Lentz v. United States Air Force
Filing
41
ORDER granting 29 Defendant United States Air Force's Motion to Dismiss, and dismissing this action for lack of subject matter jurisdiction. ORDERED denying as moot Defendant United States Air Forces Motion to Continue Deadlines to Conduct Good Faith Settlement Talks and to File Dispositive Motions (Doc. 37 ). FURTHER ORDERED directing the Clerk of Court to enter judgment accordingly and close this case. Signed by Judge John J Tuchi on 7/13/18. (EJA)
1
WO
2
3
4
5
6
IN THE UNITED STATES DISTRICT COURT
7
FOR THE DISTRICT OF ARIZONA
8
9
Gary Lentz,
No. CV-17-01660-PHX-JJT
Plaintiff,
10
11
v.
12
ORDER
United States Air Force,
13
Defendant.
14
15
At issue is Defendant United States Air Force’s (USAF) Rule 12(b)(1) Motion to
16
Dismiss (Doc. 29, MTD), to which pro se Plaintiff Gary Lentz has filed a Response
17
(Doc. 30, Resp.), and the USAF has filed a Reply (Doc. 31, Reply). No party requested
18
oral argument on the Motion and the Court finds it appropriate for resolution without
19
such argument. See LRCiv 7.2(f). For the reasons set forth below, the Court will grant the
20
USAF’s Motion and dismiss Plaintiff’s claim with prejudice.
21
I.
BACKGROUND
22
In this lawsuit, Plaintiff brings a property damage claim against the USAF
23
pursuant to the Federal Tort Claims Act (FTCA), 28 U.S.C. §§ 1346(b), 2671-80. On
24
July 29, 2016, an unexpected storm known as a “microburst” struck the area near Gila
25
Bend Air Force Auxiliary Field (GBAFAF) in Maricopa County, Arizona. (Compl. ¶ 3;
26
Resp. at 3.) The storm produced wind speeds of up to nearly 90 mph, the highest wind
27
gust speeds encountered at GBAFAF in a seven month period. (MTD Ex. 3 ¶¶ 7-8.) The
28
storm’s high wind speeds resulted in significant damage to the roof of GBAFAF’s main
1
lodging/lobby, also known as Building 4300. (MTD Ex. 2 ¶ 15.) A portion of Building
2
4300’s tarred asphalt roof landed northeast of the building in a tennis court and parking
3
lot area. (MTD Ex. 1 ¶ 36.)
4
At the time of the storm, Plaintiff’s recreational vehicle (RV) was parked
5
approximately 500 feet to the northwest of Building 4300 at a family campground known
6
as “Fam Camp.” (Compl. ¶ 1; MTD at 3.) Plaintiff submitted a written claim for damages
7
to the USAF approximately two weeks after the storm, alleging that flying debris from
8
Building 4300 had caused damage to his RV. (Compl. ¶¶ 3-5.) The USAF rejected
9
Plaintiff’s claim for damages on January 11, 2017, approximately five months later.
10
(Compl. ¶ 6.) Plaintiff now alleges that the USAF’s negligent maintenance of Building
11
4300 caused damages to his RV and seeks damages in the amount of $48,000 for storage
12
fees, meals and incidental expenses, hotel and lodging, salvage value of the RV, and
13
upgrade extras to the RV. (Compl. ¶ 14.)
14
In its Motion to Dismiss, the USAF argues that Plaintiff’s claim is barred by the
15
independent contractor exception to the FTCA because contractor Tunista Services, LLC
16
(Tunista) maintained and was independently responsible for the roofs at GBAFAF. (MTD
17
at 4.)
18
II.
LEGAL STANDARD
19
“A motion to dismiss for lack of subject matter jurisdiction under Rule 12(b)(1)
20
may attack either the allegations of the complaint as insufficient to confer upon the court
21
subject matter jurisdiction, or the existence of subject matter jurisdiction in fact.”
22
Renteria v. United States, 452 F. Supp. 2d 910, 919 (D. Ariz. 2006) (citing Thornhill
23
Publ’g Co. v. Gen. Tel. & Elecs. Corp., 594 F.2d 730, 733 (9th Cir. 1979)). “Where the
24
jurisdictional issue is separable from the merits of the case, the [court] may consider the
25
evidence presented with respect to the jurisdictional issue and rule on that issue, resolving
26
factual disputes if necessary.” Thornhill, 594 F.2d at 733; see also Autery v. United
27
States, 424 F.3d 944, 956 (9th Cir. 2005) (“With a 12(b)(1) motion, a court may weigh
28
the evidence to determine whether it has jurisdiction.”).
-2-
1
The burden of proof is on the party asserting jurisdiction to show that the court has
2
subject matter jurisdiction. See Indus. Tectonics, Inc. v. Aero Alloy, 912 F.2d 1090, 1092
3
(9th Cir. 1990). However, in FTCA cases, the “United States bears the burden of proving
4
the applicability of one of the exceptions to the FTCA’s general waiver of immunity.”
5
Prescott v. United States, 973 F.2d 696, 702 (9th Cir. 1992). Here, the USAF has filed
6
declarations and other evidence with its Motion to Dismiss, thus mounting a factual
7
attack on the existence of subject matter jurisdiction in this case. In response, Plaintiff has
8
neglected to file any additional evidence, affidavits, or declarations to support his
9
position. Plaintiff does not dispute the supplemental declarations and exhibits filed by the
10
USAF. In evaluating the USAF’s factual Rule 12(b)(1) challenge, the Court will consider
11
the evidence submitted beyond the Complaint.
12
III.
ANALYSIS
13
A.
14
The USAF’s contract with Tunista became effective on February 9, 2015, and
15
extends into the year 2020. (MTD Attach. A, LENTZ-USAF-000161.) As part of its
16
contract with the USAF, Tunista was required to provide Civil Engineering services,
17
including roof maintenance and repair, to GBAFAF. (MTD Ex. 1, Attach. A, LENTZ-
18
USAF-000163.) These services were required to be performed “in accordance with the
19
performance works statement.” (MTD Ex. 1, Attach. A, LENTZ-USAF-000163.) The
20
performance works statement (PWS) states that “[t]he quality of the work performed
21
under this contract is the responsibility of the contractor,” and that Tunista must “provide
22
and maintain a quality control program” as well as “perform all required inspections.”
23
(MTD Ex. 1, Attach. B, LENTZ-USAF-000581, 696.) Tunista must also provide a site
24
manager “who shall be responsible for the performance of all work.” (MTD Ex. 1,
25
Attach. B, LENTZ-USAF-000583.) In his declaration, Timothy Sizemore avers that
26
Richard Carr was Tunista’s site manager during 2016 and was responsible for overseeing
27
all work performed under the contract. (MTD Ex. 1 ¶ 16.) Moreover, in addition to the
28
maintenance of GBAFAF, Tunista is responsible for maintaining Fam Camp and its
The USAF’s Contract with Tunista
-3-
1
utilities, parking spaces, improved grounds, and road and fire suppression systems. (MTD
2
Ex. 1, Attach. B, LENTZ-USAF-000610.)
3
The PWS projected that 220 man hours per year would be necessary for Tunista’s
4
maintenance and repair of the roofs, trim, and gutters at GBAFAF. (MTD Ex. 1, Attach.
5
B, LENTZ-USAF-000721.) Specifically, the PWS stated that “the contractor shall install,
6
repair, [and] replace components and maintain built up roofs, felts, bitumen, aggregate,
7
stops, flashing, and insulation. [The contractor shall] [r]epair pitched roofs, shingles, roll
8
roofs, felt and flashing, drip edges, gutters and down spouts[,] [and] [r]epair metal roofs,
9
roof beams, purling, sag rods and brace rods IAW AFI 32-1051. The contractor’s repairs
10
shall match the rest of the roof.” (MTD Ex. 1, Attach. B, LENTZ-USAF-000605.)
11
In addition to the PWS, Tunista was required to adhere to and follow the
12
Department of Defense’s (DoD) United Facilities Criteria (UFC). (MTD Ex. 1 ¶ 13.) The
13
UFC
14
modernization criteria, and applies to the Military Departments, the Defense Agencies,
15
and the DoD Field Activities” and is “used for all DoD projects and work for other
16
customers where appropriate.” (MTD Ex. 1, Attach. C, LENTZ-USAF-000237.) UFC
17
Series 3-110-04 specifically applies to and “unifies the roofing maintenance and repair
18
criteria for the DoD” and states that “[f]acility roof maintenance requirements and
19
standards shall be performed by personnel responsible for this task.” (MTD Ex. 1, Attach.
20
C, LENTZ-USAF-000238, 000241). Section 1-4.4 defines maintenance as “proactive
21
efforts expended on a recurrent, periodic schedule that are necessary to preserve the
22
condition of the roof components and systems” and states that “[m]aintenance efforts
23
generally occur prior to failure of the roof system . . . and include periodic inspections
24
and resulting diagnosis of required repairs.” (MTD Ex. 1, Attach. C, LENTZ-USAF-
25
000241).
“provides
planning,
design,
construction,
sustainment,
restoration,
and
26
Consistent with the periodic inspections required by the UFC, the PWS
27
additionally clarifies that Tunista must “provide and maintain a quality control program”
28
and must “perform all required inspections.” (MTD Ex. 1, Attach. B, LENTZ-USAF-
-4-
1
000581.) To comply with these requirements, Tunista maintained a computer program
2
called Maintenance 500 for tracking scheduled roof maintenance and roof repairs at
3
GBAFAF. (MTD Ex. 2 ¶ 9.) Mr. Joaquin Alegria, a Tunista employee, was responsible
4
for reviewing the program and conducting visual inspections of GBAFAF roofs to
5
determine if the roofs were in need of repairs. (MTD Ex. 2 ¶ 8.) Mr. Alegria avers that
6
“[n]o Air Force personnel ha[d] access to/oversee/make inputs or changes to [the
7
Maintenance 500] program.” (MTD Ex. 2 ¶ 9.) He further states that the program is
8
overseen by Tunista’s site manager, Mr. Carr. (MTD Ex. 2 ¶ 9.)
9
On June 5, 2016, after noticing that GBAFAF’s Building 4300 was due to be
10
inspected soon as part of Tunista’s regular maintenance program, Mr. Alegria placed a
11
work order into the system for the “Roof Semiannual Scheduled Inspection.” (MTD Ex. 2
12
¶ 11.) He performed the annual inspection three days later, on June 7, 2016, and
13
determined that the roof did not need repairs and was structurally sound. (MTD Ex. 2
14
¶ 12.) This inspection occurred 52 days before the “microburst” storm on July 29, 2016,
15
that caused damage to the roof of Building 4300.
16
B.
17
“The Federal Tort Claims Act is a limited waiver of sovereign immunity, making
18
the Federal Government liable to the same extent as a private party for certain torts of
19
federal employees acting within the scope of their employment.” United States v.
20
Orleans, 425 U.S. 807, 813 (1976); 28 U.S.C. § 1346. Section 2671 of Title 28 U.S.C.
21
defines “employee of the government” as “officers or employees of any federal agency,”
22
but expressly states that the definition of “‘Federal agency’ . . . does not include any
23
contractor with the United States.” This language has been interpreted to create an
24
“independent contractor exception” to the FTCA, which protects the United States from
25
being held vicariously liable for the negligent actions of an independent contractor.
26
Orleans¸ 425 U.S. at 814; Edison v. United States, 822 F.3d 510, 518 (9th Cir. 2016).
FTCA and the Independent Contractor Exception
27
Because the FTCA is a waiver of the government’s sovereign immunity, it must be
28
strictly construed and any vagueness is interpreted in favor of the United States. United
-5-
1
States v. Nordic Village Inc., 503 U.S. 30, 34 (1992); see also Orleans, 425 U.S. at 814
2
(“Since the United States can be sued only to the extent that it has waived its immunity,
3
due regard must be given to the exceptions, including the independent contractor
4
exception, to such waiver.”); Robb v. United States, 80 F.3d 884, 894 (4th Cir. 1996)
5
(“The FTCA, as a waiver of sovereign immunity, is strictly construed and . . .
6
[a]ccordingly, the independent contractor exception to the waiver of sovereign immunity
7
has been construed broadly.” (citations omitted)).
8
Whether the independent contractor exception applies to a government contractor
9
turns on “the existence of federal authority to control and supervise the ‘detailed physical
10
performance’ and ‘day-to-day operations’ of the contractor, and not whether the agent
11
must comply with federal standards and regulations.” Ducey v. United States, 713 F.2d
12
504, 516 (9th Cir. 1983). The Court in Ducey found that “regulation-mandated
13
contractual restrictions” imposed on an independent contractor that were designed to
14
standardize and “secure federal objectives” were not enough to convert the independent
15
entrepreneur into an “agent” of the federal government. Id.; see also Logue v. United
16
States, 412 U.S. 521, 528 (1973) (“the critical factor in making this determination is the
17
authority of the principal to control the detailed physical performance of the contractor”);
18
Autrey v. United States, 424 F.3d 944, 957 (9th Cir. 2005) (“Contractual provisions
19
directing detailed performance generally do not abrogate the contractor exception.”);
20
Letnes v. United States, 820 F.2d 1517, 1519 (9th Cir. 1987) (“[T]he ability to compel
21
compliance with federal regulation does not change a contractor’s personnel into federal
22
employees.”).
23
Applying these standards, the undisputed evidence submitted by the USAF shows
24
that Tunista was an independent contractor to the USAF and not an employee. Tunista
25
was responsible for all of the Civil Engineering services on GBAFAF, including the
26
maintenance and repair of the roof on Building 4300, and maintained a separate work
27
order program to which no Air Force employees had access. The contract, PWS, and
28
UFC all indicate that the USAF did not direct the actual performance of the contract and
-6-
1
that Tunista and its site manager, Mr. Carr, were responsible for the duties specified by
2
the contract. Plaintiff disputes that the USAF delegated all duties related to the roof to
3
Tunista, arguing that the USAF retained the duty to evaluate Tunista’s performance,
4
although Plaintiff does not argue that the USAF was responsible for the day-to-day
5
operations of Tunista. As the Ninth Circuit points out in Letnes, compelling compliance
6
with federal regulations does not abrogate the independent contractor exception. It also
7
does not imply that the USAF controlled the detailed physical performance of Tunista.
8
Thus, the Court finds that Tunista was an independent contractor and not an employee
9
working for the USAF.
10
C.
11
The crux of Plaintiff’s argument, however, is not that the independent contractor
12
exception does not apply here because Tunista was in fact an employee of the USAF.
13
Rather, Plaintiff asserts that the independent contractor exception cannot apply here
14
because the USAF owed Plaintiff a non-delegable duty under Arizona law. (Resp. at 3.)
The USAF’s Non-Delegable Duty
15
“Whether the United States may be held liable under the FTCA for its own acts or
16
omissions is a three-step inquiry.” Edison, 822 F.3d at 519. The first step is determining
17
whether state law would impose a duty of care on a private individual in like
18
circumstances. Id. The second step is determining whether, in the language of the
19
contract or in the parties’ actions, the United States retained some portion of that duty for
20
which it may be held liable. Id. The final step states that the United States may still be
21
liable for the negligent actions of an independent contractor if the duty owed was one that
22
was non-delegable under state law. Id. (citing Yanez v. United States, 63 F.3d 870, 874-
23
75 (9th Cir. 1995); McGarry v. United States, 549 F.2d 587, 590 (9th Cir. 1976)).
24
Here, Plaintiff relies on the Restatement (Second) of Torts § 422 and Ft. Lowell-
25
NSS Ltd. Partnership v. Kelly, 800 P.2d 962 (1990), to assert that Arizona law imposes
26
non-delegable duties on landowners. (Resp. at 3.) The second step of the Edison analysis
27
is made irrelevant following the Court’s finding above that the USAF had delegated all of
28
its duties to Tunista regarding the maintenance and repair of the roofs at GBAFAF.
-7-
1
However, Plaintiff asserts that the USAF fails at the third step of the inquiry and should
2
be held liable because § 422 of the Restatement (Second) of Torts and Ft. Lowell state
3
that Arizona law imposes a non-delegable duty on landowners, and therefore the
4
independent contractor exception cannot apply here.
5
While Plaintiff’s argument correctly identifies Arizona state law, Plaintiff’s
6
argument fails to address the fact that state law cannot preempt the FTCA if the state law
7
imposes strict liability on the Government. See Laird v. Nelms, 406 U.S. 797, 804 (1972);
8
Dalehite v. United States, 346 U.S. 15, 30-31, 44-45 (1953) (“[O]ur decisions have
9
interpreted the Act to require clear relinquishment of sovereign immunity to give
10
jurisdiction for tort actions.”); Bramer v. United States, 595 F.2d 1141, 1144 n.7 (9th Cir.
11
1979) (“Jurisdiction is similarly lacking if state law would impose upon the government a
12
type of liability, such as strict liability, which is beyond the cognizance of the Federal
13
Tort Claims Act.”); Morris v. United States, No. CV-07-1837-PHX-PGR, 2009 WL
14
2486013, *17 (D. Ariz. Aug. 12, 2009) (“the FTCA precludes the application to the
15
United States of any state law imposing strict liability”).
16
It is without question that § 422 of the Restatement is a rule of vicarious liability,
17
as is explicitly stated in the case that Plaintiff cites. Ft. Lowell-NSS Limited Partnership,
18
800 P.2d at 970 (“[S]ection 422 holds a possessor of land liable to his invitees for injuries
19
that occur while he is in possession and result from his independent contractor’s
20
negligence in performing the duties of the possessor or of the contractor . . . although no
21
fault of the possessor need be shown, the negligence of the independent contractor must
22
be proven before liability may attach to the employer.”); Restatement (Second) of Torts,
23
ch. 15, topic 2, intro. note at 394 (“The rules stated in the following §§ 416-429 . . . are
24
rules of vicarious liability, making the employer liable for the negligence of the
25
independent contractor, irrespective of whether the employer has himself been at fault.”).
26
Indeed, the plaintiff in Morris v. United States cited to the same section of the
27
Restatement that Plaintiff cites to here, and the court held that the section could not
28
preempt the FTCA’s independent contractor exception because § 422 is a rule of
-8-
1
vicarious liability. Morris, 2009 WL 2486013 at *19; cf. Camozzi v. Roland/Miller &
2
Hope Consulting Grp., 866 F.2d 287, 289 n.7 (9th Cir. 1989) (holding that immunity
3
under the FTCA’s discretionary function exception is not overridden by state tort rules
4
and cannot be preempted by state law).
5
Consequently, Plaintiff’s theory of liability is impermissible under the FTCA, as
6
§ 422 of the Restatement (Second) of Torts is a rule of vicarious liability and cannot
7
preempt the independent contractor exception to the FTCA. Because that exception
8
applies here, the Court lacks subject matter jurisdiction to hear the claim presented.
9
IT IS THEREFORE ORDERED granting Defendant United States Air Force’s
10
Motion to Dismiss (Doc. 29), and dismissing this action for lack of subject matter
11
jurisdiction.
12
IT IS FURTHER ORDERED denying as moot Defendant United States Air
13
Force’s Motion to Continue Deadlines to Conduct Good Faith Settlement Talks and to
14
File Dispositive Motions (Doc. 37).
15
16
17
IT IS FURTHER ORDERED directing the Clerk of Court to enter judgment
accordingly and close this case.
Dated this 13th day of July, 2018.
18
19
20
Honorable John J. Tuchi
United States District Judge
21
22
23
24
25
26
27
28
-9-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.