Urata & Sons Concrete, Inc. v. Gilbane Federal, et al.,

Filing 22

MEMORANDUM and ORDER signed by District Judge Morrison C. England, Jr on 11/5/19 GRANTING 15 Motion for Order Lifting Stay, Confirming Final Arbitration, and Entry of Judgment and DENYING 17 Counter-Motion to Vacate Arbitration Award. CASE CLOSED. (Kaminski, H)

Download PDF
1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 EASTERN DISTRICT OF CALIFORNIA 10 11 12 UNITED STATES OF AMERICA for the Use and Benefit of URATA & SONS CONCRETE, INC., 13 Use-Plaintiff / Plaintiff, 14 15 16 17 No. 2:17-cv-02635-MCE-AC MEMORANDUM AND ORDER v. GILBANE FEDERAL, a California corporation; and TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, a Connecticut corporation, 18 Defendants. 19 Through this action, the United States of America for the Use and Benefit of Urata 20 21 & Sons Concrete, Inc., and Urata & Sons Concrete Inc. (“Plaintiff”) seek confirmation 22 and enforcement of an arbitration award against Defendants Gilbane Federal (“Gilbane”) 23 and Travelers Casualty and Surety Company of America (collectively, “Defendants”). 24 Presently before the Court is Plaintiff’s Motion for Order Lifting Stay, Confirming Final 25 Arbitration, and Entry of Judgment. ECF No. 15. Plaintiff also moves for attorney’s fees 26 and costs. Concurrently before the Court is Defendants’ Counter-Motion to Vacate 27 /// 28 /// 1 1 Arbitration Award. ECF No. 17. For the reasons set forth below, Plaintiff’s Motion is 2 GRANTED and Defendants’ Counter-Motion is DENIED.1 3 4 BACKGROUND2 5 6 In 2014, Gilbane entered into a written design-build construction contract with the 7 United States Army Corps of Engineers (“USACE”) for the construction of a general 8 purpose warehouse at the Defense Distribution Depot in Tracy, California (the “Project”). 9 In May 2015, Plaintiff and Gilbane entered into a written subcontract whereby Plaintiff 10 agreed to provide and install specific concrete work according to Gilbane’s plans and 11 specifications (the “Subcontract”). The Subcontract further provided that Plaintiff “shall 12 perform all Work required to complete the Project in strict accordance with the 13 [Statement of Work documents]” and that Plaintiff “agrees to be fully bound by all 14 [Statement of Work] Documents to be later provided.” Ex. 1, ECF No. 1, at 15. The 15 original Project specifications did not require the use of air entrained concrete. After the 16 Subcontract was executed, Gilbane provided Plaintiff with revised specifications, which 17 were changed to require air entrained concrete. At the same time, a note was included 18 stating that “[e]ntrained air should not be used for concrete to be given a smooth, dense, 19 hard-troweled finish because blistering and delamination may occur.” In December 20 2015, Gilbane provided Plaintiff with its Issued for Construction (“IFC”) specifications, 21 which required Plaintiff to install the warehouse slab on grade with a “smooth, dense 22 hard-trowel finish, along with the placement of air entrained concrete,” thus creating a 23 design conflict. See Arbitration Award, ECF No. 15-2, at 20. 24 /// 25 /// 26 27 28 1 Having determined that oral argument would not be of material assistance, the Court ordered this matter submitted on the briefs in accordance with E.D. Local Rule 230(g). 2 The following statement of facts is taken, sometimes verbatim, from the Complaint. ECF No. 1. 2 1 In March 2016, Plaintiff submitted air entrained concrete mix designs to Gilbane, 2 who approved those designs for use in areas with a hard trowel finish such as the 3 warehouse slab on grade. Plaintiff notified Gilbane of additional costs associated with 4 the changed concrete specifications, and alerted Gilbane to the design conflict between 5 the requirements for air entrained concrete and the hard trowel finish, which Gilbane 6 acknowledged. Gilbane communicated with USACE about removing air entrainment 7 from the concrete mix design. See Arbitration Award, ECF No. 15-2, at 9. 8 In August 2016, Plaintiff and Gilbane executed Change Order No. 1 to the 9 Subcontract, which included the increased cost for air entrained concrete in the areas 10 that did not require a hard trowel finish. Based on their prior discussions and written 11 memorialization, Plaintiff and Gilbane excluded from Change Order No. 1 the cost for the 12 air entrained concrete in the warehouse slab on grade, reserving the issue for future 13 adjustment if the specification requirement was not changed by USACE. 14 Plaintiff was scheduled to perform its concrete work from December 2016 to 15 February 2017. Having not received any notice or revisions to the specifications that 16 deleted the air entrainment requirement from the warehouse slab on grade, Plaintiff 17 began performing its work in accordance with the specifications, including those 18 requiring the use of air entrained concrete with a hard trowel finish for the warehouse 19 slab on grade. Gilbane was responsible for quality control on the Project and was fully 20 aware that Plaintiff was placing the warehouse slab on grade in accordance with the 21 specifications and the approved mix design and participated in that placement by, 22 among other things, testing the concrete at the time of delivery for compliance with the 23 approved mix design and signing off on the placement of the concrete for the warehouse 24 slab on grade. After completion, Plaintiff billed Gilbane for this concrete installation, and 25 Gilbane paid Plaintiff for its work, excluding retention. 26 It was not until after work under the Subcontract was complete that Plaintiff 27 learned USACE actually approved a design change deleting the air entrainment from the 28 warehouse slab on grade prior to the execution of Change Order No. 1; Gilbane never 3 1 conveyed or provided any such approval or design change to Plaintiff in any form. 2 Further, USACE alerted Gilbane to the occurrence of delamination of the warehouse 3 slab on grade due to the air entrainment. Gilbane issued cure notices to Plaintiff, stating 4 the delamination resulted from Plaintiff’s unauthorized use of air entrained concrete for 5 the warehouse slab on grade and Plaintiff must remedy its non-compliance by replacing 6 the entire warehouse slab on grade. Plaintiff denied responsibility for the issues, and 7 Gilbane refused to pay Plaintiff amounts due for work completed. 8 9 On December 18, 2017, Plaintiff filed this action against Defendants for, among other things, breach of contract and Miller Act violations. ECF No. 1. Subsequently, this 10 Court entered an order staying the action pending arbitration, pursuant to the parties’ 11 stipulation. ECF No. 8. Kenneth C. Gibbs (the “Arbitrator”) served as the arbitrator for 12 this dispute, and arbitration took place on November 12-14, 2018. ECF No. 15-1. On 13 March 21, 2019, the Arbitrator issued the Final Award (the “Award”), which concluded 14 that Plaintiff’s installation of the air entrained concrete constituted performance, or, 15 alternatively, that Plaintiff was excused from performing under the Subcontract. See 16 Arbitration Award, ECF No. 15-2, at 19-24. Plaintiff was awarded the sum of 17 $2,669,018.13, which consisted of: (1) the principal amount of $2,097,055.00; 18 (2) interest of $311,906.53 at the per annum rate of 10%, equivalent to a daily rate of 19 $574.54; (3) costs of $94,959.60; and (4) attorneys’ fees pursuant to the Subcontract in 20 the amount of $165,097.00. Id. at 33. 21 22 STANDARD 23 24 It is well established that a federal court’s review of an arbitrator’s decision is 25 “extremely narrow.” Stead Motors v. Auto. Machinists Lodge, 886 F.2d 1200, 1208 n.2 26 (9th Cir. 1990) (emphasis in original), cert. denied, 495 U.S. 946. Courts may vacate an 27 arbitration decision if the “arbitrators exceeded their powers.” 9 U.S.C. § 10(a)(4) 28 (2006). “Arbitrators exceed their powers . . . not when they merely interpret or apply the 4 1 governing law incorrectly, but when the award is completely irrational, or exhibits a 2 manifest disregard of the law.” Schoenduve Corp. v. Lucent Techs., Inc., 442 F.3d 727 3 (9th Cir. 2006) (alteration in original) (quoting Kyocera Corp. v. Prudential-Bache Trade 4 Servs., Inc., 341 F.3d 987, 997 (9th Cir. 2003)). 5 Federal courts are not empowered to second guess an arbitrator’s findings and 6 will enforce an arbitration award if it represents a “plausible interpretation of the contract 7 in the context of the parties’ conduct.” United States Life Ins. Co. v. Superior Nat’l Ins. 8 Co., 591 F.3d 1167, 1177 (9th Cir. 2010) (citing Pac. Motor Trucking Co. v. Auto. 9 Machinists Union, 702 F.2d 176, 177 (9th Cir. 1983)). Accordingly, the court must defer 10 to the arbitrator’s decision “as long as the arbitrator . . . even arguably construed or 11 applied the contract.” Id. (quoting United Paperworkers Int’l Union, AFL-CIO v. Misco, 12 Inc., 484 U.S. 29, 38 (1987)). Conversely, an award that directly conflicts with a contract 13 cannot be a “plausible interpretation.” Pac. Motor Trucking Co., 702 F.2d at 177. 14 Thus, as long as the arbitrator’s decision “draws its essence from the contract, 15 meaning that on its face it is a plausible interpretation of the contract, then the courts 16 must enforce it.” Truesdell v. S. Cal. Permanente Med. Grp., 151 F. Supp. 2d 1161, 17 1173 (C.D. Cal. 2001) (internal quotations omitted) (citing Sheet Metal Workers’ Int’l 18 Assoc. Local Union No. 359 v. Madison Indus., Inc. of Ariz., 84 F.3d 1186, 1190 (9th Cir. 19 1996)). This same deference applies to the particular remedy chosen by the arbitrator. 20 See, e.g., Assoc. of W. Pulp & Paper Workers, Local 78 Rexam Graphic, Inc., 221 F.3d 21 1085, 1091 (9th Cir. 2000). 22 /// 23 /// 24 /// 25 /// 26 /// 27 /// 28 /// 5 1 ANALYSIS 2 3 A. 4 The Arbitrator found that Plaintiff’s installation of the air entrained concrete 5 constituted performance under the Subcontract. See Arbitration Award, ECF No. 15-2, 6 at 20-22. Defendants base their Counter-Motion to Vacate on belief that the Award was 7 “completely irrational” in that the Arbitrator disregarded key Subcontract provisions and 8 modifications. See ECF No. 17. Motion to Confirm/Counter-Motion to Vacate The “completely irrational” standard is extremely narrow and is satisfied only 9 10 where the arbitration decision fails to draw its essence from the agreement. Comedy 11 Club, Inc. v. Improv West Assocs., 553 F.3d 1277, 1288 (9th Cir. 2009). An award 12 draws its essence from the agreement if the award is derived from the agreement, 13 viewed in light of the agreement’s language and context, as well as other indications of 14 the parties’ intentions. Bosack v. Soward, 586 F.3d 1096, 1106 (9th Cir. 2009). Here, 15 the Arbitrator reviewed the Subcontract language to find that Plaintiff was required to use 16 air entrained concrete. Specifically, the Arbitrator found that the Subcontract required 17 Plaintiff to perform “in strict accordance” with Gilbane’s Statement of Work documents, 18 including future documents such as the IFC specifications. See Arbitration Award, ECF 19 No. 15-2, at 20. Additionally, the Arbitrator found that Gilbane’s conduct further 20 supported a finding that Plaintiff performed under the Subcontract, such as Gilbane’s 21 rejection of Plaintiff’s initial concrete mix for lack of air entrainment and failure to notify 22 Plaintiff that USACE removed the air entrainment requirement. See id. at 20-21. Defendants contend that the Arbitrator erred in determining Change Order No. 1 23 24 was a pricing agreement instead of a change in scope because Change Order No. 1 25 excluded air from the warehouse slab on grade. Defs.’ Counter-Motion, ECF No. 17, 26 at 9. However, the Arbitrator concluded Change Order No. 1 did not change the scope 27 of the Subcontract because Gilbane was still communicating with USACE about 28 /// 6 1 removing the air entrainment requirement and Gilbane failed to inform Plaintiff that 2 USACE deleted the requirement. Arbitration Award, ECF No. 15-2, at 20-21. 3 Ultimately, Defendants have failed to show that the Arbitrator exceeded his 4 power. There is no evidence in the record that the Award failed to draw its essence from 5 the contract therefore rendering it “completely irrational.” See Bosack, 586 F.3d at 1106 6 (“Under this standard of review, we do not decide the rightness or wrongness of the 7 arbitrator’s contract interpretation, only whether the panel’s decision draws its essence 8 from the contract.”) (internal citations and quotation marks omitted). Therefore, the 9 Court finds that the Award should be confirmed, and hereby GRANTS Plaintiff’s Motion 10 to Confirm and DENIES Defendants’ Counter-Motion to Vacate.3 11 B. 12 Plaintiff seeks to recover the following: (1) additional attorneys’ fees for time 13 associated with filing the instant motion and reply, totaling $16,605, plus $845 for federal 14 court costs; (2) attorneys’ fees and costs for enforcement and collection of judgment; 15 (3) prejudgment interest in an amount of $574.54/day from March 21, 2019, to the entry 16 of judgment; and (4) post-judgment interest at the legal rate until satisfaction of the 17 judgment. ECF No. 15. Such recovery is allowed under the Subcontract, the Award, 18 and by law. See Arbitration Award, ECF No. 15-2, at 33. Accordingly, the Court grants 19 Plaintiff’s request at the amount estimated by Plaintiff. 4 20 /// 21 /// 22 23 24 25 26 27 Plaintiff’s Request for Additional Fees and Interest 3 Defendants also assert that the Arbitrator’s decision manifests an error of law because Plaintiff’s performance is not excused under U.S. v. Spearin, 248 U.S. 132 (1918). Although the Arbitrator found Plaintiff would be excused from non-performance, this was not the basis for his decision because he concluded Plaintiff did in fact perform under the Subcontract. See Arbitrator’s Award, ECF No. 15-2, at 22 (“[T]he Arbitrator finds that [Plaintiff] performed according to the subcontract. However, even if one accepted Gilbane’s argument that [Plaintiff] installed non-conforming concrete, the Arbitrator also finds that [Plaintiff] would be excused from non-performance.”). Defendants’ disagreement with this alternative analysis is thus insufficient to overturn the Award. See Comedy Club, 553 F.3d at 1290 (“[F]or an arbitrator’s award to be in manifest disregard of the law, it must be clear from the record that the arbitrator recognized the applicable law and then ignored it.”). 4 28 The Court notes that Defendants failed to address this request for additional fees and interest in both their Counter-Motion and Reply brief. See ECF Nos. 17, 19. 7 1 CONCLUSION 2 3 For the foregoing reasons, Plaintiff’s Motion for Order Lifting Stay, Confirming 4 Final Arbitration, and Entry of Judgment, ECF No. 15, is GRANTED and Defendants’ 5 Counter-Motion to Vacate Arbitration Award, ECF No. 17, is DENIED. The arbitration 6 award is hereby confirmed and enforced. The Clerk of the Court is hereby ordered to 7 enter judgment for Plaintiff and to close this case. 8 9 IT IS SO ORDERED. Dated: November 5, 2019 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 8

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?