Solar Utilities Network LLC v. Navopache Electric Cooperative Incorporated
Filing
89
ORDER - IT IS ORDERED that defendant Navopache Electric Cooperative, Inc.'s Motion to Exclude James Dudley Howard, Jr. as a Witness (Doc. 71 ) is denied. IT IS FURTHER ORDERED that plaintiff Solar Utilities Network. LLC's Motion to Strike Defendant Navopache Electric Cooperative, Inc.'s Improper Controverting Statement to Sun's Supplemental Statement of Facts (Doc. 85 ) is granted and that defendant Navopache Electric Cooperative, Inc.'s Controverting Statement to S UN's Supplemental Statement of Facts (Doc. 84 ), and Exhibits A, B, C, D, E, F, and G attached thereto (Doc. 84 -1) are stricken from the record. IT IS FURTHER ORDERED that defendant Navopache Electric Cooperative, Inc.'s Alternative Mot ion for Leave to File Amended Reply (Doc. 86 ) is denied. IT IS FURTHER ORDERED that defendant Navopache Electric Cooperative, Inc.'s Motion for Summary Judgment Pursuant to Rule 56 (Doc. 72 ) is denied. (See document for further details). Signed by Senior Judge Paul G Rosenblatt on 9/29/15. (LAD)
1
WO
2
3
4
5
6
IN THE UNITED STATES DISTRICT COURT
7
FOR THE DISTRICT OF ARIZONA
8
9
)
)
)
Plaintiff,
)
)
vs.
)
)
Navopache Electric Cooperative, Inc., )
)
Defendant.
)
)
)
Solar Utilities Network, L.L.C,
10
11
12
13
14
15
No. CV-12-08095-PCT-PGR
ORDER
16
Pending before the Court is defendant Navopache Electric Cooperative, Inc.’s
17
Motion for Summary Judgment Pursuant to Rule 56 (Doc. 72), which the Court finds
18
should be denied. Also pending are three related procedural motions: Navopache
19
Electric Cooperative, Inc.’s Motion to Exclude James Dudley Howard, Jr. as a
20
Witness (Doc. 71), which the Court finds should be denied; plaintiff Solar Utilities
21
Network. LLC’s Motion to Strike Defendant Navopache Electric Cooperative, Inc.’s
22
Improper Controverting Statement to Sun’s Supplemental Statement of Facts (Doc.
23
85), which the Court finds should be granted; and Navopache Electric Cooperative,
24
Inc.’s Alternative Motion for Leave to File Amended Reply (Doc. 86), which the Court
25
26
1
finds should be denied.1
2
Background
3
According to the Second Amended Complaint (“SAC”) (Doc. 35), this diversity-
4
based action arises out defendant Navopache Electric Cooperative, Inc. (“NEC”)’s
5
alleged wrongful repudiation and termination of the parties’ Solar Energy Power
6
Purchase Agreement (“PPA”) dated October 15, 2010. The purpose of the PPA was
7
to assist NEC in complying with requirements of the Arizona Corporation
8
Commission that it obtain certain amounts of its electricity from renewable energy
9
sources. Pursuant to the PPA, NEC agreed to purchase for twenty years all of the
10
electric energy and related environmental benefits produced at or attributable to a
11
one megawatt solar power plant that plaintiff Solar Utilities Networks, LLC (“SUN”)
12
was to construct and operate in Hunt Valley, Arizona. In a letter to SUN dated
13
August 4, 2011, NEC terminated the PPA and repudiated its contractual obligations
14
“due to SUN’s failure to commence construction of the Generation Facility and to
15
secure Construction Financing by July 31, 2011.” The SAC alleges state law claims
16
for Breach of Contract (First Claim for Relief) and for Breach of the Implied Covenant
17
of Good Faith and Fair Dealing (Second Claim for Relief), both arising from the
18
termination of the PPA. The PPA provides that it is to be governed and construed
19
in accordance with Arizona law.
20
21
22
23
24
25
26
1
While the parties have requested oral argument, the Court concludes
that oral argument would not significantly aid the decisional process. See Partridge
v. Reich, 141 F.3d 920, 926 (9th Cir.1998).
The Court notes that it has intentionally not discussed every argument raised
by the parties and that those arguments not discussed are considered by the Court
to be unnecessary to its resolution of the pending motions.
-2-
1
NEC’s Motion to Exclude Testimony of James Howard
2
NEC has moved to preclude James Howard from being either an expert or fact
3
witness and to exclude SUN from offering Howard’s opinions, reports or testimony
4
in this action.
5
The Court considers the following facts to be undisputed for the purposes of
6
this motion. In January 2011, after the execution of the PPA, SUN partnered with
7
Dudley Ventures (“DV”), an investment and advisory services firm that specializes
8
in utilizing congressionally-sanctioned tax credits and other complex federal and
9
state subsidy programs. DV is involved in numerous investments regarding power
10
generation facilities, including solar plants. SUN turned the solar power plant project
11
over to DV to obtain financing and to manage the construction and operation of the
12
solar plant. DV ultimately became a joint venture partner with SUN and the manager
13
of the project. Under the joint venture agreement between SUN and DV, DV is
14
contributing 50% of the attorney fees and legal costs of this action and is to receive
15
50% of any damages recovered in this action. James Howard is the founder and
16
CEO of DV and is a 75% owner of the company. SUN views Howard as likely its
17
most important witness in this action as he was intimately involved with almost all of
18
the operative issues involved in this action, including DV’s efforts to obtain
19
construction financing, to commence construction of the power plant, to obtain tax
20
benefits and subsidies, the efforts to obtain NEC’s audited financial statements, the
21
time line for completion of the project, and the events occurring after NEC terminated
22
the PPA. Howard’s involvement in this action also included choosing the litigation
23
counsel for SUN.
24
Since Arizona law supplies the rule of decision in this action, Arizona law
25
governs Howard’s competency as a witness. Fed.R.Evid. 601. NEC argues that
26
-3-
1
Howard cannot be allowed to be a witness because Arizona law prohibits the
2
presentation of evidence from a witness whose compensation is based on the
3
outcome of the litigation. See Laos v. Soble, 503 P.2d 978, 979 (Ariz.App.1972)
4
(“We are of the opinion, and so hold, that a contract providing for compensation of
5
a witness contingent on the success of the litigation is subversive of public justice
6
for the reason that his evidence may be improperly influenced. Public policy
7
considerations brand such [a] contract illegal.”)2 NEC reasons that Howard’s
8
testimony as a witness is improper because he stands to receive contingent
9
compensation inasmuch as his company, DV, stands to receive 50% of any
10
damages awarded to SUN. SUN alleges in its SAC that its damages from NEC’s
11
allegedly wrongful termination of the PPA exceed $7,000,000.
12
While the Court agrees with NEC that Howard, as the majority owner of DV,
13
has a financial interest in this action given that he may personally profit if SUN wins,
14
the Court cannot agree that under the particular facts at issue that Arizona public
15
policy absolutely forbids him from testifying. First, Arizona law does not deem a
16
person with an interest in the litigation to be incompetent to testify. A.R.S. § 12-
17
2201(B) (“A person shall not be incompetent to testify because he is a party to an
18
action or proceeding or interested in the issue tried[.]” Second, this is not at all the
19
usual situation underlying Arizona’s policy in which a party has a contract with a
20
witness to testify on its behalf and is directly paying that witness a contingent fee to
21
2
22
23
24
25
26
NEC secondarily argues that Howard should be excluded from testifying
pursuant to Arizona Supreme Court’s Rule of Professional Conduct 3.4(b), which
prohibits a lawyer in part from “offer[ing] an inducement to a witness that is
prohibited by law.” Even if the Court were to assume that such an ethical violation
is occurring here, which the Court is not willing to do based on the record before it,
the Court would not in any case conclude that excluding Howard’s evidence on that
basis alone would be the proper remedy.
-4-
1
testify. While the Court understands that Howard is not a party plaintiff, his company
2
is so closely allied with SUN regarding the issues presented in this action and he is
3
so personally involved in this action that his testimony is more realistically compared
4
to that of a party representative than that of a compensated independent witness.
5
While it may be a close question, the Court concludes Howard’s evidence should not
6
be stricken because the issue here is more one of Howard’s credibility as a witness
7
rather than his competency as a witness.
8
Motions Related to NEC’s Controverting Statement of Facts
9
SUN filed a 91-paragraph supplemental statement of facts in conjunction with
10
its opposition to NEC’s summary judgment motion. NEC, in conjunction with its
11
summary judgment reply, filed a 23-page controverting statement of facts for the
12
purpose of disputing what it considers to be facts in SUN’s statement of facts “that
13
are irrelevant to the determination of the [summary judgment] motion, inaccurate
14
characterizations of the record, or editorialization as to the application of facts in the
15
record[;]” NEC appended some fifty pages of additional exhibits as support for its
16
controverting statement of facts. SUN has moved to strike NEC’s controverting
17
statement of facts and its additional exhibits on the ground that they are not
18
authorized by LR 7.2(m)(1) or 56.1. NEC’s opposition to the motion to strike
19
includes a motion for leave to file an amended, overlength summary judgment reply
20
if the Court concludes that its controverting statement of facts should be stricken.
21
The Court will grant SUN’s motion to strike NEC’s Controverting Statement of
22
Facts and its attached exhibits and will deny NEC’s motion to file an amended, over-
23
length reply, to which NEC has attached the same new exhibits it attached to its
24
Controverting Statement of Facts. See Parker v. Arizona, 2013 WL 3286414, at *8
25
(D.Ariz. June 28, 2013) (“District courts in Arizona have uniformly held that the Local
26
-5-
1
Rules of Civil Procedure do not permit a party moving for summary judgment to file
2
a supplemental statement of facts or attach[] exhibits with its reply.”); B2B CFO
3
Partners, LLC v. Kaufman, 856 F.Supp.2d 1084, 1086 (D.Ariz.2012) (Court
4
concluded that LRCiv 56.1 “does not provide for a reply statement of facts or a
5
response to the non-moving party’s separate statement of facts.”). Any objections
6
that NEC desired to make regarding SUN’s controverting and additional statements
7
of facts should have been set forth in its reply memorandum and it did not need an
8
overlength memorandum to do so.3 See Gressett v. Central Arizona Water
9
Conservation District, 2014 WL 4053404, at *2 (D.Ariz. Aug. 14, 2014) (Court noted
10
that while a summary judgment movant may neither attach new evidence to its reply
11
or file separate objections to the non-movant’s controverting and additional
12
statements of facts, “the movant may use its reply memorandum to respond to the
13
non-movant’s objections to the movant’s supporting statement of facts.”) (emphasis
14
in original).
15
NEC’s Motion for Summary Judgment
16
(1) Breach of Contract Claim
17
NEC argues that it is entitled to summary judgment on the SAC’s breach of
18
contract claim because the undisputed evidence establishes that it properly
19
terminated the PPA because SUN did not timely secure construction financing for
20
the solar power plant and did not timely commence construction of the plant.
21
Section 2.02 of the PPA, entitled “Certain Termination Rights Prior to
22
Commercial Operation,” granted both parties the right to terminate the PPA under
23
24
25
26
3
The Court, having reviewed the additional argument and evidence that
NEC seeks to add to its reply memorandum, notes that even if the Court permitted
it to be filed, none of it would in any case have affected the Court’s resolution of
NEC’s summary judgment motion.
-6-
1
certain circumstances; § 2.02(a) set forth SUN’s termination rights, and § 2.02(b)
2
and § 2.02(c) set forth NEC’s termination rights. At issue here is § 2.02(b), which
3
NEC relied on to terminate the PPA, which provides in its entirety: “In the event that
4
Construction Financing has not been secured, and construction of the Generating
5
Facility commenced, by July 31, 2011, Buyer [NEC] shall have the right to terminate
6
this Agreement without payment or penalty by giving Notice to Seller [SUN], which
7
Notice when given shall automatically terminate this Agreement.”4
8
A. § 2.02(b)’s right of termination
9
A preliminary issue is whether § 2.02(b) permitted NEC to terminate the PPA
10
solely because SUN failed to meet the July 31, 2011 deadline.5 SUN argues that
11
there is no independent significance to the July 31, 2011 benchmark date in §
12
2.02(b) for securing financing and commencing construction other than as it relates
13
to the July 31, 2012 deadline for commercial operation of the solar plant. SUN’s
14
15
16
17
18
19
20
21
22
23
24
25
26
4
Section 2.02(c) provided NEC with a separate termination circumstance:
“In the event that Commercial Operation has not been achieved by July 31, 2012,
Buyer shall have the right to terminate this Agreement without payment or penalty
by giving Notice to Seller, which Notice when given shall automatically terminate this
Agreement.”
5
Although neither party has raised it as an issue, the Court notes that §
2.02(b) provides that NEC had the right to terminate the PPA in the event that
construction financing had not been secured and construction commenced by July
31, 2011. Since this termination right is phrased conjunctively rather than
disjunctively, and in light of the lack of any evidence of a contrary intent in the
record, the Court construes this conjunctive phrase as meaning that SUN had to fail
to timely complete both tasks before NEC could terminate the PPA pursuant to §
2.02(b). See Bither v. Country Mutual Ins. Co., 245 P.3d 883, 885 (Ariz.App.2010)
(“The word ‘and’ is a conjunction connecting words or phrases expressing the idea
that the latter is to be added or taken along with the first.”) (some internal quotation
marks omitted.)
-7-
1
contention is that “the PPA only required SUN to complete construction of the
2
contemplated power plant ... by July 31, 2012 and only required that SUN be far
3
enough along by July 31, 2011 in terms of financing and construction to assure NEC
4
that SUN would complete construction by the completion date.”
5
The “[i]nterpretation of a contract is a question of law for the court where the
6
terms of a contract are found to be plain and unambiguous. Whether a contract is
7
ambiguous is a question of law; the mere fact that parties disagree as to its meaning
8
does not establish an ambiguity.” Chandler Medical Bldg. Partners v. Chandler
9
Dental Group, 855 P.2d 787, 791 (Ariz.App.1993). The Court concludes that §
10
2.02(b) is unambiguous as a matter of law on the issue of NEC’s right to terminate
11
the PPA if SUN had not secured financing and had not commenced construction by
12
July 31, 2011, and that this termination deadline constituted a material term of the
13
PPA.6 The contract language of § 2.02(b) is not reasonably susceptible to SUN’s
14
6
15
16
17
18
19
20
21
22
23
24
25
26
SUN argues in its summary judgment response that the parties never
discussed or negotiated § 2.02(b) and that the provision was inserted into the draft
PPA by NEC’s counsel at the last minute. To the extent that SUN is contending that
it signed the PPA with no knowledge of the existence of § 2.02(b), the Court rejects
that contention. There is no dispute that SUN left the final negotiation of the details
of the PPA to its contract counsel, the law firm of Snell and Wilmer, and SUN has not
submitted any evidence from its contract counsel to the effect that its counsel did not
know about the existence of § 2.02(b). More importantly, Mark Moore, SUN’s
president and CEO who signed the PPA, testified at his deposition that he “did
review the entire contract” before he signed it and that he did not recall having any
specific reaction one way or the other to the language of § 2.02(b) before he signed
the PPA. Moore also initialed the specific page of the PPA containing § 2.02(b), and
did so right below where § 2.02(b) and § 2.02(c) were set forth.
Furthermore, whatever understandings SUN may have had stemming
from earlier negotiations and drafts of the PPA did not survive the execution of the
PPA inasmuch as § 10.17 of the PPA provides in part:
This Agreement ... constitutes the entire agreement between the
Parties relating to the subject matter hereof. Upon each Party’s
execution of this Agreement, the Prior Understandings are hereby
-8-
1
asserted interpretation, which relies solely on the July 31, 2012 commercial
2
operation deadline § 2.02(c), because that interpretation ignores the clear language
3
of § 2.02(b) and would in effect make that language meaningless by improperly
4
reading it out of the PPA.7 See Cardon v. Cotton Lane Holdings, Inc., 841 P.2d 198,
5
202 (Ariz.1992) (“A contract must be construed in its entirety and in such a way that
6
every part is given effect.”) The Court therefore declines to consider any parol
7
evidence submitted by SUN regarding the parties’ alleged intent regarding this issue.
8
See Shattuck v. Precision-Toyota, Inc., 566 P.2d 1332, 1334 (Ariz.1977) (“Where the
9
intent of the parties is expressed in clear and unambiguous language, there is no
10
need or room for construction or interpretation and a court may not resort thereto.”);
11
In re Estate of Lamparella, 109 P.3d 959, 963 (Ariz.App.2005) (“Language in a
12
contract is ambiguous only when it can reasonably be construed to have more than
13
one meaning. Although determination of the intent of contracting parties from
14
extrinsic evidence may require fact finding, whether contract language is reasonably
15
susceptible to more than one interpretation so that extrinsic evidence is even
16
17
18
19
20
21
22
23
24
25
26
terminated and of no further force or effect. This Agreement shall be
considered for all purposes as prepared through the joint efforts of the
Parties and shall not be construed against one Party or the other as a
result of the preparation, substitution, submission or other event of
negotiation, drafting or execution hereof.
This provision is underscored by the fact that at the very end of the PPA, below the
parties’ signatures executing the PPA, Mark Moore additionally signed a statement
reading: “CONSENT TO TERMINATION OF PRIOR UNDERSTANDINGS.”
(Capitalization and underlining in original.)
7
The Court agrees with NEC that a failure on SUN’s part to meet the
benchmark deadline of § 2.02(b) makes SUN’s oft-repeated contention that the solar
power plant would have been constructed and operational by the deadline set forth
in § 2.02(c) irrelevant since the two provisions unambiguously give NEC distinct and
separate termination rights. The Court rejects SUN’s argument that construing §
2.02(b) as a separate termination right renders § 2.02(c) a nullity.
-9-
1
admissible is a question of law for the court.”) (internal citations omitted).
2
B. Securing of Construction Financing
3
NEC argues in part that summary judgment is appropriate in its favor because
4
the evidence establishes that SUN failed to timely secure construction financing;
5
SUN argues that summary judgment cannot be entered because it timely secured
6
financing, and that even if it did not, summary judgment is still not appropriate
7
because any failure to do so on its part was caused by NEC’s failure to timely
8
provide SUN with its necessary financial statements.
9
While § 2.02(b) provides that construction financing must be “secured” by July
10
31, 2011, the PPA does not define what constitutes the securing of construction
11
financing other than to the extent that the PPA defines “Construction Financing” to
12
mean “the initial financing, in whatever form(s), required to reasonably commence
13
and pursue through completion (consistent with Prudent Practice) the construction
14
of the Generating Facility, which financing may include, but is not limited to debt or
15
equity finance, sponsor or developer contributions and secured and unsecured
16
loans.”
17
means in the context of § 2.02(b) that it had to secure a lender who was prepared
18
to make a loan to SUN for the construction of the solar plant, and that an
19
unconditional commitment to lend was not necessary. NEC contends that for
20
purposes of § 2.02(b), financing is not secured until a lender has unconditionally
21
bound itself to provide SUN financing.
SUN contends that the requirement for securing construction financing
22
“The controlling rule of [contract] interpretation requires that the ordinary
23
meaning of language be given to words where circumstances do not show a different
24
meaning applicable.” Brady v. Black Mountain Inv. Co., 459 P.2d 712, 714
25
(Ariz.1969). Since no evidence has been submitted that establishes that the
26
- 10 -
1
requirement that financing be “secured” has any trade meaning or industry usage or
2
other special meaning, the Court, for purposes of the summary judgment motion, will
3
construe the word “secured” in its normal, ordinary meaning, which in this context
4
means “firmly established” and “sure; certain; assured[,]” Webster’s New Universal
5
Unabridged Dictionary (1996), and “capable of being expected or counted on with
6
confidence[.]” Webster’s Third New International Dictionary of the English Language
7
(1961).
8
The following relevant evidence regarding the securing of financing is in the
9
record; the Court considers this evidence to be either undisputed or at least not
10
sufficiently controverted. DV, which was tasked with obtaining financing for SUN for
11
the Hunt Valley solar plant project, sent a financing proposal to Matthew Wright at
12
National Cooperative Bank (“NCB”) on April 13, 2011, three and a half months
13
before § 2.02(b)’s deadline. On July 22, 2011, Wright, a senior vice-president at
14
NCB who was directly involved in reviewing SUN’s financing request, sent DV a term
15
sheet regarding the funding request. The first page of the term sheet stated that
16
“[t]his is a term sheet outlining the salient terms of the credit facility and not the
17
actual commitment to lend.” The term sheet included terms for both a bridge loan
18
of approximately $1.2 million, the purpose of which was “to bridge Federal 1603
19
Grants allowing for the construction” of the solar plant, and a separate permanent
20
loan of approximately $2.5 million, the purpose of which was “[t]o provide term
21
financing for the development” of the plant. The term sheet also stated that: “This
22
proposal is subject to further due diligence by Lender. To indicate acceptance of
23
these general terms, and to induce Lender to begin the formal underwriting process,
24
please sign and return a copy of this proposal along with a deposit of $10,000. This
25
deposit will be returned in the event that lender is unable to issue a formal
26
- 11 -
1
commitment for financing. Note that the terms highlighted in this proposal are good
2
for 30 days from the date of issuance.” The term sheet, in part, listed twenty
3
“Conditions Precedent to Closing.”8
4
On July 27, 2011, a DV representative sent Matthew Wright an email
5
regarding the term sheet that requested: “Would you be able to put a period after
6
‘credit facility’ in the first paragraph and strike the reference that this is ‘not an actual
7
commitment to lend.’ We fully understand this is a term sheet and not an obligation
8
or commitment to lend, but would prefer if that language could be removed or
9
modified.” Wright sent DV the requested modification to the first page of the term
10
11
8
These twenty conditions precedent were:
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
An executed Power Purchase Agreement (PPA); An executed Site
Lease Agreement; All necessary and relevant operating permits; A
review of the executed Interconnection Agreement; Evidence of tax
equity interest to fund; Appraisal of solar installation; Independent
engineering report and other consultant reports as reasonably
requested by lender, including Independent Engineer approval;
Confirmation that project company has received clear title to any and
all equipment from the installer; An approved project financial model,
using a P90 solar resource production forecast, contractual revenue
streams demonstrating debt service coverage of at least 1.10x after all
operating and fixed expenses, and a P50 solar resource production
forecast requirement of debt service coverage of at least 1.20x;
Consents to collateral assignment with respect to material project
documents; Customary legal opinions; Deeds of trust/mortgages
plaintiff-relator fixture filings as appropriate; Receipt of Loan
Documents; Payment of fees and expenses; Accuracy of reps and
warranties; Loan documents, project documents and applicable permits
in full force and effect; All documentation to be satisfactory to Lender
in its sole discretion; Borrower will provide customary insurance
coverage or caused to be provided for the project from a carrier
acceptable to Lender; No material adverse change in the financial
condition of the Borrower or Guarantor; Any other documents or
information reasonably requested by lender.
- 12 -
1
sheet on July 29, 2011. Wright testified that he did so because the modification was
2
no going to add any risk to NCB because it was clear throughout the document that
3
it was just a term sheet.
4
On September 15, 2011, six weeks after the expiration of the securing
5
financing deadline of July 31, 2011, Matthew Wright sent DV’s representative an
6
email that stated in part: “Also wanted to remind you that given your previous time
7
constraints I sent out the term sheet without going through our formal credit
8
committee vetting process. While I do not expect much to change I wanted to remind
9
you that we still have to get some internal comments on the deal. I am waiting for
10
updated financials, projections and financials on the developers before bringing it to
11
our credit group.” In response, DV’s representative emailed Wright on that same
12
day to state in part that DV “would like to target an October closing if possible.”
13
Wright emailed a reply that same date that stated in part: “We could shoot for that.
14
Once I bring this through the credit committee with the updated numbers I will send
15
out a new term sheet. Once we get that signed off on we can dual track the
16
commitment with closing documents.”
17
Matthew Wright testified that NCB’s regular business practice was to issue a
18
term sheet after it had completed a substantial portion of its underwriting with
19
respect to the loan transaction. He also testified that NCB and SUN had agreed to
20
the overall financial structure of the loan transaction as reflected in the term sheet,
21
that he was confident as of July 22, 2011, the date that NCB issued the term sheet,
22
that NCB, barring any unforeseen circumstances, would have closed on SUN’s
23
financing request and funded the loan within two weeks to 30 days depending on
24
how quickly NCB got the deliverables, i.e., due diligence items, from SUN. Wright
25
further testified that he believed that as July 22, 2011, SUN had secured bridge loan
26
- 13 -
1
financing from NCB.
2
While Mark Moore, as president of SUN, signed the term sheet on July 25,
3
2011, there is no evidence that he returned it to NCB notwithstanding that NEC did
4
not send its PPA termination letter to SUN until August 4, 2011. Matthew Wright
5
testified that NCB never received the signed term sheet from either SUN or DV, and
6
that NCB never received the $10,000 good faith deposit from either SUN or DV.
7
Wright further testified that NCB would not undertake its underwriting steps
8
necessary to get to the loan commitment letter stage without the good faith deposit.
9
SUN argues that its evidence establishes that it had obtained a financing
10
proposal and a term sheet from NCB on July 22, 2011, and that NCB would have
11
promptly closed on the financing terms set forth in the term sheet had NEC not
12
terminated the PPA; SUN asserts that this term sheet was sufficient to establish that
13
it had timely secured financing. NEC argues that SUN did not even meet its own
14
proposed definition of securing financing because it at best had achieved only
15
tentative and conditional steps to obtaining financing by the deadline. While it is
16
questionable whether the above evidence by itself constitutes a sufficient basis for
17
a reasonable trier of fact to conclude that SUN had sufficiently secured financing by
18
the July 31, 2011 deadline regardless of how “secured” is defined, this issue cannot
19
be resolved separately from SUN’s claim that NEC impeded SUN’s ability to timely
20
secure financing.
21
This aspect of SUN’s breach of contract claim is based on the general
22
principle that “[i]f one party to a contract prevents the other party from performing
23
one of the conditions to the contract, then he cannot use the failure to deny his own
24
obligation under the agreement.” Fowler v. Dana, 436 P.2d 166, 167 (Ariz.App.
25
1968). The record contains the following undisputed or insufficiently controverted
26
- 14 -
1
evidence submitted by SUN related to its contention that NEC’s delay in providing
2
SUN with its audited financial statements impeded SUN’s ability to timely secure
3
financing for the solar power plant project. James Howard of DV, who was
4
responsible for obtaining financing for the project on SUN’s behalf, testified that
5
audited financials from NEC were absolutely critical because the banks’ assessment
6
of the creditworthiness of the project was dependent on NEC’s ability to pay for the
7
power and the renewable energy credits. Mark Moore of SUN testified that he first
8
requested NEC’s audited financial statements on February 14, 2011 when he then
9
informed NEC that SUN’s lenders were requesting the information as part of SUN’s
10
movement toward closing on the financing for the project. Moore further testified
11
that despite NEC receiving a letter on February 25, 2011 from DV which further
12
explained why SUN needed NEC’s audited financial statements, David Plumb,
13
NEC’s CEO, repeatedly refused to provide the financial information to SUN. Plumb
14
testified that although he could potentially have provided the requested financial
15
information in less than a day, he initially refused to provide NEC’s financial
16
information for various reasons, which included that the PPA should have given
17
sufficient information to SUN’s lenders, that the PPA did not require NEC to provide
18
SUN with its audited financial statements, that NEC was not in the habit of providing
19
audited financials on just any request, and that SUN could obtain the necessary
20
NEC documents from the Arizona Corporation Commission. Moore testified that
21
SUN made repeated attempts to obtain the financial information from NEC and that
22
NEC did not provide its financial information until May 18, 2011, more than three
23
months after SUN’s first request.
24
Matthew Wright of NCB testified that it is essential and consistent with industry
25
custom and practice for a lender to require a utility’s audited financial statements
26
- 15 -
1
before making a financing offer such as the one NCB made to SUN, that the utility’s
2
delay in providing audited financial statements will delay the lender’s decision to
3
issue a financing offer, that NCB was not prepared to make a financing proposal to
4
SUN without NEC’s audited financials, which NCB did not receive until May 19,
5
2011, and that it was quite possible that the bank would have been in a position to
6
issue its financing proposal, which it did not send to SUN until July 22, 2011, sooner
7
had it received NEC’s audited financial statements months earlier.
8
The Court agrees with SUN that the evidence it submitted, together with the
9
justifiable inferences from that evidence, all viewed in SUN’s favor, constitutes
10
significant probative evidence creating a genuine dispute of material fact as to
11
whether NEC improperly interfered with SUN’s efforts to timely secure construction
12
financing. Because the Court cannot conclude as a matter of law that NEC did not
13
breach the PPA by terminating it pursuant to § 2.02(b) in part based on its belief that
14
SUN had not timely secured construction financing, NEC is not entitled to entry of
15
summary judgment in its favor on the breach of contract claim.
16
C. Commencement of Construction
17
Pursuant to § 2.02(b), SUN also had to commence construction of the
18
Generating Facility by July 31, 2011.9
19
construction of the generating facility had to have been commenced by the July 31,
20
2011 deadline, argues that the Court can conclude as a matter of law based on the
NEC, which asserts that “vertical”
21
22
23
24
25
26
9
Article One of the PPA defined “Generating Facility” in relevant part as
meaning SUN’s “electric generating facility that qualifies as an Eligible Renewable
Energy Resource, with a nameplate equal to the Capacity, ... together with all
materials, equipment systems, structures, features and improvements, additions,
modifications or expansions as determined in [SUN’s] discretion and necessary to
produce electric energy at such facility, excluding land rights and interests in land.”
- 16 -
1
undisputed evidence that SUN had not actually commenced construction by the
2
deadline. SUN asserts that the PPA does not require the commencement of vertical
3
construction by the deadline and that it sufficiently commenced construction to meet
4
the deadline. Since the PPA does not define the term “commenced” for purposes
5
of § 2.02(b) and since there is no evidence in the record that establishes that the
6
term has any special trade meaning or industry usage, the Court will construe the
7
word “commenced” in its normal, ordinary meaning, which in this context means “to
8
begin” or “to start.”
9
The following relevant evidence concerning SUN’s commencement of
10
construction is in the record; the Court considers this evidence to be undisputed for
11
purposes of the summary judgment motion. On March 7, 2011, DV asked Sundt,
12
Inc., a large construction company, to prepare a construction proposal on SUN’s
13
behalf for its Hunt Valley solar power plant. Chad Buck, then a senior estimator at
14
Sundt, provided a construction proposal to DV on March 24, 2011 based on a
15
conceptual design of the plant provided by DV; the proposal estimated the cost to
16
construct the plant and the time it would take to complete physical construction of
17
the plant, which Buck estimated to be approximately two months to three months
18
depending on the construction alternative to be selected.
19
construction-site surveys in April 2011, which did not include the placement of a
20
future roadway that needed to be built on the site property, and on April 20, 2011,
21
SUN closed escrow on the lease option for the property on which the plant was to
22
be built.
SUN secured two
23
Mark Moore, SUN’s CEO, testified that on July 31, 2011, the construction
24
commencement deadline, SUN conducted a ground breaking ceremony on the site
25
property which consisted solely of Moore, a SUN consultant, and the landowner
26
- 17 -
1
installing a sign, made from two 4x4 posts and a piece of plywood with SUN’s logo
2
on it, on the site property by digging holes and pouring cement for the sign posts.
3
Moore, at some unspecified date, also had 32 linear feet of chain link fence installed
4
to delineate a single corner of the site property, which consisted of the placement of
5
sixteen feet of fencing on either side of the corner. Moore also testified that to his
6
knowledge no other construction-related activity had been done at the site prior to
7
August 4, 2011, the date NEC terminated the PPA.
8
Chad Buck of Sundt testified that Sundt had never reached a construction
9
contract with either SUN or DV, that Sundt would have insisted on a written contract
10
before it commenced work, and that Sundt would not go on a job site and move dirt
11
or start to retain subcontractors and order supplies without a written construction
12
contract. Buck also testified that Sundt does not start the build part of a design build
13
project until the design is far enough along for it to know what it was building, and
14
that he agreed that the SUN project never got out of the box in terms of design, let
15
alone getting specific enough for him to know what Sundt was going to build. He
16
further testified that the SUN project had never advanced far enough for Sundt to
17
apply for any permits, such as a permit for clearing and grubbing the building site
18
because the project design was not even far enough along for Sundt to know what
19
to clear and grub. He also testified that Sundt had no formal design for the project,
20
but had developed its anticipated layout and had based its pricing off of that. He
21
finally testified that Sundt had not commenced construction on the SUN project as
22
of July 31, 2011.
23
NEC’s termination letter, dated August 4, 2011, stated in part regarding the
24
commencement of construction requirement that a NEC representative visited the
25
site on August 1, 2011 and found no evidence that there had been construction
26
- 18 -
1
mobilization or construction activity related to the solar power plant and that pictures
2
taken during the site visit showed no ground disturbance or construction vehicles on
3
site.
4
The termination letter further stated in part that if SUN provided sufficient
5
documentation to NEC by August 19, 2011 that construction had been timely
6
commenced then NEC would rescind the termination letter. In response thereto, on
7
August 22, 2011, SUN sent NEC a letter stating that the construction proposal that
8
Sundt sent to SUN met the specified terms of the PPA and that a draft contract had
9
also been delivered. The copy of the draft contract attached to the letter was simply
10
a standard model form construction contract in which all of the blank spaces where
11
relevant project-specific information were to be filled in were left blank.
12
The Court, having viewed the evidence of record and the justifiable inferences
13
from that evidence in SUN’s favor, concludes that there is no triable issue of fact as
14
to this portion of SUN’s breach of contract claim because a fair-minded trier of fact
15
could not conclude that SUN had timely commenced construction of the solar power
16
plant under any reasonable definition of the word “commenced.”
17
installation of a corporate sign and the installation of 32 feet of fencing on one corner
18
of the site where the plant was to be constructed simply cannot be reasonably
19
considered to constitute anything more that a scintilla of evidence that is insufficient
20
to show that construction had been commenced, particularly in light of SUN’s failure
21
to submit any significant probative evidence establishing either that it had negotiated
22
a construction contract with Sundt or that it had provided Sundt with a completed
23
design for the plant before the termination deadline.10 While there is no dispute that
The mere
24
10
25
26
To the extent that SUN is in any way contending in its response to the
summary judgment motion that NEC’s three-month delay in providing its audited
- 19 -
1
SUN had timely concluded a lease for the plant site, that does not create a genuine
2
issue of material fact regarding the commencement of construction because the
3
PPA’s definition of “Generating Facility” specifically excludes “land rights and
4
interests in land.”
5
preparations for the commencement of construction prior to the July 31, 2011
6
deadline, not that it had actually started the construction of the plant.
7
(2) Breach of the Implied Covenant of Good Faith and Fair Dealing Claim
SUN has, at best, shown only that it had begun some
8
NEC also argues that it is entitled to summary judgment on SUN’s claim that
9
NEC’s termination of the PPA violated the contract’s implied covenant of good faith
10
and fair dealing. SUN argues in its summary judgment response that NEC violated
11
the implied covenant in two ways, one of which is that NEC terminated the PPA for
12
a reason beyond the risks assumed by SUN. The Court concludes that SUN has not
13
raised a triable issue of fact as to this aspect of the breach of its implied covenant
14
claim.
15
Arizona law implies a covenant of good faith and fair dealing in every contract.
16
Wells Fargo Bank v. Arizona Laborers, Teamsters and Cement Masons Local No.
17
395 Pension Trust Fund, 38 P.3d 12, 28 (Ariz.2002), and the breach of the implied
18
covenant may provide the basis for imposing contract damages. Id. at 29; United
19
Dairymen of Arizona v. Schugg, 128 P.3d 756, 760 (Ariz.App.2006). The duty to act
20
in good faith does not “alter the specific obligations of the parties under the contract”
21
22
23
24
25
26
financial statements to SUN prevented SUN from timely commencing construction
of the solar power plant, the Court rejects that contention. There is nothing in SUN’s
statements of facts that establishes that construction would have commenced earlier
but for the delay in obtaining NEC’s financial statements, and SUN’s response does
not contain any cogent argument raising such an issue (as opposed to the issue that
the delay in obtaining NEC’s financial information delayed the securing of financing
for the project).
- 20 -
1
and “[a]cts in accordance with the terms of one’s contract cannot without more be
2
equated with bad faith.” Wells Fargo Bank, at 30 (emphasis in original). The
3
necessary something “more” may arise if one party exercises discretion retained
4
under a contract “in such a way as to deny the other a reasonably expected benefit
5
of the bargain.” Id.
6
SUN’s contention is that NEC’s termination of the PPA pursuant to § 2.02(b)
7
constitutes a violation of the implied covenant because the risk SUN assumed under
8
the PPA was that NEC could terminate the contract only if the plant was not
9
commercially operational by July 31, 2012 as required by § 2.02(c). The Court
10
concludes that this argument has no merit because SUN, as a matter of law,
11
expressly assumed the risk of a § 2.02(b) termination by executing the PPA. As the
12
Court has already noted, § 2.02(b) and § 2.02(c) unambiguously provided NEC with
13
distinct and separate termination rights, and because SUN has not established the
14
existence of any disputed issue of material fact concerning its failure to timely
15
commence construction of the plant, SUN had no justifiable expectation that a
16
termination pursuant to § 2.02(b) could not be partially based on such a failure on
17
its part.
18
SUN argues that NEC also violated the implied covenant by failing to
19
cooperate with SUN’s efforts to timely obtain construction financing and that §
20
2.02(b) does not constitute an agreement on its part that NEC could terminate the
21
PPA for delays that NEC caused.
22
Arizona law recognizes that a party to a contract “may not exercise a retained
23
contractual power in bad faith.” Wells Fargo Bank, 38 P.3d at 30. See also,
24
Restatement (Second) of Contracts § 205, cmt d. (noting that for purposes of the
25
obligation of good faith and fair dealing, bad faith may be overt or may consist of
26
- 21 -
1
inaction and that interference with or failure to cooperate in the other party’s
2
performance has been recognized by the courts as a type of bad faith.)
3
Based on the evidence already set forth, the Court concludes that SUN has
4
established the existence of a genuine dispute of material fact as to whether NEC
5
breach the implied covenant of good faith and fair dealing by improperly interfering
6
with Sun’s efforts to timely secure construction financing. Therefore,
7
8
9
IT IS ORDERED that defendant Navopache Electric Cooperative, Inc.’s
Motion to Exclude James Dudley Howard, Jr. as a Witness (Doc. 71) is denied.
IT IS FURTHER ORDERED that plaintiff Solar Utilities Network. LLC’s Motion
10
to Strike Defendant Navopache Electric Cooperative, Inc.’s Improper Controverting
11
Statement to Sun’s Supplemental Statement of Facts (Doc. 85) is granted and that
12
defendant Navopache Electric Cooperative, Inc.’s Controverting Statement to SUN’s
13
Supplemental Statement of Facts (Doc. 84), and Exhibits A, B, C, D, E, F, and G
14
attached thereto (Doc. 84-1) are stricken from the record.
15
16
IT IS FURTHER ORDERED that defendant Navopache Electric Cooperative,
Inc.’s Alternative Motion for Leave to File Amended Reply (Doc. 86) is denied.
17
IT IS FURTHER ORDERED that defendant Navopache Electric Cooperative,
18
Inc.’s Motion for Summary Judgment Pursuant to Rule 56 (Doc. 72) is denied. The
19
Court, however, finds pursuant to Fed.R.Civ.P. 56(g) that the following material facts
20
are not genuinely in dispute and are to be treated as established in this case for trial
21
purposes: (1) that plaintiff Solar Utilities Network, LLC did not timely commence
22
construction of the Generating Facility for purposes of § 2.02(b) of the parties’ Solar
23
Energy Power Purchase Agreement; and (2) that a termination of the contract
24
pursuant to § 2.02(b) by defendant Navopache Electric Cooperative, Inc., regardless
25
of whether the deadline of § 2.02(c) for the commencement of the commercial
26
- 22 -
1
operation of the Generating Facility could have been met, was a risk that plaintiff
2
Solar Utilities Network, LLC expressly assumed by executing the parties’ Solar
3
Energy Power Purchase Agreement
4
IT IS FURTHER ORDERED that a separate order will be entered in due
5
course setting deadlines for filing the Joint Pretrial Statement and trial-related
6
documents, and setting dates for holding the Joint Pretrial Conference and
7
commencing the trial.
8
DATED this 29th day of September, 2015.
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
- 23 -
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?