Black & Veatch Corporation v. Modesto Irrigation District
Filing
231
FINDINGS and RECOMMENDATIONS recommending that Black & Veatch Corporation's Motion for determination of Good Faith Settlement 223 be GRANTED. Matter referred to Judge O'Neill; Objections to F&R due within ten (10) days of service of this recommendation; signed by Magistrate Judge Sheila K. Oberto on 2/4/2013. (Timken, A)
1
2
UNITED STATES DISTRICT COURT
3
EASTERN DISTRICT OF CALIFORNIA
4
5
BLACK & VEATCH CORPORATION,
CASE NO. 1:11-cv-00695-LJO-SKO
6
Plaintiff,
FINDINGS AND
RECOMMENDATIONS THAT
BLACK & VEATCH'S MOTION FOR
GOOD FAITH SETTLEMENT AND
INDEMNITY BAR BE GRANTED
7
v.
8
MODESTO IRRIGATION DISTRICT,
9
10
Defendant.
(Docket No. 223)
11
OBJECTIONS DUE: 10 days
12
MODESTO IRRIGATION DISTRICT,
13
Counterclaimant,
14
v.
15
BLACK & VEATCH CORPORATION,
16
Counterdefendant.
17
18
AND RELATED ACTIONS.
19
/
20
21
I. INTRODUCTION
22
On December 31, 2012, Plaintiff/Counter-Defendant Black & Veatch ("B&V") filed an
23
Application for Motion for Good Faith Settlement and Indemnity Bar. (Doc. 223.) Third-Party
24
Defendant/Counterclaimant/Cross-Defendant/Cross-Complainant Western Summit Constructors,
25
Inc. ("Western Summit") filed a Statement of Non-Opposition, and no other party has filed a
26
responsive brief. The Court has reviewed the motion as well as the supporting documentation and
27
finds that the matter is suitable for decision without oral argument pursuant to Rule 230(g) of the
28
1
Local Rules of the United States District Court, Eastern District of California; thus, the February 6,
2
2013, hearing is VACATED.
3
4
For the reasons set forth below, the Court RECOMMENDS that B&V's Motion for Good
Faith Settlement and Indemnity Bar be GRANTED.
5
II. FACTUAL AND PROCEDURAL BACKGROUND
6
Pursuant to B&V's complaint, filed on April 29, 2011, this case arises out of a contractual
7
dispute regarding work performed during the expansion of the Modesto Regional Water Treatment
8
Plant (the "Project"). (Doc. 1, ¶¶ 5-8.) B&V and Modesto Irrigation District ("MID") entered into
9
a written contract, and then an amended contract, for the design and construction of the Project.
10
(Doc. 1, ¶¶ 9-15.) B&V's complaint alleges that MID and B&V discussed amending their agreement
11
to include further construction phase work that extended beyond the original 2009 completion date
12
and to provide compensation for those services. (Doc. 1, ¶ 17.) B&V contends that it provided
13
additional services throughout 2010 at MID's direction and that MID assured B&V that its requests
14
for a contract amendment and additional compensation would be timely and fairly addressed. (Doc.
15
1, ¶¶ 18-31.) However, B&V was not paid for these services. (Doc. 1, ¶ 33-34.)
16
MID’s counterclaim was filed on July 25, 2011, and alleges B&V’s construction phase
17
services commenced in June 2007 after MID’s construction contract was awarded to Western
18
Summit. (Doc. 17, ¶ 18.) During the construction phase, MID alleges that the construction was
19
behind schedule, there were numerous engineering defects and errors attributable to B&V, and
20
widespread quality control errors by Western Summit that were not adequately addressed by B&V
21
in its capacity as construction manager. (Doc. 17, ¶ 19.) MID pleads that B&V’s failure to fulfill
22
its duties as the construction manager resulted in damages and a widespread overpayment by MID.
23
(Doc. 17, ¶ 23.) As a result, in September 2010, MID suspended its contract with B&V and was
24
required to retain other professionals to rectify the substantial problems caused by B&V. (Doc. 17,
25
¶ 24.)
26
On August 8, 2011, MID filed a complaint-in-impleader against third-party defendants
27
Western Summit, Big B Constructors, Inc. ("Big B"); Federal Insurance Company; Fidelity and
28
2
1
Deposit Company of Maryland; and Travelers Casualty and Surety Company of America.1 The
2
complaint-in-impleader alleges that Western Summit and Big B entered into a written subcontract
3
agreement.
4
deficiencies with Western Summit and Big B’s work, which substantially delayed the project and
5
prevented its completion. (Doc. 22, ¶¶ 23-24.)
(Doc. 22, ¶ 20.)
During construction, MID discovered numerous defects and
6
On August 19, 2011, City of Modesto ("City") filed a motion for intervention, which was
7
granted by the Court on October 12, 2011. (Docs. 25, 49.) City of Modesto filed a counter-claim on
8
October 14, 2011, alleging that the purpose of the Project was to provide water to City, and that, in
9
exchange for paying for the construction of the Project and its maintenance, City was entitled to the
10
entire output of treated water provided by the Project. (Doc. 50-1, ¶ 8.) Accordingly, City sought
11
damages based on B&V's alleged breaches in managing the Project. (Doc. 50-1, ¶¶ 33-36.)
12
On April 30, 2012, Western Summit filed a cross-claim against Siemens Industry, Inc. fka
13
Siemens Water Technologies Corporation ("Siemens"), alleging that Western Summit and Siemens
14
entered into a contract for goods and special services for the delivery and installation of the
15
membrane filtration system for the Project; the contract included an indemnification clause. (Doc.
16
100, ¶ 10.) Western Summit sought express, implied, and equitable indemnity from Siemens. (Doc.
17
100, ¶¶ 18-35.) On June 21, 2012, Siemens answered and filed a counter-claim against Western
18
Summit for breach of contract, alleging that Western Summit had not been paid for services
19
provided, including the removal of the installed membrane filtration modules. (Doc. 128, ¶¶ 18-23.)
20
On October 2, 2012, B&V and MID respectively filed Motions for Summary Judgment,
21
which remain pending before the District Judge Lawrence J. O'Neill. (Docs. 193, 195.) On October
22
11, 2012, a Notice of Partial Settlement was filed representing that a settlement had been reached
23
between B&V, MID, and City. (Doc. 213.) The instant Motion for Good Faith Settlement was filed
24
on December 31, 2012. (Doc. 223.)
25
26
27
28
1
The insurance companies have not been served and have not appeared in this action, as the appearing parties
have set forth that MID's complaint-in-impleader is not yet at issue. (Doc. 57, 3:4-9.)
3
1
2
III. DISCUSSION
A.
Legal Standard
3
A motion for good faith settlement is governed by California Code of Civil Procedure §§ 877
4
and 877.6, which apply to federal court diversity proceedings and authorizes the Court to determine
5
whether a settlement agreement was entered into in good faith.2 See Slottow v. Am. Cas. Co. of
6
Reading, Penn., 10 F.3d 1355 (9th Cir. 1993) (en banc). In relevant part, section 877 states as
7
follows:
8
9
10
11
12
Where a release, dismissal with or without prejudice, or covenant not to enforce
judgment is given in good faith before verdict or judgment to one or more of a
number of tortfeasors claimed to be liable for the same tort, or to one or more other
co-obligators mutually subject to contribution rights, it shall have the following
effect:
(a) It shall not discharge any such party from liability unless its terms so provide, but
it shall reduce the claims against the others in the amount stipulated by the release,
the dismissal or the covenant, or in the amount of the consideration paid for it, which
ever is greater.
13
14
(b) It shall discharge the party to whom it is given from all liability for any
contribution to any other parties.
15
Cal. Civ. Proc. Code § 877; see also Rutgard v. Haynes, 61 F. Supp. 2d 1082, 1085 (S.D. Cal. 1999).
16
The legislative objectives in promulgating Section 877 were "equitable sharing of costs among the
17
parties at fault, and . . . encouragement of settlements." River Garden Farms, Inc. v. Super. Ct.,
18
26 Cal. App. 3d 986, 993 (1972). However, "equitable sharing" does not require equal sharing. Id.
19
The California Supreme Court has held that "[t]he good faith provision of section 877
20
mandates that the courts review agreements purportedly made under its aegis to insure that such
21
settlements appropriately balance the contribution statute's dual objectives." Tech-Bilt, Inc. v.
22
Woodward-Clyde & Assocs., 38 Cal. 3d 488, 494 (1985). In considering whether the settlement is
23
in good faith, the factors to consider include the following:
24
25
26
a rough approximation of plaintiffs' total recovery and the settlor's proportionate
liability, the amount paid in settlement, the allocation of settlement proceeds among
plaintiffs, and a recognition that a settlor should pay less in settlement than he would
if he were found liable after trial. Other relevant considerations include the financial
conditions and insurance policy limits of settling defendants, as well as the existence
27
28
2
Section 877.6 provides that good faith settlements are subject to approval of the court through noticed motion
and hearing. See Cal. Civ. Proc. Code § 877.6(a)(1). Section 877.6 is the procedural vehicle under which B&V brings
its motion.
4
1
of collusion, fraud, or tortuous conduct aimed to injure the interests of the nonsettling
defendants.
2
3
Id. at 499 (citations omitted).
4
A party opposing the motion for good faith settlement bears the burden of establishing a lack
5
of good faith. Id. at 493; see also Cal. Civ. Proc. Code § 877.6(d). An opposing party "must
6
demonstrate . . . that the settlement is so far 'out of the ballpark' in relation to these factors as to be
7
inconsistent with the equitable objectives of the statute." Id. at 499-500. The determination as to
8
whether a settlement is made in good faith is a matter within the court's discretion. Id. at 502.
9
B.
Terms of Settlement
10
The settlement at issue in this motion is the settlement agreement reached between B&V,
11
MID, and City. B&V's motion represents that B&V, MID, and City participated in extensive
12
mediation and settlement efforts and have agreed to settle the claims and allegations amongst them.
13
B&V sets forth the following material terms of the settlement agreement:
14
1.
B&V will pay jointly MID and the City $8.5 million.
15
2.
B&V will assign to MID (a) its $3.0 million claim for equitable
adjustment against MID, (which MID passed through to Western
Summit in its impleader action, and (b) B&V's express defense and
indemnity rights against Western Summit. All other B&V claims
against MID and/or the City will be released and discharged.
3.
MID and the City will release and discharge any and all claims
regarding the MID-B&V Agreements and the Project.
4.
MID will indemnify, defend, and hold B&V harmless as against any
third party claims arising out of the Project, including, without
limitation, MID's continued use of the B&V prepared Project
drawings and specifications.
16
17
18
19
20
21
22
(Doc. 223-1, 5:15-6:8.)
23
C.
Analysis
24
As set forth above, in determining whether a settlement falls within the reasonable range, the
25
court should weigh the amount of the settlement in light of (1) the rough approximation of the
26
plaintiff's potential recovery and the settlor's proportionate liability in view of the settlement amount;
27
(2) a recognition that a settlor should pay less in settlement than if found liable at trial; (3) the
28
financial conditions and insurance policy limits of the settling defendants; and (4) any evidence, or
5
1
absence of evidence, of collusion, fraud or tortious conduct between the settling parties aimed at
2
making non-settling parties pay more than their fair share. Tech-Bilt, Inc., 38 Cal. 3d at 499.
3
1.
4
"A determination as to the good faith of a settlement, within the meaning of section 877.6,
5
necessarily requires the trial court to examine and weigh a number of relevant factors, one of the
6
most important of which is the settling party's proportionate liability." Toyota Motor Sales U.S.A.,
7
Inc. v. Super. Ct., 220 Cal. App. 3d 864, 871 (1990). A "settlement figure must not be grossly
8
disproportionate to what a reasonable person, at the time of the settlement, would estimate the . . .
9
liability to be." Torres v. Union Pac. R. R. Co., 157 Cal. App. 3d 499, 508 (1984).
Proportionate Liability
10
B&V asserts that the damages alleged by MID and City in their respective counter-claims
11
overlap for the most part and amount to a prayer of approximately $25 million. (Doc. 223-1,
12
7:17-20.) B&V contends, however, that there are multiple factors and defenses in B&V's favor that
13
could reduce MID and City's potential recovery to an amount significantly less than the alleged
14
damages. These factors and defenses include: (1) MID's Rule 26 Disclosure Statement allocates
15
$11.2 as B&V's alleged share of liability for the claimed Project delays and deficiencies, (2) B&V's
16
engineering contract includes a limitation of liability in an amount not to exceed $5 million and
17
includes a waiver of consequential damages, (3) the MID-Western Summit contract includes an
18
obligation by Western Summit to defend and indemnify B&V, and (4) B&V has asserted in its
19
motion for summary judgment, pending before the Court (Doc. 193), that MID and City 's contract
20
and tort claims were barred by contract.
21
22
As such, the Court finds that the material terms of the settlement agreement set out in B&V's
motion are within the reasonable range of B&V's proportionate share of comparative liability.
23
2.
24
The Court has considered and recognizes that the settlement amount is less than the amount
25
Settlement Amount
B&V may have paid had it been found liable. Tech-Bilt, Inc., 38 Cal. 3d at 499.
26
3.
27
There are no disputes regarding B&V's financial condition and insurance policy limits. The
28
parties agreed to the settlement terms through the assistance of counsel after arm's length
Financial Conditions and Insurance Policy Limits
6
1
negotiations before a neutral mediator, which indicates that any ability of B&V to pay a larger
2
amount has been balanced against the facts of the case and the degree to which B&V is liable.
3
Therefore, the Court finds this factor does not weigh against finding that the parties have entered into
4
a good faith settlement.
5
4.
6
Finally, there is no evidence of collusion, fraud, or tortious conduct aimed to injure the
7
interests of the other remaining parties. Significantly, no opposition to B&V's motion has been filed.
8
Further, the settlement agreement has been approved by both the MID Board of Directors and the
9
Modesto City Council. (Doc. 223-2, Cali Decl., ¶ 5., Exh. 4.) This factor also weighs in favor of
10
11
12
a finding that the parties have entered into a good faith settlement.
In sum, the above factors weigh in favor of granting B&V's motion for a determination of
good faith settlement.
13
14
15
Evidence of Collusion, Fraud, or Tortious Conduct
IV. CONCLUSION AND RECOMMENDATION
Based on consideration of the declarations, pleadings, and exhibits to the present motion, the
Court RECOMMENDS that:
16
1.
B&V's motion for determination of good faith settlement be GRANTED; and
17
2.
Pursuant to California Code of Civil Procedure, Sections 877 and 877.6(c), B&V is
18
hereby discharged from all liability for any contribution, equitable comparative
19
contribution, or partial or comparative indemnity, to the other parties including,
20
without limitation, the named third-party defendants and/or cross-defendants to this
21
litigation, specifically Western Summit, Big B Contractors, Inc., and Siemens
22
Industry, Inc., f/a Siemens Water Technologies Corporation.
23
These findings and recommendations are submitted to the district judge assigned to this
24
action, pursuant to 28 U.S.C. § 636(b)(1)(B) and this Court's Local Rule 304. Within ten (10) days
25
of service of this recommendation, any party may file written objections to these findings and
26
recommendations with the Court and serve a copy on all parties. Such a document should be
27
captioned "Objections to Magistrate Judge's Findings and Recommendations." The district judge
28
will review the magistrate judge's findings and recommendations pursuant to 28 U.S.C.
7
1
§ 636(b)(1)(C). The parties are advised that failure to file objections within the specified time may
2
waive the right to appeal the district judge's order. Martinez v. Ylst, 951 F.2d 1153 (9th Cir. 1991).
3
4
IT IS SO ORDERED.
5
Dated:
ie14hj
February 4, 2013
/s/ Sheila K. Oberto
UNITED STATES MAGISTRATE JUDGE
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?