 151 F.3d 1132, 1139 (9th Cir. 1998) (affirming the 13 district court’s denial of motion to amend pleadings filed on the eve of the discovery 14 deadline). The Ninth Circuit has summarized the appropriate Rule 15 factors to include the 15 following: (1) undue delay; (2) bad faith; (3) prejudice to the opponent; and (4) futility of 16 amendment. Loehr v. Ventura County Cmty. Coll. Dist., 743 F.2d 1310, 1319 (9th Cir. 17 1984). Granting or denial of leave to amend rests in the sound discretion of the trial court. 18 Swanson v. United States Forest Serv., 87 F.3d 339, 343 (9th Cir. 1996). 19 Rule 14 Impleader 20 If the party is able to establish good cause for modifying the case management 21 schedule, the party must also demonstrate that impleading a third-party defendant is proper 22 under Fed. R. Civ. P. 14. Under Rule 14, a defendant may bring a third-party complaint 23 against “a nonparty who is or may be liable to it for all or part of the claim against it” as a 24 matter of right. Fed. R. Civ. P. 14(a)(1). Thus, a party can assert a third-party claim where 25 a third-party defendant’s liability to the third-party plaintiff is dependent on the outcome of 26 the main claim and is secondary or derivative thereto. Stewart v. Am. Int’l Oil & Gas Co., 27 845 F.2d 196, 199 (9th Cir. 1988). If a defendant, and would-be third-party plaintiff, files 28 the third-party complaint more than 14 days after serving its original answer, however, “the -3- 1 third-party plaintiff must, by motion, obtain the court’s leave.” Fed. R. Civ. P. 14(a)(1). 2 Whether to grant leave is within the “sound discretion of the trial court.” United States v. 3 One 1977 Mercedes Benz, 708 F.2d 444, 452 (9th Cir. 1983). 4 The court’s purpose in granting leave to implead a third party is “to promote judicial 5 efficiency by eliminating the necessity for the defendant to bring a separate action against 6 a third individual who may be secondarily or derivatively liable to the defendant for all or 7 part of the plaintiff’s original claim.” Sw. Adm’rs, Inc. v. Rozay’s Transfer, 791 F.2d 769, 8 777 (9th Cir. 1986). However, the trial court may deny impleader based on the timeliness 9 of the motion, whether the impleader is likely to delay the trial, and whether the impleader 10 will cause prejudice to the original plaintiff. See Irwin v. Mascott, 94 F. Supp.2d 1052, 1056 11 (N.D. Cal. 2000). The court also considers whether the impleader will “disadvantage the 12 existing action” by, among other things, complicating and lengthening the trial, or 13 introducing extraneous questions. See Sw. Adm’rs, 791 F.2d at 777. 14 Discussion 15 Leave to File Third-Party Complaint 16 B&L contends that the Court should grant leave to implead Crawford and Corvel 17 because: 1) their motion was timely brought; 2) Knight’s litigation position that Crawford 18 and Corvel negligently handled the worker’s compensation claims assigned to them 19 demonstrates that B&L has a legitimate complaint against Crawford and Corvel; 3) 20 impleading Crawford and Corvel will not delay trial or lengthen the proceeding; and 4) B&L 21 will be prejudiced if not allowed to implead Crawford and Corvel. (Doc. 169.) 22 Knight responds that B&L has not established good cause for modifying the case 23 management deadlines because it was not diligent in seeking impleader. (Doc. 176.) Knight 24 further contends that the setting for trial will be delayed significantly because it will need to 25 conduct significant additional discovery if Crawford and Corvel are impleaded and further 26 that the matter will be lengthened and complicated by the addition of new parties and issues. 27 (Id.) Knight also argues that they will be prejudiced by having to defend itself against new 28 discovery, claims and counterclaims. (Id.) Finally, Knight contends that impleader is not -4- 1 the only way for B&L to recover against Crawford and Corvel as it can seek contribution in 2 a subsequent lawsuit. (Id.) 3 The Court agrees with Knight and for multiple reasons will deny leave for B&L to file 4 the requested third-party complaint against Crawford and Corvel. Most importantly, based 5 on the following, the Court finds that B&L was not diligent in pursuing the requested third- 6 party complaint. On March 4, 2011, the Court issued its Case Management Order stating that 7 “[t]he deadline for joining parties . . . is 60 days from the date of this Order.” (Doc. 19.) The 8 resulting deadline for joining parties was May 3, 2011. Subsequently, in August 2011, in 9 preparation for mediation, the preliminary report of Knight’s expert, Wayne Austin, was 10 provided to B&L. In this report, Knight’s expert alleged that B&L was liable for any 11 professional negligence committed by Crawford and Corvel. (Doc. 176-1 at 6.) In May 12 2012, Wayne Austin, after completing his review of the 92 claims against B&L, issued a 13 supplemental report alleging that B&L was liable for its supervision of the claims negligently 14 handled by Crawford and Corvel. (Doc. 169 at 4.) In August 2012, B&L issued subpoenas 15 to Crawford and Corvel and conducted discovery on this point. (Doc. 176-1 at 3.) However, 16 it was not until September 2013 that B&L moved for leave to file its third-party complaint. 17 The Court finds that B&L did not exercise the requisite diligence to implead Crawford and 18 Corvel. See Johnson, 975 F.2d at 609 (stating that “the focus of the [Rule 16(b)] inquiry is 19 upon the moving party’s reasons for seeking modification . . . [i]f that party was not diligent, 20 the inquiry should end”); see also Learjet, Inc. v. Oneok, Inc., 715 F.3d 716, 736 (9th Cir. 21 2013) (finding nine month delay showed lack of movant’s diligence). 22 The Court further finds that these proceedings will be unduly lengthened and 23 complicated by the addition of new parties and issues at this time. This is already an 24 extremely complicated and time-consuming case. Since the initial case management order 25 in March 2011, it has been necessary for the Court to grant the parties five extensions to the 26 case management deadlines. (Docs. 50, 62, 73, 123, 165.) The parties are performing full- 27 scale investigations into the handling of 93 worker’s compensation claims. Additional 28 parties and additional claims will mean additional witnesses, written discovery, depositions, -5- 1 and documents, and the Court has already had numerous, and lengthy discovery dispute 2 hearings. The Court finds that adding these new parties and new issues will unduly lengthen 3 this already protracted litigation. 4 Finally, the Court rejects B&L’s argument that this is the only litigation by which it 5 may recover contribution from Crawford and Corvel. The Court finds that neither the 6 Arizona Uniform Contribution Among Tortfeasors Act (“UCATA”), A.R.S. § 12-2506, nor 7 related case law, including Wiggs v. City of Phoenix, 198 Ariz. 367, 10 P.3d 625 (2000), 8 prevents B&L from initiating a separate lawsuit for indemnity or contribution against 9 Crawford and Corvel. For example, subsequent lawsuits are specifically contemplated by 10 A.R.S. § 12-2506(B), which states that nonparty at fault allocations shall not play any role 11 in any subsequent action. Similarly, Wiggs does not preclude a subsequent indemnity or 12 contribution action. In Wiggs, the plaintiff’s daughter was killed by an automobile while 13 crossing a street in the City of Phoenix (“City”). Id. at 368, 10 P.3d at 626. The plaintiff 14 sued the City for wrongful death, alleging improper maintenance of the streetlight. Id. The 15 City conceded its non-delegable duty to maintain its streets in a reasonably safe condition but 16 named as a non-party at fault Arizona Public Service (“APS”), an independent contractor 17 obligated to operate and maintain the streetlight under a contract with the City. Id. The 18 Supreme Court held that the vicarious liability of an employer of an independent contractor, 19 where that employer has a non-delegable duty, was unaffected by the comparative fault 20 statute. Id. at 371, 10 P.3d at 629. In its ruling, the supreme court specifically stated that 21 “[t]he employer may seek indemnity against the independent contractor in cases of pure 22 vicarious liability, or contribution against an independent contractor in cases in which the 23 employer has some degree of independent liability.” Id. 24 Based on the same reasoning as Wiggs, if B&L is found vicariously liable for 25 negligence committed by Crawford and Corvel, it may seek indemnity and/or contribution 26 from them in a subsequent action. Neither case law nor UCATA precludes such a 27 subsequent action. Based on the foregoing, the Court denies B&L’s motion for leave to file 28 a third-party complaint against Crawford and Corvel for contribution. -6- 1 Leave to File Amended Answer 2 Next, B&L requests that the Court grant it leave to file an amended answer including 3 a statute of limitations affirmative defense because: 1) B&L recently obtained evidence from 4 Shelly Howick that she was informally involved with Knight’s worker’s compensation 5 claims prior to the formal contractual relationship that she established with Knight in October 6 2008; 2) prior to obtaining this new evidence, B&L did not have a reasonable belief 7 sufficient to satisfy its Rule 11 obligations for asserting a statute of limitations defense; 3) 8 Knight’s failure to produce documents related to the time frame of January 2008 to July 2008 9 kept B&L from thoroughly investigating whether it had a statute of limitations defense; and 10 4) Knight will not be prejudiced by addition of the statute of limitations affirmative defense. 11 (Docs. 171, 180.) 12 Knight contends that B&L has not established good cause for modifying the case 13 management deadlines or Rule 15 standards for leave to file an amended answer because the 14 evidence recently obtained is not new, rather B&L already knew this information but chose 15 not to pursue a statute of limitations defense. (Doc. 177.) Knight further contends that B&L 16 has not been diligent in discovery regarding its potential statute of limitations defense even 17 though they had more than adequate opportunity. (Id.) Finally, Knight argues that 18 amendment to include a statute of limitations defense would prejudice them because it would 19 turn back the clock and require substantial additional discovery. (Id.) 20 The Court will consider and discuss B&L’s statute of limitations arguments, Knight’s 21 contentions, and relevant case law, all in the context of these labored case proceedings, 22 which have now passed the 3-year mark. First, B&L must satisfy good cause under Rule 16 23 to modify the case management order. The good cause standard primarily considers the 24 diligence of the party seeking the amendment. See Johnson, 975 F.2d at 609. The focus of 25 the inquiry is upon the moving party’s reasons for seeking modification. Id. Second, B&L 26 must satisfy Rule 15’s factors for allowing amendment to its answer. Those factors include 27 undue delay, bad faith, dilatory motive and undue prejudice to Knight. See Waldrip v. Hall, 28 548 F.3d 729, 732-33 (9th Cir. 2008). -7- 1 Recent Evidence 2 First, B&L argues that during the August 2013 re-deposition of Shelly Howick, it 3 recently became aware that she was informally involved with Knight’s worker’s 4 compensation claims prior to her relationship with Knight being formalized in October 2008. 5 (Doc. 171 at 3-8.) Based on this new evidence, B&L seeks to develop its argument that the 6 trigger which commences the running of Knight’s professional negligence claim arose 7 earlier. (Id.) Knight counters that B&L already had an adequate opportunity to investigate 8 the extent of Howick’s involvement with Knight’s worker’s compensation claims at her first 9 deposition based on information B&L obtained through discovery. (Doc. 177.) 10 The Court first finds that Knight is correct that B&L had information that Knight was 11 unhappy with the performance of B&L prior to July 2010 and that B&L is responsible for 12 thoroughly conducting its own investigation. While it is also true that B&L could have more 13 thoroughly questioned Howick at her first deposition, the Court further finds that in July 14 2010 Knight argued to B&L and took the position that B&L did not have a statute of 15 limitations affirmative defense because Howick did not have a formal relationship with 16 Knight prior to October 2008. (Doc. 171-1 at 16.) 17 Thus, as to diligence or undue delay, the “recent” evidence cuts both ways. While 18 B&L could have conducted a more thorough investigation, its investigation was hindered by 19 the legal position Knight took regarding Howick’s responsibilities with Knight prior to 20 October 2008. The Court does not find that B&L lacked diligence or unduly delayed based 21 on these facts. 22 Rule 11 23 B&L argues that it did not have a valid statute of limitations argument until it obtained 24 the new Howick evidence and recently obtained emails regarding Howick’s informal role 25 with Knight regarding its worker’s compensation claims. (Docs. 171, 180.) Absent a valid 26 statute of limitations argument, B&L contends that it would have run afoul of Rule 11 by 27 pleading the statute of limitations affirmative defense. Knight counters that the Rule 11 issue 28 is not whether B&L had a “valid” statute of limitations defense but whether B&L, upon -8- 1 information and belief, could legitimately assert the affirmative defense. 2 The statute of limitations in a professional negligence case begins to run when a 3 reasonable client is put on notice to investigate whether the injury suffered may be 4 attributable to negligence. See Walk v. Ring, 202 Ariz. 310, 318, 44 P.3d 990, 998 (App. 5 2002). The failure to achieve an expected result, is not, as a matter of law, always sufficient 6 to trigger the statute of limitations in a professional negligence case. Id. at 315, 44 P.3d at 7 995. Something more is required than the mere knowledge that one has suffered an adverse 8 result while under the care of professional fiduciary. Id. 9 In this case, the key time mark on the statute of limitations issue for professional 10 negligence is July 2, 2008, which is two years prior to Knight initiating this civil action. 11 B&L seeks leave to include a statute of limitations defense so that it can argue that the trigger 12 for the running of Knight’s professional negligence claim arose earlier than July 2, 2008. 13 The Court agrees with Knight that B&L would not have run afoul of Rule 11 if it had 14 asserted the affirmative defense in its answer. However, that does not preclude the Court 15 from granting leave to B&L to assert it now, so long as B&L satisfies good cause for the 16 modification and Rule 15 amendment. See Strategic Diversity Inc., v. Alchemix Corp., No. 17 CV 07-929-PHX-GMS, 2013 WL 4511971 at *11 (D. Ariz. August 28, 2013) (citing Owens 18 v. Kaiser Found. Health Plan, Inc., 244 F.3d 708, 713 (9th Cir. 2001) (stating that a 19 defendant’s failure to raise an affirmative defense in its answer does not necessarily waive 20 the defense; the defense may be raised later “if the delay in raising [it] does not prejudice the 21 plaintiff”)); see also Camarillo v. McCarthy, 998 F.2d 638, 639 (9th Cir. 1993). 22 Knight’s Failure to Produce Documents 23 B&L asserts that it has now learned that Howick, through Blue Star and another 24 entity, TransStar, was actively involved in the process to replace B&L as Knight’s third party 25 administrator for worker’s compensation claims as early as January 2008. (Doc. 180 at 8.) 26 On this point, B&L further asserts that Howick’s and Blue Star’s correspondence and related 27 documents have not yet been fully produced in discovery and that B&L still expects to 28 receive re-subpoenaed documents from Howick and Blue Star sometime after October 2013. -9- 1 (Id.) B&L contends that its failure to bring a statute of limitations defense earlier was due 2 to Knight’s database failures and Knight’s one-year document retention policy which resulted 3 in Knight failing to produce all documents covering the key time frame of January to July 4 2008. 5 The Court is quite familiar with the ongoing problems regarding discovery in this 6 case. (See Doc. 165 (giving Knight until Friday, November 29, 2013 to provide relevant 7 email discovery to B&L).) The current discovery cut-off deadline for the parties is August 8 8, 2014. (Id.) At issue is whether Knight’s ongoing problems with production of documents 9 during discovery affected B&L’s diligence in pursuing a statute of limitations affirmative 10 defense. The Court finds that Knight’s ongoing discovery production issues has affected 11 B&L’s ability to pursue a statute of limitations defense. The Court does not find that B&L 12 lacked diligence or unduly delayed in seeking to amend its answer to include this affirmative 13 defense. 14 Prejudice 15 Finally, B&L asserts that Knight will not be prejudiced by assertion of a statute of 16 limitations defense as the discovery cut-off deadline is not until August 8, 2014 and no 17 further case management deadlines will need to be adjusted. (Doc. 171 at 8-10.) Knight 18 contends that it will be prejudiced because B&L could have brought the affirmative defense 19 earlier; consequently, allowing it to be asserted now will result in additional and duplicative 20 discovery costs. 21 The Court does not find that Knight will be significantly or unduly prejudiced. The 22 Court has already found that Knight’s problems with the production of documents has 23 affected B&L’s diligence and ability to pursue this affirmative defense. Further, the parties 24 are still conducting discovery, with the discovery cut-off deadline not being until August 8, 25 2014. 26 The Court finds that B&L established good cause under Rule 16 to modify the case 27 management order. The Court further finds that B&L satisfied the standards for allowing it 28 to amend its answer under Rule 15. Therefore, the Court will grant leave for B&L to amend - 10 - 1 its answer to assert a statute of limitations defense. 2 Accordingly, on the basis of the foregoing, 3 IT IS HEREBY ORDERED DENYING B&L’s motion for leave to file third-party 4 complaint for contribution. (Doc. 169.) 5 IT IS FURTHER ORDERED GRANTING B&L’s motion for leave to file an 6 amended answer that asserts a new statute of limitations affirmative defense. (Doc. 171.) 7 The Clerk of Court shall file B&L’s lodged proposed amended answer. (Doc. 171-1.) 8 DATED this 24th day of January, 2014. 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 - 11 -

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?