Toll Brothers, Inc v. Lin et al
Filing
287
FINDINGS OF FACT AND CONCLUSIONS OF LAW ON REMAND. Signed by Judge Samuel Conti on 05/23/2012. (sclc2, COURT STAFF) (Filed on 5/23/2012)
1
2
3
4
IN THE UNITED STATES DISTRICT COURT
5
FOR THE NORTHERN DISTRICT OF CALIFORNIA
6
TOLL BROTHERS, INC.,
7
Plaintiff,
8
v.
10
For the Northern District of California
United States District Court
9
11
CHANG SU-O LIN; HONG LIEN LIN;
and HONG YAO LIN,
12
Defendants.
)
)
)
)
)
)
)
)
)
)
)
Case No. 08-987 SC
FINDINGS OF FACT AND
CONCLUSIONS OF LAW ON
REMAND
13
14
I.
INTRODUCTION
This case arises from a 2004 agreement for the purchase and
15
Ex. 26 ("PSA").1
16
sale of land in Dublin, California.
Landowners
17
Chang Su-O Lin, Hong Lien Lin, and Hong Yao Lin (the "Lins") agreed
18
to sell a homebuilder, Toll Brothers, Inc. ("Toll"), three separate
19
parcels of land in three separate closings for a total sale price
20
of $241.5 million.
21
account, to be paid out in increments with each closing.
22
the Lins successfully closed on two parcels of land, Sub-Areas 1
23
and 2.
24
failure to close on Sub-Area 3 and the disposition of the
25
$7,735,000 that remains in the escrow fund.
26
had been scheduled for either (1) June 30, 2007 or (2) three days
Toll deposited $21,735,000 into an escrow
Toll and
The present dispute between Toll and the Lins concerns the
The Sub-Area 3 closing
27
28
1
"Ex." refers to exhibits accepted into evidence at the March 2009
bench trial of this case.
1
after all of the special and general closing conditions had been
2
met, whichever came later.
3
2007, and on December 7, 2007 Toll terminated the PSA.
4
litigation followed, culminating in a nine-day bench trial on the
5
parties' claims and counter-claims for breach of the PSA.
6
short, Toll claims that it is entitled to the remaining escrow fund
7
as a returned deposit, while the Lins say they are entitled to the
8
remaining funds as liquidated damages.
The closing did not occur on June 30,
This
In
Of the many matters raised at trial, the Court is presently
9
United States District Court
For the Northern District of California
10
concerned with only one: a temporary, non-exclusive easement that
11
the Lins granted to non-party Pacific Gas and Electric ("PG&E") in
12
late 2005.
13
ground electrical wires over Sub-Area 3 for the purpose of
14
connecting a water pump station needed by the Dublin San Ramon
15
Services District ("DSRSD"), a project whose completion was
16
required to satisfy conditions in the PSA.2
17
ground electrical facilities were a stopgap measure that would have
18
to be replaced by permanent, below-ground facilities pursuant to
19
local ordinance.
20
the above-ground facilities in September 2006, but PG&E did not
21
quitclaim the easement until June 2008, roughly a year after Sub-
22
Area 3's scheduled closing date of June 30, 2007.
Notably, the above-
The Lins asked PG&E to abandon the easement for
Following trial, the Court issued a memorandum of decision
23
24
The easement allowed PG&E to string temporary, above-
setting forth extensive findings of fact and conclusions of law,
25
26
27
28
2
Specifically, the water pump station was needed to complete the
development of a separate property owned by the Lins, Fairway
Ranch. Fairway Ranch, in turn, had to be completed for the Lins to
obtain certain affordable housing credits from the City of Dublin.
These affordable housing credits were needed before Toll could
begin building on Sub-Area 2. See MOD ¶¶ 53-55.
2
226 ("Judgment").
3
reversed.
4
for rehearing.
5
Judge Callahan's dissent, agreed with this Court's earlier
6
disposition of the issues Toll raised on appeal, but determined
7
that, "[i]n ruling on the Lins['] counterclaim for breach of the
8
covenant of good faith and fair dealing, the district judge did not
9
make any finding that [1] the Lins were acting in good faith in
10
United States District Court
and entered judgment in favor of the Lins.
2
For the Northern District of California
1
ECF Nos. 216 ("MOD"),
attempting to comply with the closing conditions or [2] that the
11
delay was not unreasonable under all of the circumstances."
12
No. 252 ("Aug. 31 Memo.") at 5-6.
13
this Court to make those two findings.
14
law, "good faith and reasonableness are questions of fact."
15
Las Positas Partners v. Bollag, 172 Cal. App. 4th 101, 106 (Cal.
16
Ct. App. 2009).3
Toll appealed, and a Ninth Circuit panel
ECF No. 247.
The Lins successfully petitioned the panel
See ECF No. 250.
On rehearing, the panel, over
ECF
The panel remanded the case to
Id. at 6.
Under California
Peak-
17
18
II.
FINDINGS OF FACT
19
The Court has already made findings of fact covering the
20
period between the Lins' initial grant of the easement to PG&E on
21
December 12, 2005 and PG&E's quitclaim of the easement on June 16,
22
2008.
23
previous findings that in September 2006, the Lins had completed
24
their portion of the work that had to be done before PG&E could
25
build the permanent underground electrical service, abandon the
26
temporary overhead service, and, consequently, terminate the
See MOD ¶¶ 58-63.
Of particular import are the Court's
27
28
3
The parties have submitted briefs on the remanded issues.
Nos. 278 ("Toll Br."), 286 ("Lin Br.").
3
ECF
1
easement.
2
for PG&E to do its part.
3
additional findings:
1.
4
Id. ¶ 62.
The Lins also had submitted an application
Id.
The Court now makes the following
During the last week of October 2006, Rodney Andrade4 met
5
in person with PG&E representative Brian Bates at least twice to
6
review the project of removing the temporary overhead electrical
7
service and installing permanent underground service.
2.
8
9
Ex. 522.5
From September 6, 2006 through February 2, 2007, Andrade
and PG&E representatives had at least nine telephone contacts
United States District Court
For the Northern District of California
10
concerning the project.
11
shifted between PG&E representatives Bates and Brian McCoy several
12
times.
13
in November 2006.
3.
14
During this period, the project was
Bates replaced McCoy in October 2006.
McCoy replaced Bates
Bates replaced McCoy in December 2006.
Id.
On February 15, 2007, Andrade updated James Tong6
15
regarding a conversation with Bates.
Bates told Andrade that PG&E
16
had done no work to process the Lins' September 2006 application,
17
despite McCoy having said more than once in the previous months
18
that "all was well."
19
requested a processing schedule from him.
20
Ex. 95.
Following Bates's admission, Andrade
RT at 952:18-953:22(JT);
21
22
23
24
25
26
27
28
4
For all purposes relevant here, Andrade was the Lins' primary
civil engineer. See MOD ¶ 7; RT at 535:22-25 (Testimony of Andrade
(hereinafter "RTA")), 536:22-537:22(RTA).
5
This exhibit, relied on by Toll in its remand brief, is titled
"Summary of Lin Efforts." It sets forth a chronological list. The
Court finds that, due to typographical errors, the dates listed as
"10/26/07"and "10/31/07" actually refer to October 26, 2006 and
October 31, 2006, respectively.
6
Tong was the Lins' authorized representative for the project.
See MOD ¶ 5; Transcript of Record (hereinafter "RT") at 910:9-18
(Testimony of Tong (hereinafter "JT")).
4
4.
1
On March 23, 2007, Martin Inderbitzen7 sent Toll a letter
2
outlining "closing issues" which mentioned the temporary electrical
3
facility but did not mention the easement or the status of the
4
Lins' application to PG&E.
5
minor issue that fell within the infrastructure build-out to which
6
Toll had already consented.
7
were engaged in discussion of Toll's reconveyance to the Lins of a
8
school site located in Sub-Area 2, which was a condition of closing
9
Sub-Area 3.
United States District Court
For the Northern District of California
10
Inderbitzen regarded the easement as a
At that time, Inderbitzen and Toll
RT at 1267:16-1268:13 (MI), 1400:2-22(MI), 1822:12-
19(MI), 1823:22-1824:20(MI); Ex. 101.
5.
11
No earlier than March 23, 2007 and no later than May 2,
12
2007, Toll learned for the first time of the existence of the
13
easement by independently running a title report on the property
14
comprising Sub-Area 3.
15
Inouye (hereinafter "WI")); Ex. 114.
RT at 342:9-344:9 (Testimony of Warren
16
6.
17
from Andrade.
18
title report on Sub-Area 3 which reflected the recording of the
19
easement and that the temporary facility above Sub-Area 3 was an
20
"issue of concern" for Toll.
21
the Lins had been told by their title company that the "easement
22
was not of record (yikes!)."
23
email, Tong stated that the easement would be an important issue
24
for Toll if it still existed on the scheduled closing date of June
25
30, 2007.8
26
7
27
28
On May 2, 2007, Tong and Inderbitzen received an email
Andrade wrote that Toll's title company had issued a
He further explained that to date,
Responding to Andrade's report by
Tong thought that the easement and pole line would give
Inderbitzen was the Lins' attorney. See MOD ¶ 6; RT at 1264:8-23
(Testimony of Inderbitzen (hereinafter "MI").
8
The Court previously detailed how Toll eventually treated the
issue of the easement. MOD ¶¶ 87-107.
5
1
Toll reason to refuse to close on Sub-Area 3.
2
Inderbitzen to ask Toll to waive this closing condition in exchange
3
for a holdback in the purchase price of fifty to one hundred
4
thousand dollars.
5
relocation of the temporary electrical facility with PG&E.
6
955:2-25(JT), 957:12-959:3(JT); Ex. 114.
7.
7
He instructed
He instructed Andrade to explore expediting the
RT at
On May 3, 2007, Andrade updated Tong on his efforts with
8
PG&E.
He reported that he had contacted Bates to receive a
9
schedule update.
Andrade informed Tong that PG&E would schedule
United States District Court
For the Northern District of California
10
the work after finishing engineering; preparing and signing work
11
agreements; and receiving funds for the project, estimated at
12
$150,000.
13
8.
Ex. 114.
On May 22, 2007, Tong and Andrade received an email from
14
Inderbitzen, telling them he had spoken to Gil Yamzon and Yamzon
15
had "agreed to try and help with Brian Bates."
16
representative with whom the Lins, through Tong, had worked during
17
the process of granting the easement.
18
that he would stay in contact with Yamzon.
19
whether Inderbitzen did so.
20
943:23(JT), 1836:14-1837:15(MI); Ex. 121.
21
9.
Yamzon is a PG&E
Inderbitzen's email said
It is not apparent
RT at 974:4-19(JT); RT at 942:12-
From February through June 2007, Andrade had two or more
22
telephone conversations with PG&E representatives in an attempt to
23
determine the status of the application.
24
10.
Ex. 522.
Between June 28, 2007 and November 2, 2007, Andrade sent
25
ten emails to PG&E inquiring about the status of the application,
26
to which he received five responses.
27
28
11.
Id.
In October 2007, PG&E delivered to Andrade the work
agreement that the Lins had to sign before PG&E would complete the
6
1
project.
2
paid PG&E.
12.
3
On October 31, 2007, the Lins signed the agreement and
Id.
Generally, PG&E was motivated by a desire to gain new
4
customers when completing projects related to new building.
5
prioritized such projects on the basis of which ones were closest
6
to providing PG&E with new customers, and would cooperate with
7
efforts to expedite their projects when PG&E determined there was
8
good reason to expedite.
9
Antonio), 1909:17-25 (Testimony of Thomas Gamble).
United States District Court
For the Northern District of California
RT at 1781:4-25 (Testimony of Walter
*
10
PG&E
*
*
11
As the Court already found, the parties met in August 2007 to
12
discuss the issues that had prevented them from closing Sub-Area 3
13
on June 30, 2007, as planned.
14
date by four years to June 30, 2011.
15
proposal to extend closing for three years if Toll paid an
16
additional deposit of $5 million.
17
Following the meeting, as found above, the Lins continued to
18
inquire with PG&E as to the status of the easement.
19
2007, PG&E completed engineering on the project and became ready to
20
begin work.
21
the Lins that it was terminating the PSA as to Sub-Area 3.
22
December 12, 2007, the Lins responded that they continued to
23
prepare for the Sub-Area 3 closing, and reminded Toll of its
24
obligation to reconvey the school site.
The parties engaged in an
25
unsuccessful mediation in January 2008.
MOD ¶¶ 105-07.
26
not quitclaim the easement until June 16, 2008.
27
///
28
///
Toll proposed extending the closing
See supra ¶¶ 9-11.
The Lins countered with a
Toll did not accept.
MOD ¶ 104.
In October
On December 7, 2007, Toll notified
7
On
PG&E did
Id. ¶ 63.
1
III. DISCUSSION AND CONCLUSIONS OF LAW
A.
2
The Lins Acted in Good Faith in Attempting to Comply with
3
the Sub-Area 3 Closing Conditions
4
1.
The Lins' Grant of the Easement to PG&E Was Made in
Good Faith
5
The Court has already concluded that the Lins did not breach
6
agreed.
9
notwithstanding these prior holdings, the Court nevertheless must
10
United States District Court
the PSA by granting the easement to PG&E, and the Ninth Circuit
8
For the Northern District of California
7
examine the circumstances of the Lins' 2005 grant of the easement
11
to determine whether the Lins acted in good faith.
12
13 (citing Carma Developers (Cal.), Inc. v. Marathon Dev.
13
California, Inc., 2 Cal. 4th 342, 372-73 (1992)).
MOD at 32-33; Aug. 31 Memo. at 6-7.
Toll argues that,
Toll Br. at 12-
The Court determines that it need not make such an examination
14
15
because the Court already implicitly made the findings required on
16
remand.
17
breach of the PSA on December 7, 2007, when Toll repudiated it.
18
MOD at 42.
19
that conclusion rested, namely, that the Lins acted in good faith
20
in attempting to comply with the closing conditions for Sub-Area 3
21
and, specifically, in granting PG&E the temporary easement for the
22
above-ground power line that crossed Sub-Area 3.
The Court earlier concluded that the Lins were not in
The Court now makes explicit the premise upon which
As the Ninth Circuit explained, the PSA was a valid contract,
23
24
notwithstanding that it gave each party the right to extend the
25
Sub-Area 3 closing beyond the scheduled closing date of June 30,
26
2007.
27
rendered the PSA illusory.
28
argument on the ground that the right to extend closing was not
On appeal, Toll contended that this right to extend closing
The Ninth Circuit rejected Toll's
8
1
indefinite; rather, it was limited by the implied covenant of good
2
faith and fair dealing, which prevented a party from delaying
3
closing in bad faith or unreasonably.
4
Aug. 31 Memo. at 4-5.
Consistent with the Ninth Circuit's view, if this Court had
5
determined that the Lins had delayed closing unreasonably or in bad
6
faith, the Court would had to have held that the Lins were in
7
breach of the PSA.
8
Lins were not in breach of the PSA when Toll repudiated it on
9
December 7, 2007.
The Court did the opposite, concluding that the
This conclusion rested on an implicit
United States District Court
For the Northern District of California
10
acknowledgment that the Lins had conducted themselves in good faith
11
in attempting to satisfy the closing conditions and had not been
12
unreasonable in extending the date of closing beyond June 30, 2007.
13
The Court now makes this conclusion express.
14
that the Lins acted in good faith when they granted the power line
15
easement to PG&E.
The Court finds that
16
Toll's arguments to the contrary amount to little more than an
17
attempt to relitigate issues that have already been decided by this
18
Court and affirmed by the Court of Appeals.
19
Developers (Cal.), Inc. v. Marathon Dev. California, Inc., 2 Cal.
20
4th 342 (1992), but nothing in that case dictates a different
21
result.
22
Lins' conduct in creating the power line easement and that the
23
Court cannot restrict its analysis "to a limited time or task."
24
Toll Br. at 13.
25
merely emphasizes "the difficulty in devising a rule of all-
26
encompassing generality" for contractual good faith claims and sets
27
forth the few general principles that may be derived from the
28
cases.
Toll relies on Carma
Toll states that Carma "mandates" this Court to assess the
But Carma stands for no such principle.
2 Cal. 4th at 373-74.
Carma
Carma does not say that a court must
9
1
take into account any and all conduct every time the question of
2
good faith arises, and certainly does not stand for the proposition
3
that a court must throw out previous findings of fact.
4
Carma acknowledges the difficulty that may arise from time to
5
time when "deciding whether . . . conduct, though not prohibited,
6
is nevertheless contrary to the contract's purposes and the
7
parties' legitimate expectations."
8
no such difficulty in this case, however.
9
allowed the Lins, inter alia, to encumber the property "as
Id. at 374.
The Court discerns
Section 13.2 of the PSA
United States District Court
For the Northern District of California
10
necessary to comply with the terms of" the PSA.
11
previously found, the purpose of the power line easement was to
12
allow PG&E to string a temporary, overhead power line across Sub-
13
Area 3 to a DSRSD water pumping station.
14
was needed to complete the development of a separate property owned
15
by the Lins, Fairway Ranch.
16
completed for the Lins to obtain certain affordable housing credits
17
from the City of Dublin.
18
needed before Toll could begin building on Sub-Area 2.
19
53-55.
20
complying with the PSA.
21
could not constitute a breach of the covenant of good faith, even
22
if it would have constituted bad faith in the absence of the PSA's
23
authorization clause.
24
party does not breach covenant of good faith if party was "given
25
the right to do what they did by the express provisions of the
26
contract").
27
28
As the Court
The water pump station
Fairway Ranch, in turn, had to be
The affordable housing credits were
See MOD ¶¶
The easement was therefore a reasonably necessary step for
As such, it was authorized by the PSA and
See Carma, 2 Cal. 4th at 374 (holding that
Toll argues that the easement was not "necessary" within the
meaning of Section 13.1 because, it says, the power line could have
10
1
been strung in a way that avoided Sub-Area 3.
Toll Br. at 13-14.
2
This argument turns on the meaning of the word "necessary."
3
appears to argue that any action contemplated in Section 13.2 could
4
be made unnecessary by the existence of an alternative.
5
its logical conclusion, this interpretation would read the "except
6
as necessary" clause out of Section 13.2 because, in all but the
7
most extraordinary circumstances, some alternative will be
8
available at some cost.
9
light of California's implied covenant of good faith and fair
Toll
Taken to
This reading is particularly untenable in
United States District Court
For the Northern District of California
10
dealing, as well as the PSA's mutual cooperation clause.
11
13.1.
12
meaning to the language of the exception for acts "necessary to
13
comply with the terms of [the PSA]."
14
reasonably necessary to comply with the closing conditions for Sub-
15
Area 3, the Court declines to find that granting the easement
16
violated Section 13.2 of the PSA.
17
PSA §
The Court reads Section 13.2 as it was written, giving
Because the easement was
In doing so, the Court effectuates the purpose of the PSA and
18
upholds the parties' legitimate expectations at the time of its
19
execution.
20
signed, the exact steps needed to develop Sub-Area 3 were difficult
21
to predict, though it was foreseeable that unforeseeable
22
difficulties would arise.
23
parties locked into the deal despite these difficulties.
24
why the parties bargained for each other's mutual cooperation and
25
the right to extend closing.
26
granted the easement to PG&E (instead of requiring PG&E to go
27
around Sub-Area 3) solely for the Lins' own benefit -- ostensibly,
28
the completion of the Lin-owned Fairway Ranch development.
See Carma, 2 Cal. 4th at 373.
At the time the PSA was
One purpose of the PSA was to keep the
This is
Toll characterizes the Lins as having
11
See
1
Toll Br. at 16.
2
the temporary power line.
3
purpose of the temporary power line was for the Lins to garner
4
affordable housing credits which, once transferred to Toll, would
5
allow Toll to build on Sub-Area 2.
6
easement to PG&E, the Lins acted to benefit Toll as well as
7
themselves, consistent with the purposes of the PSA and
8
expectations of the parties.
9
But this contention misconstrues the purpose of
As the Court already found, the ultimate
In other words, by granting the
This helps to explain why the Lins did not notify Toll of the
United States District Court
For the Northern District of California
10
easement.
11
failure to affirmatively notify Toll of the existence of the
12
easement as proof positive of the Lins' intent to deceive Toll.
13
E.g., Toll Br. at 14-15, 16 n.7.
14
Court sees no such intent.
15
is entirely consistent with a judgment that Toll already had
16
consented to such a grant, as work that was "necessary" to
17
effectuate the PSA within the meaning of Section 13.2.
18
consistent with a view that the easement, like the power line
19
itself, was nothing more than a trivial, temporary prerequisite to
20
other construction.
21
record that the Lins failed to act in good faith when they granted
22
the easement.
23
expensive means of accomplishing one facet of a large project.
24
25
26
In its briefing, Toll frequently points to the Lins'
2.
Looking at the entire record, the
The Lins' initial grant of the easement
It is also
The Court sees no persuasive evidence in the
The Court only sees the Lins pursuing the least
The Lins Conducted Themselves in Good Faith After
Granting the Easement to PG&E
The Lins did not inform Toll of the existence of the easement
27
or of their difficulties with PG&E.
28
in late April or early May 2007 when Toll independently ran a title
12
Toll discovered the easement
1
report.
The Lins had previously been told by their title company
2
that the easement was not of record, and appeared surprised by
3
Toll's discovery.
4
less than perfect, falls short of a breach of good faith.
The Court finds that the Lins' conduct, while
The important consideration here is the change in market
5
6
circumstances.
When the Lins granted the easement to PG&E, the
7
market was strong and both parties had incentives to hold each
8
other to the PSA, despite the hard-to-predict difficulties that
9
inevitably arise in a large construction project.
The Lins had no
United States District Court
For the Northern District of California
10
reason to think of the easement as anything other than one of the
11
myriad details that needed completion before the Sub-Area 3
12
closing.
13
short order, finishing in September 2006.
14
done was for PG&E, the easement's holder, to complete their portion
15
of the work and quitclaim the easement.
16
application for PG&E to do its part, PG&E told the Lins for four
17
months that all was going well.
18
had any reason to disbelieve PG&E.
The Lins finished their portion of the required work in
All that was left to be
After receiving the Lins'
No one has suggested that the Lins
It was not until February 15, 2007 that PG&E informed the Lins
19
20
that all, in fact, was not well, and that PG&E had yet to start
21
work on the Lins' September 2006 application.
22
previously strong real estate market had gone soft.
23
44.
24
"under water" by $40 million on the homes in Sub-Area 2, and was
25
facing high rates of cancellation on home purchase contracts.
26
¶¶ 46, 48-49.
27
build houses on Sub-Area 2 would be unprofitable and, rather than
28
doing so, forfeited a $30 million deposit.
By that time, the
See MOD ¶¶ 42-
Toll had sold only 50 out of 450 homes in Sub-Area 1, was
Id.
Toll determined that continuing with its plan to
13
Id. ¶¶ 49-50.
Toll
1
also had stopped its planning process for Sub-Area 3.
Id. ¶ 47.
2
Toll even considered selling part of Sub-Area 3 to an apartment
3
developer in an attempt to make at least some profit.
Id. ¶ 52.
In short, Toll, which had been gunning the accelerator during
4
5
the rising housing market, hit the brakes now that the market was
6
falling.
7
When the market was rising, both parties had an incentive to keep
8
the contract together.
9
the market began to fall, Toll had an incentive to get out of the
The falling market transformed the parties' incentives.
But, as the Court already determined, when
United States District Court
For the Northern District of California
10
PSA with respect to Sub-Area 3.
See MOD at 42 ("[D]eteriorating
11
market conditions explain why Toll wanted to get out of its
12
commitment to purchase Sub-Area 3.").
13
sophisticated real estate professionals in their employ could not
14
have failed to be aware of Toll's incentives, and they had a
15
corresponding incentive to keep Toll in the deal in what had
16
quickly become a buyer's market.
The Lins and the
It is therefore unsurprising that the Lins continued to prod
17
18
PG&E to abandon the easement and move toward closing Sub-Area 3.
19
Their representatives queried PG&E with reasonable consistency,
20
given that it was far from the only issue related to closing and
21
that Toll itself was late in focusing attention on the easement,
22
even after Toll discovered its existence.9
In the context of a
23
24
25
26
27
28
9
See MOD ¶¶ 92 (Toll expressing concern about utility vaults at
same May 2, 2007 meeting where Toll stated that it had learned of
recorded easement), 95 (June 8, 2007 letter from Toll expressing
concern about utility vaults and overhead line, but not easement),
98 (June 15, 2007 letter from Toll stating that utility vaults
violated provisions of PSA, mentioning for first time that
temporary power line encumbered property, and opining that location
of vaults likely would negatively effect development of Sub-Area
3), 100 (June 27, 2007 letter from Toll informing Lins that Toll
regarded them as having defaulted on the PSA).
14
1
large, complex development project like the one contemplated in the
2
PSA, the Lins' efforts to resolve the easement issue were
3
reasonable.
4
the status of the project; PG&E told them the project was
5
progressing.
6
them, they increased their efforts, frequently prodding PG&E in a
7
series of phone calls and emails that received only fitful
8
responses from PG&E.
9
approached, the Lins' representatives took the lead in identifying
Initially, the Lins periodically queried PG&E about
When the Lins discovered that PG&E had misinformed
As Sub-Area 3's scheduled closing date
United States District Court
For the Northern District of California
10
issues that could impede the closing, even though the Lins were
11
under no obligation to close on that date.
12
right to extend close of escrow because Toll had not complied with
13
all closing conditions).
14
even as Toll backed away from it.
15
postponing and canceling meetings, removing personnel); see also
16
MOD at 28 (Toll stopped cooperating), 33 (same), 42 (same).
17
Looking at all the circumstances, including market conditions which
18
provide strong circumstantial evidence of the parties' motives and
19
intent, the Court concludes that the Lins acted with good faith in
20
attempting to comply with the closing conditions.
21
MOD at 33-34 (Lins had
In short, the Lins moved toward closing,
E.g., MOD ¶¶ 97, 99, 101 (Toll
Toll makes much of Andrade's statement in his May 2, 2007
22
email that the Lins' title company had told him the "easement was
23
not of record (yikes!)."
24
Lins were caught in the act of trying to pull the wool over Toll's
25
eyes about the true title condition of the property.
26
16 n.7.
27
Andrade's statement is more consistent with an innocent exclamation
28
of surprise (namely, that the Lins' trusted title company had been
To Toll, the word "yikes" shows that the
The Court disagrees.
Toll Br. at
Under all the circumstances,
15
1
wrong).
The Lins and Toll were, at that point, attempting to raise
2
and resolve issues that could prevent or delay the Sub-Area 3
3
closing.
4
surprise at the existence of another issue, or perhaps concern that
5
a triviality now might take on inflated importance.
6
does not establish a lack of good faith.
In that context, Andrade's remark plausibly suggests
Either way, it
7
B.
8
For several reasons, the Court finds that the Lins' delay in
9
The Lins' Delay in Closing Was Not Unreasonable
closing was not unreasonable.
Some of the Lins' delay can be
United States District Court
For the Northern District of California
10
attributed to Toll's own unwillingness to cooperate with them by
11
extending the close of escrow, which the Court extensively detailed
12
in the Memorandum of Decision.
13
attributable to PG&E's initial misrepresentations to the Lins, as
14
suggested supra in Sections II and IV.A.2.
15
delay in obtaining the quitclaim from PG&E is that Toll had ceased
16
its planning process for developing the property; consequently,
17
PG&E de-prioritized the power line replacement project.
18
Toll itself was unable to close on Sub-Area 3 until it had arranged
19
for the school site to be reconveyed to the Lins.
20
Before that day ever came, Toll had repudiated and canceled the
21
PSA, extinguishing the Lins' obligation to perform under it.
22
Essentially, the Lins performed what they needed to do in advance
23
of the June 30, 2007 closing date, and then waited as other
24
parties, for a variety of reasons, dragged their heels.
25
Some of the delay may be
Another reason for the
Finally,
MOD at 34.
Toll faults the Lins for not having contacted anyone within
26
PG&E's legal department or having sued PG&E to quiet title.
27
Indeed, Toll insists that the Lins were "required . . . to take
28
every possible step to clear title."
16
Toll Br. at 3.
As a legal
1
matter, Toll cites no authority that would impose such an exacting
2
duty on the Lins.
3
the Lins' failure -- if it was "failure" -- to bring or threaten a
4
lawsuit against PG&E was unreasonable.
5
the Lins reached out to PG&E on a consistent basis, including at
6
least a dozen telephone calls and emails by Andrade and at least
7
one contact (by Inderbitzen to Yamzon) aimed at resolving a
8
perceived problem with the Lins' assigned PG&E representative.
9
Court finds that these efforts were reasonable under the
As a factual matter, Toll does not explain why
The record reflects that
The
United States District Court
For the Northern District of California
10
circumstances, which included Toll's having ceased planning on Sub-
11
Area 3 and Toll's having failed to comply with the closing
12
conditions of Sub-Area 3 by causing the school site to be
13
reconveyed to the Lins.
14
In short, neither the parties' covenant of mutual cooperation
15
nor the implied covenant of good faith and fair dealing required
16
the Lins to take any and every measure that bore some possibility
17
of hastening the process.
18
bringing or threatening legal action would have done anything but
19
inflame and prolong the situation.
20
have run the risk of seriously disadvantaging Toll, if Toll
21
actually did desire to close on Sub-Area 3 despite the adverse
22
market conditions.
23
to sue PG&E would have been a more reasonable course of action for
24
the Lins, that does not make the Lins' actual course of action
25
unreasonable.
26
whether the Lins did everything that was possible -- only whether
27
the Lins did something that was reasonable.
28
they did.
Further, the Court is dubious that
This course of action would
Even if Toll is right that suing or threatening
The relevant question here is not, as Toll claims,
17
The Court finds that
1
2
IV.
CONCLUSION
As set forth above, the Court finds that the Lins acted in
3
good faith in attempting to comply with the closing conditions of
4
Sub-Area 3, and that the delay was not unreasonable under all the
5
circumstances.
6
Lins, entered on June 25, 2009, stands.
Accordingly, the Court's Judgment in favor of the
ECF No. 226.
7
8
IT IS SO ORDERED.
9
United States District Court
For the Northern District of California
10
11
Dated: May 23, 2012
UNITED STATES DISTRICT JUDGE
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
18
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?