General Electric Company, et al. v. Wilkins

Filing 575

ORDER ON MOTIONS FOR RECONSIDERATION 465 475 signed by District Judge Lawrence J. O'Neill on August 2, 2012. Note: Unredacted Order will be served separately. (Munoz, I)

Download PDF
1 2 3 4 5 6 7 8 IN THE UNITED STATES DISTRICT COURT 9 FOR THE EASTERN DISTRICT OF CALIFORNIA 10 11 12 GENERAL ELECTRIC COMPANY, et al., 13 CASE NO. 1:10-cv-00674-LJO-JLT Plaintiffs, ORDER ON MOTIONS FOR RECONSIDERATION (Docs. 465, 475) vs. 14 THOMAS WILKINS, an individual 15 Defendant. 16 / 17 18 I. INTRODUCTION 19 Defendants Thomas Wilkins (“Mr. Wilkins”) and Mitsubishi Heavy Industries, Ltd. and 20 Mitsubishi Power Systems Americas, Inc. (collectively “Mitsubishi”)1 seek reconsideration of Magistrate 21 Judge Thurston’s June 22, 2012, order granting in part, General Electric’s (“GE”) motion for sanctions. 22 GE opposes defendants’ requests for reconsideration and seeks recovery of the fees incurred in preparing 23 its opposition. 24 reconsideration and DENIES GE’s request for fees. 25 26 For the reasons discussed below, this Court DENIES defendants’ motions for II. BACKGROUND GE and Mitsubishi are competitors in the wind energy market. Mr. Wilkins was formerly 27 28 1 Mr. W ilkins and Mitsubishi will be referred to collectively as “defendants.” 1 1 employed by GE.2 While employed by GE, Mr. Wilkins’ job was to develop new designs for wind 2 turbine equipment. He voluntarily left the company in late 2002. 3 In 2005, two patents were issued to GE, U.S. Patent No. 6,924,565 (“the ‘565 patent”) and U.S. 4 Patent No. 6,921,985 (“the ‘985 patent”). The ‘565 patent lists seven inventors and GE as the assignee 5 of record. One of the named inventors of the ‘565 patent is Mr. Wilkins. When preparing the patent 6 application, GE asked Mr. Wilkins to assign any interest he had in the invention to GE but Mr. Wilkins 7 refused. The ‘985 patent lists five inventors and GE as the assignee of record. Mr. Wilkins is not a 8 named inventor of the ‘985 patent. 9 In 2008, GE filed a complaint with the United States International Trade Commission (“ITC”) 10 in which it alleged that Mitsubishi infringed on three of its patents, including the ‘985 patent. Pursuant 11 to the complaint, the ITC conducted an investigation. During the pendency of the action, Mitsubishi 12 retained Mr. Wilkins to provide “consulting services . . . and possibly to serve . . . as an expert witness.” 13 (Doc. 347-7). In May 2009, the ITC held an evidentiary hearing in which Mr. Wilkins testified as a fact 14 witness. (Doc. 345-6, p. 120-23). On August 7, 2009, the ITC’s Administrative Law Judge (“ALJ”) 15 issued a decision. (Doc. 345-6). In the decision the ALJ determined that “[Mr.] Wilkins was an inventor 16 of at least the invention of claim 15 of the ‘985 patent.” (Doc. 345-6, p. 122-23). 17 August 2009: Option/Consulting Agreement 18 Following the ALJ’s determination, Mitsubishi and Mr. Wilkins entered into an 19 option/consulting agreement on August 21, 2009. (Doc. 350, p. 2). The agreement provided that in the 20 event Mr. Wilkins received a written request from Mitsubishi for a license, Mr. Wilkins would grant 21 Mitsubishi a license to the technology in the ‘985 patent. (Id.). œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 22 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 23 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 24 œ 25 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 26 œœœœœ œœœœœœœ Also in this agreement, Mitsubishi retained Mr. Wilkins as a consultant to perform research œ œ 27 28 2 Mr. W ilkins was initially employed by Enron W ind which was acquired by GE. 2 œ œ 1 tasks in response to specific requests by Mitsubishi. 2 ( I d . ) œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 3 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ The 4 consulting agreement was in addition to the prior consulting agreement associated with the ITC action. 5 (Id.). 6 December 2009: Licensing Agreement & Modification of August 2009 Agreement 7 On December 17, 2009, Mitsubishi decided to exercise its option and entered into an agreement 8 with Mr. Wilkins in which Mr. Wilkins granted Mitsubishi a nonexclusive license to whatever interest 9 he possessed in the ‘985 patent. (Doc. 338, ¶ 3.1). œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 10 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 11 œ 12 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 13 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 14 œœœœœœœœœœœœœœœœœœ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ œ 15 On December 17, 2009, the parties also modified the August 21, 2009, “option/consulting” 16 agreement. (Doc. 336). œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 17 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 18 œœœœœ 19 20 Extension of December 2009 Licensing Agreement B y N o v e m b e r 21 2011,œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 22 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 23 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 24 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 25 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ A series of emails were exchanged between Mr. Wilkins’ former attorney, 26 Michael Schulte, his current attorney, Tom Winland, and Mitsubishi’s attorneys, Steve Barber and Fil 27 Agusti regarding this issue. (Docs. 344-13, 347-10, 353, 355). œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 28 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 3 1 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 2 Discovery Requests 3 During discovery, GE asked Mr. Wilkins and Mitsubishi to provide all documents related to the 4 above negotiations and copies of the agreements.3 Both Mr. Wilkins and Mitsubishi objected to these 5 requests as protected by the attorney/client privilege, work product doctrine, community of interest 6 privilege, and/or any other applicable privilege or immunity. (Doc. 344-7, p. 3, 6, 16-18). Both agreed 7 however, to produce all responsive, non-privileged documents. (Id.). 8 Nonetheless, GE soon learned that Mr. Wilkins and Mitsubishi did not produce all responsive 9 documents. During the April 6, 2012, deposition of Mark Peterson, Mr. Wilkins’ expert, GE learned 10 that Mr. Wilkins produced the December 2009 amendment to the August 2009 “option/consulting” 11 agreement to Mr. Peterson. When GE requested a copy of the consulting agreement, Mr. Wilkins and 12 Mitsubishi initially refused but relented on April 23, 2012. 13 On April 25, 2012, Mitsubishi filed a motion, pursuant to FED . R. CIV . P. 26(c), for an order 14 protecting Mitsubishi from attempts by GE to re-open discovery regarding the licensing and consulting 15 agreements between Mitsubishi and Mr. Wilkins. (Doc. 322, p. 2). Mitsubishi continued to argue that 16 the licensing and consulting agreements were unimportant and ancillary to the central issues in the case. 17 (Id.). A telephonic conference regarding Mitsubishi’s motion was held on April 26, 2012. (Doc. 325, 18 p. 1). Based on the conference, Judge Thurston concluded that the agreements were not protected by 19 the attorney/client or attorney work product privilege. (Doc. 325, p. 2). Judge Thurston also made a 20 preliminary determination that the documents were not protected merely because they dealt with a 21 retainer agreement for an expert but ordered the parties to address this issue in their joint statement. 22 (Doc. 325, p. 3). Judge Thurston further ordered Mitsubishi and Mr. Wilkins to certify, no later than 23 May 4, 2012, that all responsive documents within their control were produced. (Doc. 325, p. 5). On 24 May 4, 2012, Mitsubishi and Mr. Wilkins certified that they produced all non-privileged documents 25 related to the negotiation of the December 2009, licensing agreement. (Docs. 345, 345-1). 26 Motion to Compel and Request for Sanctions 27 3 28 See Requests for Production (“RFP”) to Mitsubishi Nos. 14, 17, and 21 at Doc. 344-7, p. 3, 6. See also RFPs to Mr. W ilkins Nos. 1, 49, 50, 51 at Doc. 344-7, p. 16-18. 4 1 On May 11, 2012,4 GE filed a motion to compel further responses to their requests for the 2 production of documents and a request for sanctions due to Mr. Wilkins and Mitsubishi’s failure to 3 comply with GE’s requests for information concerning the duo’s licensing negotiations and agreements. 4 (Doc. 331). GE argued that Mr. Wilkins and Mitsubishi violated FED . R. CIV . P. 26 and 37 by “failing 5 to produce and/or [failing] to timely produce relevant and responsive documents, failing to preserve 6 relevant and responsive documents, providing evasive and non-responsive answers to GE’s 7 interrogatories and (in Mitsubishi’s case) failing to adequately prepare its 30(b)(6) witness.” (Doc. 331, 8 p. 2). Pursuant to FED . R. CIV . P. 37(c), GE sought: 9 (1) an order precluding Mitsubishi and Mr. Wilkins from introducing evidence, either at summary judgment or at trial, about license negotiations or agreements between Mitsubishi and Mr. Wilkins; (2) an instruction directing the fact finder to draw an adverse inference that the license agreement between Mr. Wilkins and Mitsubishi is an attempt by Mitsubishi to buy Mr. Wilkins’ loyalty and cooperation in litigation about the ‘985 patent; and (3) dismissal of Mr. Wilkins’ damages claims. 10 11 12 13 (Doc. 331, p. 2-3). 14 Shortly after GE filed its motion Mitsubishi and Mr. Wilkins provided additional documents and 15 filed supplemental certifications. Mitsubishi produced every non-privileged document that it could find 16 related to the license agreement,œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ, and all non-privileged 17 documents related to its December 2011,œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 18 œœœœœœœœœœœœœœœœ. (Doc. 343, p. 56-57). On May 21, 2012, Mr. Wilkins provided similar documents and 19 a supplemental privilege log which contained entries related to Mr. Wilkins’ consulting work with 20 Mitsubishi. (Doc. 345-2, p. 3-4). Mr. Wilkins also provided a supplemental certification without 21 conceding that his prior certification was too narrow. (Doc. 345-2, p. 5-6). On May 25, 2012, 22 Mitsubishi submitted a similar supplemental certification without conceding that its prior certification 23 was too narrow. (Doc. 346-3). 24 25 26 Order on Motion to Compel and Request for Sanctions On June 22, 2012, Judge Thurston denied GE’s motion to compel as abandoned because GE failed to support the motion with points and authorities. (Doc. 368, p. 8). 27 4 28 GE filed an amended motion to compel on May 17, 2012, which made administrative changes to the motion. The substance of the motion remained the same. (Doc. 331, fn. 1). 5 1 With regard to GE’s request for sanctions, Judge Thurston granted the request in part and denied 2 it in part. Judge Thurston determined that “Mitsubishi and Wilkins were ‘gaming’ the discovery related 3 to the amendment to the license agreement, the consulting agreements and the negotiations related to 4 all of the Mitsubishi-Wilkins agreements.” (Doc. 368, p. 11). Judge Thurston pointed out that while 5 Mr. Wilkins and Mitsubishi lodged objections to producing these records, both indicated that they would 6 produce and did produce some documents but in doing so they “obfuscated the fact that there were some 7 documents that were withheld.” (Id.). Judge Thurston further determined that Mitsubishi’s general 8 objection based upon relevance amounted to a waiver of the objection because “a specific relevance 9 objection that does not explain why the request is not relevant is not proper and does not preserve the 10 objection.” (Doc. 368, p. 12). Judge Thurston further noted that the timing of the disclosure of the 11 documents caused the Court concern in light of the fact that Mitsubishi’s current counsel had all but the 12 November 2009, emails all along. (Id.). 13 Pursuant to FED . R. CIV . P. 37(c)(1)(A), Judge Thurston ordered an award to GE of its costs and 14 fees in bringing the motion to compel and motion for sanctions. Judge Thurston awarded costs and fees 15 to GE based on her determination that “Mitsubishi and Wilkins were engaged in game-playing related 16 to the negotiation documents related to the license, the attempted amendment to the license and the 17 consulting agreements. They lodged objection[s] that were not proper, identified documents as 18 privileged when they plainly were not and delayed in producing discoverable documents.” (Doc. 368, 19 p. 20). Pursuant to the Court’s inherent power to manage its cases, Judge Thurston also authorized GE 20 to take the deposition of Michael Schulte and Thomas Winland and to re-take the deposition of Mark 21 Peterson. Judge Thurston further ordered that the cost of the Schulte and Winland depositions would 22 be shared by Mitsubishi and Mr. Wilkins and the cost of the Peterson deposition would be borne by Mr. 23 Wilkins. (Doc. 368, p. 18). 24 Motions for Reconsideration 25 On July 13, 2012, Mr. Wilkins and Mitsubishi filed motions for reconsideration (Docs. 465, 475) 26 to which GE filed an opposition (Doc. 567). Mr. Wilkins contends that Judge Thurston clearly erred 27 when she found that he engaged in gamesmanship and when she awarded GE costs and fees in bringing 28 the motion to compel and motion for sanctions. Mitsubishi argues that Judge Thurston’s award of 6 1 attorney’s fees and costs was clearly erroneous and contrary to law. Mitsubishi further seeks 2 reconsideration of the award of the costs of taking additional depositions. GE opposes the motions and 3 requests the fees associated with preparing its opposition. 4 III. LEGAL STANDARD 5 “A party seeking reconsideration of [a] Magistrate Judge’s ruling shall file a request for 6 reconsideration,” pursuant to Local Rule 303(c). This Court reviews a motion to reconsider a 7 Magistrate Judge’s ruling under the “clearly erroneous or contrary to law” standard set forth in 28 U.S.C. 8 § 636(b)(1)(A); FED . R. CIV . P. 72(a). As such, the Court may only set aside those portions of a 9 Magistrate Judge’s order that are either clearly erroneous or contrary to law. FED . R. CIV . P. 72(a); see 10 also Grimes v. City and County of San Francisco, 951 F.2d 236, 241 (9th Cir. 1991). 11 “The clearly erroneous standard applies to the magistrate judge’s factual determinations and 12 discretionary decisions, including orders imposing discovery sanctions.” Computer Econ., Inc. v. 13 Gartner Group, Inc., 50 F. Supp. 2d 980, 983 (S.D. Cal. 1999) (internal quotation marks omitted). 14 “[R]eview under the clearly erroneous standard is significantly deferential, requiring a definite and firm 15 conviction that a mistake has been committed.” Sec. Farms v. Int’l Bhd. of Teamsters, 124 F.3d 999, 16 1014 (9th Cir. 1997) (internal quotation marks omitted); Green v. Baca, 219 F.R.D. 485, 489 (C.D. Cal. 17 2003). “In contrast, the contrary to law standard . . . permits independent review of purely legal 18 determinations by the magistrate judge.” Green, 219 F.R.D. at 489 (internal quotation marks omitted). 19 Thus, a District Court may overturn a Magistrate Judge’s “conclusions of law which contradict or ignore 20 applicable precepts of law, as found in the Constitution, statutes or case precedent.” Adolph Coors Co. 21 v. Wallace, 570 F. Supp. 202, 205 (N.D. Cal. 1983). 22 23 24 25 With these standards in mind, this Court turns to Mr. Wilkins and Mitsubishi’s criticisms of Judge Thurston’s June 22, 2012, order. IV. DISCUSSION A. Mr. Wilkins’ Request for Reconsideration 26 Mr. Wilkins contends that Judge Thurston’s finding that he engaged in gamesmanship and the 27 award to GE of the costs and fees associated with bringing its motion to compel was clearly erroneous. 28 Under FED . R. CIV . P. 37(c)(1)(A), if a party fails to provide information the Court “may order 7 1 payment of the reasonable expenses, including attorney’s fees, caused by the failure.” Pursuant to this 2 rule, Judge Thurston awarded GE the costs and fees in bringing its motion to compel. (Doc. 368, p. 20- 3 21). Judge Thurston based this award on her determination that Mr. Wilkins and Mitsubishi “engaged 4 in game-playing related to the negotiation documents related to the license, the attempted amendment 5 to the license and the consulting agreements. They lodged objection[s] that were not proper, identified 6 documents as privileged when they plainly were not and delayed in producing discoverable documents.” 7 (Doc. 368, p. 20). Mr. Wilkins argues that this determination and the award of costs and fees was clearly 8 erroneous for three reasons. 9 1. GE’s Delay in Seeking the Documents 10 Mr. Wilkins contends that his delay in producing the documents was the result of GE’s delay in 11 seeking the documents. Mr. Wilkins explains that the three consulting agreements have been on his 12 privilege log since October 2011 and yet GE waited until after Mr. Wilkins voluntarily produced one 13 of the documents, which was after the close of discovery, to seek production of the remaining 14 documents. Mr. Wilkins argues that he should not be faulted for GE’s delay. 15 GE was not dilatory in seeking the documents. In GE’s requests for production, it requested all 16 documents related to the licensing of the technology in the ‘985 patent and all documents related to Mr. 17 Wilkins’ employment as a consultant for Mitsubishi. (Doc. 344-7, p. 16-18). Mr. Wilkins asserted a 18 privilege as to these documents but then provided a copy of the December 2009 amendment to the 19 August 2009 “option/consulting” agreement to its expert Mark Peterson. Once GE learned that the 20 document had been produced it requested a copy of the agreement which Mr. Wilkins initially refused 21 to provide but then relented two weeks later. Once this occurred, GE became suspicious that Mr. 22 Wilkins was withholding other documents so it filed its motion to compel and requests for sanctions. 23 This chain of events shows that GE did not wait to request the documents. GE requested the documents 24 during discovery and Mr. Wilkins withheld them. 25 2. Mr. Wilkins’ Lack of Awareness Regarding the November 2009 Email 26 Mr. Wilkins argues that he did not know that the November 2009 email message, which 27 contained negotiations regarding the December 2009 licensing agreement, existed before he agreed to 28 search for responsive materials at Mitsubishi’s request. Thus, Mr. Wilkins asserts, it was the timing of 8 1 Mitsubishi’s request, and not some scheme to delay, that dictated when Mr. Wilkins found and produced 2 the document. 3 It is hard to accept Mr. Wilkins’ argument that he was unaware that the November 2009 email 4 existed given the fact that the email was sent to Mr. Wilkins; two of his current attorneys, Tom Winland 5 and Jeffrey Totten; and his former attorney, Michael Schulte. (Doc. 344-3, p. 2). Counsel for Mr. 6 Wilkins previously reported to Judge Thurston that a search of the computers used by Mr. Winland and 7 Mr. Totten occurred and the email was not found. (Doc. 325, p. 3-4). In Mitsubishi’s motion for 8 reconsideration, it explains that at the time Mr. Winland and Mr. Totten received the emails their firm 9 email system automatically deleted incoming and outgoing emails after a certain period of time. (Doc. 10 475, p. 11 fn. 7). Thus, by the time GE requested the documents the emails had been deleted from the 11 server. (Id.). Despite this explanation, what perplexed Judge Thurston and perplexes this Court as well 12 is why Mr. Wilkins failed to demand that Mr. Schulte, his former attorney who participated in the 13 negotiations, conduct a diligent search until after the close of discovery. (Doc. 325, p.3-4). The fact that 14 Mr. Wilkins, Mr. Winland, and Mr. Totten did not have a copy of the email coupled with the fact that 15 they did not ask Mr. Schulte for his copy of the email during discovery lends support for Judge 16 Thurston’s determination that Mr. Wilkins engaged in gamesmanship during discovery. 17 3. Relevance of December 2011 Negotiations 18 Mr. Wilkins asserts that he did not display bad faith in failing to produce documents related to 19 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 20 because he did not consider the email exchange relevant to GE’s document requests. 21 “Relevant information for purposes of discovery is information reasonably calculated to lead to 22 the discovery of admissible evidence.” Surfvivor Media, Inc. v. Survivor Prods., 406 F.3d 625, 635 (9th 23 Cir. 2005) (internal quotation marks and citations omitted). “District courts have broad discretion in 24 determining relevancy for discovery purposes.” Id. 25 During discovery, GE requested “[a]ll documents, electronically stored information . . . relating 26 to, or evidencing [Mr. Wilkins’] licenses, offers of licenses or attempted licensing of the . . . ‘985 27 Patent[] or the technology allegedly embodied in th[at] Patent[] . . .” (Doc. 344-7, p. 18). Emails 28 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 9 1 œœœœœœœœœœœœœthat pertained to the ‘985 patent are plainly responsive to this request. Thus, the emails were 2 clearly relevant to GE’s document requests. 3 Mr. Wilkins contends that he did not consider the emails relevant because all parties, including 4 GE, made a general objection to producing documents created after the suit began in 2010. “[I]t is well- 5 settled that all grounds for objection must be stated with specificity.” Ramirez v. County of Los Angeles, 6 231 F.R.D. 407, 409 (C.D. Cal. 2005) (citing Davis v. Fendler, 650 F.2d 1154, 1160 (9th Cir. 1981)). 7 Thus, general objections are waived. Id. Because the objection Mr. Wilkins relies upon was a general 8 objection relied upon to prevent the parties from having to log communications with counsel and work 9 product documents related to preparing the case, see Doc. 343, p. 43 fn. 18, the objection was waived 10 and cannot be relied upon. 11 Mr. Wilkins also argues that the licensing negotiations are irrelevant to his damages claims. As 12 pointed out by GE, the negotiations are relevant to Mr. Wilkins’ compensatory damages claimsœœœœœœœœœœ 13 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 14 In sum, the above arguments set forth by Mr. Wilkins fail to leave the Court with “a definite and 15 firm conviction that a mistake” was committed when Judge Thurston awarded GE the costs and fees 16 associated with its motion to compel based on her determination that Mr. Wilkins engaged in 17 gamesmanship. Sec. Farms, 124 F.3d at 1014. Thus, Mr. Wilkins’ motion for reconsideration and 18 request for apportionment is DENIED. 19 B. Mitsubishi’s Request for Reconsideration 20 21 Mitsubishi seeks reconsideration of Judge Thurston’s award of attorney’s fees for GE’s motion to compel and the costs for taking additional depositions. 22 As discussed above, Judge Thurston awarded GE the costs and fees in bringing its motion to 23 compel based on her determination that Mr. Wilkins and Mitsubishi engaged in gamesmanship during 24 discovery. (Doc. 368, p. 20). Judge Thurston also authorized GE to depose Mr. Schulte and Mr. 25 Winland and ordered the cost of these depositions to be shared by Mitsubishi and Mr. Wilkins. (Doc. 26 368, p. 18). Mitsubishi contends that the award of attorney’s fees and the costs of the depositions was 27 clearly erroneous because Mitsubishi was substantially justified in lodging objections, in its privilege 28 claims, and in the way it handled the 2011 negotiation documents. 10 1 1. Objections 2 Mitsubishi takes issue with Judge Thurston’s determination that its relevancy objection was not 3 proper. Judge Thurston determined that “Mitsubishi’s general objection based upon relevance, 4 amount[ed] to a waiver of the objection.” (Doc. 368, p. 11). Mitsubishi now argues that it followed up 5 with a specific, written relevancy objection. Absent from Mitsubishi’s argument is a citation to the 6 specific, written objection. Accordingly, this argument is unpersuasive. 7 Mitsubishi further argues that its delay in producing the documents related to the negotiation of 8 the December 2009 agreement was harmless because GE now has the documents. Mitsubishi’s delay 9 in production was not harmless because GE was forced to file a motion to compel, prepare and attend 10 the hearing on the motion, and was forced to respond to the instant motion. Accordingly, Mitsubishi’s 11 delay wasted GE’s time and resources. 12 Mitsubishi also contends that GE should have pursued the motion to compel earlier instead of 13 waiting until after the close of discovery. As discussed above, in section IV.A.1., it was not until April 14 2012, that GE suspected that defendants may be withholding documents. At the beginning of April 15 2012, GE learned that a copy of the December 2009 amendment to the August 2009 “option/consulting” 16 agreement was provided to Mr. Wilkins’ expert, Mark Peterson, and when GE pursued a copy of the 17 document Mr. Wilkins initially refused to provide it but relented two weeks later. Once this occurred 18 GE became suspicious and pursued the motion to compel which resulted in the disclosure of a series of 19 documents from defendants. Accordingly, Mitsubishi’s delay in providing the documents cannot be 20 blamed on GE. 21 2. Privilege Claims 22 Mitsubishi argues that it was justified in withholding the 2009 consulting agreements under the 23 consulting-expert privilege. Mitsubishi further asserts that it did not engage in bad faith when it 24 withheld the agreements because once it was assured that production of the agreements would not result 25 in a “broader waiver” it produced the documents. 26 In awarding attorney’s fees and costs, Judge Thurston found that Mitsubishi “engaged in game- 27 playing related to . . . the consulting agreements [because] [t]hey . . . identified documents as privileged 28 when they plainly were not and delayed in producing discoverable documents.” (Doc. 368, p. 20). This 11 1 determination was not contrary to law or clearly erroneous. 2 FED . R. CIV . P. 26(b)(4)(D) provides that “[o]rdinarily, a party may not . . . discover facts known 3 or opinions held by an expert who has been retained . . . by another party in anticipation of litigation or 4 to prepare for trial and who is not expected to be called as a witness at trial.” “[T]he party who resists 5 discovery has the burden to show that discovery should not be allowed, and has the burden of clarifying 6 explaining and supporting its objections.” Cable & Computer Technology, Inc. v. Lockheed Saunders, 7 Inc., 175 F.R.D. 646, 650 (C. D. Cal. 1997). 8 Mitsubishi retained Mr. Wilkins as an expert to aid it in preparing for trial. Accordingly, 9 pursuant to FED . R. CIV . P. 26(b)(4)(D), GE was unable to discover facts known or opinions held by Mr. 10 Wilkins in his capacity as a non-testifying expert. The 2009 consulting agreements do not contain facts 11 or opinions. Rather, the agreements lay out the terms of Mitsubishi and Mr. Wilkins’ consulting 12 relationship. Thus, the agreements were not privileged under Rule 26. 13 Mitsubishi contends that consulting agreements are generally not subject to discovery. It relies 14 on two orders from the Northern District of California in support of its argument: Genentech, Inc. v. Tr. 15 of Univ. of Pennsylvania, 2011 WL 6002501 (N.D. Cal. Nov. 30, 2011) and Synopsys, Inc. v. Ricoh Co., 16 Ltd., 2006 WL 2458721 (N.D. Cal. Aug. 22, 2006).5 In both orders the Court determined that the 17 consulting agreements need not be produced but the Court made its determination based on the facts and 18 briefing of the case rather than on a general legal proposition that consulting agreements are not subject 19 to discovery. In Genentech, the Court determined that the university need not produce “further 20 documentation regarding its consulting arrangement” because Genentech already had the answers to the 21 information that it sought, i.e., Genentech already knew when the university concluded its agreement 22 with the consultant, whether the agreement was in writing, and how much the University paid the 23 consultant. Genentech, 2011 WL 6002501, at *2-3. In Synopsys, Ricoh sought unlogged and 24 unproduced documents which included a consulting agreement and documents related to the payment 25 of the non-testifying expert’s services. Synopsys, 2006 WL 2458721, at *2. The Court determined that 26 5 27 28 Mitsubishi also relies upon an order from the Southern District of New York, In re Gulf/Cities Service Tender Offer Litigation, 1990 WL 108352 (S.D. N.Y. Jul. 20, 1990). Mitsubishi’s reliance on In re Gulf is misplaced because it pertains to the attorney client privilege and work product rule. Id. at *2. It does not discuss the discoverability of consulting agreements. 12 1 Synopsys need not produce the documents because Ricoh’s request for relief was untimely, Ricoh failed 2 to demonstrate that Synopsys was withholding documents, and Ricoh failed to cite any authority to 3 support its claim that the consulting agreement should be produced. Id. at *2-3. Accordingly, in the 4 cases Mitsubishi relies upon the Courts determined that the consulting agreements need not be produced 5 based on several factors rather, than a general proposition that consulting agreements are not subject to 6 discovery. Thus, Judge Thurston’s determination that the consulting agreements were not privileged was 7 not contrary to law or clearly erroneous.6 8 Mitsubishi’s contention that it did not engage in bad faith when it withheld the documents is 9 unpersuasive. Mitsubishi asserts that it withheld the documents because it believed that disclosure of 10 the agreements would result in a waiver of Mr. Wilkins’ work product privilege but once it was assured 11 that this would not occur it produced the documents. The Court is unsure as to why Mitsubishi believed 12 disclosure of the documents would result in a waiver of Mr. Wilkins’ work produce privilege. Thus, the 13 argument is unpersuasive. 14 3. 2011 Negotiation Documents 15 Mitsubishi contends that its late disclosure of the 2011 negotiation documents was justified and 16 GE was not harmed by the delay. 17 Under FED . R. CIV . P. 26(e)(1)(A), a party who has responded to a request for production must 18 supplement or correct its response “in a timely manner if the party learns that in some material respect 19 the . . . response is incomplete . . . and if the additional . . . information has not otherwise been made 20 known to the other parties during the discovery process . . .” If a party fails to comply with Rule 26(e), 21 the party may not use that information at trial “unless the failure was substantially justified or is 22 harmless.” FED . R. CIV . P. 37(c)(1). “[T]he burden is on the party facing sanctions to prove 23 harmlessness.” Yeti by Molly, Ltd. v. Deckers Outdoor Corp., 259 F.3d 1101, 1107 (9th Cir. 2001). 24 During discovery, GE requested “[a]ll documents, electronically stored information and tangible 25 things constituting, relating to, or evidencing [Mr. Wilkins’] licenses, offers of licenses or attempted 26 27 28 6 It should be noted that Judge Thurston gave the parties an opportunity to flesh this issue out in their joint statement (Doc. 325, p. 3) but Mitsubishi chose to disclose the agreements, while holding on to its position that the agreements were not discoverable, with the hope of limiting the scope of the discovery dispute (Doc. 343, p. 57, fn. 26). 13 1 licensing of the . . . ‘985 Patent[] or the technology allegedly embodied in th[at] Patent[] . . .” (Doc. 344- 2 7, p. 18). The 2011 negotiation documents which pertained toœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœ 3 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœare plainly responsive to this request. Thus, Mitsubishi had 4 a duty to supplement its response to GE’s request for production. 5 Mitsubishi argues that it was substantially justified in its delayed disclosure of the documents 6 because the documents were created less than three months before the close of discovery at a time when 7 counsel was extremely busy. Rule 26(e)(1)(A) requires that requests for production be supplemented 8 in a timely manner. The negotiations occurred in late 2011, and the documents related to the 9 negotiations were produced over five months later, in May 2012, after GE had already filed a motion to 10 compel. A five month delay in production is not timely and the fact counsel was busy with other 11 discovery matters does not justify the delay. 12 Mitsubishi further argues that it was substantially justified in not supplementing its production 13 of documents because GE already had the operative license with the amount of fees. Thus,œœœœœœœœœœ 14 œœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœœwould not make any probative fact more likely true or false. The 15 problem with Mitsubishi’s argument is that GE requested all documents related to the license. (Doc. 16 344-7, p. 18). Thus, Mitsubishi’s duty to supplement its production of documents with the 2011 17 negotiations was obvious. 18 The above arguments set forth by Mitsubishi fail to leave the Court with “a definite and firm 19 conviction that a mistake” was committed when Judge Thurston awarded GE attorney’s fees and costs 20 for taking additional depositions. Sec. Farms, 124 F.3d at 1014. Thus, Mitsubishi’s motion for 21 reconsideration and request for apportionment is DENIED. 22 C. GE’s Request for Fees 23 In GE’s opposition, it requests recovery of the fees associated with opposing defendants’ requests 24 for reconsideration. GE requests fees given the nature of the conduct that resulted in Judge Thurston’s 25 award of sanctions, defendants’ continued defense of the conduct, and the failure of either party to 26 present new facts, circumstances, or other good cause for reconsideration as required by Local Rule 27 230(j). 28 “Three primary sources of authority enable courts to sanction parties or their lawyers for 14 1 improper conduct: (1) Federal Rule of Civil Procedure 11, which applies to signed writings filed with 2 the court, (2) 28 U.S.C. § 1927, which is aimed at penalizing conduct that unreasonably and vexatiously 3 multiplies the proceedings, and (3) the court’s inherent power.” Fink v. Gomez, 239 F.3d 989, 991 (9th 4 Cir. 2001). 5 FED . R. CIV . P. 11(c)(2) requires a motion for sanctions to be made separately from any other 6 motion and it must be served under FED . R. CIV . P. 5, but not filed or presented to the Court if the 7 challenged paper or contention is withdrawn or appropriately corrected within 21 days after service of 8 the motion. Because GE failed to comply with this procedure, GE cannot recover the fees associated 9 with opposing the instant motions. See Barber v. Miller, 146 F.3d 707, 710 (9th Cir. 1998) (reversing 10 sanctions award because the requesting party failed to follow the requirements of FED . R. CIV . P. 11). 11 Moreover, the Court does not wish to exercise its discretion pursuant to 28 U.S.C. § 1927 or its inherent 12 power to impose sanctions. Accordingly, GE’s request for attorney’s fees is DENIED. 13 V. CONCLUSION AND ORDER 14 For the reasons discussed above, this Court: 15 1. DENIES Mr. Wilkins’ motion for reconsideration and request for apportionment; 16 2. DENIES Mitsubishi’s motion for reconsideration and request for apportionment; and 17 3. DENIES GE’s request for attorney’s fees. 18 19 20 IT IS SO ORDERED. Dated: b9ed48 August 2, 2012 /s/ Lawrence J. O'Neill UNITED STATES DISTRICT JUDGE 21 22 23 24 25 26 27 28 15

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?