Coleman, et al v. Schwarzenegger, et al
Filing
7187
ORDER signed by Chief District Judge Kimberly J. Mueller on 5/26/2021 ORDERING that the 1/29/2021 bench order is hereby modified to require defendants to notify the Special Master immediately whenever a determination is made that a project will be delayed and, not later than ten days after notice is provided to the Special Master, to file an activation schedule updated to reflect the new projected completion date.(Becknal, R)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
FOR THE EASTERN DISTRICT OF CALIFORNIA
10
11
RALPH COLEMAN, et al.,
12
Plaintiffs,
13
14
15
v.
No. 2:90-cv-0520 KJM DB P
ORDER
GAVIN NEWSOM, et al.,
Defendants.
16
17
18
As required by court order, on January 15, 2021, defendants filed proposed
19
activation schedules for completion of court-ordered suicide prevention recommendations. ECF
20
No. 7024. On January 29, 2021, the court approved the proposed activation schedules with
21
specific direction to defendants to notify the Special Master “if any project runs thirty (30) days
22
past any due date set in any activation schedule.” ECF No. 7043. On May 4, 2021, the court
23
ordered defendants to file updated activation schedules complete with current updates to the
24
Actual Completion column. ECF No. 7150. On May 12, 2021, defendants timely filed updated
25
activation schedules. ECF No. 7160.
26
The updated activation schedules show that approved schedules for some of the
27
projects have been delayed. Defendants have appropriately included explanations for the various
28
delays. Good cause appearing, the January 29, 2021 bench order is hereby modified to require
1
1
defendants to notify the Special Master immediately whenever a determination is made that a
2
project will be delayed and, not later than ten days after notice is provided to the Special Master,
3
to file an activation schedule updated to reflect the new projected completion date.1
4
5
IT IS SO ORDERED.
DATED: May 26, 2021.
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
1
As the court noted at hearing, defendants’ representation in any activation schedule that
a particular project is completed is subject to confirmation by the Special Master’s expert, Mr.
Hayes, unless the representation clarifies that Mr. Hayes has confirmed completion.
2
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?