Californians for Alternatives to Toxics et al v USFWS et al
Filing
87
ORDER signed by Judge Garland E. Burrell, Jr on 5/8/12 DENYING 74 Motion for Attorney Fees. (Manzer, C)
1
2
3
4
5
IN THE UNITED STATES DISTRICT COURT
6
FOR THE EASTERN DISTRICT OF CALIFORNIA
7
8
9
10
11
12
CALIFORNIANS FOR ALTERNATIVES
TO TOXICS, a non-profit10/21
corporation; WILDERNESS WATCH, a
non-profit corporation; THE
FRIENDS OF SILVER KING CREEK, a
California non-profit
corporation; LAUREL AMES, an
individual and ANN MCCAMPBELL,
an individual,
Plaintiffs,
13
v.
14
15
16
17
18
19
UNITED STATES FISH AND WILDLIFE
SERVICE; ALEXANDRA PITTS, in her
official capacity; UNITED STATES
FOREST SERVICE; JEANNE M.
HIGGINS, in her official
capacity,
Defendants.
________________________________
20
21
22
23
24
25
26
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
2:10-cv-01477-GEB-CMK
ORDER*
Plaintiff Californians for Alternatives to Toxins (“CATT”)
moves for $86,299.06 in attorneys’ fees and costs under the Equal Access
to Justice Act (“EAJA”), prescribed in 28 U.S.C. § 2412 et seq.
74.
ECF No.
A memorandum and order was filed on September 6, 2011, in which
Plaintiff was granted summary judgment on its Wilderness Act of 1964
(“Wilderness Act”) claim, and Defendant was granted summary judgment on
Plaintiff’s remaining claims.
ECF No. 65.
Judgment was entered on
27
28
*
argument.
This matter is deemed suitable for decision without oral
E.D. Cal. R. 230(g).
1
1
September 7, 2011.
2
Service
3
(“USFSW”) oppose the motion.
4
justification issue involved in the motion, and for the reasons stated
5
below, Plaintiff’s motion is DENIED.
(“USFS”)
6
ECF No. 67
and
the
United
Defendants the United States Forest
States
Fish
and
Wildlife
Service
The Court only reaches the substantial
FACTUAL BACKGROUND
7
The facts involved with this case are stated in Californians
8
for Alternatives to Toxics v. U.S. Fish & Wildlife Service ("CATT"),
9
814 F.Supp.2d 992 (E.D. Cal. Sept. 06, 2011), the earlier filed order
10
on the parties’ cross-motions for summary judgment.
11
court recounts only those facts necessary to provide sufficient
12
context for the court’s analysis.
13
Therefore, the
Through this lawsuit, Plaintiff sought to set aside the
14
Defendants’ decision authorizing the paiute cuthroat trout restoration
15
project (the “Project”) in Silver King Creek.
16
the Project in order to restore the paiute cutthroat trout ("PCT") to
17
its historic range in Silver King Creek, by eradicating non-native
18
trout with the pesticide rotenone and restocking the treated area with
19
pure PCT.
20
generator, to distribute the potassium that would neutralize the
21
toxicity of the rotenone downstream.
22
Defendants instituted
Defendants selected an auger, powered by a gasoline-powered
Defendants assessed three alternative plans while developing
23
the project: the No Action Alternative ("Alternative One"); the
24
Proposed Action Alternative ("Alternative Two"); and the Combined
25
Physical Removal Alternative ("Alternative Three").
26
would have continued previous management of then existing PCT
27
populations in Silver King Creek, without introducing new populations
28
or efforts to eradicate non-native trout; Defendants concluded that
2
Alternative One
1
this alternative would not result in direct environmental benefits.
2
Alternative Two analyzed the Project at issue in this case, described
3
in the preceding paragraph.
4
alternative could result in loss of individual macroinvertebrate
5
species, potentially including rare or as yet unidentified species
6
endemic to Silver King Creek.
7
non-chemical techniques (a combination of electrofishing, gill
8
netting, seining, and other physical methods) to remove non-native
9
trout from the Project area.
The analysis acknowledged that this
Alternative Three proposed using
Defendants estimated the electrofishing
10
component would take over ten years to complete, and the
11
electrofishing batteries would be recharged with small
12
gasoline-powered generators.
13
Defendants ultimately selected Alternative Two as “the most
14
effective method to remove non-native trout within the PCT historic
15
habitat.”
16
under the Wilderness Act, “the short term negative effects to the
17
‘natural’ wilderness character through introduction of chemical
18
pesticide were balanced by the improved long term natural conditions
19
of wilderness character through restoration of a native species.”
20
at 1021.
21
the PCT from the Endangered Species Act's threatened species list.
CATT, 814 F.Supp.2d at 1000.
Id.
Defendants state they enacted the Project in order to remove
22
23
Defendants concluded that,
PROCEDURAL HISTORY
Plaintiffs challenged the Project under the National
24
Environmental Policy Act ("NEPA"), the Wilderness Act, the Endangered
25
Species Act ("ESA"), the Federal Water Pollution Control Act ("Clean
26
Water Act"), the California Environmental Quality Act ("CEQA") and the
27
Administrative Procedures Act ("APA"), seeking both declaratory and
28
injunctive relief.
3
1
Plaintiffs filed a motion for summary judgment on April 3,
2
2011, in which they sought partial summary judgment in their favor on
3
their NEPA and Wilderness Act claims.
4
filed an opposition and cross-moved for summary judgment on
5
Plaintiffs' other ESA, Clean Water Act and APA claims.
6
was heard on the motions on August 11, 2011.
7
granted Defendants summary judgment on all Plaintiffs’ claims except
8
for Plaintiffs’ Wilderness Act claim; and granted Plaintiffs summary
9
judgment on that claim.
10
11
On May 5, 2011, USFWS and USFS
Oral argument
Subsequently, the court
Defendants appealed the decision to the Ninth Circuit, ECF
No. 69, but later dismissed the appeal voluntarily.
12
ECF No. 72.
STANDARD
13
Under the EAJA, a party litigating against the United States
14
may recover attorneys’ fees where: “(1) the plaintiff is the
15
prevailing party; (2) the government has not met its burden of showing
16
that its positions were substantially justified or that special
17
circumstances make an award unjust; and (3) the requested attorney's
18
fees and costs are reasonable.”
19
791, 793 (9th Cir. 2002); 28 U.S.C. § 2412(d)(1)(A).
20
award attorneys’ fees under the EAJA is within the sound discretion of
21
the district court.
22
Perez-Arellano v. Smith, 279 F.3d
The decision to
Pierce v. Underwood, 487 U.S. 553, 563 (1988).
DISCUSSION
23
As a prevailing party, Plaintiffs are entitled to attorneys’
24
fees “unless the court finds that the position of the United States
25
was substantially justified or that special circumstances make an
26
award unjust.”
27
is substantially justified if it “ha[d] a reasonable basis both in law
28
and fact.”
28 U.S.C. § 2412(d)(1)(A). The government’s position
Gutierrez v. Barnhart, 274 F.3d 1255, 1259 (9th Cir.
4
1
2001).
2
the main’—that is, justified to a degree that could satisfy a
3
reasonable person.” Pierce, 487 U.S. at 565.
4
one of objective reasonableness.
5
Substantially justified means “‘justified in substance or in
Thus, the standard is
In undertaking this reasonableness calculus, the court
6
considers: “first, whether the government was substantially justified
7
in taking its original action; and second, whether the government was
8
substantially justified in defending the validity of the action in
9
court.”
Gutierrez, 274 F.3d at 1258 (citation omitted).
10
Plaintiff contends that Defendants had no reasonable basis
11
for implementing the project because, as the court held, the project
12
“violated the wilderness act by failing to (1) balance competing
13
values, (2) determine the most important value, and (3) justify the
14
decision to protect that value.
15
Essentially, the court held that, while the decision to reinstate the
16
PCT to its historical range would contribute to the overall wilderness
17
character, the manner in which Defendants chose to implement the
18
project—use of a gasoline-powered Auger—failed to take into account
19
the effect the project would have on other native species,
20
specifically invertebrates, such as stone flies.
21
CATT, 814 F.Supp.2d at 1019.
Defendants argue they were substantially justified in both
22
implementing the project and in defending it in court.
23
point to the fact that, of the assorted claims Plaintiffs asserted,
24
under numerous statutes, Plaintiffs only prevailed on an obscure
25
portion of their Wilderness Act claim—that defendants did not make
26
the requisite showing that the use of the motorized vehicle was
27
“necessary to meet minimum requirements for the purpose of [the Act]
28
5
Defendants
1
(including measures required in emergencies involving the health and
2
safety of persons within the area).”
3
16 U.S.C. § 1133(c).
4
Defendants were substantially justified in both implementing
5
the project and defending it in court.
6
ruled that implementation of the Project gave rise to a technical
7
violation of the Wilderness Act, it also found Plaintiffs’ other
8
arguments unavailing.
9
Although the court ultimately
For example, the court concluded that, contrary to
10
Plaintiffs’ contention, “the USFS's decision here is persuasive
11
in showing that restoration of the PCT to its native habitat is
12
contained in the conservation goal of the Wilderness Act, in
13
accordance with the Mead standard.”
14
The court also found unpersuasive Plaintiffs’ “conten[tion] that
15
the Project's benefits to recreational fishing ‘elevate
16
recreational activity over the long-term preservation of the
17
wilderness character of the land,’ and render it entirely
18
contrary to the Act.”
19
CATT, 814 F.Supp.2d at 1015.
Id. at 1016.
Ultimately, the court found that Defendants violated
20
the Wilderness Act since they failed to demonstrate why the
21
extent of the project was necessary, even though “the USFS
22
adequately reasoned that motorized equipment was necessary to
23
achieve conservation of PCT.”
24
that the extent of the project was necessary to ensure that
25
restoration of the PCT was completed expeditiously.
26
Defendants endured an adverse ruling, it does not necessarily
27
follow that Defendants were not substantially justified. Indeed,
28
the court recognized that “the Wilderness Act requires a delicate
Id. at 1018.
6
Defendants opined
Although
1
balancing between Congress’ desire to maintain lands untouched by
2
humans and Congress’ recognition that such an idealistic view is
3
subject to practical limitations.”
4
Wilderness Watch v. U.S. Fish and Wildlife Service, 629 F.3d
5
1024, 1033 (9th Cir. 2010)).
6
practical nature of the selected alternative—the relative speed
7
at which the project could be completed—supported its validity.
8
Notwithstanding the court’s disagreement with this opinion,
9
reasonable minds could disagree with how the statute should have
Id. at 1017 (quoting
Defendants opined that the
10
been interpreted in the situation.
11
administrative decision to select the project alternative they
12
opined to be the most practical in achieving their goal of
13
restoring the PCT was objectively reasonable, and thus, their
14
decision substantially justified.
15
Therefore, Defendants’
In sum, the court finds that Defendants’ decision
16
“ha[d] a reasonable basis both in law and fact.” Gutierrez, 274
17
F.3d at 1259. First, Defendants were justified in defending the
18
action in court because: (1)
19
of reinstating the PCT to its historical position was valid under
20
the Wilderness Act; (2) Defendants correctly found that the
21
project was necessary; and (3) reasonable minds could disagree as
22
to whether the extent of the project was necessary.
23
government was justified in taking its original action because
24
the Project was a legitimate and expeditious means of restoring
25
PCT to its historical range.
26
attorney’s fees is denied on the grounds that Defendants’
27
implementation of the project and subsequent legal defense of the
28
same was substantially justified.
as the court held, Defendants’ goal
Second, the
Therefore, Plaintiff’s motion for
7
1
2
CONCLUSION
Based on the foregoing, Plaintiff’s motion for attorneys’
3
fees is DENIED.
4
Dated: May 8, 2012
5
6
7
GARLAND E. BURRELL, JR.
United States District Judge
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?