MEMORANDUM AND ORDER signed by Chief Judge Morrison C. England, Jr. on 1/15/2015 ORDERING 19 that Defendant's Motion for Summary Judgment is GRANTED; the Clerk of the Court is directed to enter judgment in favor of defendant and close the case. CASE CLOSED (Reader, L)

Download PDF
1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 EASTERN DISTRICT OF CALIFORNIA 10 11 12 LABORERS’ INTERNATIONAL UNION OF NORTH AMERICA PACIFIC SOUTHWEST REGION, 13 Plaintiff, 14 15 No. 2:13-cv-02204-MCE-DAD MEMORANDUM AND ORDER v. U.S. DEPARTMENT OF ENERGY, 16 Defendant. 17 18 Before the Court is Defendant U.S. Department of Energy’s (“DOE”) Motion for 19 Summary Judgment. (ECF No. 19)1 For the following reasons, Defendant’s Motion is 20 GRANTED. 2 21 /// 22 /// 23 /// 24 /// 25 26 27 28 1 Plaintiff’s “rebuttal” to Defendant’s Reply, ECF No. 30, was not considered by the Court as rebuttals to replies are not permitted. See E.D. Cal. Local R. 230). 2 Because oral argument would not be of material assistance, the Court ordered this matter submitted on the briefs. E.D. Cal. Local R. 230(g); ECF No. 33. 1 1 2 BACKGROUND 3 4 This dispute stems from a Freedom of Information Act (“FOIA”) request by Plaintiff 5 Laborers’ International Union of North America Pacific Southwest Region (“LIUNA- 6 PSW”) made to DOE on December 7, 2012. LIUNA-PSW sought payroll information 7 from a large-scale solar utility project, Desert Sunlight, to assess compliance with the 8 Davis-Bacon Act. The Davis-Bacon Act is a federal law that requires contractors and 9 subcontractors on federally funded projects to pay their laborers no less than the 10 prevailing local wage. Because the project was funded in part with a DOE loan 11 guarantee, Sunlight’s owners were required to file certified payroll records with DOE. 12 On March 19, 2013, DOE provided LIUNA-PSW with the requested payroll 13 records. However, LIUNA-PSW alleges that DOE improperly redacted the hours worked 14 per worker per day, the total hours each worker worked per week, the deductions taken, 15 the fringe benefits paid, and the total paid to each worker. The only unredacted 16 information provided was each employee’s work classification and the rate of pay. See 17 ECF No. 19-4. LIUNA-PSW states that it needs the hours worked per day and per week, 18 as well as the total amount paid, to determine if employees who worked more than eight 19 hours per day or 40 hours per week were paid appropriate overtime wages. The DOE 20 justified the redactions under two FOIA exemptions: (1) Exemption 4, 5 U.S.C. 21 § 552(b)(4), which protects “trade secrets and commercial or financial information 22 obtained from a person and privileged or confidential” from disclosure to the public; and 23 (2) Exemption 6, 5 U.S.C. § 552(b)(6), which protects information about individuals in 24 “personnel and medical files and similar files” when the disclosure of such information 25 “would constitute a clearly unwarranted invasion of personal privacy.” 26 On April 23, 2013, LIUNA-PSW challenged DOE’s redactions by filing an appeal 27 with the DOE’s Office of Hearing and Appeals. The Office of Hearings and Appeals 28 issued a decision and order sustaining the withholding of information under Exemption 2 1 4.3 In response to the decision by the Office of Hearings and Appeals, LIUNA-PSW filed 2 this suit on October 22, 2013. The DOE then moved for summary judgment. ECF 3 No. 19. 4 STANDARD 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Most cases brought pursuant to FOIA are resolved through summary judgment. Cooper Cameron Corp. v. U.S. Dep't of Labor, 280 F.3d 539, 543 (5th Cir. 2002). Summary judgment is appropriate when “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); see also Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). “Unlike the typical summary judgment analysis, in a FOIA case, we do not ask whether there is a genuine issue of material fact, because the facts are rarely in dispute.” Miner v. CIA, 88 F.3d 796, 800 (9th Cir. 1996). Review of an agency’s response to a FOIA request is conducted de novo. 5 U.S.C. § 552(a)(3)(A). Under FOIA, federal agencies are required to disclose documents upon request, unless those documents are exempted from disclosure by statute. Willamette Indus., Inc. v. United States, 689 F.2d 865, 867 (9th Cir. 1982). “The statute contains nine enumerated exemptions allowing the government to withhold documents or portions of documents.” Lahr v. Nat’l Transp. Safety Bd., 569 F.3d 964, 973 (9th Cir. 2009). The agency responding to a request has the burden of sustaining the adequacy of its response by demonstrating that it did not improperly withhold records subject to disclosure under FOIA. 5 U.S.C. § 552(a)(3)(A); U.S. Dep’t of Justice v. Tax Analysts, 492 U.S. 136, 142 n.3 (1989). The agency must provide a relatively detailed analysis justifying any withheld information, Vaughn v. Rosen, 484 F.2d 820, 828 (D.C. Cir. 1973), and the justifications cannot be controverted by contrary evidence in the record or 3 28 While the DOE’s use of Exemption 6 was remanded, that is not of consequence here because all issues regarding Exemption 6 were resolved with stipulations. ECF No. 23 at 3 n.2. 3 1 evidence of bad faith, Hunt v. CIA, 981 F.2d 1116, 1119 (9th Cir. 1992). 2 3 ANALYSIS 4 5 As all issues regarding Exemption 6 were resolved with stipulations (ECF No. 23 6 at 3 n.2), the Court’s analysis is limited to DOE’s use of Exemption 4 to withhold 7 information from LIUNA-PSW. In order to use Exemption 4, the agency must show that 8 disclosure is likely “to cause substantial harm to the competitive position of the person 9 from whom the information was obtained.” National Parks & Conservation Ass'n v. 10 Morton, 498 F.2d 765, 770 (D.C. Cir.1974). The agency does not need to show actual 11 competitive harm, just evidence revealing (1) actual competition and (2) a likelihood of 12 substantial competitive injury. C.G. Micro Corp. v. Def. Logistics Agency, 33 F.3d 1109, 13 1113 (9th Cir. 1994). The Court must balance the strong public interest in favor of 14 disclosure against the right of private businesses to protect sensitive information. Id. at 15 1115. 16 A common sense approach is applied when determining whether there is actual 17 competition in the relevant market. Watkins v. U.S. Bureau of Customs and Border 18 Protection, 643 F.3d 1189, 1196 (9th Cir. 2011). It is common sense that the market for 19 federal contracts is competitive. DOE has provided evidence of the razor-thin margins 20 that separate successful bidders from their competitors in the bidding process (see Diller 21 Decl., ECF No. 19-6, ¶ 8), and LIUNA-PSW does not dispute this point. Accordingly, the 22 Court must focus on whether DOE has shown that releasing the requested information 23 is likely to cause substantial competitive injury. 24 Substantial competitive harm occurs when disclosure would allow competitors to 25 estimate and undercut a contractor’s bid. G.C. Micro Corp., 33 F.3d at 1115 (citing Gulf 26 & Western Indus., Inc. v. United States, 615 F.2d 527, 530 (D.C. Cir. 1979)). The 27 agency’s burden can be satisfied by producing “government affidavits so long as the 28 affiants are knowledgeable about the information sought and the affidavits are detailed 4 1 enough to allow the court to make an independent assessment of the government’s 2 claim.” Lion Raisins v. U.S. Dep’t of Agric., 354 F.3d 1072, 1079 (9th Cir. 2004). Courts 3 accord the agency’s declarations “substantial weight.” Hunt, 981 F.2d at 119. 4 DOE contends that release of the information would cause substantial competitive 5 harm to First Solar, the engineering, procurement and construction contractor selected 6 for the Desert Sunlight Project. The potential competitive harm is detailed in two 7 declarations from First Solar employees. See ECF Nos. 19-6 (Diller), 19-7 (Potsma). 8 According to those declarations, labor costs are what determine a winning bid because 9 other costs, such as materials, are usually standardized across all bidders. The concern 10 is that “[l]abor cost can be derived by multiplying the wage rates for each craft by the 11 number of hours each craft has worked on the project. If one bidder (“Bidder B”) learns 12 the number of hours each craft has worked on the project for another bidder (“Bidder 13 A”), then Bidder B can use that information to determine Bidder A’s labor cost. . . 14 . Bidder B can then use that information to underbid Bidder A when competing for solar 15 projects.” Diller Decl., ECF No. 19-6, ¶ 7. In addition, DOE argues that First Solar’s 16 labor efficiency, the allocation of work between crafts, could be determined by the 17 redacted information and knowledge of First Solar’s labor efficiency could “deprive First 18 Solar of its competitive advantage permanently.” ECF No. 19-2 at 6. 19 LIUNA-PSW counters, essentially, that each solar project varies and that the 20 payroll information from one project would not provide competitors with enough 21 information to undercut First Solar in future bidding processes. Hulett Decl., ECF 22 No. 23-5, ¶¶ 9-14. It is true that substantial competitive harm is less likely to be found 23 when the information redacted provides insight into only one of several variables a 24 competitor needs to gain an advantage. See G.C. Micro Corp., 33 F.3d at 1112-15. 25 However, LIUNA-PSW has not provided sufficient evidence to convince the Court that 26 such is the case here. LIUNA-PSW’s declarations are from individuals with no 27 experience with the bidding process for large-scale solar utility projects.4 Those 28 4 LIUNA-PSW offers declarations from two individuals to dispute DOE’s claim of likely substantial 5 1 declarants cannot say, based on their personal knowledge, that labor costs and labor 2 efficiency are not the distinguishing factors in the bidding process for large-scale solar 3 utility projects. 4 DOE has the burden to establish that Exemption 4 applies, and it has met that 5 burden. LIUNA-PSW’s declarations from individuals who are unfamiliar with the bidding 6 process on large scale solar utility projects are not enough to survive summary 7 judgment. 8 9 CONCLUSION 10 11 For the reasons set forth above, Defendant’s Motion for Summary Judgment 12 (ECF No. 19) is GRANTED. The Clerk of the Court is directed to enter judgment in favor 13 of Defendant and to close the case. 14 IT IS SO ORDERED. 15 Dated: January 15, 2015 16 17 18 19 20 21 22 23 24 25 26 27 28 competitive harm. Michael Hulett works in distributed generation, or rooftop solar, not on large scale solarutility projects. ECF No. 23-5 at ¶ 6. Izaak Velez is a former superintendent in an unnamed industry. ECF No. 23-4 at ¶ 2. 6

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?