Carey et al v. S.J. Louis Construction Inc. et al
Filing
16
ORDER signed by Judge Garland E. Burrell, Jr on 9/26/11 ORDERING that the Scheduling Order dates be modified as follows: Expert Disclosures: 10/17/11; Rebuttal Expert Disclosures: 11/14/11. (Becknal, R)
1
2
3
4
5
6
7
Richard E. Donahoo (SBN 186957)
Sarah L. Kokonas (SBN 262875)
Joseph K. Johnson (SBN 263499)
DONAHOO & ASSOCIATES
440 W. First Street, Suite 101
Tustin, California 92780
Telephone (714) 953–1010
Facsimile (714) 953–1777
rdonahoo@donahoo.com
skokonas@donahoo.com
jjohnson@donahoo.com
Attorneys for Plaintiffs
JUSTIN CAREY, et al.
8
9
UNITED STATES DISTRICT COURT
10
EASTERN DISTRICT OF CALIFORNIA
11
JUSTIN CAREY, JOSEPH
BORDEN, and PEDRO ESPINOZA
13 each as an individual, on his own
14 behalf,
12
15
16
17
18
19
20
21
22
23
Case No.: 2:10-cv-02017-GEB-GGH
[PROPOSED] ORDER REGARDING
REVISED SCHEDULING ORDER
DATES
Plaintiffs,
v.
S.J. LOUIS CONSTRUCTION INC.,
a Minnesota Corporation, LIBERTY
MUTUAL INSURANCE
COMPANY, a Massachusetts
Corporation, and DOES 1 through
200, Inclusive,
Defendants.
24
25
26
27
28
1
CASE NO. 2:10-cv-02017-GEB-GGH
1
[PROPOSED] ORDER REGARDING REVISED SCHEDULING ORDER DATES
1
IT IS HEREBY ORDERED that the Scheduling Order dates be modified as
2
follows:
3
Expert Disclosures:
October 17, 2011
4
Rebuttal Expert Disclosures:
November 14, 2011
5
6
7
8
9
10
IT IS SO ORDERED.
DATED: SEPTEMBER 26, 2011
GARLAND E. BURRELL, JR.
United States District Judge
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
2
CASE NO. 2:10-cv-02017-GEB-GGH
2
[PROPOSED] ORDER REGARDING REVISED SCHEDULING ORDER DATES
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?