Natural Resources Defense Council et al v. Norton et al
Filing
1018
MEMORANDUM DECISION AND ORDER GRANTING MOTION TO AMEND signed by District Judge Lawrence J. O'Neill on April 22, 2016. (Doc. 999) (Munoz, I)
1
2
UNITED STATES DISTRICT COURT
3
FOR THE EASTERN DISTRICT OF CALIFORNIA
4
5
NATURAL RESOURCES DEFENSE
COUNCIL, et al.,
6
Case No. 1:05-cv-01207 LJO-GSA
MEMORANDUM DECISION AND
ORDER GRANTING MOTION TO
AMEND (Doc. 999).
Plaintiffs,
7
vs.
8
DIRK KEMPTHORNE, Secretary,
U.S. Department of the Interior, et al.,
9
10
11
Defendants.
SAN LUIS & DELTA MENDOTA WATER
AUTHORITY; et al.,
Defendant-Intervenors.
12 ANDERSON-COTTONWOOD IRRIGATION
DISTRICT; et al.,
13
Joined Parties.
14
15
16
I. INTRODUCTION
Plaintiffs, a coalition of environmental interest groups led by the Natural Resources Defense
17
Council (collectively, “Plaintiffs”), allege in the currently-operative Third Amended Complaint (“TAC”)
18
that the U.S. Bureau of Reclamation (“Bureau” or “Reclamation”) and the U.S. Fish and Wildlife
19
Service (“FWS” or “Service”) (collectively, “Federal Defendants”) acted unlawfully by renewing,
20
implementing, and approving the renewal and implementation of certain long-term water contracts in
21
reliance on a 2005 Biological Opinion (“2005 FWS Smelt BiOp”) issued by FWS pursuant to the
22
Endangered Species Act (“ESA”), 16 U.S.C. §§ 1531 et seq., that the agencies knew, or should have
23
24
known, was inadequate to protect the ESA-listed delta smelt. Doc. 575 (filed Apr. 8, 2008). Specifically,
Plaintiffs challenged renewal of two sets of contracts: (1) those held by the Sacramento River Settlement
25
1
1
(“SRS”) Contractors; and (2) those held by the Delta-Mendota Canal Unit (“DMC”) Contractors. Id.
2
On June 15, 2015, the Court stayed this litigation to allow Reclamation to reinitiate ESA-
3
consultation on the contract renewals. Doc. 979. Thereafter, Reclamation requested FWS’s concurrence
4
that the impacts of these contract renewals on delta smelt were assessed in the more recent 2008
5
Biological Opinion on the Long-Term Central Valley Project Operations Criteria and Plain (“2008 FWS
6
OCAP Smelt BiOp”). FWS responded by sending Reclamation a letter (“2015 Letter of Concurrence” or
7
“2015 LOC”) concurring with Reclamation’s conclusion that “all of the possible effects to delta smelt
8
and its critical habitat by operating the CVP to deliver water under the SRS and DMC Contracts were
9
addressed in the [2008 FWS OCAP Smelt BiOP]”.
Before the Court is Plaintiffs’ motion to file a Fourth Supplemental Complaint (“4SC”), seeking
10
11 to add three new claims to the case: one claim (the proposed Fourth Claim for Relief) pertaining to
12 FWS’s renewed consultation, and two claims (the proposed Fifth and Sixth Claims for Relief) arising
13 out of the absence of any parallel consultation on how SRS Contract renewals would impact endangered
14 Sacramento River winter-run Chinook salmon (“winter-run Chinook”) and threatened Central Valley
15 spring-run Chinook salmon (“spring-run Chinook”). Doc. 999. Federal Defendants (Doc. 1007); the San
16 Luis & Delta-Mendota Water Authority, Westlands Water District, and the DMC Unit Contractors
1
17 Defendants (collectively “CVP Water Service Contractors”) (Doc. 1008); and the SRS Contractors
18 (Doc. 1009) filed oppositions, objecting only to the addition of the Fifth and Sixth Claims for relief.
19 After Plaintiffs filed their reply, the Court vacated the hearing date to afford additional time to review
20 the complex history and context of this case. Doc. 1017. Having thoroughly reviewed the record, the
21 Court deems the matter sufficiently briefed and suitable for decision on the papers without oral
2
22 argument pursuant to Local Rule 230(g), and GRANTS Plaintiffs’ motion to supplement the complaint.
23
24
25
1
Coelho Family Trust, Eagle Field Water District, Fresno Slough Water District, Mercy Springs Water District, Oro Loma
Water District, and Tranquility Irrigation District.
2
Plaintiffs filed a request for judicial notice, Doc. 1005, to which the SRS Contractors have interposed several objections.
Doc. 1010. The Court has not relied upon any of the objected to information (at least not for any objected to purpose), so it is
2
1
II. LEGAL BACKGROUND
2
“Under the ESA, the Secretary of the Interior and the Secretary of Commerce are charged with
3
identifying threatened and endangered species and designating critical habitats for those species.” Nat.
4
Res. Def. Council v. Jewell, 749 F.3d 776, 779 (9th Cir. 2014) (“NRDC v. Jewell”) (citing 16 U.S.C. §
5
1533). FWS and the National Marine Fisheries Service (“NMFS”) administer the ESA on behalf of the
6
Departments of the Interior and Commerce, respectively. See 50 C.F.R. §§ 17.11, 222.101(a), 223.102,
7
402.01(b). Section 7 of the ESA requires federal agencies to ensure that their activities do not jeopardize
8
the continued existence of listed endangered or threatened species or adversely modify those species’
9
critical habitats. 16 U.S.C. § 1536(a)(2); see also Karuk Tribe of Cal. v. U.S. Forest Serv., 681 F.3d
10 1006, 1020 (9th Cir. 2012). Section 7’s implementing regulations provide that “[e]ach Federal agency
11 shall review its actions at the earliest possible time to determine whether any action may affect listed
12 species or critical habitat[s].” 50 C.F.R. § 402.14(a). An agency proposing to take an action (often
3
13 referred to as the “action agency”) must first inquire of FWS or NMFS whether any threatened or
14 endangered species “may be present” in the area of the proposed action. See 16 U.S.C. § 1536(c)(1). If
15 endangered species may be present, the action agency must prepare a “biological assessment” (“BA”) to
16 determine whether such species “is likely to be affected” by the action. Id. If the BA determines that a
17 threatened or endangered species “is likely to be affected,” the agency must formally consult with FWS.
18 See id. § 1536(a)(2); 50 C.F.R. 402.14(a).
19
Formal consultation results in the issuance of a “biological opinion” (“BiOp”) by FWS. See 16
20 U.S.C. § 1536(b). If the BiOp concludes that the proposed action would jeopardize the species or
21
22
23
24
25
not necessary to rule on the objections.
3
Generally, FWS has jurisdiction over species of fish that either (1) spend the major portion of their life in fresh water, or (2)
spend part of their lives in estuarine waters, if the remaining time is spent in fresh water. See Cal. State Grange v. Nat’l
Marine Fisheries Serv., 620 F. Supp. 2d 1111, 1120 n.1 (E.D. Cal. 2008), as corrected (Oct. 31, 2008). NMFS is granted
jurisdiction over fish species which (1) spend the major portion of their life in ocean water, or (2) spend part of their lives in
estuarine waters, if the remaining portion is spent in ocean water. Id. FWS exercises jurisdiction over the delta smelt; NMFS
exercises jurisdiction over the winter-run and spring-run Chinook.
3
1
destroy or adversely modify critical habitat, see id. § 1536(a)(2), then the action may not go forward
2
unless FWS can suggest a “reasonable and prudent alternative[]” (“RPA”) that avoids jeopardy,
3
destruction, or adverse modification. Id. § 1536(b)(3)(A). If the BiOp concludes that jeopardy is not
4
likely and that there will not be adverse modification of critical habitat, or that there is a RPA to the
5
agency action that avoids jeopardy and adverse modification and that the incidental taking of
6
endangered or threatened species will not violate Section 7(a)(2), the consulting agency can issue an
7
“Incidental Take Statement” which, if followed, exempts the action agency from the prohibition on
8
takings found in Section 9 of the ESA. 16 U.S.C. § 1536(b)(4); Aluminum Co. of Am. v. Administrator,
9
Bonneville Power Admin., 175 F.3d 1156, 1159 (9th Cir. 1999).
Even after consultation is complete, an agency has a duty to reinitiate formal consultation under
10
11 certain circumstances, including if: “the amount or extent of taking specified in the incidental take
12 statement is exceeded”; “new information reveals effects of the action that may affect listed species or
13 critical habitat in a manner or to an extent not previously considered”; or “the identified action is
14 subsequently modified in a manner that causes an effect to the listed species or critical habitat that was
15 not considered in the biological opinion.” 50 C.F.R. § 402.16. “The consultation requirement reflects ‘a
16 conscious decision by Congress to give endangered species priority over the ‘primary missions’ of
17 federal agencies.’” Karuk Tribe, 681 F.3d at 1020 (quoting Tenn. Valley Auth. v. Hill, 437 U.S. 153, 185
18 (1978)).
III. FACTUAL AND PROCEDURAL HISTORY4
19
20
1.
The Central Valley Project and the State Water Project.
21
The Central Valley Project (“CVP”) and the State Water Project (“SWP”), “operated
22 respectively by [Reclamation] and the State of California, are perhaps the two largest and most
23 important water projects in the United States.” San Luis & Delta-Mendota Water Auth. v. Jewell, 747
24
25
4
The factual and procedural history is presented roughly in chronological order, with deviations from this ordering scheme
where subject-matter grouping is more appropriate.
4
1
F.3d 581, 592 (9th Cir. 2014) (“San Luis v. Jewell”). “These combined projects supply water originating
2
in northern California to more than 20,000,000 agricultural and domestic consumers in central and
3
southern California.” Id. As part of CVP operations, Reclamation releases water stored in CVP
4
reservoirs in northern California, which then flows down the Sacramento River to the Sacramento-San
5
Joaquin Delta (“Delta”). Id. at 594. Pumping plants in the southern region of the Delta then divert to
6
various users south of the Delta. See id. at 594-95.
7
2.
Delta Smelt.
8
The delta smelt (Hypomesus transpacificus) is a “small, two-to-three inch species of fish
9
endemic to the [Delta].” Id. at 595. In 1993, FWS concluded the delta smelt’s population had declined
10 by ninety percent over the previous twenty years and listed it as a “threatened” species under the ESA.
11 Determination of Threatened Status for the Delta Smelt, 58 Fed. Reg. 12,854, 12,855 (Mar. 5, 1993).
12 FWS further determined that “Delta water diversions,” including those resulting from operations of the
13 CVP, are the most significant “synergistic cause[ ]” of the decline in the delta smelt population. Id. at
14 12,859.
15
3.
16
Winter-run Chinook (Oncorhynchus tshawytscha) are listed as “endangered” under the ESA.
Winter-Run Chinook.
17 Endangered and Threatened Species: Final Listing Determinations for 16 ESUs of West Coast Salmon,
18 and Final 4(d) Protective Regulations for Threatened Salmonid ESUs, 70 Fed. Reg. 37,160 (June 28,
19 2005). According to the 4SC, the winter-run Chinook’s population “has declined precipitously since the
20 early 1980s, from an estimated historic high of 117,808 in 1969 to as few as 191 adult individuals
21 returning to spawn in 1991.” 4SC ¶ 64. Winter-run Chinook historically inhabited the upper Sacramento
22 River and its tributaries. Id. ¶ 66. The construction of Shasta Dam blocked access to almost all of the
23 winter-run Chinook’s rearing waters. Id. Today, the upper Sacramento River below Keswick Dam is the
24 only remaining spawning area used by winter-run Chinook. Id. It is alleged that the winter-run Chinook
25 is “at high risk of extinction” and that a prolonged drought could have devastating effects on the species.
5
1
Id. It is further alleged that winter-run are particularly vulnerable during the “temperature management
2
season,” which generally lasts from June through October. Id. ¶ 67.
Adult winter-run Chinook migrate up the Sacramento River in the winter
and spring and then hold below the Keswick Dam for several months
before spawning. During these critical months, the salmon require cold
water for the maturation of their gonads and the development of fertilized
eggs and embryos.
3
4
5
6
Id.
4.
Spring Run Chinook.
7
The spring-run Chinook (Oncorhynchus tshawytscha) historically displayed the second largest
8
salmon run in the Central Valley watershed and supported the bulk of the region’s commercial fishery.
9
Id. ¶ 68. Only remnant independent natural spring-run Chinook populations survive, relying principally
10
upon small tributaries of the Sacramento River below Shasta Dam for spawning. Id. ¶¶ 68, 71. Like
11
winter-run Chinook, spring-run Chinook require cold water temperatures for successful spawning, egg
12
incubation, and rearing. Id. ¶ 72.
13
5.
Long-Term Contract Renewal/Operations and Criteria Plan.
14
“In the 1960s, the Bureau entered into a number of long-term contracts pertaining to the CVP.”
15
NRDC v. Jewell, 749 F.3d at 780. “The [SRS] Contracts are forty-year agreements between the Bureau
16
and holders of certain senior water rights.” Id. “These contracts grant the Bureau some rights to the
17
encumbered water while also providing senior rights holders a stable supply of water.” Id. The DMC
18
Contracts allow junior water users to draw water from the Delta-Mendota Canal. Id. By 2004, the DMC
19
Contracts and the SRS Contracts had expired or were about to expire. Id. In the early 2000s, the Bureau
20
prepared an operational plan, the Operations Criteria and Plan (“OCAP”), to, among other things,
21
provide a basis for renewing various contracts, including the DMC and Settlement Contracts. Id.
22
6.
ESA § 7 Consultations Leading Up to Contract Renewal.
23
Pursuant to ESA § 7, the Bureau initiated consultation with FWS regarding the effect of the
24
OCAP on the delta smelt. Id. at 780-81. FWS issued an initial BiOp in 2004 (the “2004 FWS Smelt
25
6
1
OCAP BiOp”), which concluded that the OCAP would not jeopardize the delta smelt. Id. at 781. The
2
Bureau re-initiated consultation after the Ninth Circuit’s decision in Gifford Pinchot Task Force v. U.S.
3
Fish & Wildlife Serv., 378 F.3d 1059, 1069 (9th Cir. 2004), which invalidated a regulation upon which
4
the 2004 OCAP BiOp relied. NRDC v. Jewell, 749 F.3d at 781. In 2005, FWS issued a revised BiOp
5
(“2005 FWS Smelt BiOp”), which also concluded that the OCAP would not jeopardize the delta smelt.
6
Id.
7
Reclamation separately requested a BiOp from NMFS on whether continued operation of the
8
CVP pursuant to the OCAP would jeopardize various species under that agency’s jurisdiction, including
9
the winter-run and spring-run Chinook. See PCFFA v. Gutierrez, No. 1:06-cv-245 OWW GSA
10 (“PCFFA”), Doc. 69 ¶ 77 (First Amended Complaint) (“PCFFA FAC”). NMFS issued a BiOp on
11 October 22, 2004 regarding the effects of the OCAP on the species under its jurisdiction, including
12 several salmonid species (“2004 NMFS OCAP Salmonid BiOp”). 4SC ¶ 107.
13
Also in 2004 and 2005, the Bureau prepared BAs that concluded that renewal of the Contracts
14 would not adversely affect the delta smelt. NRDC v. Jewell, 749 F.3d at 781. The Bureau requested
15 additional consultation with FWS regarding its plans to renew the Contracts. Id.
16
17
18
19
FWS responded via a series of letters, in which it concurred with the
Bureau’s determination that renewing the Contracts was not likely to
adversely affect the delta smelt. Each FWS concurrence letter explained
that renewing the Contracts would increase the demand for water, but that,
according to the 2004 and 2005 [FWS OCAP Smelt] BiOps, this demand
would not adversely affect the delta smelt. The letters did not assess the
Contracts’ potential effects on the delta smelt beyond the reasoning
borrowed from the now-invalidated 2004 Opinion and 2005 Opinion.
20
Id. (emphasis added).
21
Again, Reclamation separately consulted with FWS on the effects of renewing the Contracts on
22
the listed salmonid species under NMFS’s jurisdiction. 4SC ¶ 108. As was the case with FWS, NMFS
23
concurred that executing the Contracts would not adversely impact listed salmonids. Id.
24
In 2004 and 2005, the Bureau renewed 141 Settlement Contracts and 18 DMC Contracts based
25
7
1
on FWS’s and NMFS’s concurrence letters. NRDC v. Jewell, 749 F.3d at 781.
2
7.
Plaintiffs Challenge the 2004/2005 FWS OCAP Smelt BiOp.
3
In February 2005, Plaintiffs initiated this lawsuit, challenging the 2004 FWS OCAP Smelt BiOp.
4
Doc. 1. Subsequent amendments to the Complaint updated Plaintiffs’ allegations to include challenges
5
to the 2005 FWS OCAP Smelt BiOp. Doc. 403 (Second Amended Complaint (“SAC”)). Plaintiffs raised
6
numerous challenges to the legal sufficiency of the 2005 FWS OCAP Smelt BiOp in the SAC, filed July
7
10, 2007. Id. Among other things, the SAC alleged that the 2005 FWS OCAP Smelt BiOp did not
8
“adequately consider or address the effects of [the] long-term water service contracts on threatened and
9
endangered species,” id. ¶ 32, and that the Bureau “has taken and is taking actions that could foreclose
10 implementation of reasonable and prudent alternatives that would avoid jeopardy, including but not
11 limited to signing and implementing new long-term contracts promising delivery of substantially
12 increased quantities of water, in violation of [ESA] section 7(d).” Id. ¶ 81. In 2007, the 2005 FWS Smelt
13 BiOp was set aside as unlawful. Nat. Res. Def. Council v. Kempthorne, 506 F. Supp. 2d 322 (E.D. Cal.
14 2007). The Bureau did not appeal.
15
8.
16
On August 9, 2005, Plaintiffs filed a parallel complaint against Reclamation and NMFS alleging
Plaintiffs Challenge the 2004 NMFS OCAP Salmonid BiOp.
17 that the NMFS 2004 OCAP Salmonid BiOp was inadequate. Pac. Coast Fed'n of Fishermen's
18 Associations v. Gutierrez, 606 F. Supp. 2d 1122, 1131 (E.D. Cal. 2008) (“PCFFA I”). Plaintiffs
19 similarly sought to “[e]njoin and set aside any and all actions” that relied on it, including the delivery of
20 water under long-term water contracts at issue here. Id. at 1183 (“Existing renewal and any new water
21 service contracts have already been challenged in this litigation.”); PCFFA FAC at 38.
22
9.
23
On May 20, 2008, the previously assigned district judge found that NMFS acted arbitrarily and
District Court Ruling in PCFFA.
24 capriciously by failing to consider certain facts in the NMFS 2004 OCAP Salmonid BiOp. PCFFA I,
25 606 F. Supp. 2d at 1193-94. In July 2008, the Court considered Plaintiffs’ motion for injunctive relief,
8
1
seeking implementation of remedies designed to aid salmonids in the Sacramento River basin. In the
2
context of this request for injunctive relief, the Court concluded that the Bureau had a “mandatory (i.e.,
3
non-discretionary) legal obligation to make releases from Shasta Reservoir for delivery to the [SRS]
4
Contactors.” Pac. Coast Fed'n of Fishermen's Associations v. Gutierrez, 606 F. Supp. 2d 1195, 1201
5
(E.D. Cal. 2008) (“PCFFA II”). Plaintiffs did not seek to amend or supplement their complaint in
6
PCFFA.
7
10.
8
In June 2008, Plaintiffs filed the TAC, directly challenging the sufficiency of FWS’s ESA
9
Third Amended Complaint in This Case.
consultation undertaken in connection with renewal of 41 Contracts. See Doc. 575 ¶¶ 44-47, 69, 72-73.
10 In seeking to set aside these contracts, Plaintiffs argue that the Bureau violated § 7(a)(2) of the ESA by
11 failing to adequately consult with the FWS prior to renewing the Contracts. Id. ¶ 85.
12
11.
13
On December 15, 2008, the FWS issued a revised BiOp (the “2008 FWS OCAP Smelt BiOp”),
FWS Issues Revised Biological Opinion.
14 which, contrary to the findings of the 2004 and 2005 FWS OCAP Smelt BiOps, concluded that the
15 OCAP would jeopardize the delta smelt and adversely modify its critical habitat. NRDC v. Jewell, 749
16 F.3d at 781. The 2008 BiOp became the subject of numerous lawsuits. See generally San Luis & Delta
17 Mendota Water Auth. v. Salazar, 1:09-cv-407 LJO BAM. Plaintiffs in this matter intervened as
18 defendants in the challenge to the 2008 BiOps. See id.
19
12.
20
On June 4, 2009, NMFS issued a revised BiOp (“2009 NMFS OCAP Salmonid BiOp”). See San
NMFS Issues a Revised BiOp
21 Luis & Delta-Mendota Water Auth. v. Locke, 776 F.3d 971, 988 (9th Cir. 2014). Three months later, the
22 previously assigned district judge entered final judgment in PCFFA, and closed the matter. PCFFA,
23 1:06-CV-0245-OWW-GSA, Doc. 458 (Judgment, Sept. 9, 2009).
24 //
25 //
9
1
13.
District Court and Ninth Circuit Rulings on Plaintiffs’ Third Amended Complaint
in This Case.
2
In rulings in late 2008 and 2009 in this matter, the previously assigned district judge held that
3
Plaintiffs did not have standing to challenge renewal the DMC Contracts and that Plaintiffs’ challenge as
4
to the Settlement Contracts failed as a matter of law because Federal Defendants lacked discretion to
5
modify the Settlement Contracts to benefit Plaintiffs’ interests. Nat. Res. Def. Council v. Kempthorne,
6
2008 WL 5054115, at *22 (E.D. Cal. Nov. 19, 2008) (“NRDC v. Kempthorne”). A divided three-judge
7
panel of the Ninth Circuit Court of Appeals affirmed. Natural Res. Def. Council v. Salazar, 686 F.3d
8
1092 (9th Cir. 2012).
9
The Ninth Circuit subsequently voted to hear the case en banc, and the en banc panel reversed
10
and remanded. NRDC v. Jewell, 749 F.3d 776. The en banc decision first found that the issuance of the
11
2008 BiOp did not moot Plaintiffs’ challenge to the Contracts:
12
This action is not moot because the 2008 Opinion does not provide
Plaintiffs with the relief that they seek. The 2008 Opinion concluded that
the Bureau’s Plan would likely jeopardize the delta smelt and adversely
modify its critical habitat. In so doing, the 2008 Opinion explained that the
Bureau’s Plan must be modified from what the Bureau envisioned in 2004
and 2005, and the Opinion identified a “reasonable and prudent
alternative” to the proposed Plan that would avoid jeopardizing the delta
smelt.
13
14
15
16
The issuance of the 2008 Opinion does not moot this appeal. The 2008
Opinion merely assesses the general effects of the Bureau’s Plan, and it
does not represent a consultation with the FWS concerning the impact of
the Bureau’s decision to renew the specific contracts before us. Although
the DMC Contracts and Settlement Contracts were renewed based on
now-invalidated opinions, the Bureau has never reconsulted with the FWS
regarding the effects of renewing these contracts, nor has it sought to
amend the challenged contracts to incorporate the protections proposed in
the 2008 Opinion. The remedy Plaintiffs seek is an injunction requiring
reconsultation with the FWS and renegotiation of the challenged contracts
based on the FWS’ assessment. This relief remains available.
17
18
19
20
21
22
23 Id. at 782.
24
On the issue of standing related to the DMC Contracts, the previously assigned judge held that
25 Plaintiffs could not establish that their injury is fairly traceable to the Bureau’s alleged procedural
10
1
violation because: (1) the DMC Contracts contain a shortage provision that absolves the government
2
from liability for breaches that result from complying with its legal obligations; (2) this provision
3
permits the Bureau to take necessary actions to meet its legal obligations under the ESA; so (3) the
4
Bureau could not have negotiated any contractual terms that better protect the delta smelt, and, therefore,
5
any injury to the delta smelt is not traceable to the contract renewal process. NRDC v. Kempthorne, 2008
6
WL 5054115, at *11-18.
7
The Ninth Circuit rejected this reasoning, finding instead that “to establish standing, a litigant
8
who asserts a procedural violation under Section 7(a)(2) need only demonstrate that compliance with
9
Section 7(a)(2) could protect his concrete interests.” 749 F.3d at 783 (emphasis in original). The Ninth
10 Circuit concluded that the consultation could have led to revisions that would have benefitted the delta
11 smelt:
Contrary to the district court’s finding, the shortage provision does not
provide the delta smelt with the greatest possible protection. Nothing
about the shortage provision requires the Bureau to take actions to protect
the delta smelt. The provision is permissive, and merely absolves the
United States of liability if there is a water shortage resulting from, inter
alia, “actions taken ... to meet legal obligations.” But even if we read the
provision to place an affirmative obligation on the Bureau to take actions
to benefit the delta smelt, the provision only concerns the quantity of
water that will be made available to the DMC Contractors. There are
various other ways in which the Bureau could have contracted to benefit
the delta smelt, including, for example, revising the contracts’ pricing
scheme or changing the timing of water deliveries. Because adequate
consultation and renegotiation could lead to such revisions, Plaintiffs have
standing to assert a procedural challenge to the DMC Contracts.
12
13
14
15
16
17
18
19
Id. at 783-84.
20
With regard to the Settlement Contracts, the previously-assigned district judge held that,
21
although Plaintiffs have standing to assert procedural challenges to the Settlement Contracts, the Bureau
22
was not required to consult under Section 7(a)(2) prior to renewing the Settlement Contracts because the
23
Bureau’s discretion in renegotiating these contracts was “substantially constrained,” in light of a line of
24
cases, including Nat’l Ass’n of Home Builders v. Defenders of Wildlife, 551 U.S. 644, 669 (2007), which
25
11
1
stands for the proposition that there is no duty to consult for actions “that an agency is required by
2
statute to undertake.” Natural Res. Def. Council v. Kempthorne, 621 F. Supp. 2d 954, 1000 (E.D. Cal.
3
2009), decision clarified, 627 F. Supp. 2d 1212 (E.D. Cal. 2009), on reconsideration, No. 1:05-CV-1207
4
OWW SMS, 2009 WL 2424569 (E.D. Cal. Aug. 6, 2009). In holding that the Bureau was not required to
5
consult under Section 7(a)(2) prior to renewing the Settlement Contracts, the district court focused on
6
Article 9(a) of the original Settlement Contracts, which provides in pertinent part:
7
8
9
10
11
During the term of this contract and any renewal thereof it shall constitute
full agreement as between the United States and the Contractor as to the
quantities of water and the allocation thereof between base supply and
Project water which may be diverted by the Contractor from the
Sacramento River for beneficial use on the land shown on Exhibit B which
said diversion, use, and allocation shall not be disturbed so long as the
Contractor shall fulfill all of its obligations hereunder, and the Contractor
shall not claim any right against the United States in conflict with the
provisions hereof.
12 Id. at 979 (emphasis omitted). This provision, according to the district court, “substantially constrained”
13 the Bureau’s discretion to negotiate new terms in renewing the contracts, thereby absolving the Bureau
14 of the duty to consult under Home Builders. Id.
15
16
17
18
The Ninth Circuit rejected this reasoning:
Section 7(a)(2)’s consultation requirement applies with full force so long
as a federal agency retains “some discretion” to take action to benefit a
protected species. [citations] While the parties dispute whether Article 9(a)
actually limits the Bureau’s authority to renegotiate the Settlement
Contracts, it is clear that the provision does not strip the Bureau of all
discretion to benefit the delta smelt and its critical habitat. F
19
20
21
22
23
First, nothing in the original Settlement Contracts requires the Bureau to
renew the Settlement Contracts. Article 2 of the original contracts
provides that “renewals may be made for successive periods not to exceed
forty (40) years each.” (emphasis added). This language is permissive and
does not require the Bureau to execute renewal contracts. Since the FWS
has concluded that “Delta water diversions” are the most significant
“synergistic cause[ ]” of the decline in delta smelt, 58 Fed. Reg. at 12,859,
it is at least plausible that a decision not to renew the Settlement Contracts
could benefit the delta smelt and their critical habitat.
24
25
But even assuming, arguendo, that the Bureau is obligated to renew the
Settlement Contracts and that Article 9(a) limits the Bureau’s discretion in
12
so doing, Article 9(a) simply constrains future negotiations with regard to
“the quantities of water and the allocation thereof....” Nothing in the
provision deprives the Bureau of discretion to renegotiate contractual
terms that do not directly concern water quantity and allocation. And, as
[is the case] with respect to the DMC Contracts, the Bureau could benefit
the delta smelt by renegotiating the Settlement Contracts’ terms with
regard to, inter alia, their pricing scheme or the timing of water
distribution.
1
2
3
4
5
For these reasons, we conclude that, in renewing the Settlement Contracts,
the Bureau retained “some discretion” to act in a manner that would
benefit the delta smelt. The Bureau was therefore required to engage in
Section 7(a)(2) consultation prior to renewing the Settlement Contracts.
6
7
8
NRDC v. Jewell, 749 F.3d at 785. The matter was reversed and remanded for further proceedings. Id.
9
14.
Stay of this Case and Further FWS Consultation.
10
On June 15, 2015, the Court stayed this litigation to allow Reclamation to reinitiate ESA-
11 consultation on the contract renewals. Doc. 979. Thereafter, Reclamation requested FWS’s concurrence
12 that the impacts of these contract renewals on delta smelt were assessed in the 2008 FWS OCAP BiOp.
13 4AC ¶¶ 103, 105. FWS responded by sending the 2015 LOC, concluding that “all of the possible effects
14 to delta smelt and its critical habitat by operating the CVP to deliver water under the SRS and DMC
15 Contracts were addressed in the [2008 FWS OCAP Smelt BiOp].” Id. ¶ 106.
16
15.
17
Plaintiffs now seek leave to file the 4SC, which proposes to add three new claims. Doc. 999.
Proposed Supplemental Claims.
18 First, Plaintiffs seek to add a claim challenging the adequacy of FWS’s consultation on the effects of the
19 SRS and DMC Contract renewals on delta smelt. 4SC ¶¶ 177-182. Plaintiffs specifically allege it was
20 improper for FWS to rely in the 2015 LOC exclusively on the 2008 FWS OCAP Smelt BiOp to evaluate
21 impacts to delta smelt because: (1) the Ninth Circuit already held that the 2008 FWS OCAP Smelt BiOp
22 is insufficient for this purpose (4SC ¶ 133); (2) the 2008 FWS OCAP Smelt BiOp only addresses effects
23 of system operations through 2030, while the SRS Contract renewals do not expire until 2045 (4SC ¶
24 134); (3) the 2008 FWS OCAP Smelt BiOp did not include analysis of the effects of the specific terms
25 of the contract renewals (4SC ¶ 135); and (4) FWS assumed in the 2008 FWS OCAP Smelt BiOp that
13
1
species-protective flow requirements and export limits described therein would remain intact, an
2
assumption Plaintiffs now assert is “unreasonable” in light of repeated waivers of those requirements in
3
2014 and 2015” (4SC ¶ 137). In addition, Plaintiffs allege that the 2015 LOC (5) fails to reflect the best
4
scientific data available (4SC ¶¶ 138-143); (6) impermissibly relies on future consultations to ensure
5
adequate protection of delta smelt (4SC ¶ 145); and (7) assumes that “if increased outflows are needed”
6
to satisfy ESA requirements, Article 7(b) of the SRS Contracts allows Reclamation to take species-
7
protective measures that may limit the water available to the SRS Contractors, an assertion that is
8
directly contradicted by Reclamation’s own assertions that it has no discretion to “alter the quantities …
9
of SRS diversions” (4SC ¶ 146).
10
Plaintiffs’ proposed claim alleges that while Reclamation reinitiated consultation on the impact
11 of contract renewal on delta smelt, Reclamation did not request re-initiation of consultation with NMFS
12 on the impacts of SRS Contract renewals on the winter-run and spring-run Chinook. Plaintiffs seek to
13 add a claim to require Reclamation to reinitiate consultation on the impacts of the SRS Contract
14 renewals on winter-run and spring-run Chinook and their critical habitats. 4SC ¶¶ 183-188 (Fifth Claim
15 for Relief).
16
Third, Plaintiffs seek to add a related claim that Reclamation and the SRS Contractors illegally
17 caused the direct loss (or “take”) of winter-run and spring-run Chinook during 2014 and 2015 because
18 Reclamation made excessive deliveries to the SRS Contractors that depleted the cold water reserves in
19 Shasta Reservoir, causing temperature increases fatal to the 2014 and 2015 “brood years” of winter-run
20 and spring-run Chinook. 4SC ¶¶ 189-193 (Sixth Claim for Relief).
21
IV. DISCUSSION
22 A.
General Standard Applicable to Requests for Leave to Amend.
23
Federal Rule of Civil Procedure 15(d) allows supplemental pleadings to add claims regarding
24 any transaction, occurrence, or event that happened after the date of the pleading to be supplemented.
25 The Ninth Circuit has entrusted application of this rule to the district court’s broad discretion:
14
1
2
Rule 15(d) is intended to give district courts broad discretion in allowing
supplemental pleadings. The rule is a tool of judicial economy and
convenience. Its use is therefore favored. As Judge Haynsworth observed
more than two decades ago:
3
4
5
6
7
8
9
10
Rule 15(d) of the Federal Rules of Civil Procedure provides for ...
supplemental pleading. It is a useful device, enabling a court to
award complete relief, or more nearly complete relief, in one
action, and to avoid the cost, delay and waste of separate actions
which must be separately tried and prosecuted. So useful they are
and of such service in the efficient administration of justice that
they ought to be allowed as of course, unless some particular
reason for disallowing them appears, though the court has the
unquestioned right to impose terms upon their allowance when
fairness appears to require them.
....The clear weight of authority, however, in both the cases and the
commentary, permits the bringing of new claims in a supplemental
complaint to promote the economical and speedy disposition of the
controversy....
11
Keith v. Volpe, 858 F.2d 467, 473 (9th Cir. 1988) (internal citations omitted).
12
13
Generally, although supplemental pleading is “favored” in certain circumstances, it cannot be
used to introduce “separate, distinct and new causes of action.” Planned Parenthood of S. Arizona v.
14
Neely, 130 F.3d 400, 402 (9th Cir. 1997). Supplementation should be permitted where doing so would
15
16
17
18
serve Rule 15(d)’s goal of judicial efficiency, and a court should assess whether an entire controversy
can be settled in one action. Id. “To determine if efficiency might be achieved, courts assess ‘whether
the entire controversy between the parties could be settled in one action....’” Id. (citation omitted).
“While the matters stated in a supplemental complaint should have some relation to the claim set forth in
19
the original pleading, the fact that the supplemental pleading technically states a new cause of action
20
should not be a bar to its allowance, but only a factor to be considered by the court in the exercise of its
21
discretion, along with such factors as possible prejudice or laches.” Keith, 858 F.2d at 474.
22
Courts also commonly apply the five factors used to evaluate Fed. R. Civ. P. 15(a) motions to
23
amend to Rule 15(d) motions to supplement, which are: (1) undue delay, (2) bad faith or dilatory motive
24
on the part of the movant, (3) repeated failure of previous amendments, (4) undue prejudice to the
25
15
1
opposing party, and (5) futility of the amendment. Lyon v. U.S. Immigration & Customs Enf't, 308
2
F.R.D. 203, 214 (N.D. Cal. 2015) (citing Foman v. Davis, 371 U.S. 178, 182 (1962)); see also Oregon
3
Nat. Desert Ass'n v. McDaniel, 282 F.R.D. 533, 537 (D. Or. 2012). Of these factors, “consideration of
4
prejudice to the opposing party . . . carries the greatest weight.” Eminence Capital, LLC v. Aspeon, Inc.,
5
316 F.3d 1048, 1052 (9th Cir. 2003).
6
B.
Proposed Fourth Claim for Relief Regarding Sufficiency of FWS’s Reconsultation and
2015 LOC.
7
As mentioned, Plaintiffs seek to add a Fourth Claim for Relief challenging the sufficiency of
8
FWS’s re-consultation, which resulted in the issuance of the 2015 LOC. No party objects to
9
supplementation with this claim, which is a natural extension of the existing litigation, nor does any
10
party suggest that this claim would be futile. The Court concludes that supplementation with the Fourth
11
Cause of Action would serve the interests of judicial efficiency, because it would permit adjudication of
12
closely related claims in one case. Therefore, the request to supplement the Complaint with the Fourth
13
Cause of Action is GRANTED.5
14
C.
15
Proposed Fifth Claim for Relief Regarding NMFS’s Failure to Re-Initiate Consultation
Regarding SRS Contract Renewals and Proposed Sixth Claim for Relief Regarding Alleged
Take Stemming from SRS Contract Deliveries.
16
1.
Overview of Claims.
17
Plaintiffs’ Proposed Fifth Claim for Relief alleges that Reclamation unlawfully failed to request
18
re-initiation of consultation with NMFS on the impacts of SRS Contract renewals on the winter-run and
19
spring-run Chinook (“spring-run Chinook”). 4SC ¶¶ 183-188. Specifically, Plaintiffs allege that the
20
2009 NMFS OCAP Smelt BiOp constituted new information that revealed effects of the SRS Contracts
21
that NMFS did not consider in consultation over the contracts. Id. ¶ 186. Plaintiffs also allege that
22
23
24
25
5
The CVP Water Service Contractors argue that the Complaint should be revised because it includes allegations regarding
already resolved claims, pointing specifically to paragraphs 5-10, 11, 52, 80-86, 164-70, 173, 174. See Doc. 1008 at 10 & n.7.
The CVP Water Service Contractors have not identified any authority requiring Plaintiffs do so, and the Court does not
necessarily agree that revision will help to clarify the record moving forward. To the extent claims have been resolved, the
relevant allegations continue to serve as background information regarding the procedural and substantive history of the case.
16
1
massive mortality episodes impacting the 2014 and 2015 generations of winter-run and spring-run
2
Chinook constituted independent new information that should have triggered re-consultation. Id. ¶ 187.
3
Plaintiffs’ Proposed Sixth Claim for relief alleges Reclamation and the SRS Contractors illegally
4
caused the take of winter-run and spring-run Chinook during 2014 and 2015 because Reclamation made
5
excessive deliveries to the SRS Contractors that depleted the cold water reserves in Shasta Reservoir,
6
causing temperature increases fatal to the 2014 and 2015 “brood years” of winter-run and spring-run
7
Chinook. 4SC ¶¶ 189-193.
8
2.
Futility of Supplementation.
9
Leave to supplement may be denied if supplementation would be futile. San Luis & Delta-
10 Mendota Water Auth. v. U.S. Dep't of Interior, 236 F.R.D. 491, 500 (E.D. Cal. 2006). Because futility
11 can operate as a threshold bar to supplementation, the Court will address the parties’ futility arguments
12 first.
13
14
a.
Legal Standard.
A proposed claim may be deemed futile if it would fail to state a claim under Federal Rule of
15 Civil Procedure 12(b)(6). See Miller v. Rykoff–Sexton, Inc., 845 F.2d 209, 214 (9th Cir. 1988). A motion
16 to dismiss pursuant to Rule 12(b)(6) is a challenge to the sufficiency of the allegations set forth in the
17 complaint. A 12(b)(6) dismissal is proper where there is either a “lack of a cognizable legal theory” or
18 “the absence of sufficient facts alleged under a cognizable legal theory.” Balisteri v. Pacifica Police
19 Dept., 901 F.2d 696, 699 (9th Cir. 1990). In considering a motion to dismiss for failure to state a claim,
20 the court generally accepts as true the allegations in the complaint, construes the pleading in the light
21 most favorable to the party opposing the motion, and resolves all doubts in the pleader’s favor. Lazy Y.
22 Ranch LTD v. Behrens, 546 F.3d 580, 588 (9th Cir. 2008). To survive a 12(b)(6) motion to dismiss, the
23 plaintiff must allege “enough facts to state a claim to relief that is plausible on its face.” Bell Atl. Corp.
24 v. Twombly, 550 U.S. 544, 570 (2007). “A claim has facial plausibility when the plaintiff pleads factual
25 content that allows the court to draw the reasonable inference that the defendant is liable for the
17
1
misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009).
b.
2
Res Judicata.
Federal Defendants argue that the two new salmonid claims (Fifth and Sixth Claims for Relief)
3
4
are barred by res judicata. Doc. 1007 at 16-176. “The doctrine of res judicata provides that a final
5
judgment on the merits bars further claims by parties or their privies based on the same cause of action.”
6
In re Schimmels, 127 F.3d 875, 881 (9th Cir. 1997) (citation and quotation marks omitted). The doctrine
7
includes
two distinct types of preclusion, claim preclusion and issue preclusion.
Claim preclusion treats a judgment, once rendered, as full measure of
relief to be accorded between the same parties on the same “claim” or
“cause of action”.... The doctrine of issue preclusion prevents relitigation
of all issues of fact or law that were actually litigated and necessarily
decided in a prior proceeding.
8
9
10
11
Robi v. Five Platters, Inc., 838 F.2d 318, 321-22 (9th Cir. 1988) (footnote, quotation marks, and
12
citations omitted). Res judicata “bars relitigation of all grounds of recovery that were asserted, or could
13
have been asserted, in a previous action between the parties, where the previous action was resolved on
14
the merits.” Tahoe–Sierra Pres. Council v. Tahoe Reg'l Planning Agency, 322 F.3d 1064, 1078 (9th Cir.
15
2003) (citation omitted).
16
“The elements necessary to establish res judicata are: ‘(1) an identity of claims, (2) a final
17
judgment on the merits, and (3) privity between the parties.” Headwaters, Inc. v. U.S. Forest Serv., 399
18
F.3d 1047, 1052 (9th Cir. 2005) (internal quotation and citation omitted). To determine whether an
19
identity of claims exists, a court should assess:
20
(1) whether rights or interests established in the prior judgment would be
destroyed or impaired by prosecution of the second action;
(2) whether substantially the same evidence is presented in the two
actions;
(3) whether the two suits involve infringement of the same right; and
(4) whether the two suits arise out of the same transactional nucleus of
21
22
23
24
25
6
Internal page references to documents in the electronic case file (“ECF”) are to the page numbering provided in the ECF file
stamp header in the upper right corner of each document.
18
1
2
3
facts.
Costantini v. Trans World Airlines, 681 F.2d 1199, 1201-02 (9th Cir. 1982).
The crux of the res judicata analysis here is whether there is an “identity of claims.” Federal
4
Defendants argue that the relevant “transactional nucleus of facts” delineating the claims that could have
5
been brought in PCFFA encompasses all challenges to the 2004 NMFS OCAP Salmonid BiOp,
6
Reclamation’s reliance on it in its ESA consultation with NMFS over the Contracts, and Reclamation’s
7
subsequent execution of the renewed Contracts following ESA consultations with NMFS on the effects
8
of the renewal. See Doc. 1007 at 17.
9
Plaintiffs do not appear to dispute this, but instead point out, correctly, that where the
10 “governmental conduct” is different in the second action, there is no claim preclusion. Cent. Delta Water
11 Agency v. United States, 306 F.3d 938, 952 (9th Cir. 2002) (citing Fund for Animals, Inc. v. Lujan, 962
12 F.2d 1391, 1399 (9th Cir. 1992), for the proposition that res judicata does not bar a subsequent challenge
13 to separate “governmental conduct”).
14
The central “governmental conduct” that gave rise to the PCFFA litigation was the issuance of
15 the 2004 NMFS Salmonid BiOp. Encompassed within the scope of the PCFFA lawsuit was a challenge
16 to Reclamation’s execution of the renewal Contracts based upon the 2004 NMFS Salmonid BiOp. See
17 PCFFA FAC ¶¶ 2, 49, 74, 112. However, the proposed Fifth and Sixth Causes of action arise from
18 separate “governmental conduct,” namely, the failure to re-initiate consultation and the continued
19 delivery of water to SRS Contractors despite alleged take of listed salmonids. The proposed claims are
20 distinct from any that were or could have been brought as part of PCFFA. See Doc. 1013 at 14.
21 Therefore, the Fifth and Sixth Claims for Relief are not barred by res judicata.
22
23
c.
Statute of Limitations.
The Fifth Claim for Relief in this case alleges “the Bureau arbitrarily and capriciously violated,
24 and continues to violate, Section 7(a)(2) of the ESA and the ESA’s implementing regulations, 50 U.S.C.
25 § 402.16, by failing to reinitiate consultation on the SRS Contracts based on the issuance of the [2009]
19
1
NMFS OCAP [Salmonid] BiOp and subsequent amendments.” 4SC ¶ 186.
Claims arising under the Administrative Procedure Act (“APA”) or the ESA are subject to a six-
2
3
year statute of limitations. See Wind River Mining Corp. v. United States, 946 F.2d 710, 714-15 (9th Cir.
4
1991); Coal. for a Sustainable Delta v. Fed. Emergency Mgmt. Agency, 812 F. Supp. 2d 1089, 1106
5
(E.D. Cal. 2011). The SRS Contractors argue that the six-year statute of limitations bars Plaintiffs’ claim
6
that NMFS was required to reinitiate consultation upon the issuance of the 2009 NMFS OCAP Salmonid
7
BiOp because that document was adopted more than six years ago. Doc. 1009 at 11.
Plaintiffs skirt this argument by pointing out that the statute of limitations “does not bar a
8
9
challenge to an ‘ongoing agency action,’ such as the SRS Contracts.”7 Doc. 1013 at 17. But, the SRS
10 Contractors do not appear to be challenging the entirety of the Fifth Claim for Relief, but rather only
8
11 whether the issuance of the 2009 NMFS OCAP Salmonid BiOp can be considered a “triggering event”
12 that would require re-initiation of consultation. Plaintiffs suggest that “subsequent amendments to and
13 implementation of the [2009 NMFS OCAP Salmonid BiOp] certainly triggered Reclamation’s duty to
14 reinitiate.” Doc. 1013 at 14 (citing 4SC ¶113). Whether and to what extent Reclamation’s
15 implementation of the 2009 NMFS OCAP Salmonid BiOp constitutes an “ongoing agency action” for
16 statute of limitations purposes, and/or whether several more recent actions constitute “amendments” to
17 the 2009 NMFS OCAP Salmonid BiOp are beyond the scope of the present motion. See Coal. for a
18 Sustainable Delta v. Fed. Emergency Mgmt. Agency, 812 F. Supp. 2d 1089, 1107-23 (E.D. Cal. 2011)
19 (reviewing complex state of relevant caselaw on “ongoing agency action” doctrine). What the Court can
20 state definitively is that the 4SC alleges sufficiently that temperature control events in 2014 and 2015
21 triggered the requirement for re-initiation. See 4SC ¶¶ 113, 192. Therefore, the Sixth Claim for Relief is
22 not barred in any general sense by the statute of limitations. Further refinement of the scope of that
23
7
Plaintiffs’ appear to reference as an “ongoing action” ongoing deliveries pursuant to the SRS Contracts, not execution of
24 those Contracts. See 4SC ¶¶ 150-53.
8
25
A federal agency must reinitiate consultation when it retains “Federal involvement or control over the action,” and one of
several triggering events occurs including that “new information reveals effects of the action that may affect listed species or
critical habitat in a manner or to an extent not previously considered.” 50 C.F.R. § 402.16(b).
20
1
claim must wait for another day.
2
d.
Mootness
3
The SRS Contractors and Federal Defendants argue that Plaintiffs’ claims that NMFS was
4
required to re-initiate consultation based upon 2014 and 2015 temperature control events are moot
5
because Reclamation has already reinitiated consultation regarding 2014/2015 drought operations. Doc.
6
1007 at 21-22; Doc. 1009 at 11. The consultation letter cited by Federal Defendants, see Doc. 1007 at 21
7
n. 15, explains that it was issued in response to Reclamation’s request for NMFS’s concurrence that the
8
biological effects of implementing “drought operations” (i.e., modifications to normal operations
9
required because of unprecedented drought conditions) would be “within the limits of the existing
10 Incidental Take Statement” issued in connection with the 2009 NMFS OCAP Salmonid BiOp. Id.
11 Plaintiffs are correct that this consultation document does not address the SRS Contracts specifically. As
12 the Ninth Circuit has made abundantly clear, system-wide consultation (such as consultation over the
13 OCAP that produced the 2009 NMFS OCAP Salmonid BiOp) does not obviate the need for contract14 specific consultation. See NRDC v. Jewell, 749 F.3d at 784. This logic would also seem to mean that
15 system-wide re-consultation does not obviate the need for contract-specific re-consultation.
16
Relatedly, the SRS Contractors also argue that the 2009 NMFS Samonid BiOp considered the
17 effects of full diversions under the SRS Contracts and therefore that re-consultation is not warranted.
18 Doc. 1009 at 11. Again, this reasoning was rejected in NRDC v. Jewell, 749 F.3d 782 (explaining that
19 the 2008 FWS OCAP Smelt BiOp “merely assesses the general effects of the Bureau’s [OCAP] Plan,
20 and it does not represent a consultation with the FWS concerning the impact of the Bureau's decision to
21 renew the specific contracts” challenged).
22
23
e.
Section 9 Claim Based on Purely Past Violations.
Federal Defendants also argue that the Sixth Claim for Relief, alleging take in violation of ESA
24 § 9, is futile because it is based purely on allegations of past violations. Doc. 1007 at 20-21. In support
25 of this proposition, Federal Defendants cite the text of the ESA’s citizen suit provision, 16 U.S.C. §
21
1
1538, and Gwaltney of Smithfield Ltd. v. Chesapeak Bay Found., 484 U.S. 49, 50-60 (1987) (interpreting
2
identical language in Clean Water Act (“CWA”) citizen suit provision as conferring no jurisdiction over
3
citizen suits for wholly past violations). See also Fox v. Palmas Del Mar Properties, Inc., 620 F. Supp.
4
2d 250, 262-63 (D.P.R. 2009) (concluding plaintiffs lack standing to bring Section 9 claim because
5
plaintiffs consistently referenced construction project alleged to pose harm to species in the past tense
6
and failed to allege plausibly that construction was ongoing or imminent); Forest Conservation Council
7
v. Rosboro Lumber Co., 50 F.3d 781, 787 (9th Cir. 1995) (citing Gwaltney in ESA case for the
8
proposition that “the interest of the citizen-plaintiff is primarily forward-looking”).
Plaintiffs assert in reply that because the contracts in question do not expire until 2045, the
9
10 resultant take of salmon “is not wholly past” insofar as “[d]eliveries and diversions that may cause take
11 will occur again this year and every year the contracts are in effect.” Doc. 1013 at 15 n. 10. The 4SC
12 makes this clear in Prayer “J,” which asks the Court to “[e]njoin the Secretary from continuing to make
13 releases of water from Shasta Reservoir, and the SRS Contractors from diverting such water, to satisfy
14 the terms of the SRS Contracts where such releases and diversions will cause the unauthorized take of
15 winter-run and spring-run Chinook.” 4SC at 66-67. Therefore, the Court concludes that, even if the
16 ESA’s citizen suit provision precludes claims based upon purely past violations, the Sixth Claim for
17 Relief is “forward looking” and therefore not futile.
18
3.
Judicial Estoppel
19
The CVP Water Service Contractors argue that Plaintiffs should be estopped from arguing that
20 supplementation with these new claims should be permitted because they previously argued against
21 combining the delta smelt and salmon claims. Doc. 1008 at 5-6. Specifically, in response to a motion to
22 consolidate Plaintiffs’ initial challenge to the 2005 FWS Smelt BiOp with their parallel challenges to the
23 2004 NMFS Salmonid BiOp, Plaintiffs argued against consolidation for the following reasons, among
24 others:
25
The claims “arise from separate agency actions involving separate factual records, are at very
22
1
different stages of litigation, and concern the effects of different water project operations on
2
entirely distinct species that have different biological needs and are under the protection of
3
separate agencies.” Doc. 278 at 1.
4
“Any facial similarity in the legal claims made in each case must yield to the vastly different
5
facts needed to prove the inadequacy of the biological opinion for delta smelt versus that for the
6
salmonid species.” Doc. 278 at 9.
7
“[J]udicial estoppel is an equitable doctrine invoked by a court at its discretion.” New Hampshire
8
v. Maine, 532 U.S. 742, 750 (2001) (internal quotation marks omitted). “[I]ts purpose is to protect the
9
integrity of the judicial process by prohibiting parties from deliberately changing positions according to
10 the exigencies of the moment.” Id. at 749-50 (citation and internal quotation marks omitted). As the
11 Ninth Circuit recently summarized:
12
13
14
15
16
17
18
19
Although judicial estoppel is “probably not reducible to any general
formulation of principle, ... several factors typically inform the decision
whether to apply the doctrine in a particular case.” [New Hampshire, 532
U.S.] at 750 (citations and internal quotation marks omitted). “First, a
party's later position must be ‘clearly inconsistent’ with its earlier
position.” Id. “Second, courts regularly inquire whether the party has
succeeded in persuading a court to accept that party's earlier position, so
that judicial acceptance of an inconsistent position in a later proceeding
would create the perception that either the first or the second court was
misled.” Id. (internal quotation marks omitted). “A third consideration is
whether the party seeking to assert an inconsistent position would derive
an unfair advantage or impose an unfair detriment on the opposing party if
not estopped.” Id. at 751. “In enumerating these factors, we do not
establish inflexible prerequisites or an exhaustive formula for determining
the applicability of judicial estoppel. Additional considerations may
inform the doctrine's application in specific factual contexts.” Id.
20
Ah Quin v. Cty. of Kauai Dep't of Transp., 733 F.3d 267, 270-71 (9th Cir. 2013) (emphasis added).
21
Here, the Court does not believe that Plaintiffs’ present position is “clearly inconsistent” with the
22
position they took in connection with the prior motion to consolidate. In the context of the previous
23
motion to sever, the parties and the previously-assigned district judge were faced with the prospect of
24
highly complex, direct challenges to two, separate biological opinions, including numerous arguments
25
23
1
that those biological opinions were not based upon the best available science.
2
The present motion to supplement presents a different procedural situation. First, the salmonid
3
claims sought to be added to this smelt case by supplementation are more narrowly focused than those
4
discussed in the previous motion to consolidate. Second, as discussed below, the proposed salmonid
5
claims share common legal issues with the remaining smelt claims, a situation that was at least not
6
entirely apparent in the prior motion. In addition, over the course of the two parallel smelt and salmonid
7
litigations, it has become clear that actions taken to protect the smelt may actually harm salmonids and
8
vice versa, presenting a risk of inconsistent rulings if claims regarding the two sets of species are not
9
treated together. Because Plaintiffs’ present position is not clearly inconsistent with its prior position,
10 judicial estoppel does not apply.
11
4.
Prejudice to Non-Moving Party.
12
As mentioned, “consideration of prejudice to the opposing party . . . carries the greatest weight”
13 in evaluating a motion to supplement or amend. See Eminence Capital, 316 F.3d at 1052. “While
14 prejudice to the non-movant is a valid reason for denying leave to amend, such prejudice must in fact be
15 ‘undue.’” Dove v. Wash. Metro. Area Transit Auth., 221 F.R.D. 246, 248 (D.D.C. 2004). “Undue
16 prejudice is not mere harm to the non-movant but a denial of the opportunity to present facts or evidence
17 which would have been offered had amendment been timely.” Id.
18
Federal Defendants claim that they will suffer undue prejudice if they are forced to defend
19 against claims that concern listed salmonids in a case that originally concerned only smelt. See Doc.
20 1007 at 22. In support of this assertion, they cite Sierra Club v. Penfold, 857 F.2d 1307, 1316 (9th Cir.
21 1988), for the proposition that adding a “new claim for relief” was sufficient to cause prejudice to the
22 opposing party. But, that case evaluated prejudice in the context of the Sierra Club’s argument that a
23 particular claim (otherwise barred by the statute of limitations) should relate back under Fed. R. Civ. P.
24 15(c) to the original complaint. Id. at 1315-16. In that context, the opposing party is not prejudiced by
25 relation back where the new claim arises out of the same facts as the original claim because the opposing
24
1
party would already have notice of the nature of the action. See id. This reasoning is not applicable
2
outside the context of the relation back procedure.
The CVP Water Service Contractors assert that supplementation with the new salmonid claims
3
4
would prejudice them because it would “further delay[] final resolution of the only remaining claim
5
against them regarding water service contracts they signed over 10 years ago and which have 25-year
6
terms.” Doc. 1008 at 3. They complain that the “lingering legal uncertainty” caused by this litigation
7
hinders long-term planning by the DMC Unit Contractors and their constituent water users for things
8
such as capital improvements and investments to infrastructure or farms. Doc. 1008 at 8. The Court
9
takes this concern seriously, but does not believe that denying the motion to supplement is likely to
10 shorten the period of legal uncertainty in any significant sense. Until the fate of the long-term contracts
11 held by senior rights holders (e.g., the SRS Contractors) is settled, it is unclear how any legal uncertainty
9
12 plaguing long-term contracts held by the DMC Unit Contractors can be resolved.
13
5.
Undue Delay.
14
Federal Defendants argue Plaintiffs unduly delayed requesting leave to file their supplemental
15 claims. Doc. 1007 at 18-20. Undue delay has been described as “delay that prejudices the nonmoving
16 party or imposes unwarranted burdens on the Court.” Davis v. Powell, 901 F. Supp. 2d 1196, 1212 (S.D.
17 Cal. 2012) (citation and quotation marks omitted). In evaluating an assertion of undue, a court may
18 inquire “whether the moving party knew or should have known the facts and theories raised by the
19 amendment in the original pleading.” AmerisourceBergen Corp. v. Dialysist W., Inc., 465 F.3d 946, 953
20 (9th Cir. 2006) (citation and quotation marks omitted).
The Fifth Claim for Relief alleges that the obligation to re-initiate consultation was triggered by,
21
22 among other things, the issuance of the 2009 NMFS OCAP Salmonid BiOp. See 4SC ¶ 186 (“The
23 [2009] NMFS OCAP [Salmonid] BiOp constituted new information that undermined the January 10,
24
25
9
The CVP Water Service Contractors also argue prejudice would result from addition of new plaintiffs, but fail to explain
why. Doc. 1008 at 8.
25
1
2005 letters of concurrence and revealed effects of the SRS Contracts that were not previously
2
considered.”). As discussed above, it is not clear whether this aspect of the Fifth Claim for Relief will
3
survive a dispositive motion on statute of limitations grounds. Critically, however, there are aspects of
4
this claim that arose more recently, including the allegation that the 2009 NMFS OCAP Salmonid BiOp
5
was amended in 2011, 2014 and 2015, id. ¶113, and the separate allegation that Federal Defendants
6
acted unlawfully “by failing to reinitiate consultation based on information relating to the massive
7
mortality to the 2014 and 2015 generations of winter-run and spring-run Chinook that occurred when it
8
made excessive releases to satisfy the renewed SRS Contracts.” Id. ¶ 187. Federal Defendants suggest
9
that that these events should be viewed as “additional chances, going back years,” at which points
10
10 Plaintiffs could have filed their claims. Doc. 1007 at 19.
Plaintiffs counter by asserting that they are bringing their claims now because of the mortality
11
12 events that took place in 2014 and 2015. See Doc. 1013 at 12. After the 2015 mortality event, Plaintiffs
13 filed motions to lift the stay and for leave to supplement the complaint, Doc. 981, which were held in
14 abeyance pursuant to the stipulation of all parties. Doc. 990.
On balance, the Court concludes Federal Defendants have not established any “undue” delay.
15
16 Several relatively recent events underpin the salmonid claims. The scope of those claims is more
17 properly determined in the context of a dispositive motion.
18
6.
Judicial Efficiency.
19
The Court is mindful that Fed. R. Civ. P. 15(d) is, at its core, “a tool of judicial economy and
20 convenience,” the use of which “is therefore favored.” Keith v. Volpe, 858 F.2d at 473. The interests of
21
10
22
23
24
Relatedly, Federal Defendants argue they will be prejudiced if they have to compile an administrative record addressing
decisions that are not “reasonably close in time.” Doc. 1007 at 23. Federal Defendants suggest this process will be made
more difficult because some relevant material may have been archived and staff members may have left. Id. While Federal
Defendants’ practical concern is valid, denying Plaintiffs’ motion to amend would not preclude Plaintiffs from filing a
separate action to prosecute the proposed salmonid claims. In either circumstance, the scope of the proposed claim may be
subject to narrowing on various grounds (e.g., statute of limitations). This motion really raises the question of how the
various claims should be organized – as one case or in several. Therefore, the Court does not find Federal Defendants’
argument persuasive.
25
26
1
judicial economy and convenience are served where “the plaintiffs’ motion to supplement their
2
complaint raises similar legal issues to those already before the court, thereby averting a separate,
3
redundant lawsuit.” Fund For Animals v. Hall, 246 F.R.D. 53, 55 (D.D.C. 2007). As all parties are well
4
aware, if Plaintiffs’ motion to supplement is denied, any separate lawsuit based upon the additional
5
claims is likely to end up litigated before the undersigned as a related case. See Local Rule 123. It is
6
through this lens that the Court evaluates the judicial efficiency impacts of supplementation.
7
The Fifth and Sixth Claims for relief will bring into the smelt case issues pertaining to salmonid
8
species and the salmonid consultation history. This will undoubtedly complicate the case. However,
9
again, the question is not whether the Court will ever have to tackle both sets of issues; rather, the
10 question is whether merging the sets of issues into one case will serve the interests of judicial efficiency.
11 There are significant overlapping legal issues among the existing and proposed supplemental claims. For
12 example, a major legal issue in all of the claims concerning the SRS Contracts (both smelt and salmonid
13 claims) is likely to be the extent, nature, and implications of any discretion Reclamation may have to
14 reduce deliveries to the SRS Contractors. Permitting supplementation will allow for more efficient
15 adjudication of claims that turn on this issue. There are also common legal issues that link the smelt
16 claims concerning the DMC Contracts to the salmonid claims, namely, whether and to what extent FWS
17 and NMFS can rely on the 2008 FWS OCAP Smelt BiOp and 2009 NMFS OCAP Salmonid BiOp,
18 respectively, to satisfy their obligations to consult about the long-term contracts. There are linkages
19 between the smelt and salmon facts as well. For example, it is alleged that in both 2014 and 2015,
20 Reclamation sought and received approval to decrease Delta flow requirements designed to protect delta
21 smelt in order to increase Shasta Reservoir reserves to satisfy the SRS Contracts in the dry months and
22 to increase cold-water reserves to manage temperatures for salmonids in the summer. 4SC ¶¶ 57-59.
23
This case is unlike Neely, 140 F.3d at 401, where supplementation was not permitted. In Neely,
24 the plaintiffs sought to enjoin a state statute requiring parental consent prior to an abortion. Id. The
25 district court entered a final order granting that relief. Id. at 402. Plaintiffs later sought to supplement
27
1
their complaint to challenge a new consent statute. Id. The Ninth Circuit did not permit supplementation,
2
concluding that the supplemental complaint constituted a “separate, distinct and new cause of action”
3
that should be filed separately because it (1) challenged a different statute, (2) final judgment had been
4
entered in the original action, and (3) the district court did not retain jurisdiction. Id. Here, the Court has
5
yet to reach the merits of Plaintiffs’ challenge to the DMC and SRS Contracts based upon failure to
6
consult over impacts to the delta smelt and the Court has not relinquished jurisdiction.
7
In contrast, in Keith, 858 F.2d at 471, the plaintiffs originally filed suit in 1972, alleging that, in
8
planning a freeway construction project, defendants failed to comply with environmental laws and other
9
federal statutes addressing transit impacts to communities. In 1981, the parties signed a consent decree
10 that included commitments to build low-income housing. Id. In 1985, new plaintiffs joined several
11 original plaintiffs to add supplemental claims against new municipal defendants for denying housing
12 permits. Id. at 471-72. The supplemental claim proposed to add numerous, entirely new claims,
13 including constitutional claims and allegations that defendants violated federal and state statutes.
14 Compare id. with Keith v. Volpe, 352 F. Supp. 1324, 1382-29 (C.D. Cal. 1972). The Ninth Circuit
15 rejected defendants’ arguments against supplementation, explaining that “some relationship” existed
16 between the newly alleged matters and the subject of the original action.” Keith, 858 F.2d at at 474.
17 Here, for the reasons discussed above, the Court finds there is “some relationship” between the salmonid
18 claims and the smelt claims.
19
The new salmonid claims will require the preparation of an additional administrative record
20 covering the consultation history vis-à-vis the SRS Contracts and salmonid impacts. Federal Defendants
21 cite Center for Food Safety v. Vilsack, No. C-10-04038-JSW, 2011 WL 672802, at *3 (N.D. Cal. Feb.
22 18, 2011), for the proposition that a supplemental pleading that requires preparation of a new
23 administrative record should be deemed to constitute a “separate, distinct, and new cause of action”
24 warranting denial of a motion to supplement. In Vilsack, plaintiffs originally challenged a decision by
25 the U.S. Department of Agriculture’s Animal and Plant Health Inspection Service (“APHIS”) to issue
28
1
permits for the use of “Roundup Ready” Sugar Beets without conducting environmental review under
2
the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-4335, and other statutes. Id. at *1.
3
The district court granted plaintiffs’ request for a preliminary injunction in November 2010. Id. In
4
February 2011, APHIS completed and released relevant NEPA environmental review documents. Id.
5
Plaintiffs proposed to amend the complaint to add allegations regarding the new NEPA documents. Id.
6
The district court denied the request, mentioning that the new claims would need a “separate
7
administrative record,” which suggested that the claim “should be the subject of a separate action.” Id. at
8
*3. But, the district court was still “[m]indful that Rule 15(d) ‘permits the bringing of new claims in a
9
supplemental complaint to promote the economical and speedy disposition of the controversy.’” Id. at *4
10 (quoting Keith, 858 F.2d at 473). What ultimately drove the district court’s decision to deny amendment
11 was the fact that the February 2011 NEPA documents were already the subject of a lawsuit in the
12 District Court for the District of Columbia, such that the interest of judicial economy would be better
13 served by presenting plaintiffs’ new claims in that court. Id.
The unique circumstances in Vilsack are not present here, so the Court does not find Vilsack to
14
15 be helpful. While it is true that having multiple administrative records in one case will complicate record
16 review, this Court is prepared to handle a complex record and has handled cases (some related to this
11
17 one) in which multiple records have been submitted by different agencies agencies.
Of more concern to the Court is the addition of the Sixth Claim for Relief, arising under ESA §
18
19 9, which may require an entirely separate discovery procedure. See Oregon Nat. Desert Ass'n v. Kimbell,
20 593 F. Supp. 2d 1217, 1220 (D. Or. 2009) (“[T]he scope of judicial review in a claim brought under the
21 ESA [§ 9] may not be subject to APA limitations.”); see also Aransas Project v. Shaw, 775 F.3d 641,
22 653-63 (5th Cir. 2014) (reviewing bench trial ruling addressing ESA § 9 take claim). It is unclear at this
23 stage of the case what types of extra-record evidence and/or discovery will be appropriate in this case. It
24
25
11
The new claims will require bringing in at least one new defendant: NMFS. Yet, any negative impact to judicial efficiency
of that addition is likely to be relatively minor.
29
1
is also unclear how long it will take to develop any extra record evidence and/or whether such
2
development should be delayed until after the preparation of the administrative record(s). Moreover, the
3
Court cannot determine at this time whether there are dispositive issues that can be placed before the
4
Court for decision while extra record evidence is being developed. All of these issues are best dealt with
5
during the scheduling process. In this and related cases, the parties have worked well together to come
6
up with litigation schedules that allow merits issues to be placed before the Court on a staggered basis. If
7
the Sixth Claim for relief proves to be unwieldy or threatens to delay significantly merits decisions on
8
other issues, ruling on that claim can be delayed relative to other merits issues or, if that proves
9
impracticable, a motion to sever will be entertained by the Court.
10
Overall, the Court believes that the interests of judicial efficiency will be served by allowing
11 supplementation.
V. CONCLUSION
12
13
Overall, the Court concludes that the claims sought to be added by way of supplementation are
14 not futile and are not barred by judicial estoppel. The Court further concludes that no party will be
15 prejudiced and that, as a whole, Plaintiffs did not unduly delay bringing these claims. Finally, the Court
16 finds that the interests of judicial efficiency will be served by allowing supplementation. Should
17 unexpected difficulties render continued treatment of these new salmonid claims within the smelt case
18 unwieldy, appropriate adjustments can be made.
19
20 IT IS SO ORDERED.
21
Dated:
/s/ Lawrence J. O’Neill
April 22, 2016
UNITED STATES DISTRICT JUDGE
22
23
24
25
30
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?