Natural Resources Defense Council et al v. Norton et al
Filing
1069
MEMORANDUM DECISION AND ORDER RE MOTIONS TO DISMISS signed by Chief Judge Lawrence J. O'Neill on February 23, 2017. (Docs. 1029, 1030, 1031, 1032, 1036). (Munoz, I)
1
2
3
4
5
6
UNITED STATES DISTRICT COURT
7
FOR THE EASTERN DISTRICT OF CALIFORNIA
8
9
NATURAL RESOURCES DEFENSE
COUNCIL, et al.,
10
Case No. 1:05-cv-01207 LJO-EPG
MEMORANDUM DECISION AND
ORDER RE MOTIONS TO DISMISS
(Docs. 1029, 1030, 1031, 1032, 1036).
Plaintiffs,
11 vs.
12 GAIL A. NORTON, Secretary, U.S. Department
of the Interior, et al.,
13
Defendants.
14
15
SAN LUIS & DELTA MENDOTA WATER
AUTHORITY, et al.,
Defendant-Intervenors.
16 ANDERSON-COTTONWOOD IRRIGATION
DISTRICT, et al.,
17
Joined Parties.
18
19
20
21
I. INTRODUCTION
On April 28, 2016, Plaintiffs, a coalition of environmental interest groups led by the Natural
22 Resources Defense Council, filed the currently operative Fourth Supplemental Complaint (“4SC”),
23 which includes three pre-existing claims brought under the Administrative Procedure Act (“APA”), 5
24 U.S.C. § 701 et seq., and the Endangered Species Act (“ESA”), 16 U.S.C. §§ 1531 et seq., alleging that
25 the U.S. Bureau of Reclamation (“Bureau” or “Reclamation”) and the U.S. Fish and Wildlife Service
1
1
(“FWS” or “Service”) acted unlawfully by renewing, implementing, and approving the renewal and
2
implementation of certain long-term water contracts in reliance on a 2005 Biological Opinion (“2005
3
FWS Smelt OCAP BiOp”) issued by FWS pursuant to the ESA, that the agencies knew, or should have
4
known, was inadequate to protect the ESA-listed delta smelt. Doc. 575 (filed Apr. 8, 2008). Specifically,
5
the pre-existing claims challenged renewal of two sets of contracts: (1) those held by the Sacramento
6
River Settlement (“SRS”) Contractors; and (2) those held by the Delta-Mendota Canal Unit (“DMC”)
7
Contractors. Id.
8
9
The 4SC added three new claims to this action: the Fourth Claim for Relief alleges FWS failed to
conduct an adequate consultation on the effects of the SRS and DMC Contract renewals on delta smelt;
10 the Fifth Claim for Relief alleges Reclamation failed to reinitiate consultation on the alleged impact of
11 the SRS Contracts on ESA-listed winter-run and spring-run Chinook salmon; and the Sixth Claim for
12 Relief alleges Reclamation and the SRS Contractors have unlawfully “taken” winter-run and spring-run
13 Chinook in violation of Section 9 of the ESA (“Section 9”), 16 U.S.C. § 1538(a).
14
The SRS Contractors move to dismiss the First, Second, Third, Fifth, and Sixth Claims for
15 Relief. Doc. 1031 (“SRS MTD”). The Federal Defendants move to dismiss the Fifth and Sixth Claims
16 for Relief. Doc. 1032 (“FD MTD”). The DMC Contractors move to dismiss the First, Second, and Third
17 Claims for Relief. Doc. 1033 (“DMC MTD”). James Irrigation District and Del Puerto Water District
18 (collectively, “JID Parties”) join in the motions to dismiss the First, Second, and Third Claims for
19 Relief, Docs. 1029 & 1030 (“JID Joinder”), as does the Banta-Carbona Irrigation District, Patterson
20 Irrigation District, West Stanislaus Irrigation District, and the West Side Irrigation District (collectively,
21 “Banta-Carbona Parties”). Doc. 1036 (“Banta-Carbona Joinder”). No party moves to dismiss the Fourth
22 Claim for Relief. Plaintiffs oppose the motions. Doc. 1039 (“Pltf. Opp.”). All moving parties filed
23 replies. Docs. 1040 & 1041 (“JID Reply”), 1042 (“DMC Reply”), 1043 (“FD Reply”), 1044 (“SRS
24 Reply”).
25
On October 20, 2016, the Court issued a Memorandum Decision and Order resolving certain
2
1
aspects of the pending motions and requesting supplemental briefing on others. Doc. 1045 (“October 20,
2
2016 Order”). After stipulating to an extension of time for the filing of supplemental briefs, Doc. 1047,
3
supplemental briefs were filed in December 2016 and January 2017. Docs. 1048, 1052, 1054.
II. LEGAL BACKGROUND
4
5
“Under the ESA, the Secretary of the Interior and the Secretary of Commerce are charged with
6
identifying threatened and endangered species and designating critical habitats for those species.” Nat.
7
Res. Def. Council v. Jewell, 749 F.3d 776, 779 (9th Cir. 2014) (“NRDC v. Jewell”) (citing 16 U.S.C. §
8
1533). FWS and the National Marine Fisheries Service (“NMFS”) administer the ESA on behalf of the
9
Departments of the Interior and Commerce, respectively. See 50 C.F.R. §§ 17.11, 222.101(a), 223.102,
10 402.01(b). Section 7 of the ESA requires federal agencies to ensure that their activities do not jeopardize
11 the continued existence of listed endangered or threatened species or adversely modify those species’
12 critical habitats. 16 U.S.C. § 1536(a)(2); see also Karuk Tribe of Cal. v. U.S. Forest Serv., 681 F.3d
13 1006, 1020 (9th Cir. 2012). Section 7’s implementing regulations provide that “[e]ach Federal agency
14 shall review its actions at the earliest possible time to determine whether any action may affect listed
15 species or critical habitat[s].” 50 C.F.R. § 402.14(a). An agency proposing to take an action (often
16 referred to as the “action agency”) must first inquire of FWS or NMFS1 whether any threatened or
17 endangered species “may be present” in the area of the proposed action. See 16 U.S.C. § 1536(c)(1). If
18 endangered species may be present, the action agency must prepare a “biological assessment” (“BA”) to
19 determine whether such species “is likely to be affected” by the action. Id. If the BA determines that a
20 threatened or endangered species “is likely to be affected,” the agency must formally consult with FWS.
21 See id. § 1536(a)(2); 50 C.F.R. § 402.14(a).
22
1
Generally, FWS has jurisdiction over species of fish that either (1) spend the major portion of their life in fresh water, or (2)
23 spend part of their lives in estuarine waters, if the remaining time is spent in fresh water. See Cal. State Grange v. Nat’l
Marine Fisheries Serv., 620 F. Supp. 2d 1111, 1120 n.1 (E.D. Cal. 2008), as corrected (Oct. 31, 2008). NMFS is granted
24 jurisdiction over fish species that (1) spend the major portion of their life in ocean water, or (2) spend part of their lives in
25
estuarine waters, if the remaining portion is spent in ocean water. Id. FWS exercises jurisdiction over the delta smelt; NMFS
exercises jurisdiction over the winter-run and spring-run Chinook.
3
Formal consultation results in the issuance of a “biological opinion” (“BiOp”) by FWS. See 16
1
2
U.S.C. § 1536(b). If the BiOp concludes that the proposed action would jeopardize the species or
3
destroy or adversely modify critical habitat, see id. § 1536(a)(2), then the action may not go forward
4
unless FWS can suggest a “reasonable and prudent alternative[]” (“RPA”) that avoids jeopardy,
5
destruction, or adverse modification. Id. § 1536(b)(3)(A). If the BiOp concludes that jeopardy is not
6
likely and that there will not be adverse modification of critical habitat, or that there is a RPA to the
7
agency action that avoids jeopardy and adverse modification, and that the incidental taking of
8
endangered or threatened species will not violate Section 7(a)(2), the consulting agency shall issue an
9
“Incidental Take Statement” (“ITS”) which, if followed, exempts the action agency from the prohibition
10 on takings found in Section 9 of the ESA. 16 U.S.C. § 1536(b)(4); Aluminum Co. of Am. v.
11 Administrator, Bonneville Power Admin., 175 F.3d 1156, 1159 (9th Cir. 1999). Even after consultation
12 is complete, an agency has a duty to reinitiate formal consultation under certain circumstances, including
13 if: “the amount or extent of taking specified in the incidental take statement is exceeded”; “new
14 information reveals effects of the action that may affect listed species or critical habitat in a manner or to
15 an extent not previously considered”; or “the identified action is subsequently modified in a manner that
16 causes an effect to the listed species or critical habitat that was not considered in the biological opinion.”
17 50 C.F.R. § 402.16.
18
Section 9, prohibits, among other actions, the “take” of any listed animal species by any “person
19 subject to the jurisdiction of the United States.” 16 U.S.C. § 1538(a)(1)(B). The ESA defines “take” as
20 “to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or to attempt to engage in any
21 such conduct.” 16 U.S.C. § 1532(19). Two safe harbor provisions described in greater detail below
22 immunize persons from Section 9 liability and penalties where takings committed during otherwise
23 lawful activities occur in compliance with the terms and conditions of either an ITS issued after Section
24 7 consultation or an Incidental Take Permit (“ITP”) issued pursuant to ESA Section 10. 16 U.S.C. §
25 1539.
4
III. FACTUAL AND PROCEDURAL HISTORY
1
2
A.
The Central Valley Project and the State Water Project
The Central Valley Project (“CVP”) and the State Water Project (“SWP”), “operated
3
4
respectively by [Reclamation] and the State of California, are perhaps the two largest and most
5
important water projects in the United States.” San Luis & Delta-Mendota Water Auth. v. Jewell, 747
6
F.3d 581, 592 (9th Cir. 2014) (“San Luis v. Jewell”). “These combined projects supply water originating
7
in northern California to more than 20,000,000 agricultural and domestic consumers in central and
8
southern California.” Id. As part of CVP operations, Reclamation releases water stored in CVP
9
reservoirs in northern California, which then flows down the Sacramento River to the Sacramento-San
10 Joaquin Delta (“Delta”). Id. at 594. Pumping plants in the southern region of the Delta then divert the
11 water to various users south of the Delta. See id. at 594-95.
12 B.
Delta Smelt
13
The delta smelt (Hypomesus transpacificus) is a “small, two-to-three inch species of fish
14 endemic to the [Delta].” Id. at 595. In 1993, FWS concluded the delta smelt’s population had declined
15 by ninety percent over the previous twenty years and listed it as a “threatened” species under the ESA.
16 Determination of Threatened Status for the Delta Smelt, 58 Fed. Reg. 12,854, 12,855 (Mar. 5, 1993).
17 FWS further determined that “Delta water diversions,” including those resulting from operations of the
18 CVP, are the most significant “synergistic cause[ ]” of the decline in the delta smelt population. Id. at
19 12,859.
20 C.
Winter-Run Chinook
21
Winter-run Chinook (Oncorhynchus tshawytscha) are listed as “endangered” under the ESA.
22 Endangered and Threatened Species: Final Listing Determinations for 16 ESUs of West Coast Salmon,
23 and Final 4(d) Protective Regulations for Threatened Salmonid ESUs, 70 Fed. Reg. 37,160 (June 28,
24 2005). According to the 4SC, the winter-run Chinook’s population “has declined precipitously since the
25 early 1980s, from an estimated historic high of 117,808 in 1969 to as few as 191 adult individuals
5
1
returning to spawn in 1991.” 4SC ¶ 64. Winter-run Chinook historically inhabited the upper Sacramento
2
River and its tributaries. Id. ¶ 66. The construction of Shasta Dam blocked access to almost all of the
3
winter-run Chinook’s rearing waters. Id. Today, the upper Sacramento River below Keswick Dam is the
4
only remaining spawning area used by winter-run Chinook. Id. It is alleged that the winter-run Chinook
5
is “at high risk of extinction” and that a prolonged drought could have devastating effects on the species.
6
Id. It is further alleged that winter-run Chinook are particularly vulnerable during the “temperature
7
management season,” which generally lasts from June through October. Id. ¶ 67.
Adult winter-run Chinook migrate up the Sacramento River in the winter
and spring and then hold below the Keswick Dam for several months
before spawning. During these critical months, the salmon require cold
water for the maturation of their gonads and the development of fertilized
eggs and embryos.
8
9
10
11 Id.
D.
12
Spring-Run Chinook
The spring-run Chinook (Oncorhynchus tshawytscha) historically displayed the second largest
13
salmon run in the Central Valley watershed and supported the bulk of the region’s commercial fishery.
14
Id. ¶ 68. Only remnant independent natural spring-run Chinook populations survive, relying principally
15
upon small tributaries of the Sacramento River below Shasta Dam for spawning. Id. ¶¶ 68, 71. Like
16
winter-run Chinook, spring-run Chinook require cold water temperatures for successful spawning, egg
17
incubation, and rearing. Id. ¶ 72.
18
E.
Long-Term Contract Renewal/Operations and Criteria Plan
19
“In the 1960s, the Bureau entered into a number of long-term contracts pertaining to the CVP.”
20
NRDC v. Jewell, 749 F.3d at 780. “The [SRS] Contracts are forty-year agreements between the Bureau
21
and holders of certain senior water rights.” Id. “These contracts grant the Bureau some rights to the
22
encumbered water while also providing senior rights holders a stable supply of water.” Id. The DMC
23
Contracts allow junior water users to draw water from the Delta-Mendota Canal. Id. By 2004, the DMC
24
Contracts and the SRS Contracts had expired or were about to expire. Id. On June 30, 2004, the Bureau
25
6
1
prepared an operational plan, the Operations Criteria and Plan (“OCAP” or “2004 OCAP”), to provide,
2
among other things, a basis for renewing various contracts, including the DMC and SRS Contracts. Id.
3
F.
ESA § 7 Consultations Leading Up to Contract Renewal
4
Pursuant to ESA § 7, the Bureau initiated consultation with FWS regarding the effect of the
5
OCAP on the delta smelt. Id. at 780-81. FWS issued an initial BiOp in 2004 (the “2004 FWS Smelt
6
OCAP BiOp”), which concluded that the OCAP would not jeopardize the delta smelt. Id. at 781. The
7
Bureau re-initiated consultation after the Ninth Circuit’s decision in Gifford Pinchot Task Force v. U.S.
8
Fish & Wildlife Serv., 378 F.3d 1059, 1069 (9th Cir. 2004), which invalidated a regulation upon which
9
the 2004 FWS Smelt OCAP BiOp relied. NRDC v. Jewell, 749 F.3d at 781. In 2005, FWS issued a
10 revised BiOp (the “2005 FWS Smelt OCAP BiOp”), which also concluded that the OCAP would not
11 jeopardize the delta smelt. Id.
12
Reclamation separately requested a BiOp from NMFS on whether continued operation of the
13 CVP pursuant to the OCAP would jeopardize various species under that agency’s jurisdiction, including
14 the winter-run and spring-run Chinook. See PCFFA v. Gutierrez, No. 1:06-cv-245-OWW-GSA
15 (“PCFFA”), Doc. 69 ¶ 77 (First Amended Complaint) (“PCFFA FAC”). NMFS issued a BiOp on
16 October 22, 2004 regarding the effects of the OCAP on the species under its jurisdiction, including
17 several salmonid species (“2004 NMFS Salmonid OCAP BiOp”). 4SC ¶ 107.
18
Also in 2004 and 2005, the Bureau prepared BAs that concluded that renewal of the Contracts
19 would not adversely affect the delta smelt. NRDC v. Jewell, 749 F.3d at 781. The Bureau requested
20 additional consultation with FWS regarding its plans to renew the Contracts. Id.
21
22
23
24
FWS responded via a series of letters, in which it concurred with the
Bureau’s determination that renewing the Contracts was not likely to
adversely affect the delta smelt. Each FWS concurrence letter explained
that renewing the Contracts would increase the demand for water, but that,
according to the 2004 and 2005 [FWS Smelt OCAP] BiOps, this demand
would not adversely affect the delta smelt. The letters did not assess the
Contracts’ potential effects on the delta smelt beyond the reasoning
borrowed from the now-invalidated 2004 Opinion and 2005 Opinion.
25
7
1
Id. (emphasis added).
Again, Reclamation separately consulted with NMFS on the effects of renewing the Contracts on
2
3
the listed salmonid species under NMFS’s jurisdiction. 4SC ¶ 108. As was the case with FWS, NMFS
4
concurred that executing the Contracts would not adversely impact listed salmonids. Id.
In 2004 and 2005, the Bureau renewed 141 SRS Contracts and 18 DMC Contracts based on
5
6
FWS’s and NMFS’s concurrence letters. NRDC v. Jewell, 749 F.3d at 781.
7
G.
In February 2005, Plaintiffs initiated this lawsuit, challenging the 2004 FWS Smelt OCAP BiOp.
8
9
Plaintiffs Challenge the 2004/2005 FWS Smelt OCAP BiOp
Doc. 1. Subsequent amendments to the Complaint updated Plaintiffs’ allegations to include challenges
10 to the 2005 FWS Smelt OCAP BiOp. Doc. 403 (Second Amended Complaint (“SAC”)). Among other
11 things, the SAC alleged that the 2005 FWS Smelt OCAP BiOp did not “adequately consider or address
12 the effects of [the] long-term water service contracts on threatened and endangered species,” id. ¶ 32,
13 and that the Bureau “has taken and is taking actions that could foreclose implementation of reasonable
14 and prudent alternatives that would avoid jeopardy, including but not limited to signing and
15 implementing new long-term contracts promising delivery of substantially increased quantities of water,
16 in violation of [ESA] section 7(d).” Id. ¶ 81. In 2007, the 2005 FWS Smelt OCAP BiOp was set aside as
17 unlawful. Nat. Res. Def. Council v. Kempthorne, 506 F. Supp. 2d 322 (E.D. Cal. 2007). The Bureau did
18 not appeal.
19 H.
Parallel Challenge to the 2004 NMFS Salmonid OCAP BiOp
20
On August 9, 2005, a coalition of environmental organizations largely overlapping with the
21 present Plaintiffs filed a parallel complaint against Reclamation and NMFS alleging that the NMFS
22 2004 OCAP Salmonid BiOp was inadequate. Pac. Coast Fed’n of Fishermen’s Associations v.
23 Gutierrez, 606 F. Supp. 2d 1122, 1131 (E.D. Cal. 2008) (“PCFFA I”). Plaintiffs similarly sought to
24 “[e]njoin and set aside any and all actions” that relied on it, including the delivery of water under long25 term water contracts at issue here. Id. at 1183 (“Existing renewal and any new water service contracts
8
1
have already been challenged in this litigation.”); PCFFA FAC at 38.2
2
I.
District Court Ruling in PCFFA
On May 20, 2008, the previously assigned district judge found that NMFS acted arbitrarily and
3
4
capriciously by failing to consider certain facts in the NMFS 2004 Salmonid OCAP BiOp. PCFFA I,
5
606 F. Supp. 2d at 1193-94. In July 2008, the Court considered Plaintiffs’ motion for injunctive relief,
6
seeking implementation of remedies designed to aid salmonids in the Sacramento River basin. In the
7
context of this request for injunctive relief, the Court concluded that the Bureau had a “mandatory (i.e.,
8
non-discretionary) legal obligation to make releases from Shasta Reservoir for delivery to the [SRS]
9
Contactors.” Pac. Coast Fed’n of Fishermen’s Associations v. Gutierrez, 606 F. Supp. 2d 1195, 1201
10 (E.D. Cal. 2008) (“PCFFA II”). Plaintiffs did not seek to amend or supplement their complaint in
11 PCFFA.
12 J.
Third Amended Complaint in This Case
13
In June 2008, Plaintiffs filed the Third Amended Complaint (“TAC”) in this case, directly
14 challenging the sufficiency of FWS’s ESA consultation undertaken in connection with the renewal of 41
15 Contracts. See Doc. 575 ¶¶ 44-47, 69, 72-73. In seeking to set aside these contracts, Plaintiffs argued
16 that the Bureau violated § 7(a)(2) of the ESA by failing to consult adequately with the FWS prior to
17 renewing the Contracts. Id. ¶ 85.
18 K.
FWS Issues Revised Biological Opinion
19
On December 15, 2008, the FWS issued a revised BiOp (the “2008 FWS Smelt OCAP BiOp”),
20 which, contrary to the findings of the 2004 and 2005 FWS Smelt OCAP BiOps, concluded that the
21 OCAP would jeopardize the delta smelt and adversely modify its critical habitat. NRDC v. Jewell, 749
22
2
The Court is cognizant of the fact that some parties to these related cases prefer to cite to the Electronic Case File (“ECF”)
23 automatic page stamp references. This Court will continue to cite to the internal page references of documents wherever
possible, primarily because some parties continue to present courtesy copies to the Court that do not bear ECF page stamps.
24 Rather than re-print lengthy documents at taxpayer expense or take time to correlate page citations to the ECF page stamps,
25
the Court uses the courtesy copies and cites to them the only way it can efficiently do so: using the document’s own internal
page references. For reasons of consistency, the Court therefore always cites to internal page references unless none is
available, in which case it references ECF page stamp pages as “p. __ of ___.”
9
1
F.3d at 781. The 2008 BiOp became the subject of numerous lawsuits. See generally San Luis & Delta
2
Mendota Water Auth. v. Salazar, 1:09-cv-407-LJO-BAM. Plaintiffs in this matter intervened as
3
defendants in the challenge to the 2008 FWS Smelt OCAP BiOp. See id.
4
L.
NMFS Issues a Revised BiOp
On June 4, 2009, NMFS issued a revised BiOp (“2009 NMFS Salmonid OCAP BiOp”). See San
5
6
Luis & Delta-Mendota Water Auth. v. Locke, 776 F.3d 971, 988 (9th Cir. 2014) (“San Luis v. Locke”).
7
Three months later, the previously assigned district judge entered final judgment in PCFFA, and closed
8
the matter. PCFFA, 1:06-CV-0245-OWW-GSA, Doc. 458 (Judgment, Sept. 9, 2009).
9
M.
10
District Court and Ninth Circuit Rulings on Plaintiffs’ TAC
In rulings in late 2008 and 2009 in this case, the previously assigned district judge held that
11 Plaintiffs did not have standing to challenge renewal of the DMC Contracts and that Plaintiffs’ challenge
12 to the SRS Contracts failed as a matter of law because Federal Defendants lacked discretion to modify
13 the SRS Contracts to benefit Plaintiffs’ interests. Nat. Res. Def. Council v. Kempthorne, 2008 WL
14 5054115, at *22 (E.D. Cal. Nov. 19, 2008) (“NRDC v. Kempthorne”). A divided three-judge panel of the
15 Ninth Circuit Court of Appeals affirmed. Nat. Res. Def. Council v. Salazar, 686 F.3d 1092 (9th Cir.
16 2012).
17
The Ninth Circuit subsequently voted to hear the case en banc, and the en banc panel reversed
18 and remanded. NRDC v. Jewell, 749 F.3d at 776. The en banc decision first found that the issuance of
19 the 2008 FWS Smelt OCAP BiOp did not moot Plaintiffs’ challenge to the Contracts:
20
21
22
23
This action is not moot because the 2008 Opinion does not provide
Plaintiffs with the relief that they seek. The 2008 Opinion concluded that
the Bureau’s Plan would likely jeopardize the delta smelt and adversely
modify its critical habitat. In so doing, the 2008 Opinion explained that the
Bureau’s Plan must be modified from what the Bureau envisioned in 2004
and 2005, and the Opinion identified a “reasonable and prudent
alternative” to the proposed Plan that would avoid jeopardizing the delta
smelt.
24
25
The issuance of the 2008 Opinion does not moot this appeal. The 2008
Opinion merely assesses the general effects of the Bureau’s Plan, and it
10
does not represent a consultation with the FWS concerning the impact of
the Bureau’s decision to renew the specific contracts before us. Although
the DMC Contracts and Settlement Contracts were renewed based on
now-invalidated opinions, the Bureau has never reconsulted with the FWS
regarding the effects of renewing these contracts, nor has it sought to
amend the challenged contracts to incorporate the protections proposed in
the 2008 Opinion. The remedy Plaintiffs seek is an injunction requiring
reconsultation with the FWS and renegotiation of the challenged contracts
based on the FWS’ assessment. This relief remains available.
1
2
3
4
5
6
Id. at 782.
On the issue of standing related to the DMC Contracts, the previously assigned district judge
7
8
held that Plaintiffs could not establish that their injury is fairly traceable to the Bureau’s alleged
9
procedural violation because: (1) the DMC Contracts contain a shortage provision that absolves the
10 government from liability for breaches that result from complying with its legal obligations; (2) this
11 provision permits the Bureau to take necessary actions to meet its legal obligations under the ESA, so
12 (3) the Bureau could not have negotiated any contractual terms that better protect the delta smelt, and,
13 therefore, any injury to the delta smelt is not traceable to the contract renewal process. NRDC v.
14 Kempthorne, 2008 WL 5054115, at *11-18.
15
The Ninth Circuit rejected this reasoning, finding instead that “to establish standing, a litigant
16 who asserts a procedural violation under Section 7(a)(2) need only demonstrate that compliance with
17 Section 7(a)(2) could protect his concrete interests.” 749 F.3d at 783 (emphasis in original). The Ninth
18 Circuit concluded that the consultation could have led to revisions that could have benefitted the delta
19 smelt:
20
21
22
23
24
25
Contrary to the district court’s finding, the shortage provision does not
provide the delta smelt with the greatest possible protection. Nothing
about the shortage provision requires the Bureau to take actions to protect
the delta smelt. The provision is permissive, and merely absolves the
United States of liability if there is a water shortage resulting from, inter
alia, “actions taken ... to meet legal obligations.” But even if we read the
provision to place an affirmative obligation on the Bureau to take actions
to benefit the delta smelt, the provision only concerns the quantity of
water that will be made available to the DMC Contractors. There are
various other ways in which the Bureau could have contracted to benefit
the delta smelt, including, for example, revising the contracts’ pricing
11
scheme or changing the timing of water deliveries. Because adequate
consultation and renegotiation could lead to such revisions, Plaintiffs have
standing to assert a procedural challenge to the DMC Contracts.
1
2
3
4
Id. at 783-84.
With regard to the SRS Contracts, the previously assigned district judge held that, although
5
Plaintiffs have standing to assert procedural challenges to them, the Bureau was not required to consult
6
under Section 7(a)(2) prior to renewing the SRS Contracts because the Bureau’s discretion in
7
renegotiating these contracts was “substantially constrained” in light of a line of cases, including Nat’l
8
Ass’n of Home Builders v. Defenders of Wildlife, 551 U.S. 644, 669 (2007), which stands for the
9
proposition that there is no duty to consult for actions “that an agency is required by statute to
10 undertake.” Nat. Res. Def. Council v. Kempthorne, 621 F. Supp. 2d 954, 1000 (E.D. Cal. 2009), decision
11 clarified, 627 F. Supp. 2d 1212 (E.D. Cal. 2009), on reconsideration, No. 1:05-CV-1207-OWW-SMS,
12 2009 WL 2424569 (E.D. Cal. Aug. 6, 2009). In holding that the Bureau was not required to consult
13 under Section 7(a)(2) prior to renewing the SRS Contracts, the previously assigned district judge
14 focused on Article 9(a) of the original SRS Contracts, which provides in pertinent part:
15
16
17
18
19
During the term of this contract and any renewal thereof it shall constitute
full agreement as between the United States and the Contractor as to the
quantities of water and the allocation thereof between base supply and
Project water which may be diverted by the Contractor from the
Sacramento River for beneficial use on the land shown on Exhibit B which
said diversion, use, and allocation shall not be disturbed so long as the
Contractor shall fulfill all of its obligations hereunder, and the Contractor
shall not claim any right against the United States in conflict with the
provisions hereof.
20 Id. at 979 (emphasis omitted). This provision, according to the district court, “substantially constrained”
21 the Bureau’s discretion to negotiate new terms in renewing the contracts, thereby absolving the Bureau
22 of the duty to consult under Home Builders. Id.
23
24
25
The Ninth Circuit rejected this reasoning as well:
Section 7(a)(2)’s consultation requirement applies with full force so long
as a federal agency retains “some discretion” to take action to benefit a
protected species. [citations] While the parties dispute whether Article 9(a)
12
1
2
3
4
5
6
7
8
9
10
11
12
actually limits the Bureau’s authority to renegotiate the Settlement
Contracts, it is clear that the provision does not strip the Bureau of all
discretion to benefit the delta smelt and its critical habitat.
First, nothing in the original Settlement Contracts requires the Bureau to
renew the Settlement Contracts. Article 2 of the original contracts
provides that “renewals may be made for successive periods not to exceed
forty (40) years each.” (emphasis added). This language is permissive and
does not require the Bureau to execute renewal contracts. Since the FWS
has concluded that “Delta water diversions” are the most significant
“synergistic cause[ ]” of the decline in delta smelt, 58 Fed. Reg. at 12,859,
it is at least plausible that a decision not to renew the Settlement Contracts
could benefit the delta smelt and their critical habitat.
But even assuming, arguendo, that the Bureau is obligated to renew the
Settlement Contracts and that Article 9(a) limits the Bureau’s discretion in
so doing, Article 9(a) simply constrains future negotiations with regard to
“the quantities of water and the allocation thereof....” Nothing in the
provision deprives the Bureau of discretion to renegotiate contractual
terms that do not directly concern water quantity and allocation. And, as
[is the case] with respect to the DMC Contracts, the Bureau could benefit
the delta smelt by renegotiating the Settlement Contracts’ terms with
regard to, inter alia, their pricing scheme or the timing of water
distribution.
13
14
15
For these reasons, we conclude that, in renewing the Settlement Contracts,
the Bureau retained “some discretion” to act in a manner that would
benefit the delta smelt. The Bureau was therefore required to engage in
Section 7(a)(2) consultation prior to renewing the Settlement Contracts.
16 NRDC v. Jewell, 749 F.3d at 785. The matter was reversed and remanded for further proceedings. Id.
17 N.
Stay of this Case and Further FWS Consultation
18
On June 15, 2015, the Court stayed this litigation to allow Reclamation to reinitiate ESA-
19 consultation on the contract renewals. Doc. 979. Thereafter, Reclamation requested FWS’s concurrence
20 that the impacts of these contract renewals on delta smelt were assessed in the 2008 FWS Smelt OCAP
21 BiOp. 4SC ¶¶ 103, 105. FWS responded by sending a letter of concurrence (“2015 LOC”), concluding
22 that “all of the possible effects to delta smelt and its critical habitat by operating the CVP to deliver
23 water under the SRS and DMC Contracts were addressed in the [2008 FWS Smelt OCAP BiOp].” Id. ¶
24
25
13
1
106.3
2
O.
Plaintiffs Obtain Leave to Amend
On April 22, 2016, the Court granted Plaintiffs’ motion for leave to file the 4SC, permitting the
3
4
addition of three new claims. Doc. 1018. The Fourth Claim for Relief challenges the sufficiency of
5
FWS’s re-consultation, which resulted in the issuance of the 2015 LOC. 4SC ¶¶ 177-182. No party
6
objected to adding this claim, which is a natural extension of the existing litigation.4
Plaintiffs’ Fifth Claim alleges that Reclamation unlawfully failed to request re-initiation of
7
8
consultation with NMFS on the impacts of SRS Contract renewals on the winter-run and spring-run
9
Chinook. 4SC ¶¶ 183-188. Specifically, Plaintiffs allege that the 2009 NMFS Smelt OCAP BiOp
10 constituted new information that revealed effects of the SRS Contracts that NMFS did not consider in
11 consultation over the contracts. Id. ¶ 186. Plaintiffs also allege that massive mortality episodes
12 impacting the 2014 and 2015 generations of winter-run and spring-run Chinook constituted independent
13 new information that should have triggered re-consultation. Id. ¶ 187.
Plaintiffs’ Sixth Claim for relief alleges Reclamation and the SRS Contractors illegally caused
14
15 the take of winter-run and spring-run Chinook during 2014 and 2015 because Reclamation made
16 excessive deliveries to the SRS Contractors that depleted the cold water reserves in Shasta Reservoir,
17 causing temperature increases fatal to the 2014 and 2015 “brood years” of winter-run and spring-run
18 Chinook. 4SC ¶¶ 189-193.
19 P.
October 20, 2016 Order
20
In response to multiple motions to dismiss, the Court issued an order resolving some aspects of
21 those motions and requesting supplemental briefing on others. See October 20, 2016 Order. Specifically,
22
3
According to the 4SC, Reclamation has not engaged in further consultation with NMFS over impacts of the contracts on
23 salmonids. See 4SC at ¶ 29 (explaining that NMFS issued a final letter of concurrence regarding the effects of the Settlemetn
Contracts on salmonids on January 10, 20015).
24
25
4
Although the SRS Contracts were renewed in 2004 and 2005, the Fourth Claim for Relief, based upon Reclamation’s failure
to consult over impacts of renewal upon delta smelt, was first raised in the TAC filed in 2008 and has been preserved
throughout the present case.
14
1
the Court denied the DMC Contractors’ and SRS Contractors’ motion to dismiss the First and Third
2
Claims for Relief because Plaintiffs admit they included these claims in the 4SC for informational
3
purposes only. The Court found it was not unreasonable to leave claims on which judgment has already
4
entered in an operative complaint for this reason, particularly given the exceedingly complex procedural
5
history of this case. Id. at 19.
The Court found that allegations in the Second Claim for Relief that pertain directly to
6
7
Reclamation’s reliance on the 2005 FWS Smelt OCAP BiOp are moot in light of the fact that FWS
8
issued the 2008 FWS Smelt OCAP BiOp, which superseded and in large part rejected the 2005 FWS
9
Smelt OCAP BiOp. Id. at 19-20. While the Court found other allegations in the Second Claim pertaining
10 to ongoing obligations and the 2015 consultation were not moot, the Court nevertheless concluded those
11 remaining allegations must be dismissed for failure to comply with the ESA’s 60-day notice
12 requirement. Id. at 20-25.
13
The Court resolved some challenges to the Fifth and Sixth Claims for Relief, but requested
14 supplemental briefing on other issues, which are discussed in greater detail below.
15
16
IV. STANDARD OF DECISION
A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) is a challenge to the
17 sufficiency of the allegations set forth in the complaint. A 12(b)(6) dismissal is proper where there is
18 either a “lack of a cognizable legal theory” or “the absence of sufficient facts alleged under a cognizable
19 legal theory.” Balisteri v. Pacifica Police Dept., 901 F.2d 696, 699 (9th Cir. 1990). In considering a
20 motion to dismiss for failure to state a claim, the court generally accepts as true the allegations in the
21 complaint, construes the pleading in the light most favorable to the party opposing the motion, and
22 resolves all doubts in the pleader’s favor. Lazy Y. Ranch LTD v. Behrens, 546 F.3d 580, 588 (9th Cir.
23 2008).
24
To survive a 12(b)(6) motion to dismiss, the plaintiffs must allege “enough facts to state a claim
25 to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). “A claim
15
1
has facial plausibility when the Plaintiff pleads factual content that allows the court to draw the
2
reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S.
3
662, 678 (2009). “The plausibility standard is not akin to a ‘probability requirement,’ but it asks for
4
more than a sheer possibility that a defendant has acted unlawfully.” Id. (quoting Twombly, 550 U.S. at
5
556). “While a complaint attacked by a Rule 12(b)(6) motion to dismiss does not need detailed factual
6
allegations, a Plaintiff’s obligation to provide the ‘grounds’ of his ‘entitlement to relief’ requires more
7
than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.”
8
Twombly, 550 U.S. at 555 (internal citations omitted). Thus, “bare assertions . . . amount[ing] to nothing
9
more than a ‘formulaic recitation of the elements’ . . . are not entitled to be assumed true.” Iqbal, 556
10 U.S. at 681. “[T]o be entitled to the presumption of truth, allegations in a complaint . . . may not simply
11 recite the elements of a cause of action, but must contain sufficient allegations of underlying facts to
12 give fair notice and to enable the opposing party to defend itself effectively.” Starr v. Baca, 652 F.3d
13 1202, 1216 (9th Cir. 2011). In practice, “a complaint . . . must contain either direct or inferential
14 allegations respecting all the material elements necessary to sustain recovery under some viable legal
15 theory.” Twombly, 550 U.S. at 562; see also Starr, 652 F.3d at 1216 (“the factual allegations that are
16 taken as true must plausibly suggest an entitlement to relief”). To the extent that the pleadings can be
17 cured by the allegation of additional facts, a plaintiff should be afforded leave to amend. Cook, Perkiss
18 and Liehe, Inc. v. N. Cal. Collection Serv., Inc., 911 F.2d 242, 247 (9th Cir. 1990) (citations omitted).
V. DISCUSSION
19
20 A.
Fifth Claim for Relief
21
Plaintiffs’ Fifth Claim alleges that Reclamation unlawfully failed to request re-initiation of
22 consultation with NMFS on the impacts of SRS Contract “implementation” on the winter-run and
23 spring-run Chinook. 4SC ¶¶ 183-88. Specifically, Plaintiffs allege that the 2009 NMFS Salmonid OCAP
24 BiOp constituted new information that revealed effects of the SRS Contracts that NMFS did not
25 consider in consultation over the contracts. Id. ¶ 186. Plaintiffs also allege that massive mortality
16
1
episodes impacting the 2014 and 2015 generations of winter-run and spring-run Chinook constituted
2
independent new information that should have triggered re-consultation. Id. ¶ 187.
3
4
An agency is required to reinitiate consultation where
discretionary Federal involvement or control over the action has been
retained or is authorized by law and:
5
6
7
8
9
10
11
(a) If the amount or extent of taking specified in the incidental take
statement is exceeded;
(b) If new information reveals effects of the action that may affect
listed species or critical habitat in a manner or to an extent not
previously considered;
(c) If the identified action is subsequently modified in a manner
that causes an effect to the listed species or critical habitat that was
not considered in the biological opinion; or
(d) If a new species is listed or critical habitat designated that may
be affected by the identified action.
12
50 C.F.R. § 402.16 (emphasis added). The duty to reinitiate consultation lies with both the action agency
13
and the consultation agency. See id.; see also Envtl. Prot. Info. Ctr. v. Simpson Timber Co., 255 F.3d
14
15
16
1073, 1076 (9th Cir. 2001) (“EPIC”).
Plaintiffs allege that Reclamation has “discretionary federal involvement and control over the
implementation of the SRS Contracts.” 4SC ¶ 186. Federal Defendants dispute this, arguing that “while
17
Reclamation retains some limited discretionary control or involvement in implementing the terms of the
18
SRS Contracts, that level of involvement is not sufficient to trigger re-initiation because in the end,
19
Reclamation ultimately cannot unilaterally alter the existing terms of the contracts in a manner that will
20
inure to the benefit of [the] species.” FD MTD at 9.
21
Plaintiffs argued in the initial round of briefing that the Ninth Circuit’s decision in NRDC v.
22
Jewell controls on the issue of discretionary involvement and control. The relevant portion of that
23
decision addressed Plaintiffs’ claim, contained in the TAC, that Reclamation violated Section 7(a)(2) by
24
failing to consult adequately with FWS over impacts to delta smelt prior to renewing the SRS Contracts.
25
17
1
See 749 F.3d at 781. The previously assigned district judge ruled that Reclamation was not required to
2
comply with Section 7 in connection with renewal of the SRS contracts because the terms of the original
3
SRS Contracts “substantially constrained” Reclamation’s discretion to modify the terms during the
4
renewal process. Id. at 784. The Ninth Circuit reversed, holding that the appropriate question is not
5
whether the agency’s discretion is “substantially constrained” but rather whether the agency retains
6
“some discretion” to take action for the benefit of a protected species. Id. Applying the “some
7
discretion” standard, the Ninth Circuit reasoned:
8
9
In holding that the Bureau was not required to consult under Section
7(a)(2) prior to renewing the Settlement Contracts, the district court
focused on Article 9(a) of the original Settlement Contracts, which
provides in pertinent part:
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
During the term of this contract and any renewals thereof: (1) It
shall constitute full agreement as between the United States and the
Contractor as to the quantities of water and the allocation thereof
between base supply and Project water which may be diverted by
the Contractor from its source of supply for beneficial use on the
land shown on Exhibit B ...; (2) The Contractor shall not claim any
right against the United States in conflict with the provisions
hereof.
(emphasis added). According to the district court, the Bureau was not
required to consult because this provision “substantially constrained” the
Bureau’s discretion to negotiate new terms in renewing the contracts.
In so concluding, the district court applied an erroneous standard. Section
7(a)(2)’s consultation requirement applies with full force so long as a
federal agency retains “some discretion” to take action to benefit a
protected species. [Citations] While the parties dispute whether Article
9(a) actually limits the Bureau’s authority to renegotiate the Settlement
Contracts, it is clear that the provision does not strip the Bureau of all
discretion to benefit the delta smelt and its critical habitat.
First, nothing in the original Settlement Contracts requires the Bureau to
renew the Settlement Contracts. Article 2 of the original contracts
provides that “renewals may be made for successive periods not to exceed
forty (40) years each.” (emphasis added). This language is permissive and
does not require the Bureau to execute renewal contracts. Since the FWS
has concluded that “Delta water diversions” are the most significant
“synergistic cause[ ]” of the decline in delta smelt, 58 Fed. Reg. at 12,859,
it is at least plausible that a decision not to renew the Settlement Contracts
could benefit the delta smelt and their critical habitat.
18
1
But even assuming, arguendo, that the Bureau is obligated to renew the
Settlement Contracts and that Article 9(a) limits the Bureau’s discretion in
so doing, Article 9(a) simply constrains future negotiations with regard to
“the quantities of water and the allocation thereof....” Nothing in the
provision deprives the Bureau of discretion to renegotiate contractual
terms that do not directly concern water quantity and allocation. …[T]he
Bureau could benefit the delta smelt by renegotiating the Settlement
Contracts’ terms with regard to, inter alia, their pricing scheme or the
timing of water distribution.
2
3
4
5
6
For these reasons, we conclude that, in renewing the Settlement Contracts,
the Bureau retained “some discretion” to act in a manner that would
benefit the delta smelt. The Bureau was therefore required to engage in
Section 7(a)(2) consultation prior to renewing the Settlement Contracts.
7
8
9
Id. at 784-85 (italics in original; underlining added). NRDC v. Jewell unambiguously held that the
10 Section 7(a)(2) consultation requirement applies to the renewal of the SRS Contracts.
11
In the October 20, 2016 Order, the Court concluded that NRDC v. Jewell’s holding is “directly
12 relevant to the Fourth Claim for Relief in the 4SC, which challenges the sufficiency of the consultation
13 between Reclamation and FWS as to impacts to delta smelt related to renewal of the SRS Contracts.”
14 October 20, 2016 Order at 28. However, Plaintiffs’ Fifth Claim for relief demands re-initiation of
15 consultation regarding the previously-executed SRS Contracts. After carefully considering the nature
16 and scope of the Fifth Claim for relief, the Court concluded in the October 20, 2016 Order that “the only
17 logical reading of the Fifth Claim for Relief is that Plaintiffs allege Reclamation retains discretionary
18 involvement or control over SRS Contract implementation and that the new information alleged in the
19 complaint regarding impacts of SRS Contract implementation on salmonids requires re-initiation of the
20 consultation regarding SRS Contract adoption.” Id. at 30. The Court then explained that “[t]here is a
21 significant hurdle associated with such an allegation, rooted in a line of authority highlighted by Federal
22 Defendants.” Id. Because it is critical to the analysis here, the Court repeats its explanation of that line of
23 authority here:
24
25
While acknowledging the holding of NRDC v. Jewell, Federal Defendants
argue that once executed, “the terms of the SRS Contracts are set and
Reclamation administers the contracts as executed.” FD MTD at 10.
19
1
2
Therefore, Federal Defendants’ argument continues: “Reclamation does
not retain the authority to alter the contract terms to inure to the benefit of
listed species and thus, re-initiation on the execution of the SRS contracts
has not been triggered.” Id.
3
4
5
6
7
8
9
10
Federal Defendants’ position finds support in EPIC, which concerned a
lawsuit brought against FWS for its alleged failure to re-initiate
consultation over the impact an ITP issued to [] Simpson Timber for the
northern spotted owl might have on two other species (the marbled
murrelet and the coho salmon) listed after the issuance of the ITP. FWS
retained some ongoing authority over the ITP:
ten years after the permit’s issuance, the FWS will review the
permit and evaluate whether Simpson has complied with its terms
before allowing Simpson to continue logging operations under the
permit. The FWS can also suspend the permit at any time in the
event of “any significant violation or breach” of the permit; it also
has the authority to revoke the permit if activities authorized under
it result in the taking of threatened species not the subject of the
permit, including the marbled murrelet and coho salmon.
11
12
13
14
15
16
17
18
19
20
21
Id. at 1078. In evaluating whether FWS retained sufficient discretionary
involvement or control, the Ninth Circuit first confirmed that the
appropriate standard comes from Sierra Club v. Babbitt, 65 F.3d 1502 (9th
Cir. 1995). EPIC, 255 F.3d at 1079. As EPIC summarized:
Sierra Club involved a suit against the Bureau of Land
Management (“BLM”) for its failure to consult with the FWS
about the effect of a proposed logging road on the northern spotted
owl. A private timber company was going to build a road on public
land pursuant to a right-of-way agreement with the BLM. The
Sierra Club claimed that the agreement represented ongoing
agency action and that the BLM was required to consult with the
FWS about the potential impact of the road on a newly listed
species, the spotted owl, because the BLM retained discretionary
involvement and control over the right-of-way. Under the right-ofway agreement, the BLM could object to the timber company’s
project in three limited instances, none of which was at issue or
related to endangered or threatened species. [Sierra Club, 65 F.3d]
at 1509 n. 10. We held that the BLM did not have a duty to consult
with the FWS because it could not influence construction of the
roadway for the benefit of the spotted owl:
22
23
24
25
In light of the statute’s plain language, the agency’s
regulations, and the case law construing the scope of
“agency action,” we conclude that where, as here, the
federal agency lacks the discretion to influence the private
action, consultation would be a meaningless exercise; the
agency simply does not possess the ability to implement
20
1
2
3
4
5
measures that inure to the benefit of the protected species.
Id. at 1509 (emphasis added). Under Sierra Club, to survive a Rule
12(b)(6) motion to dismiss, EPIC must allege facts to show that the
FWS retained sufficient discretionary involvement or control over
Simpson’s permit “to implement measures that inure to the benefit
of the” [species in question]. Id.
EPIC, 255 F.3d at 1079-80 (emphasis added).
6
***
7
The Ninth Circuit then examined the ITP issued to Simpson Timber to
determine whether it reserved to FWS “discretionary involvement and
control to such an extent that it must reconsult on the impact of Simpson’s
spotted owl permit on marbled murrelet and coho salmon.” Id. at 1080.
Ultimately, the Ninth Circuit concluded that neither the ITP nor any
permit-related documents reserved to FWS such discretionary
involvement or control. Id. at 1080-82.
8
9
10
11
12
13
14
15
16
Critically for purposes of this case, the EPIC court next addressed the
applicability of Natural Resources Defense Council v. Houston, 146 F.3d
1118, 1126 (9th Cir. 1998). In Houston, Reclamation was required to
consult with NMFS because Reclamation’s renewal of certain CVP water
contracts, which were statutorily mandated to be negotiated on “mutually
agreeable” terms with water users, involved at least “some” agency
discretion to set the contract terms because Reclamation had discretionary
power to decrease the total supply of water for sale and thereby decrease
the amount of water granted in the renewed contracts. Id. The Ninth
Circuit applied similar reasoning in NRDC v. Jewell to the SRS Contract
renewal process.
24
In EPIC, however, the Ninth Circuit emphasized that Houston should not
be read to “suggest … that once the renewed contracts were executed, the
agency had continuing discretion to amend them at any time to address the
needs of endangered or threatened species.” 255 F.3d at 1082. Rather, the
terms of the contract or agreement must be examined to determine
whether and to what extent the agency retained discretion to impose
measures to protect the species in question. See id. (finding terms of ITP
permit issued regarding impacts to spotted owl did not give FWS the
power to implement measures to benefit species other than the spotted
owl); see also Crowman Corp. v. United States, 51 Fed. Cl. 654, 656
(2002) (finding contract term permitting agency to adjust the time period
for contract operations in the event that an “act of Government” disrupted
contract operations reserved to the agency the discretionary authority to
re-initiate consultation to evaluate impact of contracted operations on
recently-listed species”).
25
Contrary to Plaintiffs’ suggestion, Pltf. Opp. at 8, in light of EPIC, the
17
18
19
20
21
22
23
21
Ninth Circuit’s holding in NRDC v. Jewell is not law of the case with
respect to Plaintiffs’ Fifth Claim for relief. In other words, NRDC v.
Jewell’s holding that Reclamation has discretion in the renewal process to
alter the timing of water distribution and the pricing scheme related to
contracted-for water does not necessarily mean Reclamation retained
similar discretion in the executed contracts (or otherwise possess similar
discretion pursuant to law) that would permit revisions to executed
contracts.
1
2
3
4
5
October 20, 2016 Order at 30-33.
6
The Court then requested supplemental briefing addressing the following questions:
7
(1) In light of the Court’s ruling that EPIC controls as to the Fifth Claim
for Relief and necessitates an examination of SRS Contracts themselves to
determine whether Reclamation retains discretion under the Contracts to
act on behalf of salmonid species, are there provisions in the SRS
Contracts that support Plaintiffs’ allegation that Reclamation retains such
discretion?
8
9
10
(2) Relatedly, on what authority may the Court consider Plaintiffs’
allegations that Reclamation actually has exercised discretion over
contract implementation in practice?
11
12
13 Id. at 37.
14
1.
Interpretation of EPIC
15
While the Court has determined that EPIC controls disposition of the Fifth Claim for Relief, the
16 parties are not on the same page as to how EPIC should be applied. EPIC generically holds that “to
17 survive a Rule 12(b)(6) motion to dismiss, [a plaintiff] must allege facts to show that [the action agency]
18 retained sufficient discretionary involvement or control over [the permit or contract in question] to
19 implement measures that inure to the benefit of the [relevant species].” EPIC, 255 F.3d at 1080.
20 Plaintiffs point to numerous contract provisions and other aspects of law5 they claim grant to
21 Reclamation the discretion to take action to implement the SRS Contracts in ways that would benefit
22 winter-run and spring-run Chinook salmon and their habitats. Doc. 1048 at 1-10.
Federal Defendants advocate for a more narrow reading of EPIC, based in part on EPIC’s
23
24
25
5
See infra note 13 for a discussion of the “other aspects of law” cited by Plaintiffs.
22
1
application of Houston. As in the October 20, 2016 Order, in Houston, Reclamation was required to
2
consult under the ESA before renewing certain water contracts because in negotiations Reclamation had
3
the power to decrease the total supply of water granted in those contracts. EPIC, 255 F.3d at 1082
4
(citing Houston, 146 F.3d at 1125-16, internal quotations omitted). The Plaintiffs in EPIC argued that
5
Houston demonstrated that “existing contracts and permits that are in no way related to the ESA or do
6
not provide mechanisms to protect threatened and endangered species may require alteration if
7
necessary to comply with the ESA.” EPIC, 255 F.3d at 1082. The Ninth Circuit rejected this
8
interpretation of Houston, instead finding that Houston did not stand for the proposition that “once the
9
renewed contracts were executed, the agency had continuing discretion to amend them at any time to
6
10 address the needs of endangered or threatened species.” Id. Federal Defendants advocate for turning
11 this negative into an affirmative rule that would require allegations that the agency retained continuing
12 discretion to amend the renewed contracts to address the needs of endangered or threatened species. See
13 Doc. 1052 at 3-4. According to Federal Defendants, EPIC’s generic holding—that “to survive a Rule
14 12(b)(6) motion to dismiss, [a plaintiff] must allege facts to show that [the action agency] retained
15 sufficient discretionary involvement or control over [the permit or contract in question] to implement
16 measures that inure to the benefit of the [relevant species],” 255 F.3d at 1080—is further limited by the
17 more specific requirement that the type of discretion the action agency must retain under the
18 circumstances is discretion to modify the contracts themselves to benefit the species.
A close examination of how the EPIC court evaluated the terms of the ITP at issue in that case
19
20 suggests Federal Defendants are correct. EPIC focused on examining the ITP to determine whether the
21 action agency retained discretionary control to modify or add to the ITP’s terms by: “mak[ing] new
22
23
24
25
6
The Court relied on the reasoning of Houston to find that NRDC v. Jewell is not the law of the case with respect to
Plaintiff’s Fifth Claim for Relief because “NRDC v. Jewell’s holding that Reclamation has discretion in the renewal process
to alter the timing of water distribution and the pricing scheme related to contracted-for water does not necessarily mean that
Reclamation retained similar discretion in the executed contracts (or otherwise possesses similar discretion pursuant to law)
that would permit revisions to the executed contracts.” October 20, 2016 Order at 33 (emphasis in original).
23
1
requirements to protect species that subsequently might be listed as endangered or threatened”;
2
“expand[ing] the conservation goals of the [ITP]”; and “demand[ing] additional measures to protect new
3
species.” Id. at 1081-82 (emphasis added).7 See Nat'l Wildlife Fed'n v. Fed. Emergency Mgmt. Agency,
4
345 F. Supp. 2d 1151, 1170 (W.D. Wash. 2004) (emphasizing that EPIC involved a completed contract
5
between the agency and a private entity and interpreting EPIC as holding that FWS did not “‘retain
6
discretionary control [under the permit] to make new requirements to protect’ the marbled murrelet or
7
the coho salmon . . . or impose new requirements on the company” (quoting EPIC, 255 F.3d at 1081-
8
83)). In other words, in order to trigger the requirement for re-consultation under EPIC and 50 C.F.R. §
9
402.16 in the context of an executed and otherwise valid contract, the action agency must have retained
10 sufficient discretion in that contract to permit material revisions to it that might benefit the listed species
11 in question.
This interpretation harmonizes EPIC with its discussion of Houston. As mentioned above, EPIC
12
13 found that even though the statutory mandate to negotiate the contracts at issue in Houston on mutually
14 agreeable terms created sufficient discretion to require consultation prior to contract execution, nothing
15 suggested that “once the renewed contracts were executed, the agency had continuing discretion to
16 amend them at any time to address the needs of endangered or threatened species.” 255 F.3d at 1082.
17 This was a direct repudiation of the Houston plaintiffs’ argument that “existing contracts and permits
18 that are in no way related to the ESA or do not provide mechanisms to protect threatened and
19
20
21
22
23
24
7
Some language in EPIC suggests that the Ninth Circuit was looking more generically at “the scope of [the action agency’s]
authority to implement measures to benefit species other than the” species that was the focus of the ITP, and whether the ITP
gave the action agency “the power ... to act to benefit” the species. Id. at 1081 (emphasis added). But, a close examination of
surrounding language suggests otherwise. The following paragraph from EPIC provides a helpful example:
EPIC also argues that other provisions of the HCP and IA authorize the FWS to require protection for species other
than owls. The provisions to which EPIC refers identify thresholds for the owl population that trigger plan
modifications and corrective measures, and establish a contingency plan when thresholds are exceeded or
unforeseen events occur. The provisions also allow the FWS to review corrective action to eliminate plan
deficiencies, suspend the permit for significant violations or breaches of the permit, and incorporate revisions to the
HCP as necessary to ensure that the conservation goals of the HCP are met. None of these provisions addresses the
scope of the FWS's authority to implement measures to benefit species other than the spotted owl.
25 EPIC, 255 F.3d at 1081. The overall thrust of this paragraph suggests a search for authority to add requirements to the
contractual arrangement.
24
1
endangered species may require alteration if necessary to comply with the ESA.” Id. EPIC’s discussion
2
of Houston strongly suggests that in the context of a previously-executed contract, the type of discretion
3
EPIC demands is discretion to modify that contract. Put another way, the re-consultation regulation
4
requires as a pre-requisite “discretionary Federal involvement or control over the action.” 50 C.F.R. §
5
402.16. In light of EPIC’s discussion of Houston, the “action” in the present circumstances is contract
6
execution. Once executed, Reclamation would only retain discretion over contract execution if the
7
contract in question provided Reclamation authority to modify the contractual arrangement.
8
This interpretation also makes sense from a practical perspective. Imagine under the
9
circumstances of the present case that discretion to act on behalf of the species in question (without
10 discretion to modify the contracts) triggered a re-consultation that led to a jeopardy determination.
11 Imagine further that jeopardy could not be avoided simply through modifications to the way
12 Reclamation exercised the discretion it did possess (within the existing contractual arrangement) to act
13 on behalf of the species. Without any discretion to modify the contract, this would result in Reclamation
14 being required to invalidate an existing and otherwise valid Reclamation contract. In other words, this
15 would force Reclamation to breach the contract in question. This practical implication is particularly
16 meaningful in the present case because the SRS Contracts are crucial to Reclamation operating the CVP
8
17 in compliance with state law. This cannot be what Congress intended to be the result of the Section 7
18 consultation requirement, and the Court will not interpret the re-consultation regulation, 50 C.F.R. §
19 402.16’s, to produce such an absurd result.
Plaintiffs have pointed to no provision in the SRS Contracts, nor to any other authority, that
20
21
22
23
24
25
8
In portions of the district court decision in Nat. Res. Def. Council v. Kempthorne, not addressed on appellate review, the
previously-assigned district judge discussed the interplay between the SRS Contracts; Section 8 of the 1902 Reclamation Act,
which requires Reclamation to operate in compliance with state law, which in turn gives priority to prior appropriators such
as the SRS Contractors; and the CVPIA, which requires Reclamation to operate the CVP in compliance with state law and
the ESA. See 621 F. Supp. 2d at 989. That opinion concluded that the current SRS Contracts, which were renewed in part
based upon renewal provisions contained within the original SRS Contracts, continue to embody an agreement on “contract
quantities that must remain fixed on renewal unless a general stream adjudication occurs” and that this “facilitated the
continued operation of the CVP.” Id. at 1000.
25
1
suggests Reclamation has retained discretion to impose revisions to the executed contracts to address the
2
needs of the relevant listed species. Rather, as mentioned, Plaintiffs point to numerous provisions that
3
they allege provide discretion over contract implementation. None of the contractual provisions cited
4
satisfies EPIC.
5
2.
SRS Contract Background
6
Before evaluating each of the purported sources of contractual discretion highlighted by
7
Plaintiffs, it is helpful to review the SRS Contracts in a more general sense. Subject to the conditions in
8
each contract, an SRS Contractor is “authorized to divert from its Source of Supply at the locations
9
shown in Exhibit A, for beneficial use within the area delineated on Exhibit B . . . the Contract Total
10 designated in Exhibit A . . . in accordance with the monthly operating schedule” submitted by the SRS
11 Contractor. Glenn-Colusa Irrigation District Contract No. 14-06-200-855A-R-1 (“GCID Contract”), art.
12 3(a), located in the Supplemental Administrative Record (“SAR”) at 2695-2737. Before April 1 in each
13 Water Year, and as revisions are needed, each SRS Contractor submits a written schedule, “indicating
14 the Contract Total to be diverted by the Contractor during each month under this Settlement Contract.
15 The United States shall furnish water to the Contractor in accordance with the monthly operating
16 schedule or any revisions thereof.” Id. at art. 3(c), SAR 2705. The Contract Total is defined as the sum
17 of Base Supply and Project Water and is set forth in each Exhibit A. See, e.g., id. at art. 1(e) & Ex. A,
18 SAR 2700, SAR 2732. The Contract Total may be reduced only in a Critical Year, and then only by 25
19 percent. Id. at art. 5(a), SAR 2708. The Contractor in turn agrees to pay for Project Water as provided
20 for in Article 8 at “Rates and Charges established in accordance with: (i) the Secretary’s then current
21 rate setting policies for the Project; and (ii) applicable Reclamation law and associated rules and
22 regulations, or policies.” Id. at art. 8(a). SAR 2709-10.
23
3.
24
Article 3(i) of the SRS Contracts provides:
25
Article 3(i)
[I]f there is a shortage of Project Water because of actions taken by the
26
1
2
Contracting Officer to meet legal obligations then . . . no liability shall
accrue against the United States of any of its officers, agents, or
employees for any damage direct or indirect, arising therefrom.
3
Id. at art. 3(i), SAR 2707. Plaintiffs argue that this provision allows Reclamation to reduce the diversion
4
of project water by SRS Contractors in order “to meet legal obligations.” Doc. 1048 at 3. Citing the
5
2009 NMFS Salmonid OCAP BiOp as an example of a relevant legal obligation, Plaintiffs argue that
6
under Article 3(i) Reclamation retains discretionary control and involvement that could benefit listed
7
species “affected by the diversions of project water.” Id. at 4.
8
9
Federal Defendants rejoin that discretion over project water is immaterial to Plaintiffs’ claims
because project water was not at issue during the complained-of releases in 2014 and 2015, which
10 consisted exclusively of base supply water. See Doc. 1052 at 7-8. As discussed above, under the
11 circumstances presented in this case, an agency is required to reinitiate consultation where two elements
12 are present: (1) “discretionary Federal involvement or control over the action has been retained or is
13 authorized by law”; and (2) “new information reveals effects of the action that may affect listed species
14 or critical habitat in a manner or to an extent not previously considered.” 50 C.F.R. § 402.16. According
15 to Federal Defendants’ position, to trigger reconsultation under § 402.16, the discretion retained must be
16 discretion that could allow Reclamation to modify a contract to address or ameliorate the exact “new
17 effects of the action” complained of. However, nothing in the regulation limits the reconsultation
18 obligation in this way. It is not beyond credulity to imagine ways that Reclamation could modify a
19 contract to mitigate harm caused by one aspect of SRS Contract implementation by exercising discretion
20 over other aspects of SRS Contract implementation.
21
More compelling are the SRS Contractors’ arguments regarding interpretation of Article 3(i).
22 The SRS Contractors maintain that Article 3(i) simply limits the federal government’s liability for
23 damages when there is a shortage of project water due to actions taken by Reclamation to comply with
24 legal obligations. This Court’s predecessor previously concluded that Article 3(i) is a “force majeure
25
27
1
clause”9 and that “because supplies of Project Water may only be reduced when Project Water is
2
necessary to meet legal obligations, this does not create a level of discretion in the Contracting Officer
3
or the Bureau that satisfies” the standard set forth in Home Builders, 551 U.S. at 673. Nat. Res. Def.
4
Council v. Kempthorne, No. 1:05-CV-01207-OWW-SMS, 2009 WL 2849626, at *2 (E.D. Cal. Sept. 1,
5
2009), rev'd on other grounds sub nom. Nat. Res. Def. Council v. Jewell, 749 F.3d 776 (9th Cir. 2014).
6
In Home Builders, the Supreme Court deferred to a regulatory interpretation of Section 7’s consultation
7
and no-jeopardy requirements as applying only to “actions in which there is discretionary Federal
8
involvement or control,” 551 U.S. at 673 (quoting 50 C.F.R. § 402.03), and found that actions that are
9
legally mandated do not qualify as such. Id. This Court’s previous interpretation of Article 3(i) as not
10 constituting “discretionary Federal involvement or control” for purposes of 50 CFR § 402.03 was not
11 called into question by the Ninth Circuit’s en banc opinion in this case. The Court sees no reason why
12 the force majeure language in Article 3(i) would any more qualify as “discretionary Federal involvement
10
13 or control” in the context of 50 C.F.R. § 402.16(b).
14
4.
Article 29(a) & (e)
15
Plaintiffs next point to Article 29(a) and (e) as sources of the necessary discretion. Article 29(a)
16 provides:
Prior to the diversion of Project Water, the Contractor shall be
implementing an effective water conservation and efficiency program
based on the Basin-Wide Water Management Plan and/or Contractor’s
water conservation plan that has been determined by the Contracting
17
18
19
20
21
22
23
24
25
9
A force majeure clause is “[a] contractual provision allocating the risk of loss if performance becomes impossible or
impracticable, esp. as a result of an event or effect that the parties could not have anticipated or controlled. Force-majeure
clause, Blacks Law Dictionary 718 (9th ed. 2009).
10
Plaintiffs point out that Federal Defendants previously acknowledged that Article 3(i) allows Reclamation to reduce
project water diversions “‘to meet a legal obligation, such as compliance with the ESA.’” Doc. 1048 at 3 (citing Doc. 1048-2,
Federal Defendant’s Appellate Brief, at 49). Plaintiffs argue that in light of this admission Federal Defendants “cannot now
assert” they have no discretion to take action to benefit the winter-run and spring-run Chinook. To the extent Plaintiffs are
arguing Federal Defendants are judicially estopped from asserting a contrary position at this stage of the litigation, the Ninth
Circuit has “restricted the application of judicial estoppel to cases where the court relied on, or accepted, the party’s previous
inconsistent position.” Hamilton v. State Farm Fire & Cas. Co., 270 F.3d 778, 783 (9th Cir. 2001). Here, among other things,
there is no inconsistency. To the extent Federal Defendants have admitted anything, it is that Article 3(i) is a force majeure
clause. As discussed, this is not the same thing as admitting the existence of discretion over water deliveries.
28
1
2
3
4
Officer to meet the conservation and efficiency criteria for evaluating
water conservation plans established under Federal law. The water
conservation and efficiency program shall contain definite water
conservation objectives, appropriate economically feasible water
conservation measures, and time schedules for meeting those objectives.
Continued diversion of Project Water pursuant to this Settlement Contract
shall be contingent upon the Settlement Contractor’s continued
implementation of such water conservation program.
5
6
GCID Contract, art. 29(a), SAR 2727. Plaintiffs argue that this provides Reclamation with ongoing
7
discretion to determine whether the contractors’ programs “meet the conservation and efficiency criteria
8
for evaluating water conservation plans established under Federal Law.” See Doc. 1048 at 4. The SRS
9
Contractors correctly point out, however, that nothing in Article 29(a) permits Reclamation to reject a
10 water conservation plan that meets the “conservation and efficiency criteria for evaluating water
11 conservation plans established under Federal law.” Doc. 1054 at 8. Although no party has addressed
12 specifically the nature of the “conservation and efficiency criteria” utilized by Reclamation, the Court
13 presumes this is a reference to the criteria developed by Reclamation to meet the requirements of the
14 CVPIA and the Reclamation Reform Act of 1982, which are released for public comment and
15 periodically updated. See, e.g., Central Valley Project Improvement Act Water Management Plans, 79
16 Fed. Reg. 65,989-01 (Nov. 6, 2014); Central Valley Project Improvement Act, Regional Criteria For
17 Evaluating the Water Management Plan for the Sacramento River Contractors, 69 Fed. Reg. 4,317-01
18 (Jan. 29, 2004) (describing “Regional Criteria for the Sacramento Valley [developed as] an alternative
19 pilot program to the current Standard Criteria”). Plaintiffs do not challenge the nature of the applicable
20 criteria, the method of their promulgation, or suggest that Reclamation has authority to modify the
21 criteria in the context of Settlement Contract renewal. The existence of relevant criteria promulgated
22 through a separate process suggests application of Article 29(a) is nondiscretionary. See Alaska
23 Wilderness League v. Jewell, 788 F.3d 1212, 1225 (9th Cir. 2015) (finding no discretionary federal
24 involvement or control where agency charged with determining whether enumerated statutory criteria
25 have been achieved).
29
1
Article 29(e) states that: “In order to provide incentives for water conservation, the Contractor
2
may reduce the amount of Project Water for which payment is required under Article 8(a).” Plaintiffs
3
interpret this language as granting to Reclamation discretion to “provide financial incentives to SRS
4
Contractors to encourage water conservation.” Doc. 1048 at 4. But, the plain language of Article 29(e)
5
reveals a different arrangement. Application of Article 29(e) is triggered by an SRS Contractor filing an
6
“offer to reduce Project Water use,” which Reclamation may accept or decline. Only if Reclamation
7
accepts the SRS Contractor’s offer can project water deliveries be reduced and the SRS Contractor’s
8
obligation to pay for the water waived or reduced. Article 29(e)(1)&(2). Although there may be some
9
discretion involved in Reclamation’s decision whether or not to accept the offer, it defies logic to
10 conclude that this is the type of “discretionary Federal involvement or control” envisioned by 50 C.F.R.
11 § 402.16, because Reclamation would only have the opportunity to reduce project water deliveries if the
12 SRS Contractor voluntarily offered to do so. Even in the presence of “new information reveal[ing]
13 effects of the action that may affect listed species or critical habitat in a manner or to an extent not
14 previously considered,” 50 C.F.R. § 402.16(b), Reclamation would be powerless to modify the action in
15 any way under Article 29(e) unless the SRS Contractors agreed in advance to do so and nothing in
16 Article 29(e) provides Reclamation discretion to add to or modify terms in the Settlement Contracts.
17
5.
Article 1(d) & (o)
18
Article 1 defines terms used elsewhere in the SRS Contracts. Article 1(d) defines the term
19 “Charges” to mean “payments for project water that the Contractor is required to pay to the United
20 States in addition to the ‘Rates’ specified in [the] Settlement Contract.” GCID Contract, art. 1(d), SAR
21 2700.11 This definition further provides that Reclamation “will, on an annual basis, determine the extent
22 of . . . Charges” imposed for project water. Id. “The type and amount of each Charge shall be specified
23
24
25
11
The numbering, but not the text, of the provisions discussed in this section is different within the Anderson Cottonwood
Irrigation District (“ACID”) Contract. For example, “Charges” is defined in Article 1(c) in the ACID Contract. See SAR
0050. Hereinafter, the Court will reference only the GCID contract numbering scheme where the text is materially
indistinguishable.
30
1
in Exhibit D.” Id.
2
Article 1(o) defines the term “Rates” to mean “the payments for Project Water determined
3
annually by the Contracting Officer in accordance with then current applicable water ratesetting policies
4
for the Project, as described in subdivision (a) of Article 8.” GCID Contract, art. 1(o), SAR 2702.
5
Article 8(a), in turn, requires Reclamation to set Project Water Rates in accordance with the Secretary of
6
the Interior’s rate setting policies for the CVP, and applicable Reclamation law and associated rules and
7
regulations. Id., art. 8(a)(2), SAR 2710. Rates set under those policies must be established to recover
8
“only reimbursable operation and maintenance . . . and capital costs of the Project.” Id., art. 8(g), SAR
9
2712. Plaintiffs suggest that Articles 1(d) and (o) give Reclamation “ongoing discretion to increase the
10 price of project water—a measure that could encourage reduced diversions of project water.” Doc. 1048
11 at 5.
To the extent Plaintiffs suggest Reclamation has discretion regarding the setting of “Rates,” the
12
13 contract and applicable legal framework indicate otherwise. As mentioned, Article 1(o) defines the term
14 “Rates” to mean “the payments for Project Water determined annually by the Contracting Officer in
15 accordance with then current applicable water ratesetting policies for the Project, as described in
16 subdivision (a) of Article 8.” GCID Contract, art. 1(o), SAR 2702. Article 8(a) requires Reclamation to
17 set Project Water Rates and Charges in accordance with the Secretary of the Interior’s rate setting
18 policies for the CVP, and applicable Reclamation law and associated rules and regulations. Id., art.
19 8(a)(2), SAR 2710. Furthermore, Rates set under those policies must be established to recover “only
20 reimbursable operation and maintenance . . . and capital costs of the Project.” Id., art. 8(a)(2), SAR
21 2712. Again, these parameters substantially constrain any discretion Reclamation may have over rate12
22 setting, rendering Reclamation incapable of setting rates in a manner that would aid listed species.
23
24
25
12
Plaintiffs point out that the Ninth Circuit, in the context of assessing the extent of Reclamation’s discretion over SRS
Contract renewal, concluded that Reclamation retained sufficient discretion during contract negotiations and execution to
revise “the contracts’ pricing scheme” in ways that could benefit the listed species. See Jewell, 749 F.3d at 783-84; accord
NRDC v. Houston, 146 F.3d 1118, 1126 (9th Cir. 1998) (authority to set project rates during contract negotiations is source of
31
1
More specifically, these provisions do not afford Reclamation any authority to revise the Settlement
2
Contracts to impose a different Rate structure.
3
With respect to Charges, Article 1(d) defines “Charges” as “payments for project water that the
4
Contractor is required to pay to the United States in addition to the ‘Rates’ specified in [the] Settlement
5
Contract.” GCID Contract, art. 1(d), SAR 2700 (emphasis added). At first glance, this definition is
6
ambiguous as to whether the Charges may include only those the Contractor “is required to pay” as a
7
result of some extra-contractual requirement (e.g., a statutory obligation), or whether Reclamation can
8
require the Contractor to pay additional “Charges,” to be set by Reclamation at its discretion. When
9
viewed in context, however, Article 1(d) is not ambiguous. As with Rates, Charges must be set in
10 accordance with the Secretary of the Interior’s rate setting policies for the CVP, and applicable
11 Reclamation law and associated rules and regulations. Id., art. 8(a)(2), SAR 2710. The only example of a
12 Charge in the record stems from applicable Reclamation law: a per acre-foot charge for Restoration
13 Payments pursuant to § 3407 of the Central Valley Project Improvement Act, Pub. L. No. 102-575, 105
14 Stat. 4600, 4726-28 (1992) (“CVPIA”). SAR 0087. As the SRS Contractors point out, under CVPIA §
15 3407, Restoration Payments must be assessed in “an amount that can be reasonably expected to equal
16 the amount appropriated each year.” CVPIA § 3407(c)(2). Restoration Fund payments are limited by
17 statute to $50 million per year, CVPIA 3407(b), and to the extent Reclamation has any discretion
18 regarding the amount appropriated, the statute requires total collections to equal $50 million per year on
19 a three-year rolling average basis. CVPIA 3407(c)(2). CVPIA § 3407 does not afford Reclamation
20 discretion to adjust the Restoration Payment Charge in any significant or relevant way. Nor has any
21 party identified any other provision of Reclamation law or associated rules and regulations that affords
22 Reclamation any discretion to add additional Charges.
23
discretion). These cases stand for the proposition that Reclamation may be able to negotiate pricing structures that permit
24 rates to take into account additional interests (i.e., interests other than recoupment of operation, maintenance and capital
25
costs) and/or charges other than those mandated by law. However, these cases are not dispositive of whether Reclamation
retained discretion over the pricing scheme in the executed SRS Contracts sufficient to permit rate changes that would benefit
the listed species.
32
1
6.
Articles 8(h) and 8(i)
2
Plaintiffs further argue that pursuant to Article 8(h) and (i), Reclamation retains the discretion to
3
make determinations regarding a contractors’ ability to pay and to adjust rates and charges based on
4
those determinations. Doc. 1048 at 5.
5
Article 8(h) allows Reclamation to adjust Rates to “reflect the changed costs of delivery (if any)
6
of [] transferred, exchanged, or otherwise disposed of Project Water to the transferee’s point of delivery
7
in accordance with the then-current ratesetting policies for the Project.” GCID Contract, art. 8(h), SAR
8
2713. Given that any discretion afforded Reclamation by this provision is tied to the “costs of delivery,”
9
the Court cannot conclude that this language grants to Reclamation any discretion to act on behalf of
10 listed species, let alone any discretion to modify contract terms or add protections for the listed species.
11
Likewise, Article 8(h) indicates Reclamation may impose “lower Rates and Charges because of
12 inability to pay.” Id. Article 8(i) provides that “Pursuant to the Act of October 27, 1986 (100 Stat. 3050),
13 [Reclamation] is authorized to adjust determinations of ability to pay every five years.” GCID Contract,
14 art. 8(i), SAR 2713. However, Plaintiffs do not explain and the Court cannot imagine how the power to
15 adjust rates downward to reflect inability to pay could possibly constitute discretion that could inure to
16 the benefit of listed species, let alone any discretion to modify contract terms to increase protections for
17 the listed species.
18
7.
Article 3(e)
19
Article 3(e) provides that, during the contract term, Reclamation must approve any “sale,
20 transfer, exchange, or other disposal of any of the Contract Total ... or the right to the use thereof for use
21 on land other than” for uses designated in the contract. GCID Contract, art. 3(e), SAR 2706. The
22 “Contract Total” refers to all water made available to the contractor for diversion under the contract. See
23 id., art. 1(e), SAR 2700. Plaintiffs argue that “[t]o the extent Reclamation rejects a transfer of water by
24 the contractors or conditions the transfer on protections for listed salmon, the discretion could inure to
25 the benefit of listed species.” Doc. 1048 at 6. This argument fails for the same reason articluated in the
33
1
analysis of Article 29(e): it does not provide the type of “discretionary Federal involvement or control”
2
envisioned by 50 C.F.R. § 402.16 and EPIC. Even assuming Reclamation’s rejection of a proposed
3
water transfer would inure to the benefit of the species (as opposed to just encouraging the SRS
4
Contractor to use the water itself), Reclamation would only have the opportunity to reject a water
5
transfer if the SRS Contractor proposed making one. If re-consultation could be triggered in the presence
6
of conditional discretion, there would be no limit to the reach of 50 C.F.R. § 402.16. Taking Plaintiffs’
7
position to its logical extreme, re-consultation might be triggered under EIPC and 50 C.F.R. § 402.16
8
simply by the ever-present possibility that an SRS Contractor might willingly agree to re-negotiate its
9
own contract, which would trigger Reclamation’s “discretion” to accept or reject any newly offered
10 terms.
11
8.
Article 30(b) & Article 7(b)
12
Article 30(b) of the SRS contracts grants Reclamation the “right to make determinations
13 necessary to administer [the] Settlement Contract[s] that are consistent with the provisions of [the
14 contracts], the laws of the United States and of the State of California, and the rules and regulations
15 promulgated by the Secretary of the Interior.” GCID Contract, art. 30(b), SAR 2730. Plaintiffs argue that
16 this provision requires Reclamation to administer the contracts in compliance with not only the contracts
17 themselves but with existing environmental and other legal requirements. Doc. 1048 at 7. But this
18 entirely begs the question of whether any such administrative determinations would involve the exercise
19 of discretion.13 Article 30(b) does not, on its own, reveal the existence of any relevant discretion.
Plaintiffs also maintain that this interpretation of Article 30(b) is supported by the text of Article
20
21
22
23
24
25
13
Plaintiffs make no attempt to explain how the various provisions of federal and state law they point to, including the ESA
and California State Water Resources Control Board Decisions and orders, see Doc. 1048 at 8, provide Reclamation with any
discretion to act on behalf of the relevant listed species in the context of the SRS Contracts. As the Supreme Court made
abundantly clear in Home Builders, an agency’s action to fulfill mandatory legal obligations is not discretionary for purposes
of 50 C.F.R. § 402.03. Home Builders, 551 U.S. at 667 (“[W]hen an agency is required to do something by statute, it simply
lacks the power to “insure” that such action will not jeopardize endangered species.”). Plaintiffs further argue that
“Reclamation’s discretionary action to seek exemptions from state law requirements in recent years has caused severe harm
to listed salmonids,” but fail to explain how the existence and/or exercise of any such discretion would translate into the form
of discretion required to trigger re-consultation under EPIC.
34
1
7(b), which provides that the SRS Contractors must “comply with requirements applicable to the
2
Contractor in biological opinion(s) prepared as a result of a consultation regarding the execution of [the
3
Contractor’s respective SRS] Contract pursuant to Section 7 . . . that are within the Contractor’s legal
4
authority to implement.” GCID Contract, art. 7(b), SAR 2709. The Court declines to engage in a
5
discussion of what this provision might mean for the SRS Contractors, but it plainly does not imbue
6
Reclamation with any discretion not otherwise retained in the SRS Contracts.
7
9.
8
Plaintiffs next point to Article 9(a) of the SRS contracts, which provides:
9
10
11
12
Article 9(a) & Beneficial Use
During the term of this Settlement Contract and any renewals thereof [] it
shall constitute full agreement as between the United States and the
Contractor as to the quantities of water and the allocation thereof between
Base Supply and Project water which may be diverted by the Contractor
from its Source of Supply for beneficial use on the land shown on Exhibit
B from April 1 through October 31, which said diversion, use, and
allocation shall not be disturbed so long as the Contractor shall fulfill all
of its obligations hereunder.
13
GCID Contract, art. 9(a), SAR 2714-15 (emphasis added).
14
Plaintiffs point out, correctly, that beneficial use is an evolving and dynamic requirement of
15
federal and state law. See Joslin v. Marin Mun. Water Dist., 67 Cal. 2d 132, 140 (1967) (While “what is
16
a reasonable use of water depends on the circumstances of each case, such an inquiry cannot be resolved
17
in vacuo isolated from statewide considerations of transcendent importance.”). Section 8 of the
18
Reclamation Act of 1902 requires that all water provided pursuant to the Act be put to “beneficial use,”
19
as defined by state law. 43 U.S.C. §§ 372, 383; California v. United States, 438 U.S. 645, 665-67
20
(1978); see also City of Barstow v. Mojave Water Agency, 23 Cal. 4th 1224, 1242 (2000) (holding that
21
Article X, § 2 of the California Constitution “dictates the basic principles defining water rights: that no
22
one can have a protectible interest in the unreasonable use of water, and that holders of water rights must
23
use water reasonably and beneficially”); United States v. Alpine Land & Reservoir Co., 697 F.2d 851,
24
854- 55 (9th Cir. 1983) (assessment of beneficial use requires consideration of “alternative uses of the
25
35
1
water” which is “variable according to conditions” and “therefore over time”). Plaintiffs cite as an
2
example, the State Water Resources Control Board’s recent exercise of its authority to curtail diversions
3
under otherwise lawful water rights to provide minimum in-stream flows to protect salmon habitat. See
4
Declaration of Kate Poole (“Poole Decl.”), Ex. H (Res. No. 2014-0023), Doc. 1048-9 at 6.
5
Plaintiffs argue that “[g]iven the beneficial use requirement, Article 9(a) must be interpreted not
6
as freezing the water quantities and allocations provided in the SRS contracts, but as allowing changes
7
in those quantities and allocations in light of current conditions and competing uses for the water.” Doc.
8
1048 at 10. Plaintiffs further argue that “[t]he SRS contracts’ express incorporation of the beneficial use
9
standard in Article 9(a), together with Article 30(b), provides a continuing basis for Reclamation to
10 assess whether the contracts are being administered consistent with these federal and state law
11 standards.” Id.
12
There is no support for Plaintiffs’ interpretation of Article 9(a). Even assuming that Reclamation
13 has the authority to determine whether a particular use is beneficial, nothing in the plain language of
14 Article 9(a) suggests Reclamation may adjust contract quantities based on a beneficial use determination
15 made after contract execution. To the contrary, the plain language of Article 9(a) indicates the SRS
16 Contracts “constitute full agreement . . . as to the quantities of water and the allocation thereof between
17 Base Supply and Project water” and that the “allocation shall not be disturbed so long as the Contractor
18 shall fulfill all of its obligations” under the SRS Contract. (Emphasis added.) This language cannot
19 support Plaintiffs’ theory that Reclamation retains discretion to modify SRS Contract quantities (or
20 deliveries under an existing SRS Contract) upon determining that additional water is needed to protect
21 in-stream beneficial uses.
22
10.
23
Article 1(f) defines the term “Critical Year” to mean, in pertinent part:
24
25
Article 1(f)
[A]ny Year in which either of the following eventualities exists:
(1) The forecasted full natural inflow to Shasta Lake for the current
36
Water Year, as such forecast is made by the United States on or before
February 15 and reviewed as frequently thereafter as conditions and
information warrant, is equal to or less than 3.2 million acre-feet; or
1
2
(2) The total accumulated actual deficiencies below 4 million acrefeet in the immediately prior Water Year or series of successive prior
Water Years each of which had inflows of less than 4 million acre-feet,
together with the forecasted deficiency for the current Water Year, exceed
800,000 acre-feet.
3
4
5
6
GCID Contract, art. 1(f), SAR 2700. “In a Critical Year, the Contractor’s Base Supply and Project
7
Water . . . shall be reduced by 25 percent.” GCID Contract, art. 5(a), SAR 2708.
According to Plaintiffs, “Reclamation is responsible for selecting the forecast and has discretion
8
9
to choose which forecast will be used.” Doc. 1048 at 10 (citing GCID Contract, art. 1(f)). Plaintiffs
10 further maintain that this discretion can be exercised in a manner to benefit listed species and provides
11 the following example:
Reclamation currently uses a conservative 90% exceedance forecast,
which helps “protect the cold water pool in Shasta Reservoir so that
suitable spawning habitat can be maintained in the Sacramento River
during the summer and fall seasons for” winter-run and spring-run
Chinook.
12
13
14
15 Doc. 1048 at 10 (citing Poole Decl. Ex. I (2/20/14 NMFS Letter to Reclamation), Doc. 1049-10 at 1).
16 However, the SRS Contractors correctly point out that the 2009 NMFS OCAP Salmonid BiOp requires
17 Reclamation to use the 90% exceedance forecast. Declaration of Meredith Nikkel (“Nikkel Decl.”), Ex.
14
18 A at 597-600, Doc. 1031-5. Accordingly, Reclamation does not have any discretion to choose another
19 forecasting method. The SRS Contractors further point out that Article 1(f)(1) requires Reclamation to
20 review its forecast “as frequently thereafter as conditions and information warrant.” Given this language,
21 even if Reclamation had discretion to select a forecast that might be more likely to trigger a Critical
22 Year determination, any such forecast would have to be revised as real data became available and
23
14
The court may take judicial notice of the 2009 NMFS Salmonid OCAP BiOp “for the purpose of determining what
24 statements are contained therein, not to prove the truth of the contents or any party’s assertion of what the contents mean.”
25
United States v. S. Cal. Edison Co., 300 F. Supp. 2d 964, 975 (E.D. Cal. 2004). Here, the Court simply relies upon this
document to demonstrate what it facially requires.
37
1
therefore Reclamation’s purported discretion would not have any practical import to listed species.15
Article 10(a) in the GCID Contract16
2
11.
3
Finally, Plaintiffs point to Article 10(a) in the GCID Contract as a source of Reclamation’s
4
“discretionary involvement or control” over contract implementation. This Article provides in pertinent
5
part:
All water diverted by the Contractor from its Source of Supply will be
diverted at the existing point or points of diversion shown on Exhibit A or
at such other points as may be mutually agreed upon in writing by the
Contracting Officer and the Contractor; Provided that in any Year the
United States reserves the right to require that the Contractor shall divert
all of its Contract Total, or any portion thereof, from either the
Sacramento River or Stony Creek or from each stream in the quantities
specified by the Contracting Officer but only if the quantities so specified
to be diverted from Stony Creek are available for such diversion. This
proviso shall not be construed to deny the Contractor its right to divert its
Contract Total nor the right to divert from the Sacramento River sufficient
water to meet its minimum requirements north of Stony Creek. Any time
during the period April through October of any Year that the Contracting
Officer requires the Contractor to take water from the Sacramento River
that it would otherwise be entitled to divert from Stony Creek under its
rights thereto adjudicated in the Angle Decree, the Contractor authorizes
the United States to divert, store, or use such Stony Creek water. The
Contractor also authorizes the diversion, storage, or use of Stony Creek
water by the United States prior to April l of any Year to the extent of the
Contractor's rights under the Angle Decree. In the event of such diversion,
storage, or use prior to April 1, the United States will furnish and the
Contractor may divert a quantity of water from the Sacramento River
equivalent to the quantity of such Stony Creek water so diverted, stored, or
used by the United States. Notwithstanding the other provisions of this
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
15
In at least one communication in the record between the SRS Contractors and Reclamation, the Settlement Contractors
conceded that “there is some discretion to be exercised in forecasting” a Critical Year under the SRS contracts. See Doc. 96623 (2/21/14 Letter from SRS Contractors to Reclamation) at 1. But this communication does not detail the nature or source of
the “some discretion” it references. Nor would these communications bar the SRS Contractors from now denying that
sufficient discretion exists to trigger 50 C.F.R. § 402.16 and EPIC. Judicial estoppel does not apply to assertions in that letter
because, among other things, the assertion was not presented to the Court. Hamilton, 270 F.3d at 783 (judicial estoppel
applies only “where the court relied on, or accepted, the party’s previous inconsistent position”).
16
Plaintiffs also cite Article 10(a) of the ACID Contract, which provides that “[a]ll water diverted by the Contractor from the
23 Sacramento River will be diverted at existing point or points of diversion show on Exhibit A or at such other points as may
be mutually agreed upon in writing by the Contracting Officer and the Contractor.” SAR 0069. However, Plaintiffs fail to
24 explain how this language retains for Reclamation any relevant discretion. As discussed above, retaining the power to make
25
changes to a contractual arrangement by mutual agreement does not amount to discretion to do so unilaterally. Absent
unilateral discretion, the Court fails to see how “discretion” to accept an offered change could amount to discretion that could
inure to the benefit of salmonids in the manner intended by EPIC and 50 C.F.R. § 402.16.
38
subdivision, the Contractor reserves the right to divert water from Stony
Creek to the extent of its entitlements under the Angle Decree, for periods
not to exceed 5 consecutive days, whenever its Sacramento River pumps
are temporarily unable to meet its diversion requirements because said
pumps are partially or wholly inoperable due to an emergency or an
unforeseeable cause.
1
2
3
4
GCID Contract, art. 10(a), SAR 2717 (italics added).
5
Plaintiffs argue that Reclamation could utilize the emphasized proviso, which permits
6
7
Reclamation to require GCID to divert “all of its Contract Total, or any portion thereof, from either the
Sacramento River or Stony Creek,” to benefit listed salmon by, for example, requiring GCID to divert
8
some or all of its April and May base supply of 240,000 acre-feet from Stony Creek, reducing the need
9
to release those flows from Shasta Reservoir and preserving cold water for later in the season for
10
salmon’s needs.” Doc. 1048 at 11.
11
As a threshold matter, Plaintiffs’ assertion of the volume of water potentially subject to diversion
12
from Stony Creek is off by an order of magnitude. Article 1(q) of the GCID Contract defines the
13
14
15
16
17
“Source of Supply” as “Sacramento River and Stony Creek, from which the Contractor has rights to
divert, has diverted, and may continue to divert.” SAR 2702. GCID’s right to divert from Stony Creek is
in turn limited by the “Angle Decree,” a “judgment rendered January 13, 1930, by the United States
District Court, Northern District of California . . . entitled ‘The United States of America, Plaintiff v.
H.C. Angle et al., Defendants.’” GCID Contract, art. 1(a), SAR 2699; see also Art. 10(a) (explaining
18
that Contracting Officer may require that GCID divert water from the Sacramento River it otherwise
19
would be entitled to take from Stony Creek pursuant to the Angle Decree). The Angle Decree itself,
20
which is part of the administrative record in this case, in turn states that GCID’s diversion from Stony
21
Creek is limited to 20,315 AF annually, at a rate of diversion not to exceed 500 cubic feet per second.
22
SC 03986 (available at Doc. 801-4 & 801-5)17. GCID’s diversion is also limited to the point and method
23
24
25
17
It is appropriate to consider the content of the Angle Decree in the context of this motion to dismiss in accordance with the
incorporation by reference doctrine. The terms of the Settlement Contracts themselves may be considered incorporated into
the 4SC by reference. United States v. Ritchie, 342 F.3d 903, 908 (9th Cir. 2003) (“Even if a document is not attached to a
39
1
of diversion on Stony Creek identified in the Angle Decree: where Stony Creek intersects the GCID
2
Main Canal by “closing of the lower or easterly embankment of [GCID’s] main canal where it crosses
3
Stony Creek . . . thereby damming said flow and diverting same into its said main canal.”18 SC 3985.
Federal Defendants and the SRS Contractors point out that in 1997, a siphon was constructed as
4
5
part of the Bureau of Reclamation’s Refuge Water Supply Project. The siphon was designed to
6
“preclude the need for the annual installation of a temporary dam in Stony Creek during the irrigation
7
season.” Final Environmental Assessment/Initial Study for the Conveyance of Refuge Water Supply
8
Project West Sacramento Valley Study Area, at IV-2, Doc. 1060-1; see also id. at IV-20 (Stony Creek
9
siphon would “allow for stabilization and enhancement of riparian vegetation in the area now seasonally
10 impacted by the temporary dam, and may improve fish passage and rearing habitat, in addition to
11 allowing for year-round flows from Stony Creek to the Sacramento River.”). Plaintiffs do not dispute the
12 existence and location of the siphon, but nonetheless maintain that Reclamation could order GCID to
19
13 once again make direct diversions from Stony Creek into the GCID canal via a berm. For example,
14 Plaintiffs suggest Defendants could require GCID to remove or alter the siphon to allow direct
15 diversions. See Doc. 1061 at 2 (“[T]here is no evidence that Defendants are prohibited over the
16 contract’s 40-year term from removing or altering the siphon to allow direct diversions. Indeed, the fact
17
complaint, it may be incorporated by reference into a complaint if the plaintiff refers extensively to the document or the
18 document forms the basis of the plaintiff's claim.”). In turn, language in the GCID Settlement Contract unambiguously
incorporates into itself the extent of GCID’s entitlements under the Angle Decree. For example, in Article 10(a) “the
19 Contractor reserves the right to divert water from Stony Creek to the extent of its entitlements under the Angle Decree” under
20
21
22
23
24
25
certain circumstances. The “extent of [GCID’s] entitlements under the Angle Decree” are not specifically enumerated in the
GCID Contract, but the Angle Decree is formally cited in the Contract. Therefore, the Court believes it is appropriate to
consider GCID’s entitlements under the Angle Decree incorporated into the 4SC by reference as well.
18
Because the Angle Decree identifies a specific location and method of diversion, Plaintiffs’ suggestion that Reclamation
could require GCID to divert water indirectly via diversion points on Stony Creek controlled by other, nearby water districts,
see Doc. 1061 at 3-4, is without merit. Nothing in the GCID Settlement Contract gives (or could give) GCID the right to
divert water from Stony Creek in any volume or in any manner other than defined in the Angle Decree.
19
The Court takes judicial notice of the existence of the siphon, as the existence and location of the siphon are not subject to
reasonable dispute. See Cal. State Grange v. Nat’l Marine Fisheries Serv., 620 F. Supp. 2d 1111, 1197 (E.D. Cal. 2008)
(taking judicial notice of the geographic proximity of two fish hatcheries to two dams because it was “a matter not subject to
reasonable dispute”); San Luis & Delta-Mendota Water Auth. v. Jewell, 969 F. Supp. 2d 1211 (E.D. Cal. 2013) (taking
judicial notice of the locations of reservoirs, dams, Indian reservations, and the confluence of rivers relative to those Indian
reservations based on a map that was inadvertently not admitted into evidence).
40
1
that Defendants retained authority to [order GCID to] divert from Stony Creek in the contract which was
2
executed several years after the siphon was constructed, demonstrates Defendants preserved the option
3
of [requiring] divers[sion] from Stony Creek, whether or not physical limitations on diversions currently
4
exist.”) (emphasis in original). The General Manager of GCID indicates that “GCID does not currently
5
have any diversion or temporary pumping facilities at the Stony Creek Siphon location to indirectly
6
divert water from Stony Creek into GCID’s Main Canal and distribution system,” but impliedly
7
acknowledges that diversion from Stony Creek into GCID’s Main Canal might nevertheless be possible
8
by indicating that “[i]nstallation and use of any new diversion or temporary pumping facilities at the
9
Stony Creek Siphon location would likely require a streambed alteration agreement approval by the
10 California Department of Fish and Wildlife, a permit from the U.S. Army Corps of Engineers for any
11 installation or channel work, and potentially other regulatory approvals and environmental review.”
12 Declaration of Thaddeus Bettner (“Bettner Decl.”), Doc. 1063-1 at ¶ 4. On the present record, the Court
13 can identify no provision of the GCID Contract or any principle of contract interpretation that would
14 preclude Reclamation from requiring GCID to once again use its permitted method of diversion.
However, even assuming (1) that GCID could once again make arrangements to divert directly
15
16 from Stony Creek into the GCID Main Canal via the method of diversion permitted by the Angle
17 Decree, and (2) the diversion of 20,315 AF from Stony Creek (as opposed to from the Sacramento
18 River) would make some material difference to salmonids, the fact that Article 10(a) appears to afford
19 Reclamation discretion to require GCID to do so still does not trigger the re-consultation requirement
20 under EPIC because this is still not a form of discretion that would allow Reclamation to amend the
20
21 GCID Contract to require additional protections for salmonids. In other words, the fact that
22
23
24
25
20
The Court notes that under the 2009 NMFS Salmonid OCAP BiOp, in dry years Reclamation is already required to
“conserve Shasta storage to the maximum extent possible, in order to increase the probability of maintaining cold water
supplies necessary for egg incubation for the following summer’s cohort of winter-run.” 2009 NMFS Salmonid OCAP BiOp
at 596. Re-consultation over GCID Contract implementation based on existing forms of discretion, absent discretion to
modify the Contract in other ways, would therefore be redundant. There would simply be no way for the consultation process
to produce any additional protections. This is yet another reason why the Court believes its interpretation of EPIC, discussed
41
1
Reclamation may have an opportunity to act on behalf of salmonids within the bounds of the existing
2
contractual arrangement does not trigger the re-consultation requirement under EPIC because the
3
contract’s terms offer no means by which Reclamation can modify the contractual arrangement.
4
For all the reasons set forth above, Plaintiffs’ Fifth Claim for Relief must be DISMISSED.
5
Plaintiffs have failed to plausibly allege that Reclamation retains “discretionary Federal involvement or
6
control” sufficient to trigger re-consultation under 50 C.F.R. § 402.16 and EPIC.
7
Despite the Court’s invitation to do so, Plaintiffs failed to provide any authority to support
8
consideration under EPIC’s framework of allegations of conduct (as opposed to contract provisions)
9
evidencing discretion. As an example of conduct evidencing discretion, Plaintiffs discuss
10 correspondence between the SRS Contractors and Reclamation in the late winter and spring of 2014 and
11 2015. A February 21, 2014 letter from the SRS Contractors to Reclamation objects to Reclamation’s
12 preliminary decision to allocate only 40% of the SRS Contract total that year. Declaration of Natalie
13 Wolder, Doc. 132-2, at 8. An April 2014 letter from Reclamation to the SRS Contractors indicated that
14 updated model supported provision of 75% of Contract supply “but only if the SRS contractors defer
15 diversions of Base Supply in April and May 2014 to later in the water year.” Id. at 13. Similarly, in April
16 2015, Reclamation informed the SRS Contractors that their 75% allocation for 2015 was “contingent”
17 on their agreement to five measures designed to improve temperature control and other factors relevant
18 to salmonid survival, including an alteration of the SRS Contractors’ diversion schedule. Id. at 26.
19 “Absent this rescheduling of your Base Supply, due to continued drought and hydrologic conditions this
20 Water Year, Reclamation cannot guarantee that conditions will allow for the diversion of 75% of
21 Contract Total. Id. at 27. Plaintiffs assert that “[e]ven though the SRS Contractors may have agreed to
22 these changes, [these letters] illustrate[] Reclamation’s discretion both to negotiate changes and to
23 provide less than a 75% allocation if the SRS Contractors did not agree to Reclamation’s conditions.”
24
25 above in Part V.A.1, is logical under the circumstances.
42
1
Pltf. Opp. at 11. The Court does not agree. As discussed in the context of the analysis of Article 29(e)
2
and Article 3(e), without more, the fact that Reclamation may attempt to renegotiate contractual terms
3
does not constitute “discretion.” Moreover, nothing in these letters suggests Reclamation would be
4
exercising “discretion” of any kind if it ultimately had to deliver less than 75% of Contract Total to SRS
5
Contractors due to hydrologic conditions. See GCID Contract at art. 3(h)(4), SAR 2707 (United States
6
“assumes no responsibility for . . . nor . . . shall have any liability for or on a account of . . . [a]ny
7
damage whether direct or indirect arising out of or in any manner caused by a shortage of water whether
8
such shortage be on account of errors in operation, drought, or unavoidable causes.”).
9
In light of the findings articulated above and in the interest of expedience, the Court declines to
10 address the parties’ other, alternative arguments regarding dismissal of the Fifth Claim for Relief. It is
11 time for the surviving claims in this case to move forward.
12 B.
Sixth Claim for Relief
13
Plaintiffs’ Proposed Sixth Claim for Relief alleges Reclamation and the SRS Contractors
14 illegally caused the take of winter-run and spring-run Chinook during 2014 and 2015 because
15 Reclamation made excessive deliveries to the SRS Contractors, who in turn diverted the delivered water,
16 which in combination depleted the cold water reserves in Shasta Reservoir, causing temperature
17 increases fatal to the 2014 and 2015 “brood years” of winter-run and spring-run Chinook. 4SC ¶¶ 18918 193.
19
The SRS Contractors moved to dismiss this claim as against them on the ground that the claim
20 does not contain sufficient factual allegations regarding an act or omission by the SRS Contractors that
21 could plausibly state a claim for relief. In the October 20, 2016 Order, the Court rejected this argument,
22 reasoning: “it is reasonable to infer from [the] allegations [in the 4SC] that the SRS Contractors’
23 diversions were the actual physical mechanism by which water was removed from the watershed, that
24 Reclamation would not have released the same volume of water from upstream reservoirs were it not for
25 the SRS Contractors’ planned downstream diversions, and therefore that the SRS Contractors’
43
1
diversions were a ‘but for’ cause of the resulting loss of temperature control that is described in detail in
2
the 4SC.” October 20, 2016 Order at 39-40. The Court also rejected the SRS Contractors’ alternative
3
argument that the Sixth Claim for Relief must be dismissed because Plaintiffs failed to allege any
4
ongoing or future harm, finding that Plaintiffs’ claim “is not based wholly on past violations.” Id. at 43.
5
The Sixth Claim for Relief therefore may proceed against the SRS Contractors.
6
The Court then analyzed Federal Defendants’ motion to dismiss. Federal Defendants argued that
7
the Plaintiffs’ Section 9 claim against them is barred because the alleged take was covered by the ITS
8
included in the 2009 NMFS Salmonid OCAP BiOp. Relatedly, Federal Defendants also argue that an
9
agency cannot, as a matter of law, be the proximate cause of any take that occurs as a result of that
10 agency implementing a legally mandated water delivery (i.e., a non-discretionary action). The Court
11 began its analysis by providing background on Section 7 ITSs and Section 10 ITPs, which is helpful to
12 repeat here:
13
14
15
16
17
18
19
20
21
22
23
24
25
Section 7 requires that every federal agency, before undertaking an “action
authorized, funded, or carried out by” that agency, must ensure that the
action is not likely to jeopardize the continued existence of a protected
species or harm the critical habitat of a protected species. 16 U.S.C. §
1536(a)(2). When effects on protected species are likely, the agency must
go through a formal consultation process with FWS and/or NMFS. Id. If
the resulting BiOp concludes that the proposed action (or its reasonable
and prudent alternative) will cause “the taking of a[] [listed] species
incidental to the agency action,” but that despite this taking, the action will
not jeopardize the species or threaten critical habitat, FWS or NMFS shall
provide the agency with a written statement that:
(i) specifies the impact of such incidental taking on the species,
(ii) specifies those reasonable and prudent measures that the
Secretary considers necessary or appropriate to minimize such
impact
(iii) ..., and
(iv) sets forth the terms and conditions (including, but not limited
to, reporting requirements) that must be complied with by the
Federal agency or applicant (if any), or both, to implement the
measures specified under clauses (ii) and (iii).
16 U.S.C. § 1536(b)(4). The resulting ITS provides the applicant agency
with immunity from Section 9. Section 7 provides that “any taking that is
in compliance with the terms and conditions specified in a written [ITS] ...
44
1
2
3
shall not be considered to be a prohibited taking of the species concerned.”
16 U.S.C. § 1536(o)(2). “Where the agency’s action involves
authorization or approval of private party conduct, then the private party is
also protected from Section 9 by compliance with the agency’s [ITS].”
Defs. of Wildlife v. U.S. Fish, No. 16-CV-01993-LHK, 2016 WL 4382604,
at *2 (N.D. Cal. Aug. 17, 2016).
4
5
6
7
8
A related provision[, ESA Section 10,] governs incidental take by private
parties and authorizes FWS and NMFS to issue an ITP “under such terms
and conditions as [the service] may prescribe.” 16 U.S.C. § 1539(a)(1). As
with an ITS, an ITP may excuse take that “is incidental to, and not the
purpose of, the carrying out of an otherwise lawful activity.” 16 U.S.C. §
1539(a)(1)(B). An applicant for an ITP must submit a habitat conservation
plan demonstrating that the take “will not appreciably reduce the
likelihood of the survival and recovery [of the species] in the wild.” ESA §
10(a)(2)(B)(iv).
9
October 20, 2016 Order at 44-45.
10
In evaluating Federal Defendants’ argument that the salmonid mortality that occurred in 2014
11
and 2015 was covered by the ITS issued in connection with the 2009 NMFS Salmonid OCAP BiOp, the
12
October 20, 2016 Order acknowledged that the 2009 NMFS Salmonid OCAP BiOp explicitly indicated
13
that it considered “the overall impacts of the total volume of water diverted from the Central Valley.” Id.
14
at 45 (citing 2009 NMFS Salmonid OCAP BiOp at 729). Thus, the 2009 NMFS Salmonid OCAP BiOp
15
evaluated the impacts of any possible water deliveries that might occur pursuant to the SRS Contracts.
16
17
See 2009 NMFS Salmonid OCAP BiOp at 35 (“The analysis of effects of the proposed actions . . .
assumes water deliveries under the contracts, as described and modeled in the BA.”).
18
However, the October 20, 2016 Order also noted that the 2009 NMFS Salmonid OCAP BiOp
19
was “direct about its own limitations,” by indicating:
20
21
22
This consultation addresses the long-term operations of the CVP and
SWP, and does not satisfy Reclamation’s ESA section 7(a)(2) obligations
for issuance of individual water supply contracts. Reclamation should
consult with NMFS separately on their issuance of individual contracts.
23 October 20, 2016 Order at 45 (citing 2009 NMFS Salmonid OCAP BiOp at 35). Furthermore, the 2009
24 NMFS Salmonid OCAP BiOp also recognized that, at least at the time of its issuance, Reclamation
25 claimed certain contracted-for volumes were “nondiscretionary.” Id. As a result, NMFS requested that
45
1
“Reclamation provide written notice to NMFS . . . of any contract that it believes is [sic] creates a
2
nondiscretionary obligation to deliver water, including the basis for this determination and the quantity
3
of nondiscretionary water delivery required by the contract.” Id. In direct reference to such
4
nondiscretionary deliveries, the 2009 NMFS Salmonid OCAP BiOp indicated: “Any incidental take due
5
to delivery of water to such a contractor is not be [sic] exempt from the ESA section 9 take prohibition
6
in this Opinion.” Id. (emphasis in October 26, 2016 Order). Similar language is contained in the section
7
of the 2009 NMFS Salmonid OCAP BiOp designated as the ITS:
In the event that Reclamation determines that delivery of quantities of
water to any contractor is nondiscretionary for purposes of the ESA, any
incidental take due to delivery of water to that contractor would not be
exempted from the ESA section 9 take prohibition in this Opinion.
8
9
10
2009 NMFS Salmonid OCAP BiOp 729.21
11
12
13
The Court found it “difficult to square this language with Federal Defendants’ opening position
that the ITS covers take caused in connection with the delivery of water under the SRS Contracts.”
October 20, 2016 Order at 46. The Court’s reasoning continued:
14
As acknowledged by NMFS in the 2009 NMFS Salmonid OCAP BiOp,
Reclamation maintained at the time of the issuance of that BiOp that
deliveries to the SRS Contractors were non-discretionary. See, e.g., 2009
NMFS Salmonid OCAP BiOp at 684 (explaining that “[t]emperature
related effects on spring-run in the mainstem Sacramento River will
persist into the future, and cannot be fully off-set through Shasta reservoir
storage actions, due to physical and hydrological constraints on the CVP
system, and the delivery of water to non-discretionary CVP contractors
(e.g., Sacramento River Settlement Contractors)”) (emphasis added).
Likewise, as discussed, the ITS itself explicitly excludes from its coverage
non-discretionary activities. Federal Defendants even point out that an
ITS, which is issued pursuant to Section 7(b)(4), 16 U.S.C. § 1536(b)(4),
is only available as part of the Section 7 consultation process, which in
turn only applies to []discretionary agency action. See 50 C.F.R. § 402.03;
see also Nat’l Ass’n of Home Builders v. Defs. of Wildlife, 551 U.S. 644,
15
16
17
18
19
20
21
22
23
24
21
Other text reiterates that the 2009 NMFS Salmonid OCAP BiOp covered the “overall impacts of the total volume of water
diverted from the Central Valley,” while also calling for Reclamation to consult separately on the “issuance of individual
contracts,” including analysis of the effects of “activities of parties to agreements with the U.S. that recognize a previous
vested water right.” 2009 NMFS Salmonid OCAP BiOp at 729.
25
46
2
667 (2007) (Section 7 does not apply where an agency “simply lacks the
power to ‘insure’ that [its] action will not jeopardize endangered
species.”).
3
Id. (emphasis in original). “All this [led] the Court to conclude, at least for the purpose of [the pending
4
motion to dismiss], that the ITS issued in connection with the 2009 NMFS Salmonid OCAP BiOp could
5
not possibly cover deliveries to the SRS Contractors, which Reclamation (the agency that applied for the
6
ITS) maintained at the time the BiOp and ITS issued were non-discretionary.” Id.
1
7
Federal Defendants appear to request reconsideration of this finding in their supplemental
8
briefing. Doc. 1052 at 4-6. To the extent any of the threshold findings the Court made in the October 20,
9
2016 Order constitute law of the case, under the law of the case doctrine, “a court is generally precluded
10 from reconsidering an issue that has already been determined by the same court, or a higher court, on the
11 identical case.” United States v. Alexander, 106 F.3d 874, 876 (9th Cir. 1997) (citation omitted). A court
12 may depart from the law of the case if: (1) the first decision was clearly erroneous; (2) an intervening
13 change in the law has occurred; (3) the evidence on remand is substantially different; (4) other changed
14 circumstances exist; or (5) a manifest injustice would otherwise result. Id. If none of the requisite factors
15 are present, failure to apply the law of the case is an abuse of discretion. Id.
16
For the sake of clarity, the Court concludes that it is appropriate to depart from its previous
17 reasoning in one respect. The Court made a threshold finding that “[b]ecause, as discussed, Section 7
18 only applies to []discretionary agency action, see 50 C.F.R. § 402.03; see also Home Builders, 551 U.S.
19 at 667, it is logical to—and the Court does[—]conclude [] that an ITS can never provide an incidental
20 take exemption for non-discretionary agency activities.” October 26, 2016 Order at 49. In justifying this
21 finding, the Court assumed that because Section 7 consultation is not required for non-discretionary
22 activities, see Home Builders, 551 U.S. at 667 (upholding regulation that provides “Section 7 . . .
23 appl[ies] to all actions in which there is discretionary Federal involvement or control), an ITS issued in
24 the context of Section 7 consultation could never apply to non-discretionary activities. Upon further
25 review, the Court concludes this assumption runs counter to established precedent. Rather, a federal
47
1
agency may request Section 7 consultation regarding a project that involves both discretionary and non-
2
discretionary actions. In fact, the 2009 NMFS Salmonid OCAP BiOp does just that for the OCAP. See
3
2009 NMFS Salmonid OCAP BiOp at 729 (indicating that BiOp considered “the overall impacts of the
4
total volume of water diverted from the Central Valley.”); id. at 35 (“The analysis of effects of the
5
proposed actions . . . assumes water deliveries under the contracts, as described and modeled in the
6
BA.”); see also San Luis & Delta-Mendota Water Auth. v. Jewell, 747 F.3d 581, 639 (9th Cir. 2014)
7
(proper not to segregate discretionary from nondiscretionary operations of the OCAP Proposed Action
8
in describing project baseline); and San Luis & Delta-Mendota Water Auth. v. Locke, 776 F.3d 971,
9
1008 (9th Cir. 2014) (same).
10
However, this does not necessarily mean that every time an action agency requests Section 7
11 consultation on a project that includes both discretionary and non-discretionary actions, the ITS that
12 results provides take coverage for all aspects of the project. ESA Section 7(o) provides that “any taking
13 that is in compliance with the terms and conditions specified in a written [ITS] ... shall not be considered
14 to be a prohibited taking of the species concerned.” 16 U.S.C. § 1536(o)(2). Federal Defendants argue
15 that pursuant to this provision, “any taking”—whether from a discretionary or nondiscretionary aspect of
16 the OCAP action—that complied with the terms of the 2009 NMFS Salmonid OCAP BiOp ITS is
17 permitted. Doc. 1052 at 5. But this begs the question of whether the 2009 NMFS Salmonid OCAP BiOp
18 ITS covers the particular aspect of the OCAP action in question. See Strahan v. Roughead, 910 F. Supp.
19 2d 358, 374 (D. Mass. 2012) (“[W]hile an incidental take statement may . . . shield an agency from § 9
20 liability, it does so only if the ITS and its accompanying biological opinion address the agency's actions,
21 and the agency complies with the conditions and take limits established by the ITS.”).
22
Here, the express language of the ITS strongly suggests Reclamation’s deliveries to the SRS
23 Contractors are excluded from coverage. In addition to the limiting language discussed above, within the
24 section of the RPA prescribing actions in the Sacramento River Division required to avoid jeopardy,
25 NMFS describes Action I.2.3.C, which provides for “Drought Exception Procedures” to be triggered if
48
1
forecasting indicates temperature compliance in the Upper Sacramento River is not achievable. 2009
2
NMFS Salmonid OCAP BiOp at 600-601. The Action assumes “Reclamation does not have discretion
3
to curtail [deliveries to] the [SRS] contractors to meet Federal ESA requirements,” and that “[t]herefore,
4
NMFS is limited in developing an RPA that minimizes take to acceptable levels in these circumstances.”
5
Id. In light of this, the Action requires that notice be given to the State Water Resources Control Board
6
that “delivery of water to nondiscretionary [SRS] Contractors, and Delta outflow requirements per [State
7
Water Resources Control Board Decision 1641] may be in conflict in the coming season and requesting
8
the Board’s assistance in determining appropriate contingency measures and exercising their authorities
9
to put these measures in place.” Id. at 601. In addition, the rationale provided for the action states:
Separate from this consultation, NMFS will work with the SWRCB to
determine whether contingency plans within the Board’s authority are
warranted, and to assist in developing such plans that will allow
Reclamation to meet ESA requirements. The incidental take statement for
this Opinion also provides limitations of ESA incidental take coverage for
Settlement Contractors under the terms of this Opinion.
10
11
12
13
Id. Read alongside the other language in the 2009 NMFS Salmonid OCAP BiOp, this Action
14
acknowledges the real possibility that making non-discretionary deliveries to the SRS Contractors could
15
cause loss of temperature control (and presumably threaten jeopardy) and that NMFS is powerless to
16
design an RPA that would effectively eliminate this possibility because the applicant agency
17
(Reclamation) does not have the power to curtail the potentially jeopardizing deliveries. Instead, the
18
Action requires Reclamation to seek the assistance of state regulators, leaving open the possibility that
19
state regulators will either be unwilling or unable to intervene in any material way. The emphasized
20
sentence in the above-quoted paragraph also clearly indicates that the ITS issued as part of the BiOp
21
would not provide take coverage to the SRS Contractors for any take caused by non-discretionary
22
deliveries.
23
What exactly this means for Reclamation’s take coverage is less clear. Does the omission of any
24
mention of Reclamation in the emphasized sentence imply, as Federal Defendants suggest (see Doc.
25
49
1
1052 at 6), that Reclamation’s non-discretionary deliveries are protected from Section 9 liability by the
2
ITS? The Court thinks not. In the face of a jeopardy BiOp, a proposed action may not go forward unless
3
the consulting agency can suggest an RPA that avoids jeopardy, destruction, or adverse modification, 16
4
U.S.C. § 1536(b)(3)(A), and concludes the taking of the listed species “incidental to the agency action
5
will not violate” Section 7(a)(2)’s jeopardy prohibition. Id. at § 1536(b)(4)(B). Only if those, and certain
6
other conditions, are satisfied, can an ITS issue. In the case of Action I.2.3.C, NMFS admits that “NMFS
7
is limited in developing an RPA that minimizes take to acceptable levels in these circumstances.” NMFS
8
Salmonid OCAP BiOp at 601. This is tantamount to an admission that NMFS cannot avoid jeopardy in
9
all circumstances related to the non-discretionary deliveries. Put simply, NMFS cannot lawfully issue an
10 ITS to cover a potentially jeopardizing circumstance for which it has no mechanism to suggest
11 appropriate RPA. Accordingly, the Court declines to depart from its preliminary conclusion that the
12 2009 NMFS Salmonid OCAP BiOp ITS does not provide take protection to Reclamation for non13 discretionary deliveries under the SRS Contracts.
14
The Court must turn to Federal Defendants’ alternative argument: that an agency cannot, as a
15 matter of law, be the proximate cause of any take that occurs as a result of that agency implementing a
16 legally mandated water delivery (i.e., a non-discretionary action). As mentioned in the October 20, 2016
17 Order, it is well-established that concepts of proximate cause apply to Section 9 claims. See Cascadia
18 Wildlands v. Kitzhaber, 911 F. Supp. 2d 1075, 1084 (D. Or. 2012) (collecting cases supporting the
19 proposition that “[i]t is well accepted that proximate cause is an element of ESA Section 9 claims,” and
20 explaining that “[i]n the context of the ESA, proximate cause issues entail determining whether the
21 alleged injury . . . is fairly traceable to the challenged action of [d]efendants.”).
22
Federal Defendants rely on U.S. Department of Transportation v. Public Citizen, 541 U.S. 752
23 (2004), for the proposition that a sufficient causal connection cannot possibly exist if the agency “has no
24 ability to prevent a certain effect due to its limited statutory authority over the relevant actions.” Id. at
25 770. In that case, the Supreme Court held that the defendant federal agency, the Federal Motor Carrier
50
1
Safety Administration (“FMCSA”), did not violate the National Environmental Policy Act (“NEPA”),
2
42 U.S.C. §§ 4321-4370f, when it failed to analyze the environmental impact of permitting cross-border
3
truck traffic. The Supreme Court noted that “NEPA requires a reasonably close causal relationship
4
between the environmental effect and the alleged cause,” analogous to the “familiar doctrine of
5
proximate cause from tort law,” and instructed that “courts must look to the underlying policies or
6
legislative intent in order to draw a manageable line between those causal changes that may make an
7
actor responsible for an effect and those that do not.” 541 U.S. at 767 (internal citation and quotation
8
omitted). Because FMCSA was statutorily required to allow the trucks to enter the country, an
9
environmental analysis of any alternative action would not serve “the underlying policies behind NEPA”
10 to provide information to the public and to inform the decision-making process. Id. at 768. Put another
11 way, “[s]ince FMCSA has no ability categorically to prevent the cross-border operations of Mexican
12 motor carriers, the environmental impact of the cross-border operations would have no effect on
13 FMCSA’s decisionmaking—FMCSA simply lacks the power to act on whatever information might be
14 contained in the EIS.” Id.
15
Federal Defendants maintain that Public Citizen applies with equal force to ESA Section 9 and
16 that, as a result, an agency cannot be held liable under Section 9 for an action it is legally mandated to
17 perform. FD MTD at 20.
18
Plaintiffs cite the Supreme Court’s decision in Home Builders to argue that Public Citizen is
19 inapplicable in the context of the ESA. Doc. 1048 at 14-15. Home Builders concerned the
20 Environmental Protection Agency’s decision to transfer to the State of Arizona regulatory responsibility
21 under the National Pollutant Discharge Elimination System (“NPDES”), a program described in Section
22 402(b) of the Clean Water Act (“CWA”), 33 U.S.C. § 1342. See Home Builders, 551 U.S. at 649-51.
23 Under CWA Section 402(b), the EPA “shall approve” a State's request to assume the permitting
24 program “unless [the EPA] determines that adequate authority does not exist” to ensure that nine
25 specific criteria set forth in the statute are satisfied. If the criteria are met, the transfer must be approved.
51
1
Id. at 650-51. At the same time, ESA Section 7 requires federal agencies to consult with either FWS or
2
NMFS to “insure that any action authorized, funded, or carried out by such agency ... is not likely to
3
jeopardize” endangered or threatened species or their habitats. Id. at 652 (quoting ESA Section 7). Home
4
Builders recognized that “[a]lthough a later enacted statute (such as the ESA) can sometimes operate to
5
amend or even repeal an earlier statutory provision (such as the CWA), repeals by implication are not
6
favored and will not be presumed unless the intention of the legislature to repeal is clear and manifest.”
7
Id. at 662. The Supreme Court reasoned that requiring the EPA to comply with ESA Section 7 when
8
approving a transfer application “would effectively repeal § 402(b)’s statutory mandate by engrafting a
9
tenth criterion onto the CWA.” Id.
10
11
12
13
Section 402(b) of the CWA commands that the EPA “shall” issue a permit
whenever all nine exclusive statutory prerequisites are met. Thus, § 402(b)
does not just set forth minimum requirements for the transfer of permitting
authority; it affirmatively mandates that the transfer “shall” be approved if
the specified criteria are met. The provision operates as a ceiling as well as
a floor. By adding an additional criterion, the Ninth Circuit's construction
of § 7(a)(2) raises that floor and alters § 402(b)'s statutory command.
14 Id. at 663-64 (emphasis in original).
15
Home Builders approved a joint NMFS/FWS regulation that provided: “Section 7 and the
16 requirements of this part apply to all actions in which there is discretionary Federal involvement or
17 control.” 50 C.F.R. § 402.03.
18
19
20
21
22
23
24
25
Pursuant to this regulation, § 7(a)(2) would not be read as impliedly
repealing nondiscretionary statutory mandates, even when they might
result in some agency action. Rather, the ESA's requirements would come
into play only when an action results from the exercise of agency
discretion. This interpretation harmonizes the statutes by giving effect to
the ESA's no-jeopardy mandate whenever an agency has discretion to do
so, but not when the agency is forbidden from considering such
extrastatutory factors.
***
We conclude that this interpretation is reasonable in light of the statute's
text and the overall statutory scheme, and that it is therefore entitled to
deference under Chevron [U.S.A. Inc. v. Natural Resources Defense
Council, Inc., 467 U.S. 837 (1984) ]. Section 7(a)(2) requires that an
agency “insure” that the actions it authorizes, funds, or carries out are not
likely to jeopardize listed species or their habitats. To “insure” something52
1
2
3
as the court below recognized-means “‘[t]o make certain, to secure, to
guarantee (some thing, event, etc.).’” 420 F.3d, at 963 (quoting 7 Oxford
English Dictionary 1059 (2d ed. 1989)). The regulation's focus on
“discretionary” actions accords with the commonsense conclusion that,
when an agency is required to do something by statute, it simply lacks the
power to “insure” that such action will not jeopardize endangered species.
4
Id. at 665-67 (emphasis in original).
5
Of particular import to the present case, the Home Builders Court addressed Public Citizen, a
6
NEPA case, directly:
7
8
9
10
11
12
13
We do not suggest that Public Citizen controls the outcome here; §
7(a)(2), unlike NEPA, imposes a substantive (and not just a procedural)
statutory requirement, and these cases involve agency action more directly
related to environmental concerns than the FMCSA’s truck safety
regulations. But the basic principle announced in Public Citizen—that an
agency cannot be considered the legal “cause” of an action that it has no
statutory discretion not to take—supports the reasonableness of the FWS’
interpretation of § 7(a)(2) as reaching only discretionary agency actions.
See also California v. United States, 438 U.S. 645, 668, n. 21 (1978)
(holding that a statutory requirement that federal operating agencies
conform to state water usage rules applied only to the extent that it was not
“inconsistent with other congressional directives”).
14 Id. at 667-68. Contrary to Plaintiffs’ suggestion, the Court does not read this as an absolute bar to
15 applying the logic of Public Citizen to the ESA.
16
At least one district court has declined to apply Public Citizen’s logic to a Section 9 case. In
17 Seattle Audubon Soc’y v. Sutherland, No. C06-1608MJP, 2007 WL 1577756, at *1 (W.D. Wash. May
18 30, 2007), the defendant agency argued that under Public Citizen agency officials could not be the
19 proximate cause of any alleged take because those officials did not have discretion to deny permits that
20 comply with the requirements of the Forest Practices Act. The district court rejected this argument,
21 reasoning that “[a]lthough [Public Citizen’s] holding makes sense in the context of a procedural,
22 information-forcing statute like NEPA, it is inapplicable under the ESA, which serves completely
23 different purposes.” Id.
24
Seattle Audubon is not binding and its limited reasoning regarding this issue fails to apply the
25 broader principle articulated in Public Citizen and relied upon in Home Builders’ Chevron analysis—
53
1
that wherever principles of proximate causation are applicable, “courts must look to the underlying
2
policies or legislative intent in order to draw a manageable line between those causal changes that may
3
make an actor responsible for an effect and those that do not.” Public Citizen, 541 U.S. at 767 (internal
4
citation and quotation omitted). Although Public Citizen does not give detailed instructions as to how to
5
perform this analysis, it provides some guidance. For example, Public Citizen observes that “proximate
6
cause analysis turns on policy considerations and considerations of the ‘legal responsibility’ of actors.”
7
Public Citizen, 541 F.3d 767 (quoting W. Keeton, D. Dobbs, R. Keeton, & D. Owen, Prosser and
8
Keeton on Law of Torts 264, 274-275 (5th ed. 1984)). In general terms, as Justice O'Connor noted in her
9
concurrence in Babbitt v. Sweet Home Chapter of Communities for a Great Oregon, 515 U.S. 687
10 (1995), “[p]roximate causation is not a concept susceptible of precise definition.” Id. at 713 (O’Connor,
11 J., concurring). Black's Law Dictionary defines “proximate cause” as (1) a cause that is legally sufficient
12 to result in liability; an act or omission that is considered in law to result in a consequence, so that
13 liability can be imposed on the actor; and (2) a cause that directly produces an event and without which
14 the event would not have occurred. Proximate Cause, Black’s Law Dictionary 250 (9th ed. 2009).
15
NEPA, the statute considered in Public Citizen, is an information-forcing statute with the dual
16 purpose of ensuring both that a federal agency “will have available, and will carefully consider, detailed
17 information concerning significant environmental impacts” of any proposed action, and “that the
18 relevant information will be made available to the larger audience that may also play a role in both the
19 decisionmaking process and the implementation of that decision.” 541 U.S. at 768. Public Citizen found
20 that this purpose would not be served by requiring an agency to “prepare a full [Environmental Impact
21 Statement] due to the environmental impact of an action it could not refuse to perform.” Id. at 769.
22
The ESA’s purpose is decidedly different. It was designed to be “the most comprehensive
23 legislation for the preservation of endangered species ever enacted by any nation.” TVA v. Hill, 437 U.S.
24 153, 180 (1978). “Whereas predecessor statutes enacted in 1966 and 1969 had not contained any
25 sweeping prohibition against the taking of endangered species except on federal lands, the 1973 Act
54
1
applied to all land in the United States and to the Nation’s territorial seas.” Babbitt v. Sweet Home
2
Chapter of Communities for a Great Oregon, 515 U.S. 687, 698 (1995). As stated in ESA Section 2,
3
among the ESA’s central purposes is “to provide a means whereby the ecosystems upon which
4
endangered species and threatened species depend may be conserved.” Id. (quoting 16 U.S.C. §
5
1531(b)). But this does not mean that there should be no “line between those causal changes that may
6
make an actor responsible for an effect and those that do not” in the context of Section 9. In Home
7
Builders, the Supreme Court ultimately approved of an agency regulation that drew such a line in the
8
context of Section 7, precluding Section 7 from applying to non-discretionary agency action. Home
9
Builders, 551 U.S. at 667-68.
Plaintiffs correctly point out that the Supreme Court has held that “[a]ll persons, including
10
11 federal agencies, are specifically instructed not to ‘take’ endangered species.” TVA, 437 U.S. at 184
12 (emphasis added). But this does not resolve the key question: whether a federal agency acting to
13 implement a non-discretionary duty imposed by a valid contract should be subject to Section 9 liability.
14 Here, to be blunt, analogizing to Public Citizen, the Court does not believe it is appropriate to impose
15 Section 9 liability on a government agency for take caused by an action over which it has no control. In
22
16 this case, to do the opposite would require Reclamation to either breach still-valid SRS Contracts
23
17 necessary to operation of the CVP in compliance with state law, or obtain a Section 10 ITP before
18 implementing any non-discretionary aspect of the SRS Contracts. Accordingly, the Court finds that a
19 federal agency that is legally required to take an action pursuant to federal law, such as by implementing
20
21
22
23
24
25
22
As mentioned in the October 20, 2016 Order, the Court mentioned the “bizarre procedural situation” created by the fact
that “[u]nless and until Plaintiffs prevail on their Fourth Claim for Relief,” which alleges that the Settlement Contracts were
not validly executed because they were executed without proper Section 7 compliance, “the Court must consider the SRS
Contracts final.” See October 20, 2016 Order at 34 n. 6 (discussing the Fifth Claim for Relief). If Plaintiffs prevail on the
Fourth Claim for Relief, a subsequent analysis of the Sixth Claim for Relief might warrant a different analysis, provided the
Sixth Claim for Relief is not mooted by such a result.
23
As the Court previously discussed in the October 20, 2016 Order, it is far from clear that Section 10 ITPs are even
available to federal agency applicants. October 20, 2016 Order at 49-50. But, for the purposes of the present discussion, the
Court will assume that they are.
55
1
non-discretionary terms in an otherwise valid water delivery contract, that agency cannot be the
2
proximate cause of Section 9 take by undertaking that non-discretionary action. While the concept of
3
proximate cause limits a federal agency’s Section 9 liability for actions over which it has no control,
4
such a limit naturally would not apply where the federal agency does retain some degree of control.
5
Accordingly, Section 9 take liability may attach to take otherwise proximately caused by actions over
6
which a federal agency does have control.24
7
As discussed above, the text of Article 10(a) of the GCID Contract indicates, at least facially,
8
that Reclamation retains discretion to require GCID to directly divert up to 20,315 AF of water from
9
Stony Creek, rather than from the Sacramento River. The Court has concerns that factual impossibility
10 may in reality eviscerate any discretion Reclamation may facially retain in Article 10(a) of the GCID
11 Contract. See, e.g., Gaines v. Sargent Fletcher, Inc. Grp. Life Ins. Plan, 329 F. Supp. 2d 1198, 1221
12 (C.D. Cal. 2004) (“under basic principles of contract law, impossibility generally excuses breach and
13 renders the impossible contract term unenforceable”). The Court also questions whether Plaintiffs will
14 be able to demonstrate that Reclamation’s failure to require GCID to divert up to 20,315 AF of water
15 from Stony Creek, rather than from the Sacramento River, could have proximately caused any of the
16 harms alleged in the Sixth Claim for Relief. These are factual issues best resolved in light of a complete
17 record. Accordingly, because the Sixth Claim for Relief survives as against the SRS Contractors, the
18 Claim will also be allowed to proceed against Federal Defendants on this narrow ground.
In addition, Plaintiffs argue that other aspects of “Reclamation’s discretionary conduct caused
19
20 and will cause illegal takes.” Doc. 1048 at 15. As one example, Plaintiffs point to Reclamation’s ability
21 to agree (or not agree) to transfers of SRS Contract water. In the context of the EPIC analysis applicable
22 to the Fifth Claim for Relief, the Court found above that this approval authority did not constitute
23
24
The Court is cognizant of the fact that during Section 7 consultation, an agency is not required to distinguish discretionary
24 from non-discretionary activities and may evaluate the impacts of both simultaneously. See San Luis v. Jewell, 747 F.3d at ,
25
639. But given that Section 9 liability turns in part on whether the defendant proximately caused “take,” the Court believes it
is necessary to parse discretionary from non-discretionary activities in the Section 9 context.
56
1
discretion to modify the contracts. However, there is no authority that suggests the type of discretion that
2
is necessary to trigger Section 9 liability is so limited. Accordingly, the Sixth Claim for Relief may also
3
proceed as against Federal Defendants on this second, narrow ground: that approval of transfers
4
proximately caused the take alleged in the Sixth Claim for Relief.25
5
VI. CONCLUSION AND ORDER
6
For the reasons set forth above:
7
(1) Federal Defendants’ motion to dismiss the Fifth Claim for Relief is GRANTED;
8
(2) Federal Defendants’ motion to dismiss the Sixth Claim for Relief is GRANTED IN
9
PART AND DENIED IN PART. The Claim may proceed against Federal Defendants on the two
10
limited theories outlined above based upon Reclamation’s purported discretion to require GCID
11
to divert up to 20,315 AF from Stony Creek and to approve transfers of SRS Contractor water.
12
13
IT IS SO ORDERED.
14
Dated:
February 23, 2017
/s/ Lawrence J. O’Neill _____
UNITED STATES CHIEF DISTRICT JUDGE
15
16
17
18
19
20
21
22
23
24
25
25
Plaintiffs also point generically to other paragraphs of the 4SC in which they claim they allege Reclamation engaged in
discretionary conduct that caused or will cause illegal takes. Doc. 1048 at 15 (citing 4SC at ¶¶ 73-77, 151, 153, 162, 192-93).
The only potentially discretionary act the Court is able to isolate from Paragraphs 73-77 concerns temperature modeling. As
discussed supra at Part V.A.10, “even if Reclamation had discretion to select a forecast that might be more likely to trigger a
Critical Year determination, any such forecast would have to be revised as real data became available and therefore
Reclamation’s purported discretion would not have any practical import to listed species.” Paragraph 152 discusses the fact
that “the Bureau makes real-time determinations regarding the timing and volume of releases that allow the Contractors to
make diversions of water,” but fails to even remotely suggest how these determinations could have proximately caused take
under the circumstances. Paragraphs 151, 162 and 192-193 do not articulate any particular form of relevant discretion, at least
not in any way that allows the Court to distinguish between acts that may have been taken to fulfill non-discretionary
obligations and those that may have involved the exercise of some discretion.
Finally Plaintiffs argue “Reclamation’s discretionary action to seek exemptions from state law requirements in
recent years has caused severe harm to listed salmonids.” Doc. 1048 at 8 (citing 4SC ¶¶57, 58, 73-77). But, in light of the fact
that the 2009 NMFS Salmonid OCAP BiOp requires Reclamation to apply for exemptions when necessary, the Court does
not view Reclamation’s conduct in seeking exemptions under these circumstances as discretionary. 2009 NMFS Salmonid
OCAP BiOp at 600-601.
57
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?