South Yuba River Citizens League et al v. National Marine Fisheries Service et al
Filing
402
ORDER signed by Senior Judge Lawrence K. Karlton on 7/25/11 ORDERING that Plaitiffs' MOTION for Final Remedies 363 is GRANTED in part and DENIED in part; Defendants MAY move for relief from Judgment upon a showing that they have complied with this Court's remand order 398 . Defendants' MOTION to STRIKE and/or Exclude Evidence 380 is DENIED. American Rivers, Inc.'s unopposed MOTION for Leave to File an Amicus Brief 392 is GRANTED. (Mena-Sanchez, L)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
EASTERN DISTRICT OF CALIFORNIA
10
11
12
SOUTH YUBA RIVER CITIZENS
LEAGUE and FRIENDS OF THE
RIVER,
NO. CIV. S-06-2845 LKK/JFM
13
Plaintiffs,
14
v.
O R D E R
15
16
NATIONAL MARINE FISHERIES
SERVICE, et al.,
17
Defendants.
18
19
/
This
order
addresses
whether
any
interim
measures
are
20
appropriate during the remand period where the federal defendants
21
were found to have violated the Endangered Species’ Act (“ESA”).
22
In an order issued on July 8, 2010, (the “July Order”) this court
23
held that the National Marine Fishery Service acted arbitrarily and
24
capriciously in issuing a 2007 Biological Opinion (“BiOp”) that
25
concluded that operations associated with the Englebright and
26
Daguerre dams on the Yuba River posed no jeopardy to the survival
1
1
of spring-run Chinook salmon (“chinook”), Central Valley Steelhead
2
(“steelhead”),
3
threatened species list. In an order issued on April 29, 2011, this
4
court remanded the matter back to the National Marine Fishery
5
Service (“NMFS”) to prepare a new BiOp consistent with the court’s
6
July Order. The April order requires the NMFS to complete the BiOp
7
by December 12, 2011. See ECF No. 378.
and
green
sturgeon,
all
of
which
are
on
the
8
Plaintiffs seek injunctive relief in the form of nine interim
9
measures to protect the species until a new BiOp is prepared by the
10
agency. Defendants argue that the only appropriate remedy is to
11
remand the matter to the NMFS. For the reasons stated below, the
12
plaintiffs’ motion is GRANTED in part and DENIED in part.
I. Procedural Background
13
14
This court’s July Order addressed claims by plaintiff that
15
the
National
16
capriciously in adopting the BiOp, in violation of Section 7 of the
17
Endangered Species Act. This court held that the BiOp was arbitrary
18
and capricious because it concluded that the operation of the dams
19
would
20
conclusion was not supported by the record. Upon a finding that a
21
project poses no jeopardy to the survival or recovery of a
22
threatened species, an agency may operate the project pursuant to
23
an Incidental Take Statement (“ITS”). The ITS specifies (1) what
24
incidental “takings” of individual species will result from the
25
project, (2) the mitigation measures that are necessary to minimize
26
the takings, and (3) the terms and conditions that must be complied
pose
Marine
“no
Fishery
jeopardy”
to
Service
the
2
acted
threatened
arbitrarily
fish,
when
and
that
1
with to implement those mitigation measures. The court held that
2
the NMFS had not sufficiently supported its no-jeopardy conclusion,
3
“but not that a jeopardy conclusion was inescapable.” July 8 Order
4
16:18. In particular, the court found the following defects in the
5
BiOp:
6
(1) The BiOp did not conclude that the populations of the
7
three listed fish are stable, yet it concluded that the project’s
8
unmitigated
9
conclusion about the effects of the project must take the current
10
status of the population into account. Without a finding that the
11
three
12
rationally conclude that the unmitigated effects of the project
13
would not jeopardize the species. July Order 19.
listed
effects
fish
would
not
populations
jeopardize
are
stable,
the
species.
the
BiOp
Any
cannot
14
(2) The BiOp concludes that the project will continue to
15
impose stressors on listed species without explaining why these
16
stressors will not jeopardize the species. Those stressors are:
17
migration barriers caused by Daguerre Point Dam and Engelbrigt Dam;
18
irregular flow regimes and temperature, leading to pre-spawning
19
mortality and reduced reproductive success; interference with
20
gravel
21
Englebright Dam; and entrainment and impingement.1 Because the BiOp
22
failed “to discuss (through some method) the magnitude of the
accumulation
and
compromised
spawning
habitat
below
23
24
25
26
1
Where water is diverted, a screen is used to keep fish from
being “entrained,” i.e., diverted from the river to the diversion
channel. Although these screens are necessary to protect fish, they
also present a risk to fish, as fish can be “impinged,” i.e.,
trapped against the screen by the force of water.
3
1
stressors’ impact,
the populations’ ability to tolerate this
2
impact, and the reason why any decline will not reduce the overall
3
likelihood
of
4
determine
that
5
reproduction, population, distribution, or diversity–the factors
6
necessary for the species to survive. July Order 38.
survival
the
or
recovery,”
stressors
will
it
not
could
cause
not
a
properly
decline
in
7
(3) The BiOp omits any analysis of the possibility of a period
8
of increased entrainment due to the cumulative effect of the
9
challenged project and the Wheatland project. Additionally, the
10
BiOp did not support its conclusion that the Corps’ operations,
11
when considered in the context of the Wheatland project, will not
12
jeopardize the green sturgeon population.
13
(4) The BiOp does not discuss other stressors that might
14
jeopardize the listed species. Those stressors are: hatcheries, the
15
San Francisco Bay Delta, the species’ overall depressed conditions,
16
global warming, and poaching. Even if the agency determined these
17
factors to be unimportant, it must provide a reasoned explanation
18
for that conclusion.
19
(5) With respect to critical habitat for the listed species,
20
the BiOp does not support its conclusion that the restoration
21
measures
22
magnitude outweighs the project’s impacts.
described
in
the
BiOp
will
provide
benefits
whose
23
The court ordered additional briefing on the issue of whether
24
the Corps violated the terms and conditions of the ITS, and whether
25
the plaintiffs would be entitled to preliminary relief if such a
26
violation had occurred. On November 16, 2010, after supplemental
4
1
briefing on the issue the court dismissed as prudentially moot
2
plaintiffs’ claim that the Corps had violated the ITS, and denied
3
plaintiffs’ motions for a preliminary injunction. On November 23,
4
2010, this court entered an order approving a stipulation by the
5
parties. In that stipulation, the parties agreed, inter alia, that
6
the BiOp and ITS should not be vacated during remand. Thus, the
7
project is currently operating pursuant to the 2007 BiOp and the
8
ITS.
9
In April 2011, the court remanded the matter back to the NMFS
10
to complete a new BiOp consistent with the July Order by December
11
12, 2011.
II. Analysis
12
13
Plaintiffs propose an injunction requiring the defendants to
14
comply with nine measures, which plaintiffs argue are necessary to
15
prevent the project from jeopardizing the survival or recovery of
16
the listed species while a new BiOp is prepared. Plaintiffs’
17
proposed interim measures are:
18
(1) developing and implementing a written operation plan
19
for optimum operation and maintenance of the Daguerre
20
fish ladders, (2) developing and implementing a plan for
21
optimum
22
Daguerre dam spillway to try to concentrate flows over
23
the spillway toward the dam's center, away from the fish
24
ladders
25
installing and operating devices to alert the Corps of
26
debris blockages in the Daguerre
placement
which
are
of
to
movable
either
5
flash
side
of
boards
the
on
dam,
the
(3)
fish ladders, (4)
1
promptly clearing debris blockages from the Daguerre
2
fish ladders, (5) adopting a revised plan for managing
3
sediment
4
re-engineering the south bank of the Yuba River and the
5
main channel of the Yuba River as needed to improve
6
flows to the Daguerre south fish ladder, (6) installing
7
grates over the Daguerre fish ladders to prevent fish
8
from
9
poaching,
build-up
jumping
out
(7)
above
of
Daguerre
these
installing
and
ladders
a
a
and
plan
to
temporary,
for
prevent
seasonal
10
artificial segregation weir within the Yuba River below
11
Englebright to create a temporary, impassable barrier
12
segregating spring Chinook from fall run Chinook and
13
allowing the former to spawn without competition from
14
the
15
implementation
16
long-term gravel augmentation plan for creating new
17
spawning habitat in the Yuba River below Englebright,
18
and (9) developing and implementing a plan for securing
19
better
20
vegetation in the Yuba River reach from Englebright to
21
Daguerre.
fall-run
Chinook,
of
an
wood-related
(8)
adopting
improved,
structures
and
commencing
comprehensive
and
native
final
riparian
22
Pls.’ Final Remedy Brief (“Pls.’ Remedy Brief”) 3:13-4:4, ECF No
23
363. Plaintiffs also request that defendants file quarterly status
24
reports describing compliance with these measures.
25
26
Defendants argue that remand is the only appropriate remedy.
////
6
1
A. Standard of Review for Injunctive Relief under the ESA
2
As a preliminary matter, the parties disagree sharply as to
3
the standard of review to be applied for issuing an injunction
4
under the Endangered Species Act. In particular, the parties have
5
differing
6
irreparable
7
injunction may issue absent a showing of irreparable harm if there
8
is a substantial violation of ESA’s procedural requirements. Pls.’
9
Remedy Brief 6. Alternatively, plaintiffs argue that if a showing
10
of irreparable harm is required, the burden is on the defendants
11
to show that no irreparable harm will occur absent the injunction.
12
Pls.’ Remedy Brief 7. Additionally, plaintiffs argue that the
13
listed species will suffer irreparable harm absent injunctive
14
relief. Id. at 7. Defendants argue that a showing of irreparable
15
harm is always required in order to obtain an injunction, including
16
under the ESA.
views
harm.
with
respect
Plaintiffs
to
argue
the
necessity
that
under
of
the
showing
ESA,
an
17
The parties discuss the standard for granting injunctive
18
relief under the ESA without distinguishing between the standard
19
for preliminary versus permanent relief. Typically, “a preliminary
20
injunction is effective pendente lite until a decision has been
21
reached on the merits,” whereas “a permanent injunction will issue
22
only after a right thereto has been established at a trial on the
23
merits.” 11A WRIGHT & MILLER , FEDERAL PRACTICE
24
1995). Courts evaluating injunctive relief in environmental cases
25
have also conflated the two types of injunctions. In Monsanto, the
26
Court reviewed the preliminary injunction granted by the district
7
AND
PROCEDURE § 2941 (2d ed.
1
court in Geertson Farms, Inc. v. Johanns, 2007 U.S. Dist. LEXIS
2
21491 (N.D. Cal. 2007), but recited the four-factor test for
3
permanent injunctions: “A plaintiff seeking a permanent injunction
4
must satisfy a four-factor test before a court may grant such
5
relief. A plaintiff must demonstrate: (1) that it has suffered an
6
irreparable injury; (2) that remedies available at law, such as
7
monetary damages, are inadequate to compensate for that injury; (3)
8
that, considering the balance of hardships between the plaintiff
9
and defendant, a remedy in equity is warranted; and (4) that the
10
public interest would not be disserved by a permanent injunction."
11
Monsanto Co. v. Geertson Seed Farms, 130 S. Ct. 2743, 2756
12
(2010)(emphasis added)(quoting eBay Inc. v. MercExchange, L.L.C.,
13
547 U.S. 388, 391 (2006)). The Court went on to state, “the
14
traditional four-factor test applies when a plaintiff seeks a
15
permanent injunction to remedy a NEPA violation,” (emphasis added)
16
citing Winter v. NRDC, Inc., 555 U.S. 7 (U.S. 2008), for this
17
proposition even though Winter involved preliminary injunctive
18
relief. In Winter, the Court set forth a different four-factor test
19
to
20
plaintiff seeking a preliminary injunction must establish that he
21
is likely to succeed on the merits, that he is likely to suffer
22
irreparable harm in the absence of preliminary relief, that the
23
balance of equities tips in his favor, and that an injunction is
24
in the public interest." Winter, 555 U.S. at 20. Admittedly, the
25
tests are quite similar. Indeed, “[t]he standard for a preliminary
26
injunction is essentially the same as for a permanent injunction
determine
whether
to
grant
8
a
preliminary
injunction.
“A
1
with the exception that the plaintiff must show a likelihood of
2
success on the merits rather than actual success.” Amoco Prod. Co.
3
v. Vill. of Gambell, 480 U.S. 531, 546 (U.S. 1987).2 This court
4
nonetheless finds it necessary to set forth precisely the standard
5
to apply
to plaintiffs’ motion.
6
In this case, plaintiffs seek nine interim measures that would
7
remain in place until the defendants have remedied their ESA
8
violation by completing a new BiOp. The requested measures are not
9
preliminary in the conventional sense in that the court has already
10
decided the merits of this case. However, the measures are not
11
permanent in the conventional sense in that they may be lifted once
12
the defendants comply with this courts remand order by preparing
13
a new BiOp. Additionally, the circumstances of this case differ
14
from a typical permanent injunction request in that plaintiffs
15
request measures to prevent future irreparable harm, even if they
16
have not proven that irreparable harm has already resulted from
17
defendants’ liable conduct. Having already determined that the
18
defendants are liable for a violation of the ESA, there is no need
19
for the court to evaluate plaintiffs’ likelihood of success on the
20
merits. The court will therefore look at the following factors to
21
determine whether interim injunctive measures are appropriate in
22
this
case:
whether
the
measures
are
necessary
to
prevent
23
24
25
26
2
Additionally, the preliminary injunction standard does not
include evaluation of whether there are adequate remedies at law,
although that question is certainly intertwined with the inquiry
as to whether the type of harm likely to be suffered is
“irreparable.”
9
1
irreparable
injury;
whether
remedies
available
at
law
are
2
inadequate to compensate for that injury; whether the balance of
3
hardships weigh in favor of injunctive relief; and whether the
4
public interest would be served by the injunction.
5
i. The Balance of Hardships and the Public Interest
6
Under the Endangered Species Act, the third and fourth factors
7
always tip in favor of protecting the species. Tennesee Valley
8
Authority v. Hill, 437 U.S. 153 (1978) (“Congress has spoken in the
9
plainest of words, making it abundantly clear that the balance has
10
been struck in favor of affording endangered species the highest
11
of priorities."). Thus, “the balance of hardships and the public
12
interest tip heavily in favor of endangered species. We may not use
13
equity’s scales to strike a different balance.” Sierra Club v.
14
Marsh, 816 F.2d 1376, 1383 (9th Cir. 1987). In this case, the
15
parties agree that Monsanto’s holding that the four-factor test
16
applies to injunctions issued to remedy violations of the National
17
Environmental
18
conclusion that, under the ESA, the balance of hardships and the
19
public interest factors tip towards protecting the species. Fed.
20
Defs.’ Remedy Brief 7:3-5; Pls.’ Remedy Brief 5:26-6:3. Indeed, the
21
Court could not undo Congress’ command in this regard.
Policy
Act
(“NEPA”)
does
not
undo
Congress’
22
Accordingly, the court finds that the balance of hardships and
23
the public interest factors support granting injunctive relief in
24
this case.
25
ii. Irreparable Injury
26
Plaintiffs, however, take their argument a step further by
10
1
urging that the standard of review under ESA also differs from the
2
traditional
3
irreparable harm is required when there is a substantial procedural
4
violation of the ESA in connection with a federal project. Pls.’
5
Remedy Brief 6-7. Prior to Monsanto, the Ninth Circuit had held
6
that a substantial procedural violation of the ESA could warrant
7
issuance of an injunction. In Thomas v. Peterson, 753 F.2d 754 (9th
8
Cir. 1985), the Ninth Circuit found that defendants’ complete failure to
9
prepare a BiOp under the circumstances
analysis
for
injunctions
in
that
no
showing
of
was a substantial procedural
10
violation, for which ”the remedy must be an injunction of the
11
project pending compliance with the ESA.” Id. at 764. This holding
12
was rooted in prior Ninth Circuit cases decided under the National
13
Environmental Policy Act (“NEPA”): “Our cases repeatedly have held
14
that,
15
appropriate
16
requirements. Irreparable damage is presumed to flow from a failure
17
properly to evaluate the environmental impact of a major federal
18
action. We see no reason that the same principle should not apply
19
to procedural violations of the ESA.” Id. (internal citations
20
omitted).
21
undercuts plaintiffs’ assertion that Monsanto, a NEPA case, “does
22
not alter the law governing injunctions under the ESA.” Pls.’ Brief
23
6:4-5. In Monsanto, the Court rejected lower court holdings insofar
24
as they “presume[d] than an injunction is the proper remedy for a
25
NEPA violation except in unusual circumstances.” 130 S. Ct. at
26
2757. Instead of a presumption in favor of issuing an injunction,
absent
‘unusual
remedy
The
Thomas
circumstances,’
for
a
court’s
violation
reliance
11
an
of
on
injunction
NEPA's
earlier
is
the
procedural
NEPA
cases
1
“a court must determine that an injunction should issue under the
2
traditional four-factor test set out above.” Id. The Court went on
3
to conclude that the test had not been satisfied in the case before
4
it, because “[m]ost importantly, respondents cannot show that they
5
will suffer irreparable injury if [defendant] APHIS is allowed to
6
proceed with any partial deregulation.” Id. at 2760.
7
Plaintiffs’ argument is not completely defeated by Monsanto,
8
since in Thomas, the Ninth Circuit distinguished between ESA’s and
9
NEPA’s procedural provisions, holding that “the strict substantive
10
provisions of the ESA justify more stringent enforcement of its
11
procedural requirements [than NEPA’s procedural requirements],
12
because [ESA’s] procedural requirements are designed to ensure
13
compliance with the substantive provisions,” whereas NEPA does not
14
contain substantive provisions. Thomas 753 F.2d at 764. The court
15
went on to conclude that where a project is allowed to proceed
16
without compliance with procedural requirements, “there can be no
17
assurance that a violation of the ESA’s substantive provisions will
18
not result.” Id. Since ESA’s substantive provisions prohibit
19
jeopardizing the survival or recovery of a species--clearly an
20
irreparable
21
showing of irreparable injury is required once a substantial
22
procedural violation is shown. Absent other Ninth Circuit precedent
23
to the contrary, the court might be convinced of plaintiffs’
24
position.
injury–plaintiffs
here
argue
that
no
independent
25
However, in Nat'l Wildlife Fed'n v. Nat'l Marine Fisheries
26
Serv., 422 F.3d 782 (9th Cir. 2005), the Ninth Circuit held that
12
1
rejection by the district court of a BiOp and a finding of
2
irreparable harm were “precisely the circumstances in which our
3
precedent
4
appropriate.” Id. at 796. Further, in National Wildlife Fed'n v.
5
Burlington N. R.R., 23 F.3d 1508 (9th Cir. 1994), the court held
6
“these [Tennessee Valley Authority line of] cases do not stand for
7
the proposition that courts no longer must look at the likelihood
8
of future harm before deciding whether to grant an injunction under
9
the ESA.” Id. at 1511 (internal citations omitted).
10
In
indicates
addition
to
that
the
these
issuance
precedents,
of
an
reason
injunction
dictates
is
that
11
plaintiffs make a showing that the particular injunction they
12
request is necessary to prevent irreparable harm caused by the
13
defendants’ violation of the ESA. It could not be the case that any
14
time defendants are found liable for a significant violation of the
15
ESA’s procedural provisions, the plaintiffs are entitled to any
16
form of injunctive relief that they request. Indeed, “injunctive
17
relief must be tailored to remedy the specific harm alleged.” NRDC
18
v. Winter 508 F.3d 885, 886 (9th Cir. 2007). As a practical matter,
19
the court must decide what irreparable harms are likely to occur
20
to
21
injunction. Here, plaintiff is only entitled to an injunction that
22
prevents irreparable harm caused by defendants’ violation of the
23
Endangered Species Act. Thus, even if a showing of irreparable harm
24
was not necessary for an injunction to issue, such a showing is
25
required in order to justify the specific measures that plaintiffs’
26
request. Accordingly, the court holds that plaintiff must show that
the
species
in
order
to
craft
13
an
appropriately
tailored
1
irreparable harm to the listed species will result from defendants’
2
violation of the ESA in the absence of each measure plaintiffs
3
request.
4
iii. Adequacy of Remedies at Law
5
In environmental cases, it is presumed that remedies at law
6
are inadequate. "Environmental injury, by its nature, can seldom
7
be adequately remedied by money damages and is often permanent or
8
at least of long duration, i.e., irreparable. Cal. ex rel. Lockyer
9
v. United States Dep't of Agric., 2009 U.S. App. LEXIS 19219 (9th
10
Cir. 2009).
11
B. Plaintiffs’ Requested Relief
12
Plaintiffs argue that, given the current degraded condition
13
of
the
population
14
injunctive relief is necessary to prevent irreparable harm to those
15
species. A species’ condition is measured using four criteria:
16
abundance, productivity, spatial structure, and genetic or life
17
history diversity. Plaintiffs provide evidence that the population
18
of all three fish at issue suffer from low abundance. In addition,
19
the chinook population’s productivity is in decline, and its
20
spatial distribution is low. Plaintiffs argue that against this
21
backdrop, the Englebright and Daguerre dams and related operations
22
put the species in jeopardy of extinction while the new BiOp is
23
being produced. This position is consistent with the July Order,
24
which held that the BiOp was arbitrary and capricious because it
25
concluded
26
jeopardize the species, without first concluding that the species
that
the
of
the
three
project’s
protected
unmitigated
14
species
effects
of
fish,
would
not
1
was in a stable condition. Plaintiff argues that nine remedial
2
measures are necessary to improve the species’ chances of survival
3
while a new BiOp is prepared.
4
5
The
defendants
argue
generally
that
the
measures
are
unnecessary to prevent irreparable harm.
6
Because plaintiff is entitled to injunctive relief only
7
insofar as it prevents irreparable harm caused by defendants’
8
violation of the ESA, the court analyzes each of the plaintiffs’
9
requested measures in relation to the deficiencies that the court
10
found in the BiOp. Although the court did not reach any conclusions
11
as to what findings a properly conducted BiOp might reach, the
12
court did note some areas of deficiency upon which it based its
13
conclusion
14
capricious. The court analyzes the plaintiffs’ requested measures
15
in that context. That is, the measures must bear some relation to
16
the deficiencies in the BiOp for which the court held that the
17
defendants were liable for a violation of the ESA.
that
the
issuance
of
the
BiOp
was
arbitrary
and
18
However, because of the BiOp’s failure to produce the data and
19
analysis necessary to determine what measures, precisely, are
20
needed in order to avoid jeopardizing the listed species, it is
21
impossible for the court to tailor a remedy that goes no further
22
than the bare minimum needed to protect the species. Since the
23
irreparable harm that the court is obligated to prevent is jeopardy
24
to the very survival of the species, the court will err on the side
25
of a more protective injunction.
26
Plaintiffs’ burden is also slightly diminished since the
15
1
project is currently operating pursuant to a BiOp that this court
2
found to be inadequate. Under the ESA, “take” of listed species is
3
prohibited, ESA § 9(a); 16 U.S.C § 1538(a), and a project may not
4
operate if it will result in take. Once a valid BiOp determines
5
that the project poses no jeopardy to the survival, “incidental
6
take” is permitted if it is “in compliance with the terms and
7
conditions specified in a written incidental take statement.” ESA
8
§ 7(o)(2); 16 U.S.C § 1536(o)(2). The ITS functions to immunize the
9
Corps for otherwise-prohibited take of listed species. In this case
10
the Corps already determined that the project was likely to affect
11
the
12
obligation on the part of the Corps to seek a BiOp and ITS. In
13
cases where a BiOp relating to a new project has been found to be
14
inadequate, a court could enjoin the new project entirely. See,
15
e.g., Thomas v. Peterson, 753 F.2d 754 (9th Cir. 1985). In this case,
16
plaintiffs do not seek to enjoin operation of the South Yuba dams
17
entirely. Without suggesting that such an injunction would have
18
been granted, the court notes that absent the stipulation by the
19
parties that allows the project to continue to operate pursuant to
20
the 2007 BiOp and ITS, the Corps might not be shielded from
21
liability for take resulting from the operation of Englebright and
22
Daguerre dams.
23
three
listed
species.
This
determination
triggered
The court analyzes plaintiffs’ proposed measures in turn.
24
////
25
////
26
////
16
an
1
1. Measures 1-6 Designed to Correct Upstream Migration Problems
2
(i)
3
steehlhead
4
operation
5
Daguerre fish ladders.
Measure
1:
Reduce
passage
plan
for
the
by
impediment
developing
optimum
and
operation
to
spring
Chinook
implementing
and
a
maintenance
and
written
of
the
6
Plaintiffs request that the Corps be required to install flow
7
meters to measure the volume of water passing through the Daguerre
8
fish ladders, and to use information collected from the meters and
9
from an existing VAKI device (a device that records the number of
10
fish using the ladders) to develop data and conclusions as to the
11
optimum flow for promoting fish passage. Plaintiffs request that
12
the Corps complete and implement a written operation plan by no
13
later than December 31, 2011.
14
The
July
recognized
17
impediments
18
mitigated and constitute a ‘stressor’ on the Chinook and steelhead,
19
but that the BiOp concluded nonetheless that the stressor posed no
20
jeopardy to the species. This conclusion was not supported by the
21
record:
23
24
25
26
through
the
BiOp’s
Specifically, the July Order noted that the BiOp states that four
migration
through
the
16
upstream
migration
in
discussion
to
upstream
deficiencies
15
22
of
Order
Daguerre
Daguerre
are
Dam.
not
In order to determine that the stressors will not cause a
decline in the reproduction, population, distribution, or
diversity, the BiOp must discuss (through some method) the
magnitude of the stressors’ impact, the populations’ ability
to tolerate this impact, and the reason why a decline will
not reduce the overall likelihood of survival or recovery. .
. Because the BiOp concludes that the project will continue
to impose stressors on listed species without explaining why
these stressors will not jeopardize the species, the BiOp’s
17
1
2
no-jeopardy conclusion is arbitrary and capricious.
July Order at 39.
3
While the July Order noted the defendants’ failure to support
4
its conclusion that the stressors imposed by Daguerre did not pose
5
jeopardy to the species, plaintiffs have submitted evidence showing
6
that the populations of the listed fish species are unstable or in
7
decline, and that against that backdrop, impassable fish ladders
8
at Daguerre do indeed jeopardize the survival and/or recovery of
9
the species.
10
In her declaration, Dr. Christine Swanson stated that the
11
extinction risk for spring chinook is increasing. The abundance,
12
productivity, spatial structure, and diversity for spring chinook
13
have all declined over the past six years. For example, in 2009,
14
a total of less than 2500 spring chinook returned to three streams
15
that support genetically distinct spring chinook. This was a 78%
16
decline from the average number of spring Chinook returning to
17
those streams each year from 1998 to 2005. 2010 Swanson Decl., ¶
18
13, 14, ECF No. 362. Impassable dams in the Sacramento-San Joaquin
19
watershed contribute to the decline in the viability of steelhead
20
and spring chinook because those two species depend on access to
21
freshwater
22
restrict access to spawning and rearing habitat.
rivers
for
spawning
and
rearing.
Impassable
dams
23
Defendants’ cited expert declaration does little to rebut this
24
evidence. Defendant argues that, although the conditions are not
25
optimal, spring Chinook and steelhead are able to use the fish
26
ladders at Daguerre to migrate upstream. However, defendants’
18
1
opposition and evidence submitted therewith suffer from the same
2
flaw as the BiOP: they fail to address the effects of Daguerre
3
given the already-unstable condition of the fish population at
4
issue.
5
highlights this point: “the level of adverse impact associated with
6
the operation of Daguerre Point Dam would not in and of itself
7
result in irreparable harm to the species during the interim
8
period.” Decl. Gary Sprague ¶ 13, ECF No. 372-2 (emphasis added).
9
Moreover, Mr. Sprague’s declaration assumes what it concludes: “for
10
the purposes of this declaration, I assumed that the Yuba River
11
populations of spring-run Chinook and steelhead will not experience
12
an increase in their risk of extinction during the interim period.”
13
Id. ¶ 9. This assumption is contrary to evidence submitted by Dr.
14
Swanson, which shows that spring chinook populations are in sharp
15
decline in the Sacramento-San Joaquin river basin.3 Additionally,
16
Mr. Cavallo notes that the assumption is unreasonable, given the
17
fluctuation in chinook and steelhead populations in the Yuba River
18
over the last ten years, and the likelihood of factors that would
19
cause a downward fluctuation in the species’ population levels of
20
viability characteristics to occur. Cavallo Reply Decl. ¶ 6. For
Mr.
Sprague’s
declaration,
perhaps
unintentionally,
21
22
23
24
25
26
3
Confusingly, defendants cite Ex. Q, at 2 of the Reedy
Declaration (ECF No. 365-2) in an attempt to counter Dr. Swanson’s
conclusions. Defendants state “by contrast to other rivers, 2010
numbers indicate increased passage on the Yuba–approximately 3000
fish through Daguerre in May-August 2010, the spring-run
immigration period.” However, the chart in Ex. Q, at 2 appears to
cover a period starting in September 2010 and ending in November,
and does not appear to the court to indicate anything about fish
passage through Daguerre.
19
1
example, oceanic up-swelling, drought, wildfires, and disease
2
outbreaks are factors that have some likelihood of occurring in the
3
interim period, and would increase the risk of extinction of the
4
species. Id.
5
Defendants’ argument about Measure 1's feasibility has more
6
merit.
Defendants
assert
that
drawing
conclusions
about
the
7
correlation between flow and passage would require assessment over
8
several spawning runs, and that it is not feasible to develop a new
9
flow plan prior to the issuance of the BiOp. Ellrott Decl., 6, ECF.
10
No. 321-2. Declaration testimony from plaintiffs’ witness, Brad
11
Cavallo, supports this assertion. Cavallo described a schedule in
12
which flow meter data gathered throughout 2011 would render a
13
conclusion, “no later than December 31, 2011." Cavallo Decl. 6,
14
ECF. No. 363-2. This is much later than the plaintiffs’ proposed
15
BiOp deadline, and shortly after the December 12, 2011 BiOp
16
completion date ordered by this court. Defendants argue that since
17
a completed study and plan for optimum fish passage is not likely
18
to be implemented prior to the release of the new BiOp, this remedy
19
would not prevent the harm that occurs in the interim period.
20
Plaintiffs argue that the data collected in the interim period
21
is still likely to prevent harm caused by the defendants’ ESA
22
violation. It may well be that the new BiOp and incidental take
23
statement are very likely to require that the Corps collect data
24
and implement a program for maintaining optimal flow levels over
25
the ladders in order to facilitate upstream migration. Absent the
26
interim measure proposed by plaintiff, data collection would not
20
1
begin until after completion of the new BiOp and incidental take
2
statement, and implementation of the program would not occur until
3
sufficient data has been collected. According to plaintiff, it
4
would take approximately one year to collect the data, complete a
5
study, and implement a plan. See Cavallo Decl. ¶ 18. Data collected
6
in the interim period will shorten the amount of time overall that
7
less-than-optimal
8
migration over the Daguerre fish ladders. As put by plaintiffs’
9
expert, even after “the new biological opinion is issued there
10
necessarily will be a substantial lag (perhaps years) before any
11
of
12
implemented and begin to have benefits for promoting survival and
13
recovery of spring Chinook and steelhead. Accordingly, in terms of
14
avoiding harms that could jeopardize these fishes’ survival and
15
recovery, it makes more sense to focus on the time between now and
16
when these new biological measures are likely to be implemented.”
17
Cavallo Reply Decl. ¶ 5.
the
remedial
flow
terms
levels
and
impede
conditions
chinook
it
and
specifies
steelhead
will
be
18
Nonetheless, the court declines to order an interim measure
19
that will provide no benefit to the listed species in the interim
20
period. Accordingly, plaintiffs request for Measure 1 is DENIED.
21
ii. Measure 2: Develop a written plan for systematic use of
22
moveable flash boards on Daguerre to manipulate the flows through
23
the fish ladder in order to optimize conditions.
24
Measure 2 is closely related to Measure 1. Flash boards can
25
be used to manipulate the flow levels in the fish ladders. Flash
26
boards can divert more water to flow over the ladders or can divert
21
1
water away from the ladders. Plaintiffs argue that no systematic
2
criteria is presently used to govern the use of flash boards to
3
optimize flow levels. With proper use, flash boards can contribute
4
to optimal conditions for fish passage through the Daguerre fish
5
ladders by “reducing the tendency of the spillway flow to confuse
6
the fish and preclude them from finding the fish ladders and. . .
7
increasing the head behind the dam, thereby forcing more water into
8
the
9
attraction to and passage through the ladders.” Cavallo Decl. ¶ 21
10
. When not managed properly, flash boards can cause “collection of
11
debris that traps fish attempting to migrate past the flash boards,
12
the impingement of juveniles on the flash boards, and the promotion
13
of predation.” Id. ¶ 22.
fish
ladders
during
dry
conditions
and
improving
fish
14
As discussed above, the July Order held that impediments to
15
upstream migration through Daguerre constitute a stressor on the
16
protected species, and that stressor was not properly accounted for
17
in the BiOp. Accordingly, Measure 2 is related to an arbitrary and
18
capricious
19
utilization of flash boards would reduce impediments to migration
20
through Daguerre.
conclusion
adopted
in
the
BiOp,
because
proper
21
Plaintiffs have submitted evidence, discussed under Measure
22
1 above, showing that the populations of spring chinook and
23
steelhead
24
population degredation because of impediments to upstream migration
25
to spawning and rearing habitat. Plaintiffs have also submitted an
26
expert declaration showing that the proper use of flash boards
are
on
the
decline
and
22
are
vulnerable
to
further
1
would ease the stressor caused by Daguerre, but that improper
2
placement of the flash boards increases the risk that the listed
3
species will get trapped in debris, impinged on the flash boards,
4
or preyed upon thus jeopardizing the survival and recovery of the
5
species.
6
Defendants proffer two arguments against implementation of
7
Measure 2. First, defendants argue that it is unnecessary because
8
fish passage at Daguerre is adequate. To support that proposition,
9
defendants cite a paragraph of the Sprague declaration which reads,
10
“improved management for fish passage will reduce adverse impacts,
11
and benefit federally listed Chinook and steelhead, but it is not
12
a measure that is likely to avoid irreparable harm to these species
13
during the interim period. Take associated with poor management of
14
the dam flash boards is likely to result through delays in upstream
15
migration,
16
juveniles.” Sprague Decl. ¶ 15. In short, the paragraph cited does
17
not stand for defendants’ proposition that fish passage is already
18
adequate. Rather, Mr. Sprague appears to agree with plaintiffs that
19
poor management of the flash boards results in take of the listed
20
species, and that the species would benefit from proper management.
21
Additionally, this court, in its July Order, rejected the BiOp’s
22
conclusion that fish passage through Daguerre was adequate, holding
23
that the BiOp did not take into account the compromised condition
24
of the listed species when reaching that conclusion.
25
26
and
Defendants’
potentially
second
through
argument
is
increase
that
this
predation
measure
on
is
impractical because the placement of the flash boards is controlled
23
1
by an entity outside of the Corps’ control. The declaration that
2
defendants submit to support this assertion, however, states that
3
the entity, Cordua Irrigation District (“CID”), installs the flash
4
boards pursuant to a license issued to it by the Corp. According
5
to the declaration, the license requires CID to coordinate its
6
activities with the Corps and other defendant agencies. Decl.
7
Grothe 8:25-9:1. The court is therefore unconvinced that Measure
8
2 is impractical for the reasons stated by the defendant.
9
It appears to the court that the parties’ experts are in
10
agreement that improved management of the flash boards at Daguerre
11
would benefit the listed species by improving the ability of the
12
fish
13
Currently, impediments to upstream migration threaten the survival
14
and recovery of the species. Accordingly, the court concludes that
15
better management of the flash boards is necessary to prevent
16
irreparable harm in the interim period.
to
migrate
upstream
to
spawning
and
rearing
habitats.
17
The court therefore ORDERS the Corps to develop a written plan
18
within six weeks of the issuance of this order that specifies how
19
the flash boards can be used to maximize fish passage at Daguerre,
20
what Yuba River flow conditions will prompt the placement or
21
removal of the flash board, where the flash boards will be placed
22
under different river flow scenarios, and any other pertinent
23
criteria related to operating the flash boards in the way that best
24
facilitates fish passage at Daguerre. Additionally, the plan shall
25
specify that the Corps will monitor the flash boards at least once
26
per week to make sure that they have not collected debris that
24
1
might contribute to juvenile fish mortality, and that the Corps
2
will continually adjust the plan for operation and maintenance of
3
flash
4
monitoring efforts.
5
iii. Measures 3 and 4: Monitoring and Removal of Debris in Daguerre
6
These measures are requested by plaintiff in order to prevent
7
debris from accumulating in the Daguerre fish ladders, causing low
8
flow levels in the ladders and acting as an impediment to fish
9
using the ladders. Measure 3 is to install “pressure transducers”
10
in the ladders, which would record the water pressure in the
11
ladders in order to alert the dam operator that debris in the
12
ladder was causing reduced water pressure. Measure 4 would require
13
the Corps to promptly clear debris blockages from the ladders.
boards
based
upon
the
information
generated
through
14
The BiOp acknowledged that upstream migration through Daguerre
15
is hampered when woody debris collects in the fish ladders, see
16
July Order at 21, and that due to debris and other impediments,
17
“upstream passage conditions at Daguerre Point Dam are . . .
18
considered inadequate for Chinook salmon and steelhead throughout
19
much of the year.” BiOp at 26, 31. The accumulation of debris in
20
the
21
migration
22
sufficiently account for in reaching its no-jeopardy conclusion.
23
Defendants argue that plaintiffs have no evidentiary basis for
24
the assertion that debris causes blockages for extended periods of
25
time, and that in the absence of such evidence, “there is no need
26
for inflexible debris removal timelines, which could require unsafe
Daguerre
ladders
that
the
is
July
one
of
Order
25
the
impediments
concluded
the
to
BiOp
upstream
did
not
1
entry into the river at high flows.” Def’s Remedy Brief 23.
2
Plaintiffs’ primary offered evidence is a Corps inspection log with
3
a September 16, 2009 entry that states “Both sides flowing well.
4
Dome debris at intake of the south side ladder. Appears to have
5
been placed by beavers, chew marks on sticks. Checked all warning
6
lights . . .” Ex. 1 to Weisselberg Decl., ECF No. 350-1. The same
7
inspection log states that on September 23, 2009, the inspector
8
observed, “both sides flowing well. Debris at intake ladder is
9
gone, probably removed by Fish & Game.” Id. Plaintiffs characterize
10
the chewed-upon sticks as a “beaver dam within the presence of the
11
fish ladder,” that the Corps “for some reason failed to clear.”
12
Pls.’ Remedy Brief at 17. While the court agrees that plaintiffs
13
have mischaracterized the evidence somewhat, the inspection log
14
does indicate that the Corps did not promptly remove debris that
15
was discovered during inspections. In addition, inspection logs
16
submitted by defendants show similar incidents of debris being
17
discovered during inspections, but not removed.4 Ex. 2 of Groethe
18
Decl., ECF No. 372-4.
19
Moreover, the declaration of defendants’ expert Brian J.
20
Ellrott provides that: “What is necessary is that the ladders are
21
maintained clear of surface and subsurface debris. . . Frequent
22
inspections of the ladders for surface and sub-surface debris and
23
24
25
26
4
Plaintiffs, in their reply, also state that “the recent
inspection conducted by plaintiffs” shows that the Corps has failed
to actually clear debris discovered by inspectors, but plaintiffs
do not cite any evidence of those inspections. See Pls.’ Reply
Brief at 10.
26
1
the prompt removal of any ladder blockages would be beneficial to
2
spring-run and steelhead during the interim period. . . Consistent
3
with the operations stated in the 2007 biological opinion, any
4
removal of small debris loads should be done immediately,” and
5
large debris should be removed as soon as equipment can be
6
mobilized to the site. Ellrott Decl. at 5-6.
7
Despite their own expert’s testimony, defendants maintain that
8
the debris in the ladders is not a problem so long as there is
9
sufficient flow through the ladders. Defs.’ Remedy Brief 23.
10
However, defendants’ submitted expert report calls for immediate
11
removal of debris, flow levels notwithstanding.
12
In light of the BiOp’s finding that migration is hampered by
13
debris in the ladders, plaintiffs’ submitted evidence showing that
14
debris was discovered but not removed by the Corps on several
15
occasions,
16
maintaining the ladders clear of surface and subsurface debris is
17
necessary, the court finds that Measures 3 and 4 are warranted,
18
with two modifications.
and
defendants’
expert’s
testimony
stating
that
19
The first modification is in response to defendants’ assertion
20
that installing pressure transducers is impracticable because there
21
is no hard-wired electrical source on top of the dam. Perhaps
22
anticipating this argument, plaintiffs have requested, in the
23
alternative, that the Corps be required to inspect the ladders for
24
surface and subsurface debris weekly during routine flows, and
25
daily during flows of 4,200 cfs or greater. The court finds the
26
defendants’ impracticability argument convincing, and that manual
27
1
inspections of debris in the Daguerre fish ladders is a prudent
2
alternative.
3
The second modification of plaintiffs’ proposed measure is
4
that the court declines to adopt strict time limits on removal of
5
the debris, and leaves that matter, which implicates the safety of
6
Corps employees, to the discretion of the Corps, so long as the
7
debris is removed as promptly as feasible, given any safety
8
concerns.
9
Accordingly, the court orders as follows: the Corps SHALL
10
conduct weekly manual inspections of the ladders for surface and
11
subsurface debris during routine flows. During flows of 4,200 cfs
12
or greater, the Corps SHALL conduct daily manual inspections. Upon
13
discovering debris in the ladders, the Corps SHALL remove it within
14
twelve (12) hours, even if the Corps determines that flow levels
15
are adequate for fish passage. If conditions do not allow for safe
16
immediate removal of the debris, the Corps SHALL remove the debris
17
within twelve (12) hours after flows have returned to safe levels.
18
iv. Measure 5: Adoption of a revised sediment management plan to
19
improve flows to the south fish ladder.
20
The July Order identifies the formation of a gravel sediment
21
bar upstream from Daguerre as a barrier to upstream migration.
22
Chinook and steelhead
23
through which to migrate once they pass upstream through the
24
Daguerre fish ladders. Sediment buildup can also block the flow of
25
water that attracts fish to the ladders.
26
Measure 5 is intended to address that impediment. Plaintiffs seek
require an adequately spacious channel
28
July Order 22:2-6.
1
an order that would require the Corps to adopt a revised plan to
2
manage the sediment, including inspection of the area twice per
3
year, and after all major winter storm events and to dredge the
4
area as necessary. Measure 5 also calls for the Corps to adopt a
5
plan to re-engineer the south bank of the Yuba River. Finally,
6
Measure 5 would require the Corps to place back into the Yuba River
7
any gravel-containing sediments that it dredges in locations to
8
ensure maximum benefits to the River’s substrate.
9
a. Inspection and Dredging
10
Plaintiffs contend that this measure is necessary because the
11
Corps’ current plan only requires annual inspections, and the
12
channel could be too shallow, or even blocked, for a considerable
13
time in between the inspections. Plaintiffs also argue that the
14
“plan lacks provisions to ensure that the dredging is conducted to
15
minimize impacts on the listed species.” Pls’ Remedy Brief 18.
16
Currently, the sediment management plan required by the operative
17
BiOp calls for the Corps to inspect the channel upstream from
18
Daguerre in June, and to dredge the channel if necessary. Id. The
19
channel is inadequate for passage if it is less than three feet
20
deep and thirty feet wide. 2010 Cavallo Decl. ¶ 13.
21
Defendants argue that this measure is redundant, since a
22
sediment management plan is in place, and the Corps has dredged the
23
area in August 2009 and August 2010. Defendants’ expert Mr. Sprague
24
state that, given the Corps’ plan to address sediment management
25
in a manner to provide fish passage above Daguerre Point, he does
26
“not expect impacts associated with sediment management to rise to
29
1
the level of irreparable harm to the Chinook and steelhead stocks
2
in the Yuba River during the interim period.” Sprague Decl. ¶ 21.
3
It appears that at least one of defendants’ experts is in
4
agreement with plaintiff that inspection of the channel after a
5
“high flow event,” and dredging to restore clear passage channels
6
is necessary. Defendants’ expert Ellrott stated “inspecting and
7
keeping the river channels immediately upstream of DPD [Daguerre
8
Point Dam] sufficiently deep to allow unimpeded passage for fish
9
to exit the ladders is necessary in the longer term and could
10
benefit steelhead during the interim period if a high flow event
11
this winter clogged the river channels with sediment, necessitating
12
the Corps to restore clear passage channels by implementing a
13
dredging operation as soon as flows recede enough to do so.”
14
Ellrott Decl. VI. 8 (emphasis added). A high flow event is defined
15
as a storm “that generates Yuba River flow exceeding 20,000 cubic
16
feet per second as measured at the Marysville flow gauge or flow
17
that is sufficient to move sediment loads into the bed of the
18
river. Cavallo Decl. ¶ 29.
19
The court finds that inspections following high flow events
20
as defined above, in addition to the annual inspections required
21
by the current sediment management plan, are necessary to prevent
22
irreparable harm to the listed species. Accordingly, the Corps
23
SHALL inspect the channel immediately following a high flow event,
24
as defined above. If the inspections reveal significant sediment
25
buildup that risks impairing fish passage, the Corps SHALL dredge
26
the channel in a manner that minimizes adverse impact risks to the
30
1
fish. This order does not obviate the Corps’ inspection and
2
dredging obligations under the existing sediment management plan
3
pursuant to the 2007 BiOp and ITS.
4
b. Plan for Re-engineering the South Bank of the River
5
Plaintiff argues that a more fundamental problem with upstream
6
sediment is that the river has shifted northward in the area near
7
Daguerre, causing the area upstream of the south fish ladder to be
8
perpetually shallow and inadequate for passage and attraction. To
9
remedy this problem, plaintiffs seek an order requiring defendants
10
to create a plan to re-engineer the river channel upstream of
11
Daguerre to improve flows through the south ladder.
12
The court’s July Order makes no mention of this issue in its
13
discussion of the deficiencies of the BiOp. Therefore, there is no
14
finding of liability on the part of the Corps for failing to
15
address, in the BiOp, the impact of any morphological changes in
16
the river near Daguerre. Moreover, although plaintiffs’ expert
17
states that flows to the south ladder are perpetually low due to
18
these changes and that a “fundamental change to the geomorphology
19
of the river” would improve flows to the south ladder he does not
20
explain whether passage through only the north ladder at Daguerre
21
is inadequate in the interim period. See Cavallo Decl. ¶ 30.
22
Accordingly, the court declines to adopt this component of Measure
23
5.
24
c. Placing Dredged Gravel back into the Yuba River
25
Gravel substrate provides spawning and rearing habitat for
26
salmonids, but the quality of gravel substrate is diminished in the
31
1
Yuba River. Cavallo Decl. ¶ 32. Plaintiffs request that the Corps
2
be required to place back into the river, or on the river’s bank
3
any gravel-containing sediments that it dredges from the river.
4
Defendants make no argument, in their brief or in their submitted
5
expert reports, against a requirement that they be required to
6
place dredged gravel-containing sediment back into the river or on
7
the river’s bank.
8
The parties’ briefing on this component of Measure 5 is non-
9
existent. Mr. Cavallo is the only expert to address it, he does not
10
expressly state that it is necessary to prevent irreparable harm.
11
Instead he states only that absent this component, the problem of
12
diminished gravel substrate quality would be exacerbated. Moreover
13
the July Order did not discuss the diminished quality of gravel
14
substrate around Daguerre as a stressor that was inadequately
15
addressed in the BiOp. To the contrary, the order stated that while
16
“Englebright limits recruitment of gravel and large woody material
17
[required for salmonid spawing]. . . the BiOp does not indicate
18
that Daguerre separately interferes with gravel, and plaintiffs do
19
not contend that this is the case.” July Order 28-29. Although
20
defendants
did
21
opposition
to
22
sediment placed back into the river or on its banks, the court
23
concludes that plaintiff did not carry its burden of showing that
24
irreparable harm will occur in the absence of an injunction
25
requiring this component.
26
////
not
provide
plaintiffs’
any
statements
request
32
to
have
or
arguments
in
gravel-containing
1
vi. Measure 6: Installation of locked grates to prevent poaching
2
from the Daguerre fish ladders.
3
Defendants’ failure to discuss in the BiOp the problem of
4
poaching was one of the bases upon which this court concluded that
5
the BiOp was arbitrary and capricious. July Order 56. The court
6
held
7
discountable.” Id. To prevent poaching, as well as to prevent fish
8
from jumping from the ladders and perishing on dry land, plaintiffs
9
request an order requiring the installation of locked grates over
10
that
“poaching
is
not
insignificant
.
.
.
and
not
the Daguerre ladders.
11
In their Final Remedy Brief, plaintiffs do not assert or
12
provide any evidence about the quantity of poaching or its impact
13
on the survival of the species. The evidence that plaintiffs offer
14
to support their request for Measure 6 pertains to fish jumping
15
from the ladders onto dry land, and not to poaching. For example,
16
Mr. Cavallo stated that six chinook were found on dry land near the
17
south ladder at Daguerre in September and October 2010. Cavallo
18
Decl. ¶ 33. Mr. Reedy’s declaration and attached exhibits describe
19
chinook carcasses found on dry land near the south ladder, which
20
Mr. Reedy states are likely to be those spring Chinook having leapt
21
from
22
purportedly the problem underlying the need for locked gates over
23
the ladders, plaintiffs do not offer any evidence that poaching is
24
a threat to the recovery or survival of the species. Despite this
25
lack of evidence, plaintiffs argue “the Federal Defendants have
26
done nothing to counter the evidence presented by plaintiffs.”
the
ladder.
Reedy
Decl.
¶
33
36-37.
Although
poaching
is
1
Reply Brief 12.
2
Plaintiffs’ lack of evidence is understandable, since poaching
3
necessarily takes place unobserved. Although it is plaintiffs’
4
burden to present evidence to the court that irreparable harm is
5
likely to occur absent this measure, the court finds that in this
6
case, the July Order, combined with statements in the 2007 BiOp and
7
statements by defendants’ experts lead to a conclusion that locked
8
grates are necessary to prevent irreparable harm due to poaching.
9
In the July Order, the court noted that poaching was an ongoing
10
problem at Daguerre in 1998 and 2001. July Order 55. In 1998, the
11
Spring Run Chinook Status report stated that poaching was an
12
ongoing problem at Daguerre. In 2001, the Corps determined that
13
poaching of salmon from the ladders at Daguerre was “a persistent
14
problem.” Id. Without explanation as to how the problem of poaching
15
was diminished from 2001, the 2007 BiOp failed to explain the
16
impact of poaching on the survival and recovery of the species.
17
Statements by defendants’ expert indicate that the problem of
18
poaching has not been diminished, potentially causing irreparable
19
harm to the species. In his declaration, Mr. Sprague stated:
20
“Poaching, if in large numbers, does have the potential to cause
21
irreparable harm to a species because listed stocks by the very
22
nature of being listed are already at low abundance. Poaching can
23
potentially significantly reduce a population’s abundance.” Sprague
24
Decl. ¶ 23. Abundance (along with productivity, spatial structure,
25
and genetic diversity) is one of the factors used to determine a
26
species’ viability.
34
1
Given Mr. Sprague’s acknowledgment that poaching can cause
2
irreparable harm to a species, coupled with the July Order’s
3
conclusion based on the evidence that poaching is likely to
4
continue, July Order at 56, the court concludes that poaching from
5
the Daguerre fish ladders is likely to cause irreparable harm
6
absent an injunctive measure to prevent poaching.
7
Defendants argue that the installation of locked grates may
8
cause
injury
to
the
fish
due to
sharp
edges
on
the
grates
9
themselves. Defs.’ Remedy Brief 25; Grothe Decl. 11. In response,
10
plaintiffs offer expert testimony stating “metal grates currently
11
exist over the upper bays of both ladders where fish counting
12
equipment is located and I am aware of no evidence that these
13
grates have harmed fish.” Reedy Decl. ¶ 26. Photographs attached
14
to Mr. Reedy’s declaration indicate that there are no sharp exposed
15
edges. Ex. 9 to Reedy Decl. Accordingly, the court concludes that
16
installation of locked metal grates over the Daguerre fish ladders
17
is necessary to prevent irreparable harm to the survival and
18
recovery of the species during the interim period.5 Defendants are
19
ORDERED to install locking metal grates over the Daguerre fish
20
ladders within six (6) weeks of the issuance of this order.
21
22
23
24
25
26
5
Although the court declines plaintiffs’ invitation to
speculate as to whether it is a worse injury for an individual
salmon to be cut by sharp metal edges or die on dry land, Pls.’
Reply Brief 12, the court will note that in this case the court is
most concerned with the survival and recovery of the species, and
not the comfort of any individual salmon moving its way up the
ladder. Put another way, “logic clearly dictates that the needs of
the many outweigh the needs of the. . . one.” STAR TREK II; THE WRATH
OF KHAN (Paramount Pictures 1982).
35
1
2. Measures to correct loss of genetic diversity, reproductive
2
success, and suitable habitat of the listed species.
3
i. Measure 7: Study and develop a plan to promote secure physical
4
segregation of spring Chinook from fall Chinook, to prevent cross-
5
breeding.
6
Measure 7 is intended to preserve the genetic diversity of
7
spring Chinook. Genetic diversity is one of the four factors that
8
contribute to a species’ survival and recovery. The July Order
9
noted that the defendants’ failure to consider the impact of
10
hatcheries rendered the BiOp arbitrary and capricious, and that
11
the BiOp acknowledged that interbreeding between spring and fall
12
run Chinook was a threat to the survival or recovery of the spring
13
Chinook. July Order 49, 50. According to plaintiffs, the genetic
14
diversity
15
Englebright Dam forces fall and spring Chinook to co-inhabit the
16
same area, placing them in competition with each other and reducing
17
spring
18
diversity is also threatened by hatchery-produced fish in the Yuba
19
River, which create risk of interbreeding between hatchery-produced
20
fish and spring chinook. Cavallo Decl. 11; see also Reedy Decl.,
21
Ex. H. To prevent this harm, plaintiffs’ request an order requiring
22
defendants to create a plan for a temporary segregation weir to
23
segregate spring- from fall-run chinook. Plaintiffs request that
24
the plan also include measures to counter the influence of hatchery
25
fish on the genetic diversity of spring chinook.
26
of
spring
chinook’s
Chinook
spawning
is
currently
success.
Spring
threatened
chinook’s
because
genetic
In support of their request, plaintiffs’ expert declarations
36
1
and
exhibits
2
appropriate spawning habitat can limit spring-run Chinook salmon
3
spawning success.” Reedy Decl. Ex. H. Englebright Dam currently
4
limits the spawning habitat accessible to each species, forcing the
5
overlap that threatens spring-chinook spawning success. Absent the
6
Englebright Dam, natural segregation of the two species would
7
occur. Id. Placement of an artificial weir to separate species of
8
salmon
9
streams. Id.
has
stating
been
used
“superimposition
successfully
on
and
other
competition
Sacramento
for
River
10
Defendants argue that placement of a weir, “without adequate
11
study has the potential to result in take of a listed species.”
12
Defs.’ Oppo. 26:4. The measure that plaintiffs request, however,
13
is for the Corps to study and develop a plan to place the weir.
14
Plaintiffs do not request placement of a weir without adequate
15
study. Additionally, defendants state that the Corps lacks the
16
statutory authority to implement the requested measure. Defendant
17
cites the August 6, 2010 declaration of Douglas Grothe, a Park
18
Manager, who in fact states merely that the declarant is “not
19
certain” whether the Corps has authority to implement the measure.
20
Additionally, defendants’ expert, Mr. Ellrott, states: “In
21
order for a spring-run population to persist in the Yuba River,
22
reproductive isolation from fall-run Chinook salmon is necessary.”
23
Ellrott Decl. 9, ECF No. 321-2. Mr. Ellrott also states that, given
24
current conditions on the Yuba River, “a segregation weir and
25
restoring access to habitats upstream of Englebright Dam would
26
likely be necessary in order to begin to restore reproductive
37
1
isolation between fall-run and spring-run in the Yuba River.” Id.
2
Defendants have not rebutted plaintiffs’ argument, supported
3
by this court’s July Order and the BiOp, that interbreeding poses
4
a threat to the survival of the species, and that a plan to
5
segregate
6
irreparable harm. Accordingly, defendants are ORDERED to study and
7
develop a plan for measures that will promote and secure physical
8
segregation/separation of spring Chinook from fall run Chinook in
9
the Yuba River, allowing the former to spawn without competition
10
from or cross-breeding with the fall run Chinook. The plan shall
11
propose a seasonal segregation weir within the Yuba River below
12
Englebright. The plan shall further propose measures for impeding
13
the migration of stray hatchery fish into the Yuba River to
14
locations where hatchery fish could compete with spring Chinook
15
spawners and/or interbreed with spring Chinook. The Corps SHALL
16
provide
17
Department of Fish and Game “CDFG”), NMFS, and to plaintiffs within
18
eight (8) weeks of the issuance of this order. The Corps shall then
19
implement the plan if and as approved by CDFG and NMFS.
20
ii.
21
augmentation plan to create a new spawning habitat for spring
22
Chinook and steelhead.
spring
its
Measure
plan
8:
Chinook
for
is
review
Develop
and
required
and
in
comment
implement
order
to
a
to
the
prevent
California
long-term
gravel
23
The July Order noted that Englebright dam limits the amount
24
of gravel that can accumulate downstream from it. Salmonids require
25
clean gravel beds in which to spawn, as well as woody material for
26
protection.
Recognizing
Englebright
38
interferes
with
gravel
1
accumulation, the Corps adopted a plan to inject additional gravel
2
into the river. The 2007 BiOp required implementation of a gravel
3
augmentation plan to restore spawning habitat below Englebright by
4
November 2010. Reedy Decl. 4. This court noted that the Corps’
5
“reliance on the proposed gravel injection program was reasonable”
6
even though the program had not yet commenced at the time the BiOp
7
was issued, since at the time the BiOp was issued, the plan was
8
reasonably certain to occur. July Order 28 n. 14. Since the
9
adoption of the BiOp, the gravel augmentation implementation plan
10
has indeed commenced. In November 2007, the Corps injected a small
11
amount of gravel as a pilot program. The purpose of the pilot
12
program was to inject a small amount of gravel during a low-flow
13
period, and then waiting to see where the gravel moved during the
14
high-flow period. In September 2010, the Corps issued a Gravel
15
Augmentation Implementation Plan (“GAIP”), which the Corps intended
16
to satisfy the requirements of the 2007 BiOp. The GAIP recommends
17
an adaptive management approach, which involves monitoring the
18
movement of injected gravel, and placing additional gravel based
19
on results of the monitoring. Grothe Decl. 12. In November, 2010,
20
the Corps began placing gravel into the Englebright Dam Reach.
21
Pursuant to the stipulation between the parties, the 2007 BiOp and
22
Incidental Take Statement, including the requirement that the Corps
23
implement a gravel augmentation plan, is currently in effect.
24
Plaintiffs argue that the Corps’ placement of gravel around
25
Englebright, pursuant to the GAIP, has been inadequate to offset
26
Englebright’s adverse impacts on spawning habitat. Pls.’ Remedy
39
1
Brief 23. Plaintiffs provide expert opinions stating that the
2
amount of gravel to be injected is inadequate, and that the GAIP
3
project
4
Englebright cuts off gravel supply. In Mr. Reedy’s opinion, the
5
GAIP is inadequate “because it is based on an incorrect conclusion
6
that the only area the Corps’ gravel augmentation project should
7
encompass is the 300-700 foot section between the Narrows I pool
8
to the top of the rapid downstream of the gaging station.” The GAIP
9
does not require augmentation in the other nearby sections of the
10
river affected by Englebright. Reedy Decl. 5. Mr. Reedy cites a
11
Final Habitat Expansion Plan (“HEP”), prepared by the California
12
Department of Water Resources, which calls for gravel augmentation
13
for a one-mile area starting about one-half mile downstream from
14
Englebright, continuing to one and a half miles downstream from
15
Englebright. Reedy Decl. 7; Reedy Decl. EX. D at 66.
area
is
too
small,
given
the
large
area
for
which
16
Defendants counter that the GAIP is adequate. According to
17
defendants, the GAIP is a long-term plan, developed by a leader in
18
the field of gravel augmentation, and based on exhaustive modeling
19
of various methods of gravel placements. The GAIP calls for
20
replacement of 15,000 tons of gravel to the area, beginning with
21
an injection of 5,000 tons that commenced in November 2010. The
22
GAIP’s incremental approach “yields a more resilient and time-
23
tested outcome,” according to the GAIP. Defs.’ Remedy Brief 27.
24
Defendants argue that Mr. Reedy mischaracterizes the scope of the
25
GAIP. The GAIP itself states that its goal is for “the gravel
26
deficit for the whole [Englebright Dam] reach [to] be erased.” GAIP
40
1
at 73, Reedy Decl. Ex. D. The Englebright Dam Reach is the canyon
2
between Englebright Dam and the Yuba River’s confluence with Deer
3
Creek. This is the same area covered by the recommendations in the
4
HEP, cited by plaintiffs’ expert Mr. Reedy.
5
The court concludes that plaintiffs have not met their burden
6
of showing that irreparable injury is likely to occur in the
7
absence of an order that includes plaintiffs’ proposed Measure 8.
8
Although Mr. Reedy argues persuasively that requiring the measures
9
described in the Habitat Expansion Plan would benefit spring
10
chinook by restoring gravel spawning habitat to the area around
11
Englebright, the court is not convinced that any interim measure
12
is required, given the Corps’ existing obligation to comply with
13
the 2007 BiOp and the GAIP. The court notes that the July Order
14
specifically found that the Corps’ reliance, when preparing the
15
BiOp, on a future plan to adopt a gravel augmentation plan was
16
reasonable, since the plan “reasonably certain to occur.” July
17
Order 28 n. 14. The court specifically found that it was not
18
arbitrary or capricious for the BiOp to rely on the proposed plan.
19
The court is disinclined to order an interim measure that is
20
unrelated to a specific deficiency found in the BiOp. Defendants
21
have shown that they continue to comply with the GAIP by injecting
22
gravel into the area and monitoring its movement downstream.
23
Accordingly, plaintiffs’ request for interim Measure 8 is
24
DENIED.
25
////
26
////
41
1
iii. Measure 9: Develop a plan for riparian planting and wood
2
structure.
3
Woody debris is a necessary element of spawning habitat for
4
salmonids, as it provides a cover from predators and a refuge from
5
fast-moving water. Englebright Dam traps woody debris, preventing
6
it from flowing downstream. The July Order recognized the lack of
7
woody debris as a stressor on the listed species. July Order 28.
8
Measure 9 seeks to address this problem by requiring the Corps to
9
develop a final plan and implement a project to plant native
10
riparian vegetation on a parcel of land on the lower Yuba River.
11
The plan to be implemented is identified as “Project 10" of a
12
“Rehabilitation Concepts for the Parks Bar to Hammon Bar Reach of
13
the Lower Yuba River,” prepared in November 2010. Ex. R of Reedy
14
Decl.
15
Plaintiffs’ proposed Measure 9 is similar to a measure called
16
for in the ITS issued pursuant to the 2007 BiOp, which is currently
17
in effect. Defendants argue that this makes the measure redundant
18
because a wood installation plan is scheduled to be implemented in
19
November 2011. Plaintiffs’ final remedy brief calls the loss of
20
woody debris an “impact,” but does not explain or argue that it is
21
the cause of irreparable harm. Nor does the declaration of Brad
22
Cavallo,
23
riparian vegetation and large wood . . . would be very beneficial
24
to spring Chinook and steelhead.” Decl. Cavallo 16:2-3. Plaintiffs
25
have not shown that an irreparable injury will occur in the absence
26
of Measure 9. The court, therefore, declines to adopt it.
which
states
that
“the
42
increase
presence
of
native
1
III. Conclusion
2
For the foregoing reasons, the court ORDERS as follows:
3
[1] Plaintiffs’ Motion for Final Remedies, ECF No.
4
363, is GRANTED in part and DENIED in part.
5
[2] Corps SHALL develop a written plan within six
6
weeks of the issuance of this order that specifies how
7
the flash boards can be used to maximize fish passage
8
at Daguerre, what Yuba River flow conditions will
9
prompt the placement or removal of the flash boards,
10
where the flash boards will be placed under different
11
river flow scenarios, and any other pertinent criteria
12
related to operating the flash boards in the way that
13
best facilitates fish passage at Daguerre.
14
Additionally, the plan shall specify that the Corps
15
will monitor the flash boards at least once per week
16
to make sure that they have not collected debris that
17
might contribute to juvenile fish mortality, and that
18
the Corps will continually adjust the plan for
19
operation and maintenance of flash boards based upon
20
the information generated through monitoring efforts.
21
[3] The Corps SHALL conduct weekly manual inspections
22
the Daguerre ladders for surface and subsurface debris
23
weekly during routine flows. During flows of 4,200 cfs
24
or greater, the Corps SHALL conduct daily manual
25
inspections. Upon discovering debris in the ladders,
26
the Corps SHALL remove it within twelve (12) hours,
43
1
even if the Corps determines that flow levels are
2
adequate for fish passage. If conditions do not allow
3
for safe immediate removal of the debris, the Corps
4
SHALL remove the debris within twelve (12) hours after
5
flows have returned to safe levels.
6
[4] The Corps SHALL inspect the channel upstream from
7
Daguerre immediately following a high flow event, as
8
defined above. If the inspections reveal significant
9
sediment buildup that risks impairing fish passage,
10
the Corps SHALL dredge the channel in a manner that
11
minimizes adverse impact risks to the fish. This order
12
does not obviate the Corps’ inspection and dredging
13
obligations under the existing sediment management
14
plan pursuant to the 2007 BiOp and ITS.
15
[5] The Corps SHALL install locking metal grates over
16
the Daguerre fish ladders within six (6) weeks of the
17
issuance of this order.
18
[6] The Corps SHALL study and develop a plan for
19
measures that will promote and secure physical
20
segregation/separation of spring Chinook from fall run
21
Chinook in the Yuba River, allowing the former to
22
spawn without competition from or cross-breeding with
23
the fall run Chinook. The plan shall propose a
24
seasonal segregation weir within the Yuba River below
25
Englebright. The plan shall further propose measures
26
for impeding the migration of stray hatchery fish into
44
1
the Yuba River to locations where hatchery fish could
2
compete with spring Chinook spawners and/or interbreed
3
with spring Chinook. The Corps SHALL provide its plan
4
for review and comment to the California Department of
5
Fish and Game “CDFG”), NMFS, and to plaintiffs within
6
eight (6) weeks of the issuance of this order. The
7
Corps shall then implement the plan if and as approved
8
by DDFG and NMFS.
9
[8] Defendants MAY move for relief from judgment upon
10
a showing that they have complied with this court’s
11
remand order, ECF No. 398.
12
[9] Defendants’ Motion to Strike and/or Exclude
13
Evidence, ECF No. 380, is DENIED.
14
[10] American Rivers, Inc.’s unopposed Motion for
15
Leave to File an Amicus Brief, ECF No. 392, is
16
GRANTED.
17
IT IS SO ORDERED.
18
DATED: July 25, 2011.
19
20
21
22
23
24
25
26
45
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?