South Yuba River Citizens League et al v. National Marine Fisheries Service et al
Filing
415
STIPULATION and ORDER signed by Judge Lawrence K. Karlton on 9/12/11. The grating measure (Interim Measure 5) of the Order re interim measures, 402 at 44, is amended to remove the obligation to install grates over the lower 8 bays of the south fish ladder at Daguerre Point Dam and allow completion of grate installation by September 14, 2011. (Mena-Sanchez, L)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
IGNACIA S. MORENO, Assistant Attorney General
United States Department of Justice
Environment & Natural Resources Division
SETH M. BARSKY, Section Chief
S. JAY GOVINDAN, Assistant Chief
BRADLEY H. OLIPHANT, Trial Attorney
Wildlife & Marine Resources Section
Environment & Natural Resources Division
U.S. Department of Justice
P.O. Box 7369
Washington, D.C. 20044-7369
Tel: (202) 305-0500 | Fax: (202) 305-0275
Email: bradley.oliphant@usdoj.gov
Attorneys for the Federal Defendants
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF CALIFORNIA
SACRAMENTO DIVISION
)
)
)
Plaintiffs,
)
)
v.
)
)
NATIONAL MARINE FISHERIES SERVICE, )
et al.,
)
)
Defendants
)
)
SOUTH YUBA RIVER CITIZENS LEAGUE,
No. 2:06-cv-2845-LKK-JFM
Stipulation and Order To Amend The
Court’s July 26, 2011 Order (ECF No.
402)
20
21
22
23
24
25
26
27
28
Stipulation Re Interim Remedy Order
No. C 06-02845-LKK
1
2
WHEREAS, on July 26, 2011, the Court issued its Order re interim measures, Doc. No.
402 (July 26, 2011) (“Order”);
3
WHEREAS, Interim Measure 5 of the Order requires the installation of locking metal
4
grates over all Daguerre Point Dam fish ladder bays within six weeks of the Order (September 5,
5
2011), Doc. No. 402 at 44;
6
WHEREAS, on August 18, 2011, the California Department of Fish & Game (“CDFG”)
7
wrote the Army Corps of Engineers (“Corps”) to “express concern over implementation” of
8
Interim Measures 5, and specifically that CDFG “is not in support of putting grates over the bays
9
on the lowermost section of the south fish ladder at Daguerre Point Dam,” in part due to the
10
desire of CDFG to maintain continued access to flow modification equipment designed to
11
improve fish passage conditions in the ladder;
12
WHEREAS, on August 23, 2011, Federal Defendants moved for reconsideration of the
13
requirement to put grates over the bays on the lowermost section of the south fish ladder at
14
Daguerre Point Dam and for an extension of the deadline to complete installation of the grates to
15
October 1, 2011;
16
WHEREAS, Federal Defendants subsequently clarified to Plaintiffs that CDFG staff
17
were concerned about the lower 8 bays on the south ladder and would like only those bays to
18
remain uncovered;
19
WHEREAS, following this clarification of the scope of the CDFG objections to the fish
20
grating measure, and due to Plaintiffs’ desire to ensure that CDFG has continued access to the
21
flow modification equipment in the south fish ladder, Plaintiffs will not oppose the Federal
22
Defendants’ request to be relieved of the obligation to install grates over the lower 8 bays of the
23
fish ladders; and
24
25
WHEREAS, the Corps will complete the installation of the remaining bay grates by no
later than September 14, 2011;
26
NOW THEREFORE, it is hereby stipulated between the parties that:
27
1.
28
Plaintiffs will not oppose Federal Defendants’ request to be relieved of the
obligation to install grates over the lower 8 bays of the fish ladders; and
Stipulation Re Interim Remedy Order
1
No. C 06-02845-LKK
1
2
3
2.
Federal Defendants will complete the installation of the other fish ladder grates by
no later than September 14, 2011.
3.
The grating measure (Interim Measure 5) of the Order re interim measures should
4
be amended to remove the obligation to install grates over the lower 8 bays of the south fish
5
ladder at Daguerre Point Dam and allow completion of grate installation by September 14, 2011.
6
Dated: September 9, 2011
7
MCGREGOR W. SCOTT
United States Attorney
YOSHINORI H. T. HIMEL
Assistant United States Attorney
IGNACIA S. MORENO,
Assistant Attorney General
SETH M. BARSKY, Section Chief
8
9
10
11
By:
12
/s/ Bradley H. Oliphant
_________________________
13
BRADLEY H. OLIPHANT, Trial Attorney
United States Department of Justice
Env’t & Natural Resources Division
Wildlife & Marine Resources Section
P.O. Box 7369
Washington, D.C. 20044
Phone: (202) 305-0500
Fax: (202) 305-0275
Email: bradley.oliphant@usdoj.gov
14
15
16
17
18
19
Attorneys for Federal Defendants
20
21
As authorized on September 9, 2011
By:
22
/s/ Brian Orion
_________________________
BRIAN ORION
Attorneys for Plaintiffs
SOUTH YUBA RIVER CITIZENS
LEAGUE, and FRIENDS OF THE RIVER
23
24
25
26
27
28
Stipulation Re Interim Remedy Order
2
No. C 06-02845-LKK
1
As authorized on September 9, 2011
By:
2
/s/ Howard F. Wilkins III
_________________________
HOWARD F. WILKINS III
Remy, Thomas, Moose and Manley, LLP
455 Capitol Mall, Suite 210
Sacramento, Ca. 95814
Phone: (916) 443-2745
Fax: (916) 443-9017
cwilkins@rtmmlaw.com
3
4
5
6
7
Attorneys for Defendant YWCA
8
9
As authorized on September 9, 2011
By:
10
/s/ Andrew Hitchings
_________________________
ANDREW HITCHINGS
Somach, Simmons & Dunn
813 Sixth Street, Third Floor
Sacramento, CA 95814
Fax: (916) 446-8199
Email: ahitchings@lawssd.com
Attorneys for Intervenor-Defendants
DRY CREEK MUTUAL WATER
COMPANY, BROPHY WATER
DISTRICT, and HALLWOOD
IRRIGATION COMPANY
11
12
13
14
15
16
17
As authorized on September 9, 2011
By:
18
19
HANSPETER WALTER
Kronick Moskovitz Tiedemann & Girard
400 Capitol Mall
Sacramento, CA 95814
Tel: (916) 321-4500
Fax: (916) 321-4555
Email: hwalter@kmtg.com
Attorneys for Intervenor-Defendant
RAMIREZ WATER DISTRICT
20
21
22
23
24
25
/s/ Hanspeter Walter
_________________________
As authorized on September 9, 2011
By:
26
/s/ Dustin Cooper
_________________________
Minasian, Meith, Soares, Sexton & Cooper,
LLP
27
28
Stipulation Re Interim Remedy Order
3
No. C 06-02845-LKK
1
Paul R. Minasian
Dustin C. Cooper
P O Box 1679
Oroville, CA 95965
Tel: (530) 533-2885
Fax: (530) 533-0197
Email: pminasian@minasianlaw.com
dcooper@minasianlaw.com
Attorneys for Intervenor-Defendant
CORDUA IRRIGATION DISTRICT
2
3
4
5
6
7
8
ORDER
9
It is APPROVED and SO ORDERED. The grating measure (Interim Measure 5) of the
10
Order re interim measures, Doc. No. 402 at 44, is amended to remove the obligation to install
11
grates over the lower 8 bays of the south fish ladder at Daguerre Point Dam and allow
12
completion of grate installation by September 14, 2011.
13
14
DATED: September 12, 2011
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Stipulation Re Interim Remedy Order
4