Frontier Contracting, Inc. et al v. Allen Engineering Contractor, Inc. et al
Filing
51
ORDER on Frontier Contracting's Motion to Dismiss Amended Counterclaim 48 49 , signed by District Judge Lawrence J. O'Neill on 7/9/12. Motion hearing set for 7/11/2012 VACATED.(Verduzco, M)
1
2
3
4
5
6
IN THE UNITED STATES DISTRICT COURT
7
FOR THE EASTERN DISTRICT OF CALIFORNIA
8
9
10
FRONTIER CONTRACTING, INC.,
et al.,
11
12
13
CASE NO. CV F 11-1590 LJO DLB
ORDER ON FRONTIER CONTRACTING’S
MOTION TO DISMISS AMENDED
COUNTERCLAIM
(Docs. 48, 49.)
Plaintiffs,
vs.
ALLEN ENGINEERING CONTRACTOR,
INC., et al.,
14
Defendants.
15
/
16
17
AND RELATED COUNTERACTION
18
__________________________________/
19
20
INTRODUCTION
21
Plaintiff/counter-defendant Frontier Contracting, Inc. (“Frontier”) seeks to dismiss as
22
insufficiently pled defendant/counterclaimant Allen Engineering Contractor, Inc.’s (“Allen’s”)
23
counterclaims that Frontier committed subcontractor breaches on two separate construction projects in
24
Sequoia National Park (“Park”). Allen responds that Frontier challenges the truth of the counterclaims’
25
facts rather than their sufficiency and fails to identify meaningful errors with Allen’s counterclaims.
26
This Court considered Frontier’s F.R.Civ.P. 12(b)(6) motion to dismiss on the record and VACATES
27
the July 11, 2012 hearing, pursuant to Local Rule 230(g). For the reasons discussed below, this Court
28
DENIES dismissal of Allen’s first amended counterclaim (“FACC”).
1
1
BACKGROUND1
2
Construction Projects
3
Allen entered into two separate contracts with the Federal Highway Administration (“FHA”) to
4
improve and rebuild in the Park the Generals Highway (“highway project”) and Cedar Grove Bridge
5
(“bridge project”). The highway and bridge projects (collectively “projects”) are more than 70 miles
6
apart at opposite Park ends. Allen subcontracted work to Frontier and, at Frontier’s request, performed
7
certain work required of Frontier. Frontier challenges Allen’s FACC.
8
Allen’s Breach Of Contract Claims2
9
On April 14, 2010, Frontier and Allen entered into a “part oral and part written contract”
10
(“highway agreement”) by which Frontier was to perform certain work for the highway project. On
11
August 24, 2010, Frontier and Allen entered into a “part oral part written agreement” (“bridge
12
agreement”) by which Frontier was to perform certain work for the bridge project. Highway agreement
13
terms are evidenced in part by an April 15, 2010 Statement and Acknowledgment form with
14
“breakdowns attached.” Bridge agreement terms are evidence in part by a September 10, 2010
15
Statement and Acknowledgment form with attachments. Additional highway and bridge agreement
16
documents include plans, specifications, drawings, solicitation, and FHA contract documents.
17
Frontier breached the highway and bridge agreements in that Frontier:
18
1.
“[D]id not have substantial experienced structural concrete crews, other specialized
19
skilled trade laborers and experienced supervision” and did not provide “properly sized
20
and/or experienced supervision and crews”;
21
2.
Provided false financial statements to misrepresent Frontier’s financial condition;
22
3.
Failed to maintain its “A” contractor’s license during the performance of the highway and
23
24
bridge agreements;
4.
25
Failed to maintain workers’ compensation insurance and to pay Davis-Bacon fringes to
result in Allen’s $175,268 payment with a $156,308 unpaid balance;
26
1
27
28
The factual recitation is derived generally from Allen’s FACC, the target of Frontier’s challenges, as well
as other matters which this Court may consider on a F.R.Civ.P. 12(b)(6) motion.
2
The FACC includes (first and second) breach of contract claims which are summarized below.
2
1
5.
Used equipment which was neither licensed, registered, operational nor safe;
2
6.
Lacked an adequate volumetric mixer;
3
7.
Failed to provide a retained engineering firm with necessary documents to complete
4
designs;
5
8.
Charged Allen credit accounts $6,629.26 for fuel;
6
9.
Required Allen “to continuously supplement or replace Frontier’s workforce and
7
supervision”; and
8
10.
Underestimated substantially completion of bridge agreement items.
9
For the highway and bridge agreements, Allen issued Frontier a stop notice on June 29, 2011 and
10
terminated Frontier on July 22, 2011. The FACC seeks $1.8 million damages for Frontier’s breach of
11
the highway agreement and $2 million damages for Frontier’s breach of the bridge agreement.
12
Reasonable Value Claims
13
The FACC’s (third and fourth) reasonable value claims allege that “Frontier was not able to
14
perform its scope of work” and that “[p]ursuant to Frontier’s request Allen furnished labor, materials,
15
services and equipment to assist Frontier in performing its scope of work.” The claims identify work
16
which Allen performed at Frontier’s request to include retaining wall excavation and improvements,
17
shoring, gangbox improvements, cofferdam installation, supersack installation, and re-engineering plans.
18
The claims seek to recover the “reasonable value of the labor, materials, services, and equipment
19
rendered to Frontier.”
20
21
22
23
Promissory Fraud Claims
The FACC’s (fifth and sixth) promissory fraud claims allege that Frontier induced Allen to enter
into the highway and bridge agreements by promising that Frontier:
1.
24
25
“[W]ould provide substantially experienced structural concrete crews, other specialized
skilled trade laborers as well as experienced supervision”;
2.
26
Had ability to finance the highway and bridge agreements and Frontier’s portion of
Allen’s agreements with the FHA;
27
3.
Would maintain its “A” license during the highway and bridge agreements;
28
4.
Would maintain workers’ compensation insurance and other insurance required by
3
1
2
Allen’s projects agreements with FHA;
5.
3
4
Would comply with employee payment requirements of Allen’s projects agreements with
FHA;
6.
5
Would provide operating, insured and properly registered construction equipment to
complete the projects;
6
7.
Would retain and pay an engineering firm to provide engineering for the projects; and
7
8.
Would perform work required for the projects at stated prices.
8
The promissory fraud claims allege that “Frontier did not perform its promises” in that Frontier
9
“was financially unsound requiring Allen to provide Frontier with an up front payment of $50,000.00
10
just so Frontier could mobilize to the project site; Frontier provided construction equipment which was
11
not registered, not insured, not operating, and not safe; Frontier did not provide experienced construction
12
crews or supervision; and Frontier failed to maintain its workers compensation insurance and
13
contractor’s license.” The promissory fraud claims attribute “project delays” to Frontier’s false
14
promises.
15
DISCUSSION
16
F.R.Civ.P. 12(b)(6) Motion To Dismiss Standards
17
18
Frontier argues that the FACC is subject to global attack for failure to satisfy F.R.Civ.P. 8
pleading standards to warrant F.R.Civ.P. 12(b)(6) dismissal.
19
“When a federal court reviews the sufficiency of a complaint, before the reception of any
20
evidence either by affidavit or admissions, its task is necessarily a limited one. The issue is not whether
21
a plaintiff will ultimately prevail but whether the claimant is entitled to offer evidence to support the
22
claims.” Scheurer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683 (1974); Gilligan v. Jamco Development
23
Corp., 108 F.3d 246, 249 (9th Cir. 1997). A F.R.Civ.P. 12(b)(6) dismissal is proper where there is either
24
a “lack of a cognizable legal theory” or “the absence of sufficient facts alleged under a cognizable legal
25
theory.” Balisteri v. Pacifica Police Dept., 901 F.2d 696, 699 (9th Cir. 1990); Graehling v. Village of
26
Lombard, Ill., 58 F.3d 295, 297 (7th Cir. 1995). A F.R.Civ.P. 12(b)(6) motion “tests the legal sufficiency
27
of a claim.” Navarro v. Block, 250 F.3d 729, 732 (9th Cir. 2001).
28
In addressing dismissal, a court must: (1) construe the complaint in the light most favorable to
4
1
the plaintiff; (2) accept all well-pleaded factual allegations as true; and (3) determine whether plaintiff
2
can prove any set of facts to support a claim that would merit relief. Cahill v. Liberty Mut. Ins. Co., 80
3
F.3d 336, 337-338 (9th Cir. 1996). Nonetheless, a court is not required “to accept as true allegations that
4
are merely conclusory, unwarranted deductions of fact, or unreasonable inferences.” In re Gilead
5
Sciences Securities Litig., 536 F.3d 1049, 1055 (9th Cir. 2008) (citation omitted). A court “need not
6
assume the truth of legal conclusions cast in the form of factual allegations,” U.S. ex rel. Chunie v.
7
Ringrose, 788 F.2d 638, 643, n. 2 (9th Cir.1986), and must not “assume that the [plaintiff] can prove facts
8
that it has not alleged or that the defendants have violated . . . laws in ways that have not been alleged.”
9
Associated General Contractors of California, Inc. v. California State Council of Carpenters, 459 U.S.
10
519, 526, 103 S.Ct. 897 (1983). A court need not permit an attempt to amend if “it is clear that the
11
complaint could not be saved by an amendment.” Livid Holdings Ltd. v. Salomon Smith Barney, Inc.,
12
416 F.3d 940, 946 (9th Cir. 2005).
13
A “plaintiff’s obligation to provide the ‘grounds’ of his ‘entitlement to relief’ requires more than
14
labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Bell
15
Atl. Corp. v. Twombly, 550 U.S. 554,127 S. Ct. 1955, 1964-65 (2007) (internal citations omitted).
16
Moreover, a court “will dismiss any claim that, even when construed in the light most favorable to
17
plaintiff, fails to plead sufficiently all required elements of a cause of action.” Student Loan Marketing
18
Ass'n v. Hanes, 181 F.R.D. 629, 634 (S.D. Cal. 1998). In practice, a complaint “must contain either
19
direct or inferential allegations respecting all the material elements necessary to sustain recovery under
20
some viable legal theory.” Twombly, 550 U.S. at 562, 127 S.Ct. at 1969 (quoting Car Carriers, Inc. v.
21
Ford Motor Co., 745 F.2d 1101, 1106 (7th Cir. 1984)).
22
23
24
25
26
In Ashcroft v. Iqbal, 556 U.S. 662, 129 S.Ct. 1937,1949 (2009), the U.S. Supreme Court
explained:
. . . a complaint must contain sufficient factual matter, accepted as true, to “state
a claim to relief that is plausible on its face.” . . . A claim has facial plausibility when the
plaintiff pleads factual content that allows the court to draw the reasonable inference that
the defendant is liable for the misconduct alleged. . . . The plausibility standard is not
akin to a “probability requirement,” but it asks for more than a sheer possibility that a
defendant has acted unlawfully. (Citations omitted.)
27
28
After discussing Iqbal, the Ninth Circuit Court of Appeals summarized: “In sum, for a complaint
5
1
to survive [dismissal], the non-conclusory ‘factual content,’ and reasonable inferences from that content,
2
must be plausibly suggestive of a claim entitling the plaintiff to relief.” Moss v. U.S. Secret Service, 572
3
F.3d 962, 989 (9th Cir. 2009) (quoting Iqbal, 556 U.S. 662, 129 S.Ct. at 1949).
4
The U.S. Supreme Court applies a “two-prong approach” to address dismissal:
5
First, the tenet that a court must accept as true all of the allegations contained in
a complaint is inapplicable to legal conclusions. Threadbare recitals of the elements of
a cause of action, supported by mere conclusory statements, do not suffice. . . . Second,
only a complaint that states a plausible claim for relief survives a motion to dismiss. . .
. Determining whether a complaint states a plausible claim for relief will . . . be a
context-specific task that requires the reviewing court to draw on its judicial experience
and common sense. . . . But where the well-pleaded facts do not permit the court to infer
more than the mere possibility of misconduct, the complaint has alleged – but it has not
“show[n]”-“that the pleader is entitled to relief.” Fed. Rule Civ. Proc. 8(a)(2).
6
7
8
9
10
11
12
In keeping with these principles a court considering a motion to dismiss can
choose to begin by identifying pleadings that, because they are no more than conclusions,
are not entitled to the assumption of truth. While legal conclusions can provide the
framework of a complaint, they must be supported by factual allegations. When there are
well-pleaded factual allegations, a court should assume their veracity and then determine
whether they plausibly give rise to an entitlement to relief.
13
14
Iqbal, 556 U.S. 662, 129 S.Ct. at 1949-1950.
15
Moreover, a court may consider exhibits submitted with the complaint. Durning v. First Boston
16
Corp., 815 F.2d 1265, 1267 (9th Cir. 1987);Van Winkle v. Allstate Ins. Co., 290 F.Supp.2d 1158, 1162,
17
n. 2 (C.D. Cal. 2003). A “court may consider evidence on which the complaint ‘necessarily relies’ if:
18
(1) the complaint refers to the document; (2) the document is central to the plaintiff's claim; and (3) no
19
party questions the authenticity of the copy attached to the 12(b)(6) motion.” Marder v. Lopez, 450 F.3d
20
445, 448 (9th Cir. 2006). A court may treat such a document as “part of the complaint, and thus may
21
assume that its contents are true for purposes of a motion to dismiss under Rule 12(b)(6).” United States
22
v. Ritchie, 342 F.3d 903, 908 (9th Cir.2003). Such consideration prevents “plaintiffs from surviving a
23
Rule 12(b)(6) motion by deliberately omitting reference to documents upon which their claims are
24
based.” Parrino v. FHP, Inc., 146 F.3d 699, 706 (9th Cir. 1998).3 A “court may disregard allegations
25
in the complaint if contradicted by facts established by exhibits attached to the complaint.” Sumner Peck
26
3
27
28
“W e have extended the ‘incorporation by reference’ doctrine to situations in which the plaintiff’s claim
depends on the contents of a document, the defendant attaches the document to its motion to dismiss, and the parties do not
dispute the authenticity of the document, even though the plaintiff does not explicitly allege the contents of that document
in the complaint.” Knievel v. ESPN, 393 F.3d 1068, 1076 (9th Cir. 2005) (citing Parrino, 146 F.3d at 706).
6
1
Ranch v. Bureau of Reclamation, 823 F.Supp. 715, 720 (E.D. Cal. 1993) (citing Durning v. First Boston
2
Corp., 815 F.2d 1265, 1267 (9th Cir.1987)).
3
F.R.Civ.P. 8 Pleading Standards
4
F.R.Civ.P. 8 requires a party to “plead a short and plain statement of the elements of his or her
5
claim, identifying the transaction or occurrence giving rise to the claim and the elements of the prima
6
facie case.” Bautista v. Los Angeles County, 216 F.3d 837, 840 (9th Cir. 2000).
7
F.R.Civ.P. 8(d)(1) requires each allegation to be “simple, concise, and direct.” This requirement
8
“applies to good claims as well as bad, and is the basis for dismissal independent of Rule 12(b)(6).”
9
McHenry v. Renne, 84 F.3d 1172, 1179 (9th Cir. 1996). Moreover, a pleading may not simply allege a
10
wrong has been committed and demand relief. The underlying requirement is that a pleading give “fair
11
notice” of the claim being asserted and the “grounds upon which it rests.” Yamaguchi v. United States
12
Department of Air Force, 109 F.3d 1475, 1481 (9th Cir. 1997). Despite the flexible pleading policy of
13
the Federal Rules of Civil Procedure, a complaint must give fair notice and state the elements of the
14
claim plainly and succinctly. Jones v. Community Redev. Agency, 733 F.2d 646, 649 (9th Cir. 1984).
15
A plaintiff must allege with at least some degree of particularity overt facts which defendant engaged
16
in to support plaintiff’s claim. Jones, 733 F.2d at 649. A complaint does not suffice “if it tenders
17
‘naked assertion[s]’ devoid of ‘further factual enhancement.’” Iqbal, 556 U.S. 662, 129 S.Ct. at 1949
18
(quoting Twombly, 550 U.S. at 557, 127 S.Ct. 1955). The U.S. Supreme Court has explained:
19
While, for most types of cases, the Federal Rules eliminated the cumbersome
requirement that a claimant “set out in detail the facts upon which he bases his claim,”
Conley v. Gibson, 355 U.S. 41, 47, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957) (emphasis added),
Rule 8(a)(2) still requires a “showing,” rather than a blanket assertion, of entitlement to
relief. Without some factual allegation in the complaint, it is hard to see how a claimant
could satisfy the requirement of providing not only “fair notice” of the nature of the
claim, but also “grounds” on which the claim rests.
20
21
22
23
24
25
26
Twombly, 550 U.S. at 556, n. 3, 127 S.Ct. 1955.
With these F.R.Civ.P. 8 and 12(b)(6) standards in mind, this Court turns to Frontier’s challenges
to the FACC.
Breach Of Contract
27
Although the FACC alleges reasonable value and promissory fraud claims, Frontier focuses on
28
breach of contract. Frontier appears to contend that the entire FACC rests on breach of contract
7
1
allegations.
2
Allen characterizes Frontier’s challenges as a “regurgitation” of Frontier’s prior motion to
3
dismiss Allen’s original counterclaim. Allen accuses Frontier of misstating the FACC and argues that
4
the FACC satisfies breach of contract elements.
5
“The standard elements of a claim for breach of contract are: ‘(1) the contract, (2) plaintiff's
6
performance or excuse for nonperformance, (3) defendant's breach, and (4) damage to plaintiff
7
therefrom.’”
8
Cal.Rptr.3d 6 (2008). “To form a contract, an ‘offer must be sufficiently definite . . . that the
9
performance promised is reasonably certain.’”
10
Wall Street Network, Ltd. v. New York Times Co., 164 Cal.App.4th 1171, 1178, 80
Alexander v. Codemasters Group Limited, 104
Cal.App.4th 129, 141. 127 Cal.Rptr.2d 145 (2002).
11
“A written contract may be pleaded either by its terms – set out verbatim in the complaint or a
12
copy of the contract attached to the complaint and incorporated therein by reference – or by its legal
13
effect. In order to plead a contract by its legal effect, plaintiff must allege the substance of its relevant
14
terms.” McKell v. Washington Mutual, Inc., 142 Cal.App.4th 1457, 1489, 49 Cal.Rptr.3d 227 (2006)
15
(internal citations omitted).
16
Frontier argues that the FACC lacks allegations as to formation, terms and breach of the highway
17
and bridge agreements. Frontier claims that the FACC does not plead “any terms of the contract and
18
thus provides no basis to determine plausibility of Allen’s breach of contract claims. Frontier continues
19
that the FACC is “impossible to understand” with “its failure to connect any facts to a purported breach
20
of contract. Frontier faults the FACC’s failure to “tie actual misdeeds.”
21
Frontier’s points are not well taken. The FACC sufficiently identifies the part oral and part
22
written terms to the highway and bridge agreements. The FACC identifies 10 breach issues. Given the
23
nature of the highway and bridge agreements, discovery will be necessary to identify precise terms but
24
the FACC satisfactorily places Frontier on notice of Allen’s claims. Frontier’s overbroad attacks of the
25
FACC as a whole are unavailing.
26
Moreover, Frontier offers no precise challenges to the FACC’s reasonable value and promissory
27
fraud claims. As such, this Court need not evaluate such claims which Allen credits as sufficiently pled.
28
This Court will not endeavor to challenge the reasonable value and promissory fraud claims for
8
1
Frontier’s benefit. This Court agrees with Allen that Frontier challenges the truth, not sufficiency, of
2
the FACC’s allegations. In short, Frontier’s overbroad criticisms of the FACC are unavailing.
3
CONCLUSION AND ORDER
4
For the reasons discussed above, this Court:
5
1.
DENIES dismissal of the FACC;
6
2.
ORDERS Frontier, no later than July 20, 2012, to file and serve an answer to the FACC.
7
IT IS SO ORDERED.
8
Dated:
66h44d
July 9, 2012
/s/ Lawrence J. O'Neill
UNITED STATES DISTRICT JUDGE
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
9