Clark & Sullivan Builders, Inc. v. Incline Glass
Filing
31
FINDINGS and RECOMMENDATIONS signed by Magistrate Judge John F. Moulds on 7/10/2012 RECOMMENDING that Plaintiff's 13 motion for default judgment be granted and judgment be entered against Incline in the amount of $249,602.36, which includes attorney's fees. Motion referred to Judge Kimberly J. Mueller. Objections to F&R due within 14 days. (Zignago, K.)
1
2
3
4
5
6
7
IN THE UNITED STATES DISTRICT COURT
8
FOR THE EASTERN DISTRICT OF CALIFORNIA
9
CLARK & SULLIVAN BUILDERS, INC.,
10
Plaintiff,
No. CIV 2:12-cv-0972-KJM-JFM
11
vs.
12
INCLINE GLASS,
13
Defendant.
FINDINGS & RECOMMENDATIONS
14
/
15
Pending before the court is plaintiff Clark & Sullivan Builders, Inc.’s (“C&S”)
16
amended application for default judgment. Defendant Incline Glass (“Incline”) has not filed an
17
opposition. On review of the application and good cause appearing therefor, THE COURT
18
FINDS AS FOLLOWS:
19
ALLEGATIONS IN THE COMPLAINT
20
C&S is a California-licensed general contractor. In March 2010, the Judicial
21
Council of California, Administrative Office of the Courts (“AOC”), publicly advertised for bid
22
proposals from qualified general contractors to construct the new Susanville Courthouse located
23
at 2610 Riverside Drive, Susanville, California (“the Project”).
24
In 2010, C&S solicited bids for the Project from subcontractors for the various
25
scopes of work to be performed on the Project as part of its effort to bid the Project. Nevada26
1
1
based Incline was one of the responsive bidders for the scope of the work including the provision
2
of labor and materials related to the installation of aluminum frames, sidelites and entrances,
3
glass entrances and storefronts, balanced door entrances, glazed aluminum curtain walls, interior
4
structural glass walls, aluminum windows, bullet resistant aluminum windows, security
5
windows, metal framed skylights, glass glazing and door hardware.
6
As the lowest bidder for the Project, C&S was chosen as the general contractor on
7
October 7, 2010 and entered into a written contract for construction of the Project (“the Prime
8
Contract”).
9
On July 22, 2010, C&S and Incline entered into an agreement for performance of
10
the work on the Project. The agreement included the Subcontract Agreement and the Scope of
11
Work, and incorporated the Prime Contract, including General Conditions and Special
12
Conditions (“the Subcontract Agreement”). The contract price for the Subcontract Agreement
13
was &723,328.00. Incline was to provide all labor and materials within the listed scope of work.
14
Prior to entering into the Subcontract Agreement, C&S provided a bid package to
15
Incline which contained, among other things, a construction schedule, project drawings and
16
specifications and conditions of the contract (including, but not limited, to General, Special and
17
other Conditions), all of which were deemed part of the Subcontract Agreement.
18
19
During the course of construction of the Project, C&S issued written change
orders to Incline, which adjusted the contract balance to a total of $712,784.
20
Incline allegedly breached the Subcontract Agreement by failing to timely pay its
21
second tier subcontractors and suppliers, and failing to complete all of the work. Plaintiff alleges
22
Incline abandoned the project.
23
C&S notified Incline of its failure to perform and abandonment, and demanded
24
completion of the work. Incline failed and refused to perform. As a result, C&S itself is forced
25
to pay to complete Incline’s work and to pay suppliers and second-tier subcontractors.
26
/////
2
1
Under the express terms of the Subcontract Agreement, Incline is required to
2
indemnify and hold harmless C&S from any and all forms of liabilities, costs, damages, and
3
expenses arising out of Incline’s performance or failure to perform under the Subcontract
4
Agreement, including losses or claims related to mechanics liens.
5
RELEVANT PROCEDURAL BACKGROUND
6
Plaintiff initiated this diversity action on April 12, 2012 raising claims for breach
7
of contract, common counts and contractual indemnity. Plaintiff seeks actual, compensatory,
8
consequential and incidental damages not less than $250,000.00. Plaintiff also seeks attorney’s
9
fees.
10
Defendant was served with personal service with a copy of the summons and
11
complaint on April 26, 2012. See Doc. No. 7. The copies were served on Jones Vargas and
12
Danielle Durkee, authorized agents for the corporate defendant. Id.
On May 24, 2012, plaintiff moved for entry of default. Doc. No. 6.On May 25,
13
14
2012, the Clerk of the Court entered default as to Incline. Doc. No. 12.
15
On May 30, 2012, plaintiff filed the instant application for default judgment.
16
Doc. No. 13. Plaintiff seeks judgment in the amount of $249,902.36. This request includes
17
attorney’s fees and costs. Plaintiff avers that the only means by which to serve defendant was
18
through personal service and mail service at the home address of defendant’s president, Pat
19
Geary. Markham Decl., ¶ 9. Plaintiff asserts that, per the Nevada Secretary of State website,
20
Incline does not have a registered agent for service and the status of the company is in default.
21
Id.
22
23
24
25
26
Incline has not filed an opposition to plaintiff’s motion and has not otherwise
appeared in this action.
DISCUSSION
Pursuant to Federal Rule of Civil Procedure 55, default may be entered against a
party against whom a judgment for affirmative relief is sought who fails to plead or otherwise
3
1
defend against the action. See Fed. R. Civ. P. 55(a). However, “[a] defendant’s default does not
2
automatically entitle the plaintiff to a court-ordered judgment.” PepsiCo, Inc. v. Cal. Sec. Cans,
3
238 F. Supp. 2d 1172, 1174 (C.D. Cal. 2002) (citing Draper v. Coombs, 792 F.2d 915, 924-25
4
(9th Cir. 1986)); see Fed. R. Civ. P. 55(b) (governing the entry of default judgments). Instead,
5
the decision to grant or deny an application for default judgment lies within the district court’s
6
sound discretion. Aldabe v. Aldabe, 616 F.2d 1089, 1092 (9th Cir. 1980). In making this
7
determination, the court may consider the following factors:
8
9
10
(1) the possibility of prejudice to the plaintiff; (2) the merits of plaintiff’s
substantive claim; (3) the sufficiency of the complaint; (4) the sum of money at
stake in the action; (5) the possibility of a dispute concerning material facts; (6)
whether the default was due to excusable neglect; and (7) the strong policy
underlying the Federal Rules of Civil Procedure favoring decisions on the merits.
11
Eitel v. McCool, 782 F.2d 1470, 1471-72 (9th Cir. 1986). Default judgments are ordinarily
12
disfavored. Id. at 1472.
13
As a general rule, once default is entered, well-pleaded factual allegations in the
14
operative complaint are taken as true, except for those allegations relating to damages.
15
TeleVideo Sys., Inc. v. Heidenthal, 826 F.2d 915, 917-18 (9th Cir. 1987) (per curiam) (citing
16
Geddes v. United Fin. Group, 559 F.2d 557, 560 (9th Cir. 1977) (per curiam)); see also Fair
17
Housing of Marin v. Combs, 285 F.3d 899, 906 (9th Cir. 2002). Although well-pleaded
18
allegations in the complaint are admitted by a defendant’s failure to respond, “necessary facts
19
not contained in the pleadings, and claims which are legally insufficient, are not established by
20
default.” Cripps v. Life Ins. Co. of N. Am., 980 F.2d 1261, 1267 (9th Cir. 1992) (citing Danning
21
v. Lavine, 572 F.2d 1386, 1388 (9th Cir. 1978)); accord DIRECTV, Inc. v. Huynh, 503 F.3d 847,
22
854 (9th Cir. 2007) (“[A] defendant is not held to admit facts that are not well-pleaded or to
23
admit conclusions of law” (citation and quotation marks omitted).); Abney v. Alameida, 334 F.
24
Supp. 2d 1221, 1235 (S.D. Cal. 2004) (“[A] default judgment may not be entered on a legally
25
insufficient claim.”). A party’s default conclusively establishes that party’s liability, although it
26
does not establish the amount of damages. Geddes, 559 F.2d at 560; cf. Adriana Int’l Corp. v.
4
1
Thoeren, 913 F.2d 1406, 1414 (9th Cir. 1990) (stating in the context of a default entered
2
pursuant to Federal Rule of Civil Procedure 37 that the default conclusively established the
3
liability of the defaulting party).
4
1.
Possibility of Prejudice to Plaintiff
5
The first Eitel factor considers whether the plaintiff would suffer prejudice if
6
default judgment is not entered, and such potential prejudice to the plaintiff militates in favor of
7
granting a default judgment. See PepsiCo, Inc., 238 F. Supp. 2d at 1177. Here, plaintiff would
8
potentially face prejudice if the court did not enter a default judgment. Absent entry of a default
9
judgment, plaintiff would be without another recourse for recovery. Accordingly, the first Eitel
10
factor favors the entry of default judgment.
11
2-3.
Merits of Plaintiffs’ Substantive Claims & “Sufficiency of the Complaint”
12
The undersigned considers the merits of plaintiffs’ substantive claims and the
13
sufficiency of the complaint together below because of the relatedness of the two inquiries. The
14
undersigned must consider whether the allegations in the complaint are sufficient to state a claim
15
that supports the relief sought. See Danning v. Lavine, 572 F.2d 1386, 1388 (9th Cir. 1978);
16
PepsiCo, Inc., 238 F. Supp. 2d at 1175.
17
18
a.
Breach of Contract
A claim of breach of contract is comprised of (1) the existence of a contract, (2)
19
performance or excuse for nonperformance by the plaintiff, (3) breach by the defendants, and (4)
20
resulting damages to the plaintiff. Alcalde v. NAC Real Estate Invs. & Assignments, Inc., 316 F.
21
App'x 661, 662 (9th Cir. 2009), citing First Comm. Mort. Co. v. Reece, 89 Cal. App. 4th 731
22
(Cal. Ct. App. 2001); Haberbush v. Clark Oil Trading Co., 33 F. App’x 896, 898 (9th Cir. 2002).
23
Here, plaintiff entered into an agreement with defendant. Defendant breached the contract by
24
failing to perform. The resulting damage for defendant’s non-performance is $236,209.36. Thus,
25
taking the factual allegations in plaintiff’s complaint as true, plaintiff has adequately stated a
26
claim for breach of contract.
5
1
b.
2
Common Count
The only essential allegations of a common count are 1) the statement of
3
indebtedness in a certain sum, 2) the consideration, i.e., goods sold, work done, etc., and 3)
4
nonpayment. Farmers Ins. Exchange v. Zerin, 53 Cal. App. 4th 445, 460 (Cal. Ct. App. 1997).
5
The court concludes that the complaint was legally sufficient for this claim.
6
c.
Contractual Indemnity
“Where ... parties have expressly contracted with respect to the duty to
7
8
indemnify, the extent of that duty must be determined from the contract and not by
9
reliance on the independent doctrine of equitable indemnity.” Rossmoor Sanitation, Inc.
10
v. Pylon, Inc., 13 Cal.3d 622, 628 (Cal. 1975). Here, the Subcontract Agreement provided an
11
indemnification agreement that obliges Incline to fully indemnify and hold harmless C&S. See
12
Compl, Ex. 1 (Subcontract Agreement, p.3 ¶ 10).
Thus, this Eitel factor favors entry of default judgment.
13
14
4.
Sum of Money at Stake
15
Under the fourth factor cited in Eitel, “the court must consider the amount of
16
money at stake in relation to the seriousness of Defendant’s conduct.” PepsiCo, Inc., 238 F.
17
Supp. 2d at 1177. Plaintiff seeks judgment in the amount of $249,902.36. Under the
18
circumstances of this case, the undersigned concludes that this factor favors the entry of default
19
judgment.
20
4.
Possibility of a Dispute Concerning Material Facts
21
The facts of this case are relatively straightforward, and plaintiff has provided the
22
court with well-pleaded allegations supporting its statutory claims and affidavits in support of its
23
allegations. Here, the court may assume the truth of well-pleaded facts in the complaint (except
24
as to damages) following the clerk’s entry of default and, thus, there is no likelihood that any
25
26
6
1
genuine issue of material fact exists.1 See, e.g., Elektra Entm’t Group Inc. v. Crawford, 226
2
F.R.D. 388, 393 (C.D. Cal. 2005) (“Because all allegations in a well-pleaded complaint are taken
3
as true after the court clerk enters default judgment, there is no likelihood that any genuine issue
4
of material fact exists.”); accord Philip Morris USA, Inc., 219 F.R.D. at 500; PepsiCo, Inc., 238
5
F. Supp. 2d at 1177.
6
5.
Factor Six: Whether the Default Was Due to Excusable Neglect
7
On review of the record before the court, the undersigned finds that the default
8
was not the result of excusable neglect. See PepsiCo, Inc., 238 F. Supp. 2d at 1177. Plaintiff
9
served the defendant with the summons and complaint. Moreover, plaintiff served defendant by
10
mail and personal service with notice of its application for default judgment. Despite ample
11
notice of this lawsuit and plaintiff’s intention to seek a default judgment, defendant has not
12
appeared in this action to date. Thus, the record suggests that defendant has chosen not to
13
defend this action, and not that the default resulted from any excusable neglect. Accordingly,
14
this Eitel factor favors the entry of a default judgment.
15
6.
Policy Favoring Decisions on the Merits
“Cases should be decided upon their merits whenever reasonably possible.” Eitel,
16
17
782 F.2d at 1472. Although this factor, standing alone, is not dispositive, see PepsiCo, Inc., 238
18
F. Supp. 2d at 1177, it advises against granting plaintiffs’ motion in combination with the other
19
factors previously discussed.
In sum, the court finds that consideration of the Eitel factors favors granting the
20
21
motion for default judgment.
22
Accordingly, IT IS HEREBY RECOMMENDED that:
23
1. Plaintiff’s motion for default judgment be granted; and
24
25
26
1
Defendant’s failure to file an answer in this case or a response to the instant default
application further supports the conclusion that the possibility of a dispute as to material facts is
minimal.
7
1
2
2. Judgment be entered against Incline in the amount of $249,602.36, which
includes attorney’s fees.2
3
These findings and recommendations are submitted to the United States District
4
Judge assigned to the case, pursuant to the provisions of 28 U.S.C. § 636(b)(1). Within fourteen
5
days after being served with these findings and recommendations, any party may file written
6
objections with the court and serve a copy on all parties. Such a document should be captioned
7
“Objections to Magistrate Judge's Findings and Recommendations.” Failure to file objections
8
within the specified time may waive the right to appeal the District Court’s order. Turner v.
9
Duncan, 158 F.3d 449, 455 (9th Cir. 1998); Martinez v. Ylst, 951 F.2d 1153 (9th Cir. 1991).
10
DATED: July 10, 2012.
11
12
13
14
15
/014;clar0972.mdj
16
17
18
19
20
21
22
23
24
2
25
26
Plaintiff’s request for attorney’s fees contemplates time spent appearing at a hearing on
the instant motion. Because the hearing on this motion was vacated, see Doc. No. 30, the court
recommends deducting one billable hour from plaintiff’s request for attorney’s fees, for a total
$300 deduction. See Markham Decl., ¶¶ 7-8.
8