Paul Weldon v. Dyer et al
Filing
76
ORDER GRANTING Plaintiff's 68 69 Motion to Amend signed by Magistrate Judge Stanley A. Boone on 7/30/2014. (Sant Agata, S)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
EASTERN DISTRICT OF CALIFORNIA
10
11
PAUL WELDON,
Case No. 1:13-cv-00540-LJO-SAB
ORDER GRANTING PLAINTIFF’S
MOTION TO AMEND
Plaintiff,
12
v.
13
ECF NO. 68, 69
14
JERRY DYER, et al.,
15
Defendants.
16
17
Plaintiff Paul Weldon (“Plaintiff”) filed motions to amend his complaint on June 30,
18 2014 and July 1, 2014. (ECF Nos. 68, 69.) The Court finds that these motions are suitable for
19 adjudication based upon the record and briefs on file and therefore vacates the hearing on the
20 motions scheduled for August 13, 2014 and the parties will not be required to appear at that time.
21
For the reasons set forth below Plaintiff’s motion to amend is granted.
22
I.
23
BACKGROUND
24
This action is comprised of two consolidated actions: Paul Weldon v. Jerry Dyer, et al.,
25 Case No. 1:13-cv-00540-LJO-SAB, filed on April 15, 2013 (the “First Action”) and Paul
26 Weldon v. Economy Towing, et al., Case No. 1:14-cv-00549-LJO-SAB, filed on April 18, 2014
27 (the “Second Action”).
28 / / /
1
The operative complaint in the First Action is the Third Amended Complaint filed on
1
2 March 17, 2014. (ECF No. 36.) The facts alleged in the Third Amended Complaint concern an
3 incident on April 18, 2011, where Plaintiff was pulled over by Defendant John Conlee, a police
4 officer, and his car was towed by Defendant Econo Towing. Plaintiff asserts claims against
5 Defendant John Conlee, Econo Towing, Marty Kodman, Robert Kodman and Beryle Dodson (all
6 defendants collectively referred to as “Defendants”).1 Plaintiff asserted claims under 42 U.S.C. §
7 1983 for the use of excessive force in violation of the Fourth Amendment, an unreasonable
8 search and seizure in violation of the Fourth Amendment, failure to provide sufficient notice
9 regarding a seizure in violation of the Fourteenth Amendment’s Due Process Clause.
The complaint in the Second Action alleges similar facts regarding the same incident on
10
11 April 18, 2011. The complaint did not identify any specific causes of action. Accordingly, on
12 June 13, 2014, the Court issued an order to show cause why the complaint filed in the Second
13 Action should not be dismissed as duplicative to the claims in the First Action. Plaintiff’s
14 response to the order to show cause indicates that Plaintiff intended to assert additional claims
15 for breach of contract and conversion. Plaintiff now seeks to effectively consolidate the two sets
16 of claims in a single amended complaint.
17
II.
18
LEGAL STANDARDS FOR MOTIONS TO AMEND
Generally, amendments to pleadings should be granted with “extreme liberality.”
19
20 Chodos v. West Publishing Co., 292 F.3d 992, 1003 (9th Cir. 2002) (quoting Morongo Band of
21 Mission Indians v. Rose, 893 F.2d 1074. 1079 (9th Cir. 1990)). However, when a plaintiff has
22 already been granted leave to amend, discretion in deciding subsequent motions to amend is
23 “particularly broad.” Id. (quoting Griggs v. Pace Am. Group, Inc., 170 F.3d 877, 879 (9th Cir.
24 1999). “When considering a motion for leave to amend, a district court must consider whether
25 the proposed amendment results from undue delay, is made in bad faith, will cause prejudice to
26
1
Although the Third Amended Complaint identifies other parties as defendants, pursuant to the Court’s July 9, 2013
27 order screening Plaintiff’s claims, the only cognizable claims in this action are those against Defendants Robert
Conlee, Econo Towing, Marty Kodman, Robert Kodman and Beryle Dodson. Thus, the First Action proceeds solely
28 against those defendants.
2
1 the opposing party, or is a dilatory tactic.” Id. (citing Foman v. Davis, 371 U.S. 178, 182
2 (1962)).
3
III.
4
DISCUSSION
5
The Court finds that Plaintiff is entitled to leave to amend because there is no suggestion
6 of undue delay, bad faith, prejudice to Defendants, or dilatory tactics. Notably, leave to amend
7 was requested after consolidation of Plaintiff’s two actions. Plaintiff had the right to prosecute
8 both actions separately and should be allowed to prosecute both sets of claims in the
9 consolidated action. Moreover, Defendants filed a statement of non-opposition to Plaintiff’s
10 motion.
Accordingly, the Court will grant Plaintiff’s motion to amend the complaint to
11 consolidate the claims asserted in both complaints.
12
However, it is worth noting that Plaintiff did not allege sufficient facts to support a
13 breach of contract claim. Under California law, the elements of a breach of contract claim are 1)
14 the existence of the contract, 2) plaintiff’s performance or excuse for nonperformance, 3)
15 defendant’s breach, and 4) the resulting damages to plaintiff.
Oasis West Realty, LLC v.
16 Goldman, 51 Cal. 4th 811, 821 (2011).
17
Plaintiff thus far has alleged no facts which suggest that a valid contract existed between
18 Plaintiff and any of the defendants. Under California law, a valid contract requires mutual
19 assent—i.e., a meeting of the minds on all material points of the contract. American Employers
20 Group, Inc. v. Employment Development Dept., 154 Cal. App. 4th 836, 846-47 (2007). “Mutual
21 assent usually is manifested by an offer communicated to the offeree and an acceptance
22 communicated to the offeror.” Lopez v. Charles Schwab & Co., Inc., 118 Cal. App. 4th 1224,
23 1230 (2004). The facts alleged by Plaintiff show no such mutual assent: neither Plaintiff nor
24 Defendants communicated any sort of “offer” to the other concerning the towing of Plaintiff’s
25 car, nor did any part accept any such “offer.” The facts alleged demonstrate that Plaintiff did not
26 consent to his car being towed. Therefore, the facts alleged do not involve any form of legal
27 contract.
28 / / /
3
It does not appear that the facts alleged thus far support a valid breach of contract claim.
1
2 However, to the extent that Plaintiff can allege additional or different facts that show a valid
3 contract existed, the Court will give Plaintiff leave to amend the complaint to assert such a claim.
4 Further, Plaintiff did not request leave to assert any other claims beyond those already asserted in
5 the complaints filed thus far.
Accordingly, Plaintiff may only amend for the purposes of
6 consolidating the claims already asserted in the complaints filed thus far and may not assert any
7 new claims.
8
IV.
9
CONCLUSION AND ORDER
For the reasons set forth above, the Court grants Plaintiff leave to amend the pleadings to
10
11 consolidate the claims asserted in the Third Amended Complaint filed on March 17, 2014 in the
12 First Action and the complaint filed on April 18, 2014 in the Second Action. Plaintiff shall file
13 his amended complaint by September 1, 2014. Plaintiff may not assert any new claims in the
14 amended complaint beyond those asserted in the Third Amended Complaint in the First Action
15 and the complaint in the Second Action. Moreover, Plaintiff may not allege facts materially
16 different from those already alleged in the prior pleadings.
17
Based upon the foregoing, it is HEREBY ORDERED that:
18
1.
The hearing on Plaintiff’s motions to amend scheduled for August 13, 2014 is
VACATED and the parties are not required to appear in Court at that time;
19
20
2.
Plaintiff’s motions to amend are GRANTED; and
21
3.
Plaintiff shall file an amended complaint on or before September 1, 2014.
22
Plaintiff is forewarned that failure to timely file an amended complaint may result
23
in sanctions, including dismissal of this action.
24
25
IT IS SO ORDERED.
26 Dated:
July 30, 2014
UNITED STATES MAGISTRATE JUDGE
27
28
4
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?