Del Mar Land Partners LLC v. Stanley Consultants Incorporated

Filing 102

ORDER that defendant Stanley Consultants, Inc.'s Motion for Summary Judgment as to Plaintiff's Amended Complaint Pursuant to FRCP 56 (Doc. 80 ) is granted and that plaintiff Del Mar Land Partners, LLC's Breach of Contract claim, the First Cause of Action of the Amended Complaint and its Unjust Enrichment and Constructive Trust claim, the Fourth Cause of Action of the Amended Complaint, are both dismissed. IT IS FURTHER ORDERED that defendant Stanley Consultants, Inc.'s Moti on for Summary Judgment as to Defendant/Counterclaimant's Counterclaim Pursuant to FRCP 56 (Doc. 86 ) is granted as to the defendant's Breach of Contract counterclaim, the First Cause of Action in the Counterclaim, and is denied as moot as to the defendant's Declaratory Relief counterclaim, the Second Cause of Action in the Counterclaim. IT IS FURTHER ORDERED that defendant Stanley Consultants, Inc. shall, after consultation with the plaintiff, submit a proposed form a judgment n o later than October 7, 2013. If the plaintiff cannot agree with the defendant's proposed form of judgment, the plaintiff shall submit its objections to that proposal no later than October 21, 2013. Signed by Senior Judge Paul G Rosenblatt on 9/27/2013.(KMG)

Download PDF
1 WO 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE DISTRICT OF ARIZONA 8 9 10 Del Mar Land Partners, LLC, Plaintiff, 11 12 13 vs. Stanley Consultants, Inc. Defendant. 14 15 ) ) ) ) ) ) ) ) ) ) ) No. CV-11-08013-PCT-PGR ORDER 16 Pending before the Court is Defendant Stanley Consultants, Inc.’s Motion for 17 Summary Judgment as to Plaintiff’s Amended Complaint Pursuant to FRCP 56 (Doc. 18 80) and Motion for Summary Judgment as to Defendant/Counterclaimant’s 19 Counterclaim Pursuant to FRCP 56 (Doc. 86). 20 memoranda in light of the relevant record, the Court finds that there are no genuine 21 issues of material fact and that the defendant is entitled to summary judgment in its 22 favor as a matter of law pursuant to Fed.R.Civ.P. 56 on the plaintiff’s two remaining 23 claims in its Amended Complaint and on the defendant’s breach of contract 24 counterclaim.1 Having considered the parties’ 25 26 1 Although the parties have requested oral argument as to both motions, the Court concludes that oral argument would not aid the decisional process. 1 Background 2 This action arises from two contracts between the parties, a Professional 3 Services Agreement (“Master Agreement”) entered into in October of 2006 and a 4 Confirmation and Authorization for Work contract (“Addendum”) entered into in January 5 of 2007, which concerned civil engineering consulting services the defendant was to 6 provide to plaintiff Del Mar Land Partners, LLC in connection with its development of 7 its 324-lot residential real estate project known as Lake Mead Rancheros Units 4 & 5 8 located in Mohave County, Arizona. 9 In its Amended Complaint (Doc. 8), which is based on diversity of citizenship 10 jurisdiction pursuant to 28 U.S.C. § 1332, the plaintiff raised claims for breach of 11 contract, negligent misrepresentation, fraud, and unjust enrichment. In previous 12 orders, the Court dismissed the plaintiff’s negligent misrepresentation claim, see 2011 13 WL 2692959 (D.Ariz. July 12, 2011), and the plaintiff’s fraud claim, see 2012 WL 14 1019066 (D.Ariz. March 26, 2012), on the ground that both of these tort claims were 15 barred by Arizona’s economic loss doctrine. 16 In its Counterclaim (Doc. 24), the defendant raised claims for breach of contract 17 and for declaratory relief. 18 Discussion 19 I. Summary Judgment as to the Amended Complaint 20 A. Breach of Contract Claim 21 The defendant seeks summary judgment in part on the plaintiff’s breach of 22 contract claim, the First Cause of Action in its Amended Complaint. The Master 23 Agreement stated that the defendant “shall perform professional services as stated in 24 Exhibit 1.” Exhibit 1 sets forth in its “Scope of Services” section the several 25 26 -2- 1 professional services that the defendant would provide to the plaintiff.2 The purpose 2 of these engineering and consulting services from the defendant was to enable the 3 plaintiff to obtain the necessary approvals from state agencies, in particular a Sanitary 4 Facilities Certificate from the Arizona Department of Environmental Quality, so that the 5 plaintiff could apply for a Public Report from the Arizona Department of Real Estate, 6 which was required before it could begin closing sales of its lots to the public. The gist 7 8 2 The Master Agreement stated in relevant part as follows: 9 10 Stanley Consultants Inc. agrees to perform the following Scope of Services: 11 I. PROFESSIONAL SERVICES 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 A. Consultant will submit reports to Client and to ADWR [Arizona Dept.of Water Resources] and ADEQ [Arizona Dept. of Environmental Quality]. Client will be responsible for coordination with his Title Company for submittal of the application for a Public Report to the Arizona Department of Real Estate. B. Water Supply Report (ADEQ): Consultant will research state and county records for data related to existing water wells. Based on this information and discussions with local well drilling contractors, the Consultant will prepare a letter to ADEQ addressing the following options for water supply[:] 1) individual private wells, 2) trucked water, 3) common wells, and 4) community water system. C. Water Adequacy Application (ADWR): Consultant will prepare an application for submittal to ADWR for a determination of water adequacy. D. Flood and Drainage Report: Consultant will review FEMA maps of the area and identify areas with flood zones. A report will be prepared that identifies lots affected by flood zones. Hydrology study/drainage analysis is not part of this scope. E. Soils Report: Consultant will prepare a soils report which will be prepared based on a review of Mojave County Soil Maps. The report will identify general soil types and conditions. Atypical soil conditions will be identified and associated with specific lots. Wastewater disposal in this area will be analyzed. -3- 1 of the plaintiff’s breach of contract claim is that the defendant failed to properly submit 2 compliance reports to the appropriate state agencies, such as by submitting a mere 3 letter to ADEQ in support of the required Sanitary Facilities Certificate which ADEQ 4 refused to process because the letter did not comply with the formal application 5 requirements for the certificate, and that the defendant failed to timely complete its 6 work. 7 The Court concludes that there is no triable issue of fact regarding whether the 8 defendant failed to perform the contracted-for engineering and consulting services. 9 This is so because the admissible evidence of record and the justifiable inferences 10 arising from that evidence, all viewed in the plaintiff’s favor, is insufficient to permit a 11 jury to reasonably find that the defendant did not eventually provide all of the services 12 the plaintiff contracted for. With regard to the scope of work required by the Master 13 Agreement, the plaintiff admitted in its statement of facts that a Sanitary Facilities 14 Certificate was eventually issued by ADEQ, and Warren Church, the plaintiff’s 15 managing member and the person who negotiated and signed the contracts with the 16 defendant, admitted at his deposition that the defendant submitted the application for 17 the Sanitary Facilities Certificate, that the defendant submitted a letter to ADEQ 18 addressing options for the water supply, that it prepared an application for submittal to 19 ADWR for determination of water adequacy, that it prepared a flood and drainage 20 report, and that a soil report was prepared; the plaintiff’s answers to the defendant’s 21 requests for admissions also admit that this contractually-required work was completed 22 by the defendant. With regard to the scope of work required by the Addendum, Church 23 testified that the work was eventually completed by the defendant and that he was not 24 contending that the defendant failed to perform any term or condition of the Addendum. 25 Furthermore, the plaintiff has not submitted any expert or other significant probative 26 -4- 1 evidence establishing that the engineering and consulting services that the defendant 2 undertook in response to the contracts fell below the applicable standard of care for 3 such services. 4 The dispositive issue is instead whether the defendant breached the contracts 5 by performing its professional services in an unreasonably untimely manner. The 6 plaintiff’s position is that the defendant verbally represented prior to the signing of the 7 Master Agreement that it would take 90 days for it to perform the work being contracted 8 for, but that such services in fact took nine months to complete, resulting in the plaintiff 9 suffering over $7 million in damages because the delay caused buyers of some lots to 10 cancel their purchase agreements, caused the plaintiff to be unable to sell other lots, 11 and reduced the ultimate sales price for other lots because of a declining real estate 12 market. 13 It is undisputed that neither the Master Agreement nor the Addendum contained 14 a time of performance provision or a provision stating that time was of the essence in 15 the performance of the defendant’s services.3 The defendant argues that no such 16 provision may be read into the unambiguous contracts pursuant to the parol evidence 17 rule as adopted in Nevada because the Master Agreement contained an integration 18 clause in Paragraph 4.13 of Exhibit 3 to the contract that stated that “[t]his Agreement 19 represents the entire agreement between the parties and may be amended only by 20 21 22 23 24 25 26 3 The Court notes that the only provision in the Master Agreement even mentioning a time of completion is in Exhibit 2, which deals with compensation, which provides that “[o]nce contracted, the fees herein are valid for a period of one year. If the services in this contract have not been completed by October 17, 2007, the fee amounts will be subject to renegotiation.” -5- 1 written instrument signed by both parties[,]”4 and that this provision carried over into the 2 Addendum by the provision in that contract that stated that “[a]ll other terms and 3 conditions of the Master Agreement of 10-19-06 will prevail.” (Emphasis in original.) 4 As noted by the defendant, and inexplicably ignored by the plaintiff, the Court 5 determined in an earlier opinion in this action that the interpretation of the contracts is 6 governed by Nevada law pursuant to the choice of law provision in the Master 7 Agreement, Paragraph 4.4 of Exhibit 3, which stated that “Controlling Law. Agreement 8 shall be governed by Nevada law.” Nevada law provides that “a fundamental principle 9 of contract law is that the time of performance under a contract is not considered of the 10 essence unless the contract expressly so provides or the circumstances of the contract 11 so imply.” Mayfield v. Koroghli, 184 P.3d 362, 366 (Nev.2008) (footnote omitted.) 12 While the plaintiff does not expressly argue it, the Court presumes that the 13 plaintiff is contending that the circumstances of the making of the Master Agreement 14 made it apparent that the parties intended time to be of the essence. In support of this 15 implied contention, the plaintiff relies on the deposition testimony and declaration of 16 Warren Church and the declaration of Bruce Silver, a former employee of the 17 defendant who was involved in the plaintiff’s project. The gist of this evidence is that 18 Church verbally told the defendant’s representative Bruce Darnell prior to the signing 19 of the Master Agreement that the plaintiff was anxious to get the Public Report from 20 ADRE so that it could close lot sales during the then hot real estate market, that Darnell 21 told Church that the defendant would get the Sanitary Facilities Certificate issued within 22 90 days of the signing of the contract, and that based on Darnell’s representation 23 24 25 26 4 The Master Agreement provided in part that the defendant “shall provide professional services in accordance with the terms and conditions stated in Exhibit 3.” Exhibit 3, entitled “Standard Terms and Conditions” contained two pages of provisions governing various aspects of the Master Agreement. -6- 1 Church expected the defendant to complete its work in approximately late January or 2 early February of 2007.5 3 Under the governing Nevada law, which the plaintiff nowhere discusses, “parol 4 evidence may not be used to contradict the terms of a written contractual agreement. 5 The parol evidence rule forbids the reception of evidence which would vary or 6 contradict the contract, since all prior negotiations and agreements are deemed to have 7 been merged therein.” Kaldi v. Farmers Insurance Exchange, 21 P.3d 16, 21 8 (Nev.2001) (internal quotations marks omitted.) While Nevada law recognizes that 9 5 10 For example, Church stated in his declaration: 11 12 13 14 15 16 17 18 19 7. As time was of the essence in obtaining the required approvals, I told [defendant’s representative] Chris Darnell that this work [the obtaining of the Sanitary Facilities Certificate from ADEQ] was the last significant piece we needed to complete in order to obtain the Public Report, and that we were anxious to get that Public Report and close sales in the hot real estate market at the time. Mr. Darnell indicated that would not be a problem, that [the defendant] had extensive knowledge with this process in Arizona, and that [the defendant] could complete the work and have the Sanitary Facilities Certificate issued within 90 days of our signing a contract with [the defendant.] Based on his representations as to [the defendant’s] ability to timely deliver the Sanitary Facilities Certificate we needed, I caused [the plaintiff] to engage [the defendant] in October of 2006, and expected the work to be complete in approximately January of 2007. 20 21 22 23 24 25 26 Bruce Silver, the former employee of the defendant, stated in his declaration: 8. When we were negotiating with Mr. Church, he asked how long it would take [the defendant] to complete its work. He explained that time was of the essence, and that he wanted to obtain his Public Report as soon as possible in order to start selling lots to take advantage of the rising real estate market in Arizona at the time. Mr. Darnell and myself told Mr. Church that it should take no more than 90 days for [the defendant] to complete all of its work. ... -7- 1 mere silence on an issue, for which no contractual provision is made at all, does not 2 itself create an ambiguity warranting consideration of parol evidence, id. at 22, it does 3 allow for the admission of extrinsic oral evidence to prove the “existence of a separate 4 oral agreement as to any matter on which a written contract is silent, and which is not 5 inconsistent with its terms[.]” Id. at 22. However, the plaintiff does not specifically make 6 such an argument and, in any case, the admissible evidence of record, viewed in the 7 plaintiff’s favor, does not support the existence of a separate oral agreement regarding 8 the timing of the defendant’s performance. In fact, the plaintiff has conceded that it had 9 no separate oral agreements with the defendant and that the two written contracts are 10 the only contracts on which it bases its claims against the defendant.6 Since the 11 plaintiff has not established that the facts of this case fall within the oral agreement 12 exception to Nevada’s parol evidence rule, nor has it established any ambiguity in the 13 contracts, the Court concludes that the plaintiff may not use parol evidence to add a 14 “time is of the essence” provision to the parties’ contracts. The Court further concludes 15 that a jury could not reasonably find from the admissible, non-parole evidence of 16 record, all viewed in the plaintiff’s favor, that the plaintiff has established that the 17 circumstances of the contracts implied that time was of the essence. See Anderson v. 18 Liberty Lobby, Inc., 477 U.S. 242, 257 (1986). 19 The plaintiff cursorily argues, citing only to Arizona law, that the evidence 20 provided by Warren Church creates at least a material issue of fact as to whether the 21 6 22 23 24 25 26 The defendant’s statement of fact no. 29 (Doc. 99) in support of its summary judgment motion regarding the Amended Complaint stated: “Plaintiff has admitted the existence and identity of the Project Contracts [the Master Agreement and Addendum] as the only two contracts on which Plaintiff bases its claims against [the defendant], and that Plaintiff had no other oral agreements with [the defendant].” In its statement of facts (Doc. 94-6), the plaintiff responded to the defendant’s SOF no. 29 by stating: “Undisputed.” -8- 1 defendant completed its work in a timely manner. Nevada law provides that “[i]f time 2 is not of the essence, the parties generally must perform under the contract within a 3 reasonable time, which depends upon the nature of the contract and the particular 4 circumstances involved. Nevertheless, in the absence of a clause making time of the 5 essence, a party’s failure to perform within a reasonable time generally does not 6 constitute a material breach of the agreement.” Mayfield v. Koroghli, 184 P.3d at 366 7 (internal footnotes and quotation marks omitted.) The Court, construing the plaintiff’s 8 argument as being that the defendant materially breached the contracts because its 9 delay in performance was unreasonable, cannot conclude that the plaintiff, which bears 10 the burden of proof, has created a triable issue of fact as to this issue. While Warren 11 Church testified that he expected the defendant to complete its work some six months 12 earlier than it did, the plaintiff has not provided significant probative evidence from 13 which a jury could reasonably find that this delay was unreasonable under the 14 circumstances. What is missing from the plaintiff’s submittal is something more than 15 merely colorable evidence as to how long it reasonably should have taken an 16 engineering company in the defendant’s position to perform all of the services 17 contracted for. See United Steelworkers of America v. Phelps Dodge Corp., 865 F.2d 18 1539, 1542 (9th Cir.1989) (“Mere submission of affidavits opposing summary judgment 19 is not enough; the court must consider whether the evidence presented in the affidavits 20 is of sufficient caliber and quantity to support a jury verdict for the nonmovant. A 21 scintilla of evidence, or evidence that is merely colorable or not significantly probative, 22 is not sufficient to present a genuine issue as to a material fact.”) (Internal citation, 23 quotation marks and italics omitted.) 24 B. Unjust Enrichment Claim 25 The defendant also seeks summary judgment on the plaintiff’s unjust enrichment 26 -9- 1 claim, the Fourth Cause of Action in its Amended Complaint.7 The defendant argues, 2 and the plaintiff concedes, that under both Nevada and Arizona law an unjust 3 enrichment claim is improper if there is an express written contract governing the 4 parties’ agreement. See Leasepartners Corp. v. Robert L. Brooks Trust Dated 5 November 12, 1975, 942 P.2d 182, 186 (Nev.1997) (“An action based on a theory of 6 unjust enrichment is not available when there is an express, written contract, because 7 no agreement can be implied when there is an express agreement.”); Brooks v. Valley 8 National Bank, 548 P.2d 1166, 1170 (Ariz.1976) (“[W]here there is a specific contract 9 which governs the relationship of the parties, the doctrine of unjust enrichment has no 10 application.”) 11 The plaintiff, in a cursory argument that is bereft of any cogent legal argument 12 or citation to any supporting case law8, merely states in opposition that “Plaintiff has 13 alleged facts, which if shown, may result in the Court voiding part or all of the 14 agreements between the parties. This theory of recovery is alleged in the alternative, 15 if the Court voids the contract for fraud, bad faith, unconscionability, mistake, etc.” The 16 Court concludes that the defendant is entitled to summary judgment on the unjust 17 enrichment claim because the parties’ relationship was governed by two express 18 contracts and the admissible evidence of record and the justifiable inferences from that 19 20 21 22 23 24 25 26 7 In this claim, the plaintiff alleges that the defendant should be forced to disgorge the full value of the payments made to it by the plaintiff because the “[d]efendant failed to timely and competently deliver its agreed-upon services.” 8 As the Court pointed out to the plaintiff in a previous order in this action, “[a] litigant who fails to press a point by supporting it with pertinent authority, or by showing why it is sound despite a lack of supporting authority or in the face of contrary authority, forfeits the point. We will not do his research for him.” Pelfresne v. Village of Williams Bay, 917 F.2d 1017, 1023 (7th Cir.1990) (internal citations omitted). - 10 - 1 evidence, viewed in the plaintiff’s favor, is insufficient to create a triable issue of fact as 2 to the enforceability of the parties’ contracts, or a triable issue of fact as to whether the 3 defendant did not eventually perform all of the engineering and consulting services the 4 plaintiff contracted for. 5 II. Summary Judgment as to the Counterclaim 6 The defendant further seeks summary judgment on its counterclaim for breach 7 of contract, its First Cause of Action, wherein it alleges that the plaintiff breached its 8 contractual obligations by failing to pay the defendant in full for the services it rendered 9 under the contracts in that a principal balance of $17,592.75 remains unpaid and 10 overdue.9 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 The plaintiff, in a cursory response that is not supported by any cogent analysis or citation to any legal authority, argues only that [i]f Plaintiff states a claim for breach of contract, clearly, [the defendant] cannot be entitled to a judgment on the Counterclaim for money allegedly owed under that same contract. Any such finding as to liability must await a final determination as the fact and amount of any set-off (or a determination that [the plaintiff] is owed money greater than the claim of [the defendant.]) Plaintiff has also submitted evidence to create an issue of fact as to whether [the defendant] can recover due to its own[] fraud, 9 The defendant also seeks summary judgment on its counterclaim for declaratory relief, its Second Cause of Action, wherein it seeks a declaration that the limitation of liability provision in the Master Agreement, § 4.12 of Exhibit 3 to the contract, is enforceable and limits its liability to the plaintiff to no more than “$100,000 or the total compensation received by [the defendant], whichever is greater.” The Court concludes that this portion of the defendant’s counterclaimrelated summary judgment motion, which the plaintiff failed to address in its response, is moot since the Court is granting the defendant’s summary judgment motion related to the plaintiff’s breach of contract and unjust enrichment claims. Furthermore, to the extent that the plaintiff’s mere mention of such legal theories as unconscionability, mistake, unclean hands, etc., is meant to be directed as anything other than the enforceability of the limitation of liability provision, the Court concludes it need not reach those theories since the plaintiff has in effect made no attempt to provide any legal analysis of their applicability to this action. - 11 - 1 bad faith, unclean hands etc., based on its actions as described by Warren Church. 2 3 Since the Court has previously dismissed the plaintiff’s fraud and negligent 4 misrepresentation claims and has concluded herein that the defendant is entitled to 5 summary judgment on the plaintiff’s breach of contract claim and unjust enrichment 6 claim, the only issue to be resolved as to the breach of contract counterclaim is 7 whether there is any triable issue as to the amount the defendant is still owed. The 8 Court concludes that there is not. 9 In support of its breach of contract counterclaim, the defendant has in part 10 submitted the declarations of Henry F. Marquard, the defendant’s chief legal officer, 11 and David Frohnen, the defendant’s former vice president/area manager who oversaw 12 the defendant’s Kingman, Arizona office that was responsible for performing the 13 professional services contracted for by the plaintiff and who signed the two contracts 14 on the defendant’s behalf. While the plaintiff has submitted specific evidentiary 15 objections to Marquard’s declaration, it has not done the same for Frohnen’s 16 declaration and the Court concludes that Frohnen’s declaration, together with the 17 defendant’s relevant invoices, provide significant probative evidence sufficient to 18 establish that the defendant invoiced the plaintiff for the requested principal amount of 19 $17,592.75 and that this amount remains unpaid, and the plaintiff has not submitted 20 any significant probative evidence challenging the accuracy of the amount at issue. 21 Therefore, 22 IT IS ORDERED that defendant Stanley Consultants, Inc.’s Motion for Summary 23 Judgment as to Plaintiff’s Amended Complaint Pursuant to FRCP 56 (Doc. 80) is 24 granted and that plaintiff Del Mar Land Partners, LLC’s Breach of Contract claim, the 25 First Cause of Action of the Amended Complaint and its Unjust Enrichment and 26 - 12 - 1 Constructive Trust claim, the Fourth Cause of Action of the Amended Complaint, are 2 both dismissed. 3 IT IS FURTHER ORDERED that defendant Stanley Consultants, Inc.’s Motion 4 for Summary Judgment as to Defendant/Counterclaimant’s Counterclaim Pursuant to 5 FRCP 56 (Doc. 86) is granted as to the defendant’s Breach of Contract counterclaim, 6 the First Cause of Action in the Counterclaim, and is denied as moot as to the 7 defendant’s Declaratory Relief counterclaim, the Second Cause of Action in the 8 Counterclaim. 9 IT IS FURTHER ORDERED that defendant Stanley Consultants, Inc. shall, after 10 consultation with the plaintiff, submit a proposed form a judgment no later than October 11 7, 2013. If the plaintiff cannot agree with the defendant’s proposed form of judgment, 12 the plaintiff shall submit its objections to that proposal no later than October 21, 2013. 13 DATED this 27th day of September, 2013. 14 15 16 17 18 19 20 21 22 23 24 25 26 - 13 -

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?