ORDER signed by Magistrate Judge Craig M. Kellison on 01/26/18 GRANTING 32 Ex Parte Application for Extension of Time to File Markman Brief; the deadlines are as follows: Defendant's opening Markman brief is due 02/23/18, plaintiff' Op position is due 03/09/18, with Defendant's Reply Brief due 03/16/18. The 02/22/18 claim construction hearing is VACATED. The parties are ordered to meet and confer and propose a new date for the claim construction hearing to be held on or after 04/01/18. (Benson, A.)
1
2
3
4
5
6
7
8
Evan S. Nadel (SBN 213230)
enadel@mintz.com
Philip C. Ducker (SBN 262644)
pcducker@mintz.com
MINTZ LEVIN COHN FERRIS GLOVSKY
AND POPEO P.C.
44 Montgomery Street, 36th Floor
San Francisco, CA 94104
Telephone: 415-432-6000
Facsimile: 415-432-6001
Attorney for Defendant and Counterclaim Plaintiff,
KLEAN KANTEEN, INC.
9
UNITED STATES DISTRICT COURT
10
EASTERN DISTRICT OF CALIFORNIA
11
12
13
RICHARD STAYCHOCK, AND
KATHLEEN MACKAY STAYCHOCK,
Plaintiffs,
14
15
16
v.
KLEAN KANTEEN, INC., a corporation,
17
Defendant.
18
Case No. 2:17-cv-01012-KJM-CMK
ORDER GRANTING DEFENDANT
AND COUNTERCLAIM
PLAINTIFF KLEAN KANTEEN,
INC.’S INITIAL EX PARTE
REQUEST FOR EXTENSION OF
TIME TO FILE MARKMAN BRIEF
Judge: Hon. Craig M. Kellison
19
KLEAN KANTEEN, INC., a corporation,
20
Counterclaim Plaintiff,
21
22
23
24
v.
RICHARD STAYCHOCK, AND
KATHLEEN MACKAY STAYCHOCK,
Counterclaim Defendants.
25
26
27
28
[PROPOSED] ORDER GRANTING EX PARTE MOTION FOR CONTINUANCE OF MARKMAN SCHEDULE
CASE NO. 2:17-cv-01012-KJM-CMK
1
Having considered Defendant and Counterclaim Plaintiff Klean Kanteen, Inc.’s Initial Ex
2
Parte Request for Extension of Time to File Markman Brief (ECF No. 32), the Initial Request is
3
hereby GRANTED: The Court hereby advances and continues the deadlines as follows:
4
1. Defendant’s opening Markman brief shall be filed no later than February 23, 2018.
5
2. Plaintiff’s Opposition Brief shall be filed no later than March 9, 2018.
6
3. Defendant’s Reply Brief shall be file no later than March 16, 2018.
7
4. The claim construction hearing currently scheduled for February 22, 2018 at 10:00 AM
8
is VACATED. The parties are ordered to meet and confer and propose a new date for
9
the claim construction hearing to be held on or after April 1, 2018.
10
11
IT IS SO ORDERED.
12
13
Dated: January 26, 2018
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-1[PROPOSED] ORDER GRANTING EX PARTE MOTION FOR CONTINUANCE OF MARKMAN SCHEDULE
CASE NO. 2:17-cv-01012-KJM-CMK
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?