Brisbin v. Vulcan Materials Company

Filing 61

ORDER DENYING 53 Calmat's Motion to Compel Attendance at Deposition and Request for Sanctions. The hearing set for 7/3/2013, is VACATED. Order signed by Magistrate Judge Sheila K. Oberto on 6/28/2013. (Timken, A)

Download PDF
1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 EASTERN DISTRICT OF CALIFORNIA 10 11 12 JOHN C. BRISBIN, an individual, dba CONSTRUCTION DEVELOPMENT SYSTEMS, 13 14 15 16 17 18 CASE NO. 1:11-cv-00568-AWI-SKO ORDER DENYING CALMAT'S MOTION TO COMPEL ATTENDANCE AT DEPOSITION AND REQUEST FOR SANCTIONS Plaintiff, v. CALMAT CO, dba VULCAN MATERIALS COMPANY - WESTERN DIVISION, (Docket No. 53) Defendant, __________________________________ 19 AND RELATED ACTIONS. 20 21 22 I. INTRODUCTION 23 On June 17, 2013, Defendant/Counter-Claimant Calmat DBA Vulcan Materials Company 24 ("Calmat") filed a Motion for Order Compelling Attendance at Depositions and Request for 25 Sanctions, seeking an order compelling the attendance at depositions of the expert witnesses 26 designated by Plaintiff/Counter-Defendant John C. Brisbin, an individual and DBA Construction 27 Development Systems, ("Brisbin"). 28 Non-Opposition. (Doc. 59.) For the reasons set forth below, Calmat's motion is DENIED. On June 27, 2013, Brisbin filed a Statement of 1 1 II. RELEVANT PROCEDURAL HISTORY 2 On July 12, 2011, the Court issued a scheduling order setting a non-expert discovery 3 deadline of October 31, 2011, an expert discovery deadline of January 31, 2012, a non-dispositive 4 motion filing deadline of January, 23, 2012, a dispositive motion filing deadline of February 29, 5 2012, a settlement conference date of March 6, 2012, a pre-trial conference date of May 23, 2012, 6 and a trial date of July 17, 2012. (Doc. 13.) 7 On October 12, 2011, the parties filed a stipulation requesting to amend the scheduling 8 order, which was approved by the Court on October 17, 2011. (Docs. 15, 16.) As such, the 9 non-expert discovery deadline was continued to January 31, 2012; no other provisions of the July 10 12, 2011, scheduling order were modified. (Doc. 16.) 11 On December 29, 2011, the parties filed a stipulation requesting to amend the scheduling 12 order and continue all deadlines by 60 days to allow the parties to engage in mediation. (Doc. 13 18.) On January 5, 2012, the Court approved the request and continued the dates; the non-expert 14 and expert discovery deadlines were set for March 16, 2012, the non-dispositive motion filing 15 deadline was set for March 21, 2012, the dispositive motion filing deadline was set for April 27, 16 2012, the settlement conference was set for May 17, 2012, the pre-trial conference was set for 17 July 25, 2012, and the trial was set for September 18, 2012. (Doc. 19.) 18 On January 26, 2012, the parties filed a stipulation seeking to amend the scheduling order 19 due to Plaintiff's health issues; the Court approved the request on February 3, 2012, and set a new 20 schedule. (Docs. 20, 21.) The non-expert and expert discovery deadlines were continued to May 21 16, 2012, the non-dispositive motion filing deadline was continued to May 21, 2012, the 22 dispositive motion filing deadline was continued to June 27, 2012, the settlement conference was 23 continued to July 17, 2012, the pre-trial conference was continued September 26, 2012, and the 24 trial date was continued to November 27, 2012. (Doc. 21.) 25 On May 11, 2012, the parties filed a stipulation requesting amendment to the scheduling 26 order due to Plaintiff's ongoing health concerns. (Doc. 22.) After conferring with the parties 27 (Doc. 23), the Court issued a new scheduling order continuing the non-expert discovery to June 8, 28 2012, setting the expert disclosure deadline on June 15, 2012, the rebuttal expert disclosure 2 1 deadline for June 29, 2012, and continuing the expert discovery deadline to July 31, 2012. (Doc. 2 24.) All other deadlines remained unchanged. (Doc. 24.) 3 On August 16, 2012, the parties filed a stipulation to continue the trial and other related 4 dates due to Plaintiff's continued health issues. (Doc. 30.) On August 24, 2012, the Court issued 5 an order that continued the pre-trial conference to January 29, 2013, and the trial to March 26, 6 2013. (Doc. 31.) The parties were ordered to meet and confer and to file a stipulation regarding 7 the continuance of the remaining deadlines in the case. (Doc. 31.) 8 On August 29, 2012, the parties filed a stipulation to reset the settlement conference date 9 and extend remaining trial deadlines. (Doc. 32.) On September 4, 2012, the Court approved the 10 parties' request and ordered that the parties exchange supplemental expert disclosures on or 11 before October 1, 2012, that expert discovery be completed by December 14, 2012, and that the 12 settlement conference be continued to January 8, 2013. (Doc. 33.) No other dates or deadlines 13 were continued. 14 On January 2, 2013, the parties filed a stipulation to continue the settlement conference, 15 which was approved by the Court on January 3, 2013. (Docs. 39, 40.) The settlement conference 16 was continued to March 8, 2013; no other dates or deadlines were modified. (Doc. 40.) On 17 January 28, 2013, the parties filed a stipulation seeking to continue the pre-trial conference and 18 trial dates due to Plaintiff's health; on January 31, 2013, the Court ordered the schedule modified 19 and continued only the pre-trial conference date to June 26, 2013, and the trial date to August 20, 20 2013. (Docs. 42, 44.) No other schedule modifications were made. (Doc. 44.) 21 On March 6, 2013, the Court continued the settlement conference scheduled for March 8, 22 2013, to March 29, 2013, due to Brisbin's failure to comply with the requirements set forth in the 23 Court's December 6, 2012, Order re Settlement Conference. (Docs. 47, 48.) On March 19, 2013, 24 the Court vacated the settlement conference due to Brisbin's continued failure to comply with the 25 Court's Order re Settlement Conference. (Doc. 52.) 26 27 On June 26, 2013, a pre-trial conference was held before District Judge Ishii, and the trial was continued to November 13, 2013. (Docs. 57, 58.) 28 3 1 The Court recognizes that there were numerous schedule modifications requested and 2 granted due to mediation efforts, Plaintiff's health issues, and Plaintiff's failure to comply with 3 Court orders. However, the above referenced orders provide that the current schedule consists of 4 the following dates and deadlines: the non-expert discovery deadline was May 16, 2012, (Doc. 5 21), the expert discovery deadline was December 14, 2012, (Doc. 33), the pre-trial conference 6 was held on June 26, 2013, (Doc. 44), and the trial date is set for November 13, 2013, (Doc. 57, 7 58). There is no settlement conference currently scheduled. (Doc. 52.) 8 The parties did not request any continuances of the expert discovery deadline of 9 December 14, 2012, after it was set; the only continuances requested after that time concerned the 10 settlement conference, the pre-trial conference, and the trial. (Docs. 39, 42, 49.) Pursuant to the 11 parties' stipulated agreement and the Court's order setting the schedule, expert discovery closed 12 on December 14, 2012. (Doc. 33.) 13 III. DISCUSSION 14 Calmat's motion seeks to compel depositions of Brisbin's expert witnesses and seeks 15 monetary sanctions against Brisbin and his attorney. (Doc. 53.) Calmat indicates that, when the 16 settlement conference was scheduled for January 8, 2013, the parties "agreed to withhold taking 17 expert depositions until after the Settlement Conference." (Doc. 53, 4:17-18.) After the Court 18 ordered on March 19, 2013, that the settlement conference scheduled for March 29, 2013, be 19 vacated, on April 25, 2013, Calmat noticed the depositions of Brisbin's experts for May 13-14, 20 2013. (Doc. 52, Doc. 53, 5:4-12.) 21 On May 2, 2013, Brisbin's counsel informed Calmat's counsel that Brisbin's counsel 22 would be unable to conduct depositions as scheduled; the depositions were continued and re- 23 noticed for June 6-7, 2013. (Doc. 53, 5:14-6:13.) Brisbin's counsel contacted Calmat's counsel to 24 inform counsel that Brisbin's experts would not be available for deposition; no explanation was 25 provided for the unavailability, nor was the unavailability confirmed in writing. (Doc. 53, 26 6:15-19.) After discussion between counsel, depositions were rescheduled for June 13, 2013, but 27 canceled by Brisbin on June 12, 2013. (Doc. 53, 7:21-8:17.) Calmat's counsel discovered that 28 4 1 one of Brisbin's experts was available and could have attended the June 13, 2013, deposition. 2 (Doc. 53, 9:20-25.) 3 Calmat contends that Brisbin "has willfully and deliberately failed and refused to appear 4 for his expert deposition and deliberately refused to allow his designated experts to be deposed." 5 (Doc. 53, 10:2-4.) Calmat seeks to compel the depositions or, alternatively, bar Brisbin from 6 calling any expert witnesses at trial, and seeks monetary sanctions in the amount of $3,400. (Doc. 7 53.) 8 Brisbin filed a Statement of Non-Opposition stating that Calmat is entitled to take expert 9 depositions and proposes new dates for the depositions to take place. (Doc. 59.) Brisbin raises 10 no objections to Calmat's motion. (Doc. 59.) However, expert discovery closed in this case on 11 December 14, 2012. (Doc. 33.) The parties did not seek to continue the expert discovery 12 deadline from that date, and Calmat did not request a schedule modification in its motion. 13 Further, Calmat has not shown good cause to modify the schedule, and its motion is untimely. As 14 such, for the reasons set forth below, the Court cannot grant Calmat the relief sought and the 15 motion is DENIED. 16 A. Legal Standard for Adherence to the Scheduling Order 17 Districts courts "must issue a scheduling order" in civil actions to "limit the time to join 18 other parties, amend the pleadings, complete discovery, and file motions." Fed. R. Civ. P. 19 16(b)(1),(3). Once entered by the court, a scheduling order "controls the course of the action 20 unless the court modifies it." Fed. R. Civ. P. 16(d). Scheduling orders are intended to alleviate 21 case management problems. Johnson v. Mammoth Recreations, Inc., 975 F.2d 604, 610 (9th Cir. 22 1992). As such, a scheduling order is "the heart of case management." Koplove v. Ford Motor 23 Co., 795 F.2d 15, 18 (3rd Cir. 1986). A "scheduling conference order is not a frivolous piece of 24 paper, idly entered, which can be cavalierly disregarded without peril." Johnson, 975 F.2d at 610 25 (internal quotation marks and citation omitted). 26 27 The Ninth Circuit has established that Rule 16 deadlines must be taken seriously and that the district court: 28 5 1 needs the authority to manage the cases before it efficiently and effectively. In these days of heavy caseloads, trial courts in both the federal and state systems routinely set schedules and establish deadlines to foster the efficient treatment and resolution of cases. Those efforts will be successful only if the deadlines are taken seriously by the parties, and the best way to encourage that is to enforce the deadlines. Parties must understand that they will pay a price for failure to comply strictly with scheduling and other orders, and that failure to do so may properly support severe sanctions and exclusions of evidence. 2 3 4 5 6 Wong v. Regents of the Univ. of Cal., 410 F.3d 1052, 1060 (9th Cir. 2005); see also Singh v. 7 Arrow Truck Sales, Inc., No. 2:05-CV-2564-GEB-KJM, 2006 WL 1867540, at *2 (E.D. Cal., July 8 5, 2006) ("Rules are rules ā€“ and the parties must play by them. In the final analysis, the judicial 9 process depends heavily on the judge's credibility. To ensure such credibility, a district judge 10 must often be firm in managing crowded dockets and demanding adherence to announced 11 deadlines. If he or she sets a reasonable due date, parties should not be allowed casually to flout it 12 or painlessly to escape the foreseeable consequences of noncompliance" (citing Legault v. 13 Zambrano, 105 F.3d 24, 28-29 (1st Cir. 1997)). 14 The Ninth Circuit has deemed Rule 16 to be an essential tool in controlling heavy trial 15 court dockets by recognizing the importance of a "district court's ability to control its docket by 16 enforcing a discovery termination date, even in the face of requested supplemental discovery that 17 might have revealed highly probative evidence, when the [party's] prior discovery efforts were 18 not diligent." Cornwell v. Electra Central Credit Union, 439 F.3d 1018, 1027 (9th Cir. 2006). 19 "The use of orders establishing a firm discovery cutoff date is commonplace, and has impacts 20 generally helpful to the orderly progress of litigation, so that the enforcement of such an order 21 should come as a surprise to no one." Id. As the Ninth Circuit explained, "[d]istrict courts have 22 wide latitude in controlling discovery, and [their] rulings will not be overturned in the absence of 23 a clear abuse of discretion." Id. (citation and internal quotation marks omitted). 24 B. The Motion is Untimely 25 Though the Federal Rules of Civil Procedure place no time limit on the outside date for 26 the filing of a motion to compel discovery, motions to compel filed after the close of discovery 27 generally are deemed untimely. See, e.g., Watts v. Allstate Indem. Co., No. 2:08ā€“cvā€“01877 LKK 28 KJN, 2012 WL 5289314, at 2 (E.D. Cal., October 23, 2012) ("Motions to compel . . . discovery 6 1 had to have been heard 30 days before [the discovery] cutoff in order for discovery to be 2 completed by the cutoff."); Clinton v. California Dep't of Corr., No. CIVS05-1600-LKKCMKP, 3 2009 WL 1308984 (E.D. Cal. May 11, 2009) objections overruled, No. CIV.S-05-1600LKK 4 CMK, 2009 WL 1617811, at *7 (E.D. Cal. June 9, 2009) ("[A]ll motions to compel were to be 5 filed by the close of discovery. Therefore, any discovery requests propounded and any motions to 6 compel filed after that date are untimely."). 7 Here, expert discovery closed on December 14, 2012, and Calmat's motion was filed on 8 June 17, 2013. (Docs. 33, 53.) As such, Calmat's motion, filed more than six months after the 9 expert discovery deadline, is untimely. 10 C. The Parties Have Not Requested Modification of the Schedule 11 The expert discovery deadline in this action was December 14, 2012, the pre-trial 12 conference took place on June 26, 2013, and the trial is set for November 13, 2013. (Docs. 33, 13 44, 57.) Despite the fact that expert discovery closed in this action on December 14, 2012, 14 Calmat's motion is seeking to compel depositions of Brisbin's expert witnesses. 15 When granting a motion to compel discovery would require amendment to the scheduling 16 order, a parties' failure to seek modification of the scheduling order is a sufficient reason to deny 17 the motion. See Johnson, 975 F.2d at 608-09 (noting a court could properly deny relief that 18 would require amendment to the scheduling order solely because a party failed to request 19 modification to the scheduling order); U.S. Dominator, Inc. v. Factory Ship Robert E. Resoff, 20 768 F.2d 1099, 1104 (9th Cir. 1985), superseded by statute on other grounds, Simpson v. Lear 21 Astronics Corp., 77 F.3d 1170 (9th Cir.1996) (finding that the court may deny as untimely a 22 motion filed after the scheduling order cut-off date where no request to modify the order has been 23 made). 24 Here, neither party requested modification of the scheduling order to continue the expert 25 discovery deadline beyond December 14, 2012. Since the Court cannot grant Calmat effective 26 relief without amending the scheduling order and reopening expert discovery, the motion can be 27 denied on that basis alone. 28 7 1 The Court recognizes that the parties "agreed to withhold taking expert designations until 2 after the Settlement Conference" scheduled for January 8, 2013. (Doc. 53, 4:16-18.) However, 3 this date was past the expert discovery deadline of December 14, 2012, and neither party sought 4 approval from the Court to modify the schedule to continue the expert discovery deadline. 5 Further, "[a] schedule may be modified only for good cause and with the judge's consent." Fed. 6 R. Civ. P. 16(b)(4) (emphasis added). The parties failed to seek the Court's consent. As such, the 7 schedule was not modified to account for the parties' agreement, and expert discovery closed on 8 December 14, 2012. (Doc. 33.) 9 D. Calmat Failed to Show Good Cause to Amend the Scheduling Order 10 As noted, a party must show good cause to modify the schedule. See Fed. R. Civ. P. 11 16(b)(4). The "good cause" requirement of Rule 16 primarily considers the diligence of the party 12 seeking the amendment. Johnson, 975 F.2d at 609. "The district court may modify the pretrial 13 schedule if it cannot reasonably be met despite the diligence of the party seeking the extension." 14 Id. (internal citation and quotation marks omitted). 15 Good cause may be found to exist where the moving party shows, for example, that it: 16 (1) diligently assisted the court in recommending and creating a workable scheduling order, see In 17 re San Juan Dupont Plaza Hotel Fire Litig., 111 F.3d 220, 228 (1st Cir. 1997), (2) is unable to 18 comply with the deadlines contained in the scheduling order due to issues not reasonably 19 foreseeable at the time of the scheduling order, see Johnson, 975 F.3d at 609, and (3) was diligent 20 in seeking an amendment once the party reasonably knew that it could not comply with the 21 scheduling order, see Eckert Cold Storage, Inc. v. Behl, 943 F. Supp. 1230, 1233 (E.D. Cal. 22 1996); see also Jackson v. Laureate, Inc., 186 F.R.D. 605, 608 (E.D. Cal. 1999). "If [the] party 23 was not diligent, the inquiry should end." Johnson, 975 F.2d at 609. 24 Here, Calmat has not been diligent. As discussed above, neither party sought to extend 25 the December 14, 2012, expert discovery deadline, nor does Calmat's motion request to modify 26 the schedule. 27 settlement conference, they did not seek a court order to continue the expert discovery deadline. 28 Further, the settlement conference was vacated by the Court on March 19, 2013 (Doc. 52), but 8 Although the parties apparently agreed to hold these depositions after the 1 Calmat waited over a month until April 25, 2013, to serve notices of taking depositions for May 2 13 and 14, 2013. (Doc. 53, 5:9-12.) 3 Calmat's motion acknowledges that there were issues regarding these depositions for the 4 past several months (Doc. 53, 5:14-10:5), but did not file the motion until June 18, 2013, and 5 scheduled the hearing for July 3, 2013 ā€“ one week after the pretrial conference date of June 26, 6 2013. As such, Calmat was seeking to conduct further discovery after the pre-trial conference 7 was held. While the trial has now been continued to November 13, 2013, the expert discovery 8 deadline closed more than six months ago, and it is far too late into the schedule to seek to 9 compel discovery. (Doc. 33.) 10 In sum, Calmat has failed to explain its delay in seeking to compel the depositions and, as 11 such, cannot show that it has been diligent in seeking amendment to the schedule. Thus Calmat 12 failed to show good cause to modify the schedule to allow additional time for discovery. For the 13 reasons set forth above, Calmat's motion is DENIED. Brisbin does not oppose Calmat's motion 14 and acknowledges that Calmat is entitled to conduct expert depositions. (Doc. 59.) As such, the 15 Court encourages the parties to reach an agreement between them to conduct the depositions; the 16 Court will not, however, compel the depositions for the reasons set forth in this order. 17 IV. 18 Accordingly, IT IS HEREBY ORDERED that: 19 1. Calmat's Motion to Compel Attendance at Depositions and Request for Sanctions 20 21 CONCLUSION AND ORDER is DENIED; and 2. The hearing scheduled for July 3, 2013, is VACATED. 22 23 24 25 26 IT IS SO ORDERED. Dated: June 28, 2013 /s/ Sheila K. Oberto UNITED STATES MAGISTRATE JUDGE 27 28 DEAC_Signature-END: ie14hje 9

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?