USA v. El Dorado County, et al

Filing 416

MEMORANDUM AND ORDER signed by Judge Morrison C. England, Jr., on 7/8/11, GRANTING 394 the County's Motion for Construction, Enforcement, and Modification of Partial Consent Decree. The parties are ordered to submit a status report not later than 10 days following the date this Memorandum and Order is filed. (Kastilahn, A)

Download PDF
1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 EASTERN DISTRICT OF CALIFORNIA 10 11 UNITED STATES OF AMERICA, 12 13 14 15 No. 2:01-cv-01520-MCE-GGH Plaintiff, v. MEMORANDUM AND ORDER EL DORADO COUNTY, CALIFORNIA; and CITY OF SOUTH LAKE TAHOE, CALIFORNIA, 16 Defendants. 17 ______________________________ 18 AND ALL RELATED ACTIONS ______________________________ 19 20 ----oo0oo---- 21 22 This litigation was filed by the United States in 2001, 23 pursuant to the provisions of the Comprehensive Environmental 24 Response, Compensation, and Liability Act, 42 U.S.C. § 9601, et 25 seq. (“CERCLA”). 26 to remediate pollution discovered on the site of a former 27 landfill dump. 28 Systems lands near Meyers, California. The government sought to recover response costs That landfill was located within National Forest 1 1 Although the United States Forest Service (“USFS”) initially 2 sited, constructed and operated the so-called Meyers landfill, 3 beginning in the mid 1950’s it was run under the auspices of the 4 County of El Dorado (“County”). 5 waste in 1971. 6 The facility stopped accepting After groundwater contamination was discovered at the site 7 in the 1990’s, the USFS insisted that the County and several 8 other entities bear responsibility for remediation efforts. 9 present lawsuit ensued. The After years of litigation, the various 10 defendants sued by the USFS began to enter into Partial Consent 11 Decrees in order to resolve the claims asserted against them. 12 The last of those Partial Consent Decrees was entered into with 13 Defendant County in August of 2010. 14 modify that Partial Consent Decree (“PCD”) on grounds that the 15 design plans it incorporated, as prepared on behalf of the 16 government, 1) contained numerous inaccuracies and 17 misrepresentations regarding site conditions; 2) were 18 substantially defective and not constructible as drafted; and 19 3) were not prepared in accordance with the standard of care 20 applicable to professional engineers. 21 County’s Motion will be granted.1 22 /// 23 /// 24 /// 25 /// The County now moves to As set forth below, the 26 27 28 1 Because oral argument will not be of material assistance, the Court ordered this matter submitted on the briefs. E.D. Cal. Local Rule 230(g). 2 1 BACKGROUND 2 3 Under the terms of the PCD between the USFS and the County,2 4 the County agreed to consolidate the buried waste mass at the 5 former Meyers landfill by capping the area with a synthetic 6 liner. 7 rainwater and snowmelt could infiltrate the garbage and leach 8 potential contaminants into the site’s groundwater. 9 Gerri Silva, ¶ 9. That cap was designed to reduce the potential that See Decl. Of This was to be accomplished pursuant to the 10 USFS’s so-called “100% Final Remedial Design” (hereinafter 11 “Design”), a plan consisting of detailed design drawings and 12 specifications created by the USFS and its consulting and design 13 firm, the Energy and Environmental Research Group (“ERRG”). 14 According to the County, while it participated in some meetings 15 about the plan as it was being developed, it was not asked to, 16 nor did it prepare, the Design itself. 17 contrary, the County maintains it had access to the landfill site 18 only under very limited circumstances as permitted by the USFS. 19 The County alleges that access did not include verification of 20 the plans and specifications as contained in the Design. 21 at ¶ 11. Id. at ¶ 12. To the See id. 22 Although the USFS was itself a potentially responsible party 23 for remediation efforts under CERCLA as the owner of the landfill 24 site, the County claims it decided to enter into the PCD after 25 the government threatened to issue a Unilateral Administrative 26 Order (“UAO”) mandating cleanup by the County. 27 2 28 The PCD was approved by the Court and filed on August 20, 2010 (ECF No. 389). 3 1 The County explained that issuance of such a UAO would force it 2 to implement the Design with no financial assistance from the 3 government, and could further have resulted in the imposition of 4 additional daily and treble damages. 5 decision to settle was further motivated by the fact that a UAO 6 could also have prevented the County from obtaining indemnity 7 under its insurance policies, funds the County needed in order to 8 fund any settlement. 9 Id. at ¶ 15. The County’s Id. at ¶¶ 16, 21. According to the County, it agreed to construct the Design 10 based on bids predicated on the accuracy of the specifications 11 contained in the Design. 12 some $3.43 million, once construction began the County contends 13 that serious survey, site investigation and engineering errors 14 within the Design came to light. 15 plan errors, the initially anticipated cost for the project has 16 escalated to some $7.5 million, and after two subsequent 17 redesigns of the plans the County alleges that even more 18 additional costs may be required. 19 Although the winning bid came in at As a result of those alleged The errors within the Design plans were significant. Due to 20 a surveying error, the elevation of the buried waste to be 21 relocated was significantly lower than reflected in the plans. 22 The County alleges this meant that instead of having to relocate 23 33,900 cubic yards of waste as shown in the Design estimate, in 24 fact approximately 60,000 cubic yards of waste had to be moved. 25 Decl. of Greg Stanton, ¶ 5. 26 /// 27 /// 28 /// 4 1 Additionally, large amounts of waste were found beyond the 2 parameters depicted in the Design drawings (see Ex. B to Decl. of 3 Bryan A. Stirrat), which also meant that substantially more waste 4 than anticipated had to be excavated and relocated. 5 Decl., ¶ 6. 6 clay layer in the area where the Design called for a French drain 7 to be installed, the County’s contractor had to replace an 8 additional 30,000 cubic yards of soil over the drain site. 9 Stanton Decl., ¶ 7. Stanton Further, because of inaccuracies in the depth of the The cost estimate incorporated within the Design contained 10 11 calculations of the units of work needed to construct the 12 project. 13 to bid the job, and ultimately proved to be grossly understated 14 as a result of the above-described errors, among others. 15 Design plans as a whole reflected the need to relocate only 16 33,900 cubic yards of waste. 17 have currently been moved, the County claims that just the waste 18 removal portion of the required work virtually tripled during 19 construction. 20 flaws in the Design documents have already caused the USFS to 21 redesign the project once, and according to the County the 22 government is currently engaged in the second significant design 23 of the remedial design drawings, plans and specifications. 24 /// 25 /// 26 /// 27 /// 28 /// Those calculations were used by the County’s contractor The Because some 106,000 cubic tons See Stanton Decl., ¶ 13. 5 As indicated above, the 1 In seeking relief from the terms of the PCD as presently 2 constituted, the County alleges that the “100% Final Remedial 3 Design Plan”, as the name would appear to suggest, expressly 4 represented just what the implementation of the Design entailed, 5 both with respect to the scope and quantity of work to be 6 performed as well as the surface and subsurface conditions 7 present at the landfill.3 8 Design therefore carried with it an implied warranty that the 9 Design was both free of any major defect and prepared in The County argues that said “Final” 10 accordance with the standard of care applicable to professional 11 engineers and surveys. 12 use on its own property, and because the County relied on the 13 accuracy of the Design in agreeing to the PCD, the County 14 contends it would be unfair to saddle it with the cost overruns 15 associated with actually constructing the Design. 16 the County asks this Court to rescind or modify the PCF going 17 forward in order to relieve the County of the consequences of the 18 USFS’ misrepresentations as set forth in the design. 19 /// 20 /// 21 /// Because the USFS prepared the Design for Consequently, 22 23 24 25 26 27 28 3 According to the Crawford Declaration submitted in support of this Motion, a Final 100% Design is, according to the standards of the engineering profession, supposed to be constructible and sufficiently refined and detailed to be suitable for bidding. Crawford Decl., ¶ 11. Here, the Design’s cost estimate expressly represented that it was “considered to be accurate within a range of plus 15% to minus 10%.” Silva Decl., Ex. E. Here, given the fact that the County’s initial bid of $3.43 million has already increased to some $7.5 million and may escalate still further, it appears that the anticipated margin of error was plainly not satisfied. 6 1 In opposing the County’s request, the government does not 2 dispute the inaccuracies contained within the Design plan, as 3 enumerated by the County and discussed above. 4 government contends that because the terms of the PCD obligate 5 the County to perform such additional work as to attain 6 “performance standards” in remediating contaminants present at 7 the site, it is the County that remains responsible for doing 8 whatever work is necessary to construct the Design despite the 9 admitted faults contained within that Design as prepared. Instead, the 10 11 STANDARD 12 13 Because a consent decree operates as a final judgment 14 between the parties, “it is accompanied by finality as stark as 15 an adjudication after a full trial.” 16 Inc., v. C.R. Bard, Inc., 977 F.2d 558, 560 (Fed. Cir. 1992). 17 Particularly since a consent decree is invoked upon “the 18 deliberate choice of the parties, a movant’s burden for 19 modification of a consent order is particularly heavy.” 20 561. 21 W.L. Gore & Associates, Id. at Under the terms of the PCD at issue here the Court retains 22 jurisdiction for the duration of any performance contemplated by 23 the PCD to construe or modify the PCD as “may be necessary or 24 appropriate.” 25 within it “shall be deemed to alter the Court’s power to enforce, 26 supervise, or approve modification to [the PCD].” 27 /// 28 /// PCD, ¶ 116. The PCD goes on to state that nothing 7 Id. at ¶ 120. 1 Federal Rule of Civil Procedure Rule 60(b)(5) authorizes the 2 Court to modify the PCD if the County establishes that “applying 3 it prospectively is no longer equitable. 4 60(b)(5). 5 establishing a “significant change either in factual conditions 6 or in law.” 7 367, 384 (1992). 8 Fed. R. Civ. P. The movant, here the County, bears the burden of Rufo v. Inmates of Suffolk County Jail, 502 U.S. Even if the County can make the requisite factual showing of 9 change, as it attempts to do by way of this Motion, the Court 10 should still not necessarily modify the PCD if the events it 11 identified “actually were anticipated at the time it entered into 12 [the] decree.” 13 (9th Cir. 2005), quoting Rufo, 502 U.S. at 385. United States v. Asarco Inc., 430 F.3d 972, 979 14 15 ANALYSIS 16 17 Where a project owner like the USFS provides detailed design 18 plans and specifications, the government, and not the contracting 19 party (here the County) bears the risk if such plans and 20 specifications are ultimately determined to be deficient. 21 the County points out, this theory of implied warranty for design 22 plans and specifications has been recognized for almost a hundred 23 years and stems from the United States Supreme Court’s decision 24 in United States v. Spearin, 248 U.S. 132 (1918). 25 the government contracted for construction of a dry dock at its 26 Brooklyn Navy Yard in accordance with detailed plans prepared by 27 the government. 28 related to alleged defects associated with those plans. As In Spearin, A dispute arose concerning additional costs 8 1 The Court upheld a government against the United States and in 2 favor of its contractor, noting that “if the contractor is bound 3 to build according to plans and specifications prepared by the 4 owner, the contractor will not be responsible for the 5 consequences of defects in the plans and specifications.” 6 136. 7 Id. at Subsequent decisions following recognize the same principle 8 that such detailed plans carry with them an implied warranty. 9 Blount Bros. Corp. v. United States, 872 F.2d 1003, 1007 (Fed. 10 Cir. 1989); Stuyvesant Dredging Co. v. United States, 834 F.2d 11 1576, 1582 (Fed. Cir. 1987). 12 Placing Co. v. United States, 25 Cl. Ct. 369 (1992); “[i]n 13 exchange for the right to direct specifically how a project shall 14 be performed, the government warrants that its directions are not 15 defective.” 16 entitled to reimbursement for increased costs due to defective 17 plans and specifications. 18 Inc. v. United States, 405 F.2d 1285, 1290 (Ct. Cl. 1969). 19 Id. at 375. As the court remarked in Concrete It is well settled that a contractor is See, e.g., L.W. Foster Sportwear Co., The so-called Spearin doctrine recognizes that if the owner, 20 here the USFS, produces design specifications setting forth in 21 precise detail how the work is to be performed with 22 specifications permitting no deviation, the owner is responsible 23 for defects in those documents. 24 States, 15 Cl. Ct. 50, 56 (1988); aff’d, 878 F.2d 1445 (Fed Cir. 25 1989). 26 /// 27 /// 28 /// Haehn Mgmt. Co. v. United 9 1 That scenario contrasts with circumstances where the owner issues 2 only general performance specifications, leaving both the 3 responsibility to prepare a detailed design, and the risk 4 attendant therewith, to a contractor like the County. 5 Stuyvesant Dredging, 834 F.2d at 1582. 6 See Whether or not the PCD is a detailed design document as 7 opposed to a simple mandate that general performance 8 specifications be reached is the issue on which enforcement of 9 the PCD now turns. The County points out the Remedial Design 10 itself calls it a 100% Final Design, consists of detailed designs 11 over 800 pages in length, and is certified by both a professional 12 engineer and a professional geologist. 13 that the PCD requires that the Design be followed to the letter. 14 County’s Mot., 12:9-16. 15 costs associated with the USFS’ defective design must fall 16 squarely on the government’s shoulders. 17 The County further claims Consequently, the County argues that the The government, on the other hand, states that the document 18 established only performance standards, and that the PCD 19 specifically contemplates that the government can require the 20 County to perform additional work to meet those standards. 21 supporting that contention, the government cites paragraph 13 of 22 the PCD, which states in relevant part that the PCD does not 23 constitute “a warranty or representation of any kind by [the 24 government] that compliance with the work requirements... will 25 achieve the Performance Standards” as set forth in the Plan’s 26 Record of Decision and Statement of Work. 27 /// 28 /// 10 PCD at ¶ 13. In 1 The PCD goes on to state that the County’s compliance with such 2 standards “does not foreclose the Forest Service from seeking 3 additional work to achieve applicable performance standards.” 4 Id. 5 The Court does not find the government’s position to be 6 persuasive in this regard. 7 the right to demand that additional work be undertaken after 8 completion of the Design itself in order to achieve desired 9 performance standards, that does not affect the County’s right to 10 rely on the detailed plans contained in the Design to satisfy its 11 initial obligation. 12 be no question that the plans and specifications fall within 13 Spearin’s purview. 14 detailed design specifications approved by its professionals and 15 required that the County adhere to the scope and method of work 16 incorporated in the Design. 17 specifications prepared by the USFS and contained within the 18 Design, performance standards simply establish an overall 19 objective and allow the contractor to determine how to meet that 20 objective. 21 For purposes of Spearin, it is clear that the Design at issue 22 here consists of detailed design specifications rather than 23 overall performance objectives. Although the government may well have With respect to the Design itself, there can The government owned the property, developed Unlike the detailed plans and Haehn Mgmt. Co. v. United States, 15 Cl. Ct. at 56. There can be no question here, given the evidence before 24 25 the Court, that the USFS Design contained significant errors 26 resulting in substantially increased costs to the County in 27 construction of the Design. 28 /// 11 1 Spearin accordingly mandates that at least with regard to 2 completing the initial Design, the government is responsible for 3 additional work occasioned by defects in the Design. 4 This conclusion does not preclude the government from later 5 seeking, under the terms of the PCD, additional work to satisfy 6 overall performance standards. 7 additional work may be required, however, does not absolve the 8 government of responsibility for errors contained within the 9 Design itself. The possibility that such The fact that additional work may ultimately be 10 required even after the Design is completed, as stipulated in the 11 PCD, does not put the County on notice that the Design plan 12 itself was not constructible as prepared, contained incorrect 13 survey elevations, misrepresented the extent of waste as shown on 14 the plans, or contained misleading information on subsurface 15 conditions. 16 contained within the Design plans may have been “somewhat off the 17 mark.” 18 under the circumstances to assign to the County the 19 responsibility for both those errors and others contained within 20 the USFS Design. 21 the government, and the PCD has to be modified accordingly. 22 /// 23 /// 24 /// 25 /// 26 /// 27 /// 28 /// Even the government appears to concede that the data Opp., 1:15. The Court finds that it would be inequitable Such responsibility must instead be borne by 12 1 CONCLUSION 2 3 The County’s Motion for Construction, Enforcement, and 4 Modification of Partial Consent Decree (ECF No. 394) is GRANTED. 5 The County’s obligation to continue construction of the Design, 6 or any new designs prepared by the USFS for contaminant 7 remediation on the former Meyers landfill site, is suspended 8 pending further order of this Court. 9 for additional costs paid by the County to construct the Final The government’s liability 10 100% Remedial Design, and for any costs incurred by the County in 11 completing said Design in the future, will be determined by 12 separate evidentiary hearing. 13 and confer 1) with respect to any discovery needed in advance of 14 such a hearing; 2) the anticipated length of the hearing itself 15 and whether it should be assigned to a special magistrate for 16 adjudication; and 3) suggested dates for the hearing so that it 17 may be scheduled as soon as reasonably feasible. 18 ordered to submit that information to the Court, by way of Status 19 Report, not later than ten (10) days following the date this 20 Memorandum and Order is filed. 21 22 The parties are directed to meet The parties are IT IS SO ORDERED. Dated: July 8, 2011 23 24 25 _____________________________ MORRISON C. ENGLAND, JR. UNITED STATES DISTRICT JUDGE 26 27 28 13

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?