Center for Biological Diversity, et al. v. United States Bureau of Reclamation, et al.
Filing
23
ORDER GRANTING Motion to Compel Joinder of Absent Contractors and GRANTING Unopposed Motion to Amend 11 , 14 signed by District Judge Dale A. Drozd on 2/15/2021. (Lundstrom, T)
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 1 of 13
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
FOR THE EASTERN DISTRICT OF CALIFORNIA
10
11
12
CENTER FOR BIOLOGICAL DIVERSITY;
RESTORE THE DELTA; and PLANNING
AND CONSERVATION LEAGUE,
No. 1:20-cv-00706-DAD-EPG
ORDER GRANTING MOTION TO
COMPEL JOINDER OF ABSENT
CONTRACTORS; AND GRANTING
UNOPPOSED MOTION TO AMEND
Plaintiffs,
13
14
v.
15
UNITED STATES BUREAU OF
RECLAMATION; SCOTT DE LA VEGA, in
his official capacity as Acting Secretary of the
Interior; and UNITED STATES
DEPARTMENT OF THE INTERIOR,
16
17
(Doc. Nos. 11, 14)
18
Defendants.
19
20
21
BACKGROUND
In this lawsuit, plaintiffs challenge the U.S. Bureau of Reclamation’s (“Reclamation”)
22
23
conversion of certain existing long-term federal “water service” contracts into permanent
24
“repayment” contracts1 without first conducting any environmental review under the National
25
Environmental Policy Act (“NEPA”). (Doc. No. 1.) Named as defendants in the initial complaint
26
1
27
28
Specifically, the initial complaint, filed May 20, 2020, lists fourteen (14) contracts that had
been “converted” as of February 28, 2020, as well as twenty-six (26) contracts that were in the
process of being converted under the WIIN Act, for a total of forty (40) contracts. (Doc. No. 1 at
¶¶ 40–41.)
1
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 2 of 13
1
are Reclamation, as well as the U.S. Department of the Interior and Scott de la Vega,2 the acting
2
Secretary of the Interior (collectively, “federal defendants”).
3
Reclamation has negotiated and executed the challenged repayment contracts pursuant to
4
authority set forth in the 2016 Water Improvements for the Nation Act (“WIIN Act”), Pub. L. No.
5
114-322, 130 Stat 1628 (2016). According to plaintiffs, Reclamation asserts3 that conversion of
6
the water service contracts into permanent repayment contracts under the WIIN Act (“WIIN Act
7
conversion contracts”) is a non-discretionary act not subject to NEPA review. (Id. at ¶ 4.)
8
Plaintiffs contend that Reclamation’s position in this regard is untenable, citing various provisions
9
of the WIIN Act and the Central Valley Project Improvement Act, Pub. L. No. 102–575, 106 Stat.
10
4600 (1992). (See generally Doc. 1.) Plaintiffs seek, among other remedies, a court order that
11
would “vacate, set aside, and rescind Reclamation’s contract conversions” and enjoin federal
12
defendants from “taking any action pursuant to the contract conversions” or “converting any other
13
contracts” until NEPA compliance is achieved. (Doc. No. 1 at 21.)
14
Before the court for decision are two motions. First, federal defendants move pursuant to
15
Federal Rules of Civil Procedure 12(b)(7)4 and 19 to compel joinder of the contractors whose
16
converted contracts are being challenged. (Doc. No. 11.) In the alternative, federal defendants
17
demand that plaintiffs drop their prayer for an order that would “void”5 the converted contracts.
18
(Id. at 6.) Plaintiffs oppose joining the absent contractors. (Doc. No. 13.) Federal defendants
19
have filed a reply. (Doc. No. 18.)
20
/////
21
22
2
Scott de la Vega is automatically substituted as a federal defendant in this action for David
Bernhardt pursuant to Federal Rule of Civil Procedure 25(d).
23
3
24
25
26
27
Reclamation has in fact already made this assertion in a related case. (See N. Coast Rivers
Alliance v. U.S. Dep’t of the Interior, No. 1:16-cv-00307-DAD-SKO, Doc. No. 100 at 2.)
4
Federal defendants invoke Fed. R. of Civ. Pro. 12(b)(7), which permits any party to present by
motion the defense of “failure to join a party under Rule 19” as the procedural mechanism for
bringing this motion
Plaintiffs’ complaint does not actually use the word “void” but instead calls for the contracts to
be “set aside” pursuant to the Administrative Procedure Act, 5 U.S.C. § 706(2).
5
28
2
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 3 of 13
1
In addition, plaintiffs move to amend their complaint to enumerate additional converted
2
contracts and add claims under the Endangered Species Act (“ESA”). (Doc. No. 14.) Federal
3
defendants have not filed any opposition to this motion. (See Doc. No. 19.)
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
MOTION TO COMPEL JOINDER OF ABSENT CONTRACTORS
A.
General Legal Standard Under Rule 19
Federal Rule of Civil Procedure 19, which governs the circumstances under which persons
must be joined as parties to a lawsuit, provides in relevant part:
(a) Persons Required to Be Joined if Feasible.
(1) Required Party. A person who is subject to service of
process and whose joinder will not deprive the court of
subject-matter jurisdiction must be joined as a party if:
(A) in that person’s absence, the court cannot accord
complete relief among existing parties; or
(B) that person claims an interest relating to the
subject of the action and is so situated that disposing
of the action in the person’s absence may:
(i) as a practical matter impair or impede the
person’s ability to protect the interest; or
(ii) leave an existing party subject to a
substantial risk of incurring double, multiple,
or otherwise inconsistent obligations because
of the interest.
***
(b) When Joinder Is Not Feasible. If a person who is required to be
joined if feasible cannot be joined, the court must determine
whether, in equity and good conscience, the action should proceed
among the existing parties or should be dismissed. The factors for
the court to consider include:
(1) the extent to which a judgment rendered in the person’s
absence might prejudice that person or the existing parties;
(2) the extent to which any prejudice could be lessened or
avoided by:
(A) protective provisions in the judgment;
(B) shaping the relief; or
(C) other measures;
3
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 4 of 13
1
(3) whether a judgment rendered in the person's absence
would be adequate; and
2
3
(4) whether the plaintiff would have an adequate remedy if
the action were dismissed for nonjoinder.
4
In applying Rule 19, “a court must undertake a two-part analysis: it must first determine
5
if an absent party is ‘necessary’ to the suit; then if, as here, the party cannot be joined, the court
6
must determine whether the party is ‘indispensible’ so that in ‘equity and good conscience’ the
7
suit should be dismissed.” Makah Indian Tribe v. Verity, 910 F.2d 555, 558 (9th Cir. 1990).
8
“The inquiry is a practical one and fact specific, and is designed to avoid the harsh results of rigid
9
application.” Id. (internal citations and quotations omitted).
Here, no party suggests any of the absent contractors cannot be joined. Accordingly, the
10
11
focus of the present dispute is whether those parties are “necessary” and therefore must be joined.
12
As a result, the court need not struggle with whether the absent contractors are “indispensable” or,
13
relatedly, whether dismissal is appropriate in their absence.
14
B.
The Absent Contractors Are “Necessary” Parties
Under Rule 19(a)(1), a party may be deemed “required” (i.e. “necessary”) under one of
15
16
two circumstances. First, a party may be “required” if “in that person’s absence, the court cannot
17
accord complete relief among existing parties.” Fed. R. Civ. P. 19(a)(1)(A); Makah, 910 F.2d at
18
558 (“First, the court must decide if complete relief is possible among those already parties to the
19
suit.”). Here, there is no suggestion that complete relief could not be accomplished in the absence
20
of the absent contractors. Indeed, federal defendants do not even mention the “complete relief”
21
prong of Rule 19(a)(1). (See Doc. Nos. 11, 18.)
Federal defendants do invoke the alternative prong of Rule 19(a)(1) which deems an
22
23
absent party necessary if that party “has a legally protected interest in the suit.” Makah, 910 F.2d
24
at 558. “If a legally protected interest exists, the court must further determine whether that
25
/////
26
/////
27
/////
28
/////
4
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 5 of 13
1
interest will be impaired or impeded by the suit.” Id. “Impairment may be minimized if the
2
absent party is adequately represented in the suit.” Id.6
3
1.
Relevant Caselaw
4
Federal defendants focus on a line of cases that apply Rule 19 to various disputes
5
involving contracts. (Doc. No. 11 at 5.) These cases stand for the general principle that “a party
6
to a contract is necessary, and if not susceptible to joinder, indispensable to litigation seeking to
7
decimate that contract.” Dawavendewa v. Salt River Project Agr. Imp. & Power Dist., 276 F.3d
8
1150, 1157 (9th Cir. 2002). Dawavendewa concerned a lease between the Navajo Nation and the
9
Salt River Project Agricultural Improvement and Power District (“SRP”), a power company that
10
leased land from the Najavo Nation. Id. at 1153. The lease in question required the SRP to
11
preferentially hire members of the Navajo Nation to work at the Navajo Generating Station
12
(“NGS”). Id. Dawavendewa, a member of the Hopi Tribe, sought employment at NGS. Id.
13
When he failed to secure employment there, Dawavendewa filed suit against SRP, accusing it of
14
discriminating against him on the basis of his national origin in violation of federal civil rights
15
laws. Id. at 1154. SRP moved to dismiss Dawavendewa’s complaint for failure to join the
16
Navajo Nation, an indispensable party that could not be joined due to its sovereign immunity.
17
See id. Particularly relevant here, the Ninth Circuit reasoned that the Navajo Nation was
18
“necessary” to the lawsuit because the suit concerned a “fundamental” bargained-for lease term
19
designed to secure for the Navajo Nation employment opportunities and income for its
20
reservation that could be “grievously impaired by a decision rendered in its absence.” Id. at 1157.
21
The Ninth Circuit has drawn a line between cases such as Dawevendewa, where the nature
22
of the suit threatens to “grievously impair” an existing contractual right, and circumstances in
23
which a plaintiff is seeking only to enforce procedural requirements. “Although an absent party
24
has no legally protected interest at stake in a suit seeking only to enforce compliance with
25
administrative procedures, our case law makes clear that an absent party may have a legally
26
6
27
28
Even if impairment is not expected, necessity may be found if the court determines that a risk
of inconsistent rulings will affect the parties present in the suit. Fed. R. Civ. P. 19(a)(1)(B)(ii);
Makah, 910 F.2d at 558–59. This alternative basis for a finding of necessity under Rule
19(a)(1)(B) is not at issue here.
5
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 6 of 13
1
protected interest at stake in procedural claims where the effect of a plaintiff's successful suit
2
would be to impair a right already granted.” Dine Citizens Against Ruining Our Env’t v. Bureau
3
of Indian Affairs, 932 F.3d 843, 852 (9th Cir. 2019).
4
Makah provides an example of this distinction. In that case, the Makah Indian Tribe
5
brought a suit challenging federal regulations allocating ocean harvest of migrating Columbia
6
river salmon among various interest groups, including three other tribes. 910 F.2d at 557. The
7
lawsuit also challenged the specific allocations made under those regulations for the 1987 harvest.
8
Id. The Ninth Circuit held that the absent tribes were necessary parties to the extent the
9
complaint sought re-allocation of the 1987 harvest, but were not necessary parties to the extent
10
the complaint sought prospective injunctive relief against future decision-making under the
11
challenged regulations. Id. at 559.
12
In contrast, in Dine, the Ninth Circuit considered a suit brought by a coalition of
13
environmental organizations against agencies within the U.S. Department of the Interior after
14
those agencies reauthorized coal mining activities on Navajo Nation land. Id. at 847–48.
15
Plaintiffs alleged in Dine that the federal agency defendants violated both NEPA and the ESA by
16
approving lease amendments and accompanying rights of way agreements between the Navajo
17
Nation and power plant operators. Id. at 847. The Ninth Circuit held that the Navajo Nation was
18
a necessary party to the suit because, if the plaintiffs succeeded in vacating the agency
19
reauthorization decision, the Navajo Nation’s interest in “the existing lease, right-of-way, and
20
surface mining permits would be impaired.” Id. at 853. This is because “[w]ithout the proper
21
approvals, the [m]ine could not operate, and the Navajo Nation would lose a key source of
22
revenue in which [it] has already substantially invested.” Id. The Ninth Circuit indicated that the
23
claims before it in Dine were distinguishable from the claims allowed to proceed in Makah,
24
/////
25
/////
26
/////
27
/////
28
/////
6
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 7 of 13
1
because in Makah the court could “tailor the scope of relief to being prospective only, preventing
2
any impairment to a legally protected interest.” Id.7
3
Following these general patterns, a district judge ruling in a related case in this district
4
found that absent water contractors were necessary to a suit that sought to “invalidate, rescind, or
5
enjoin” Reclamation’s performance under water service contracts. Nat. Res. Def. Council v.
6
Kempthorne, 539 F. Supp. 2d 1155, 1186–87 (E.D. Cal. 2008). Another district judge in this
7
same district found that absent water contractors were not necessary where plaintiffs declined to
8
seek an order setting aside already-executed short-term water service contracts, but rather sought
9
only to impose environmental review requirements on Reclamation’s efforts to enter into future
10
short-term water service contracts. Pac. Coast Fed’n of Fishermen’s Associations v. U.S. Dep’t
11
of the Interior, 929 F. Supp. 2d 1039, 1062 (E.D. Cal. 2013) (“PCFFA”).8
12
2.
Necessity Analysis
13
In the instant case, plaintiffs appear to concede that a prayer to “set aside” a water service
14
contract would ordinarily be considered an impairment of a legal right sufficient to render all
15
parties to such a contract “necessary” for purposes of Rule 19. (See Doc. No. 13 at 45.) Instead,
16
plaintiffs suggest that their effort to set aside the WIIN Act conversion contracts at issue in this
17
case is distinguishable because (1) at least some of those contracts are not yet fully enforceable
18
(see Doc. No. 13 at 4) and (2) if the WIIN Act conversion contracts were vacated, the absent
19
contractors would continue to receive Central Valley Project water under their existing water
20
service contracts (id. at 5).
21
22
23
24
25
26
27
28
7
The court notes that Makah, Dine, and Dawevendewa all discuss issues of sovereign immunity
in the context of determining whether absent tribes cannot be joined and therefore are
“indispensable.” See Makah, 910 F.2d at 559–60; Dine, 932 F.3d at 856; Dawevendewa, 276
F.3d at 1150. However, sovereign immunity did not drive those courts’ determinations as to
whether any absent party held a legally protected interest. As such, any attempt to distinguish
those cases on the ground that sovereign immunity is not an issue in this case is misplaced.
8
The district court in PCFFA somewhat conflated the necessity and indispensability analyses
and therefore did not explicitly make a finding with regard to the issue of necessity. See 929 F.
Supp. 2d at 1061–63. Nonetheless, in light of the fact that the plaintiffs in PCFFA were only
requesting prospective injunctive relief against the execution of future contracts, id. at 1062, the
holding in PCFFA is entirely consistent with the necessity rules articulated herein.
7
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 8 of 13
1
a.
Enforceability of the Disputed Contracts
2
With regard to enforceability, plaintiffs correctly point out that many of the WIIN Act
3
conversion contracts in dispute contain provisions that require “judicial confirmation” in state
4
court, a step that (at least as of the date of plaintiffs’ last brief) has not yet occurred. (Doc. No. 13
5
at 5; see also Doc. No. 13-1 at ¶ 5.) For example, one of the WIIN Act conversion contracts,
6
executed on February 28, 2020, provides at Article 47:
7
Promptly after the execution of this amended Contract, the
Contractor will provide to the Contracting Officer a certified copy
of a final decree of a court of competent jurisdiction in the State of
California, confirming the proceedings on the part of the Contractor
for the authorization of the execution of this amended Contract.
This amended Contract shall not be binding on the United States
until the Contractor secures a final decree.
8
9
10
11
Irrigation and M&I Contract No. 14-06-200-495A-IR1-P between Reclamation and Westlands
12
Water District, available at https://www.usbr.gov/mp/wiin-act/docs/westlands-water-district.pdf
13
(last visited February 15, 2021).
In theory, plaintiffs’ argument could have some traction. In Northern Alaska
14
15
Environmental Center v. Hodel, absent miners submitted mining plans and access permits to the
16
National Park Service (“NPS”) for review but had not yet received approval of those plans and
17
permits. 803 F.2d 466, 469 (9th Cir. 1986). Environmental plaintiffs sued the reviewing
18
agencies to enjoin any “further” approvals of mining plans. Id. Because the subject matter of the
19
dispute concerned “NPS procedures regarding mining plan approval,” the Ninth Circuit reasoned
20
that, although the miners were certainly “interested” in how stringent those requirements would
21
be, “miners with pending plans have no legal entitlement to any given set of procedures,” and
22
therefore did not have to be joined to the suit. Id. (emphasis added).
23
However, as a matter of contract law, the present case is not truly analogous to Northern
24
Alaska because the WIIN Act conversion contracts have already been executed. As mentioned,
25
plaintiffs suggest that the court should disregard any legal rights created by a WIIN Act
26
/////
27
/////
28
/////
8
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 9 of 13
1
conversion contract even if executed, so long as that contract contains a validation9 clause and has
2
not yet been validated.10 (See Doc. No. 13 at 4.) This requires the court to interpret the terms of a
3
federal contract, a process that is governed by “federal common law” (sometimes referred to as
4
“federal contract law”), United States v. Westlands Water Dist., 134 F. Supp. 2d 1111, 1135 (E.D.
5
Cal. 2001), which in turn looks to the Restatement of Contracts, Pauma Band of Luiseno Mission
6
Indians of Pauma & Yuima Reservation v. California, 813 F.3d 1155, 1163 (9th Cir. 2015)
7
(explaining that courts “often look to the ... Restatement when deciding questions of federal
8
common law”) (internal citation and quotation omitted). Applying the Restatement, at least one
9
appellate court has found that even when an executed water repayment contract may be voidable
10
by one party, this does not mean that it is void. As the Eighth Circuit explained in Concerned
11
Irrigators v. Belle Fourche Irrigation District, “[f]ederal law gives the United States authority to
12
enter into repayment contracts with irrigation districts, but specifies that these contracts are not
13
‘binding on the United States until the proceedings on the part of the district for the authorization
14
of the execution of the contract with the United States shall have been confirmed by decree of a
15
court of competent jurisdiction, or pending appellate action if ground for appeal be laid.’ 43
16
U.S.C. § 511 (1994).” 235 F.3d 1139, 1144 (8th Cir. 2001). The Eighth Circuit reasoned that
17
“[e]ven if the United States is not bound by the [ ] contract because it was not judicially
18
confirmed, the contract is not necessarily invalid.” Id. (citing Restatement (Second) of Contracts
19
§ 7 & cmt. a (1979) (where a party has the power to avoid the legal relations created by a
20
contract, that contract is voidable but not void)). In Concerned Irrigators, the Eighth Circuit
21
enforced the terms of a repayment contract against third party landowners within the contracting
22
irrigation district, even though the contract had not been judicially confirmed because there was
23
“no evidence that the United States has ever attempted to escape any obligation created by the
24
9
26
As federal defendants point out, not all of the WIIN Act conversion contracts challenged in this
case contain a validation clause because validation is only required for irrigation district
contractors, not for municipal and industrial contractors. (Doc. No. 18 at 3 n. 3 (citing 43 U.S.C.
§ 511).)
27
10
25
28
The court will assume for purposes of this order that the challenged WIIN Act conversion
contracts in this case that do contain a validation clause have not yet been validated. No party has
suggested to the contrary.
9
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 10 of 13
1
contract.” Id. In a nutshell, that contract, although potentially voidable by the United States, was
2
not void. See id.
3
Here, as of the date of this order, there is no allegation or other suggestion that the United
4
States disclaims its contractual obligations to the absent contractors. In fact, the instant motion,
5
which explicitly argues that the WIIN Act conversion contracts create legally enforceable rights,
6
belies any such suggestion, as does the letter from Reclamation to one contractor attached to
7
Reclamation’s reply brief. (See Doc. 18-2 (Reclamation “confirm[ing] its understanding that the
8
[contractor’s] inability to obtain a validation judgment does not render the Repayment Contract
9
void.”).)11 The holding in Concerned Irrigators therefore supports a finding that the WIIN Act
10
conversion contracts can create legal rights even in the absence of judicial confirmation.
11
b.
12
Legally Protected Interest/Impairment of Interest
With the above conclusion in mind, the question becomes whether the executed WIIN Act
13
conversion contracts afford the absent contractors a legally protected “interest” sufficient to
14
trigger a finding of necessity under Rule 19(a)(1)(B). As mentioned, the WIIN Act conversion
15
contracts are “repayment” contracts that, unlike “water service” contracts, allow contractors to
16
prepay the repayment obligation imposed by Reclamation law, which in turn can reduce annual
17
payments to Reclamation; these contracts also provide significant opportunities for relief from
18
certain other requirements of Reclamation law, including acreage limitations. See WIIN Act,
19
Pub. L. No. 114-322 § 4011(a), (c)(1), 130 Stat. at 187880. These bargained-for terms are no less
20
“fundamental” than the lease terms designed to ensure employment opportunities and income for
21
Navajo Nation members at issue in Dawavendewa. 276 F.3d at 1157. Moreover, the benefit of
22
those bargained-for terms unique to a repayment contract could be “grievously impaired” if, as a
23
result of this case, the court were to “set aside” those repayment contracts. See id. at 1157.
Plaintiffs relatedly suggest that the absent contractors’ interests would not be significantly
24
25
impaired because, if plaintiffs “obtain their requested relief, and Reclamation’s conversions of
26
existing contracts are vacated, the Contractors would continue to receive CVP water under their
27
11
28
The court expresses no opinion on whether the United States could change its position as to the
enforceability of unvalidated contracts.
10
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 11 of 13
1
existing contracts.” (Doc. No. 13 at 5.) This argument, however, does not account for the above-
2
discussed unique and valuable provisions contained within a WIIN Act conversion contract. See
3
Dawavendewa, 276 F.3d at 1157 (suggesting that the impairment analysis must focus on the
4
interests unique to the bargained-for agreement at risk).
5
Before concluding whether the identified legally protected interest exists would be
6
impaired or impeded by the suit, the court must examine whether any such impairment could be
7
minimized “if the absent party is adequately represented in the suit.” See Makah, 910 F.2d at 558
8
(internal citation and quotation omitted). “In assessing an absent party’s necessity under [Rule]
9
19(a), the question whether that party is adequately represented parallels the question whether a
10
party’s interests are so inadequately represented by existing parties as to permit intervention of
11
right under [Rule] 24(a).” Shermoen v. United States, 982 F.2d 1312, 1318 (9th Cir. 1992). The
12
Ninth Circuit uses the following three-step inquiry to determine if a non-party is adequately
13
represented by existing parties:
14
A non-party is adequately represented by existing parties if: (1) the
interests of the existing parties are such that they would
undoubtedly make all of the non-party’s arguments; (2) the existing
parties are capable of and willing to make such arguments; and (3)
the non-party would offer no necessary element to the proceeding
that existing parties would neglect.
15
16
17
18
Sw. Ctr. for Biological Diversity v. Babbitt, 150 F.3d 1152, 1153–54 (9th Cir. 1998) (citing
19
Shermoen, 982 F.2d at 1318). Here, as was the case in Kempthorne, federal defendants “cannot
20
adequately represent the interests of absent contractors because they represent the government
21
and a broad set of interests that are not the same as public or private water contractors.” 539 F.
22
Supp. 2d at 1187–88.
For these reasons, the court concludes that the absent contractors are “required to be
23
24
joined” under Rule 19(a)(1)(B)(i) because they “claim[ ] interest[s] relating to the subject of the
25
action and [are] so situated that disposing of the action in [their] absence may as a practical matter
26
impair or impede [their] ability to protect [that] interest.”
27
/////
28
/////
11
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 12 of 13
1
2
C.
The Public Rights Exception Does Not Bar a Finding of Necessity
There is a “public rights exception” to Rule 19’s joinder requirements. “Under this
3
exception, even if [the absent party is a] necessary party, [the absent party is] not deemed
4
indispensable, and, consequently, dismissal is not warranted.” Kescoli v. Babbitt, 101 F.3d 1304,
5
1311 (9th Cir. 1996) (citing Makah, 910 F.2d at 559 n. 6). Generally, to fall within the public
6
rights exception, “the litigation must transcend the private interests of the litigants and seek to
7
vindicate a public right.” Id. (internal citation omitted). For the exception to apply, the litigation
8
must not “destroy the legal entitlements of the absent parties.” Id. (citations omitted) (finding the
9
public rights exception inapplicable in that case because rights of absent parties under lease
10
11
agreements “could be significantly affected” if the action proceeded in their absence).
However, the public rights exception does not operate as an exception to a finding of
12
“necessity.” Rather, it operates to exempt claims from being dismissed due to an absent party
13
otherwise being deemed indispensable. Id. Here, because no party suggests the absent
14
contractors are indispensable, the public rights exception is inapplicable.
15
In sum, the absent contractors must be joined if plaintiffs seek to set aside the executed
16
WIIN Act conversion contracts. Assuming plaintiffs retain this prayer for relief, any amended
17
complaint must name the contractors that are parties to the challenged contracts. The long history
18
of related challenges to CVP contracts indicates that these parties would participate one way or
19
another, whether joined by way of Rule 19 or intervening by way of Rule 24. As this court has
20
indicated in related cases, the undersigned will not tolerate duplicative briefing and will not allow
21
the numerosity of parties to multiply the proceedings in ways that will effectively deny plaintiffs
22
access to this forum.
23
MOTION TO AMEND
24
As noted at the outset, plaintiffs have moved to amend their complaint to challenge
25
additional contracts and add claims for relief under the ESA. (Doc. No. 14.) Federal defendants
26
have taken no position on this motion. (Id. at 3.) Good cause appearing and in light of the fact
27
that the Federal Rules favor granting leave to amend “freely,” the motion will be granted, subject
28
to the instant ruling on the motion to compel joinder.
12
Case 1:20-cv-00706-DAD-EPG Document 23 Filed 02/16/21 Page 13 of 13
1
CONCLUSION AND ORDER
2
For the reasons set forth above:
3
(1)
4
Federal defendants’ motion to compel joinder of the absent contractors (Doc. No.
11) is GRANTED; and
Plaintiffs’ motion to amend (Doc. No. 14) is GRANTED.
5
(2)
6
Plaintiffs shall file any amended complaint within forty-five (45) days of service of this
7
order.
8
IT IS SO ORDERED.
9
10
Dated:
February 15, 2021
UNITED STATES DISTRICT JUDGE
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
13
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?