High Sierra Hikers Association v. United States Department of the Interior et al
Filing
96
ORDER GRANTING IN PART AND DENYING IN PART CROSS-MOTIONS FOR SUMMARY JUDGMENT. Further Case Management Conference set for 3/1/2012 10:00 AM in Courtroom 3, 17th Floor, San Francisco. Signed by Judge Richard Seeborg on 1/24/12. (cl, COURT STAFF) (Filed on 1/24/2012)
1
*E-Filed 1/24/12*
2
3
4
5
6
7
IN THE UNITED STATES DISTRICT COURT
8
FOR THE NORTHERN DISTRICT OF CALIFORNIA
10
SAN FRANCISCO DIVISION
11
For the Northern District of California
United States District Court
9
12
HIGH SIERRA HIKERS ASSOCIATION,
13
14
Plaintiff,
v.
15
16
17
18
19
20
21
22
23
24
25
26
27
28
UNITED STATES DEPARTMENT OF
THE INTERIOR, et al.,
No. C 09-04621 RS
ORDER GRANTING IN PART AND
DENYING IN PART CROSSMOTIONS FOR SUMMARY
JUDGMENT
Defendants.
____________________________________/
I. INTRODUCTION
This case challenges administrative actions and land management practices which allegedly
impact the level of stock use in the Sequoia and Kings Canyon National Parks (“SEKI”). Plaintiff
High Sierra Hikers Association (“HSHA”) asserts that defendants violated both the Wilderness Act
and the National Environmental Policy Act (“NEPA”) by issuing a General Management Plan
(“GMP”) which permits the use of horses and mules in wilderness areas without conducting the
proper environmental assessment of the impact of such stock use. The parties have filed crossmotions for summary judgment. For the reasons set forth below, plaintiff’s motion for summary
judgment is granted in part and denied in part as is defendants’ cross-motion for summary judgment.
In issuing the Packer Permits and approving the GMP, the NPS violated the Wilderness Act by
failing to conduct the requisite specialized finding, but complied with NEPA by fulfilling the Act’s
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
1
procedural requirements.
II. RELEVANT FACTS
2
Park System under a Congressional mandate to protect the parks and comply with the provisions of
5
NEPA and the Wilderness Act. See 16 U.S.C. §§ 41, 43, 80. While NEPA applies throughout
6
SEKI, the Wilderness Act provides extra protection to the parks’ designated wilderness areas. Over
7
the past forty years, the NPS has issued a number of management plans for SEKI. It presented the
8
SEKI Master Plan (“MP”) in 1971 with the stated objective, among others, to “phase[] out as
9
conditions permit” the use of livestock in the higher elevations for any purpose. (GMP 000310).
10
This objective, based on the NPS’s concern over “damage resulting from livestock,” was never
11
For the Northern District of California
The National Park Service (“NPS”) jointly administers SEKI as a single unit of the National
4
United States District Court
3
implemented. (Id.). Notably, the MP did not meet the requirements of a general management plan
12
and was developed absent public involvement. According to the GMP, the MP is therefore outdated
13
with recommendations for “some actions [which] are no longer appropriate.” (GMP 0020243).
14
Over a decade after issuance of the MP, the NPS approved two new plans, the Stock Use and
15
Meadow Management Plan (“SUMMP”), and the Backcountry Management Plan (“BMP”). These
16
plans were prepared with public input and accompanied by Environmental Assessments (“EAs”).
17
They limited stock to twenty per party and provided a number of management practices to mitigate
18
the adverse effects of stock use. The parties largely dispute the breadth and impact of these plans.
19
The HSHA contends that neither plan made the requisite findings of necessity to permit commercial
20
stock in SEKI. In this regard, plaintiff asserts that the SUMMP and the BMP merely presented a
21
few general practices and did little to mitigate the impact of stock usage. Consequently, the plans’
22
inadequate monitoring systems only provided means for the NPS to alter stock levels in response to
23
destructive impacts.
24
Defendants contest this analysis, arguing that both plans are fully NEPA compliant and
25
provide detailed guidance for protecting meadows and managing stock use. For support, defendants
26
describe each plan’s effects in detail: The SUMMP implemented a policy change from the MP by
27
no longer seeking to phase out stock use at upper elevations. Additionally, the SUMMP established
28
specific protections for park meadows and delineated permissible grazing areas. As a final measure,
the SUMMP created an elaborate monitoring program to scrutinize the impact of stock grazing on
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
2
1
the park meadows. The BMP, alternatively, focused on the backcountry areas of SEKI, asserting as
2
one of its management objectives, the allowance “to the extent possible—pack and saddle stock . . .
3
at the same levels and patterns that have occurred in recent past years unless information from the
4
monitoring system indicates need for change.” (GMP 0027935). Together, defendants maintain
5
that the plans provide “a sound scientific base” for managing stock use. Defendants also note that in
6
1994, SEKI engaged a full-time plant ecologist to oversee the SUMMP and to summarize
7
monitoring results. In conjunction with the various monitoring programs carried out by both the
8
wilderness rangers and the commercial and administrative users, defendants insist that the SEKI
9
staff and management team have a sound scientific base on which to ground meadow-related
11
For the Northern District of California
United States District Court
10
12
resource protection decisions.
A. The General Management Plan
In 1997, the NPS began preparing the GMP at issue. The agency drafted an Environmental
13
Impact Study (“EIS”), held public hearings, received public comment, and issued a Final EIS which
14
became the 2007 GMP. The GMP’s stated purpose “is to establish a vision for what Sequoia and
15
Kings Canyon National Parks should be, including desired future conditions for natural and cultural
16
resources, as well as visitor experiences.” (GMP 0020269). Importantly, it adopted the Draft EIS’s
17
Preferred Alternative of allowing stock use up to “current levels.” (GMP 0020247). Defendants
18
emphasize that the GMP simply offers a broad programmatic direction for SEKI, providing
19
guidelines to park management not only on stock use, but also on matters ranging from light
20
pollution to visitor accessibility—issues largely unrelated to stock. In support of the assertion that
21
the GMP is simply a programmatic document, defendants invoke language from the Record of
22
Decision (“ROD”) which implemented the GMP. The ROD stated that, following the GMP, a
23
stock-related Wilderness Stewardship Plan (“WSP”) “will be developed—with formal opportunities
24
for review and comment as well as informal public meetings—to regulate use and protect wilderness
25
values . . . [N]o installation of new structures nor any new commercial activities will be undertaken
26
until after [the WSP’s] approval.” (GMP 0021661-62). Consistent with this assertion, the NPS
27
published a Notice of Intent to Prepare an EIS for the WSP on April 26, 2011, characterizing the
28
goal as “an implementation level plan, [that] will provide guidance on a variety of issues including .
. . stock use.” 76 Fed. Reg. 23335. From this language, defendants insist that the GMP is not the
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
3
1
implementation plan. Rather it simply provides guidelines without affecting stock levels in any
2
way. Only upon completion of the WSP, they argue, will the NPS determine whether substantial
3
changes to stock use are necessary.
The HSHA disagrees with defendants’ characterization of the GMP as a programmatic
4
5
document. Rather, it asserts that the GMP not only continues stock use at “unidentified” current
6
levels, but also provides for the expansion and enhancement of facilities for stock users. The GMP
7
thus cannot be characterized as a programmatic plan, but rather an implementation plan with site-
8
specific effects. The HSHA further contends that the NPS’s assurances that it will conduct the
9
requisite needs assessment in a future, more specific WSP is unreliable and insufficient to
demonstrate that the NPS has complied with either the Wilderness Act or NEPA. Based on these
11
For the Northern District of California
United States District Court
10
facts, plaintiff filed an action asserting that defendants violated the Wilderness Act and NEPA in
12
adopting the GMP without adequately assessing environmental impacts.1
B. Packer Permits
13
The HSHA also claims that defendants violated the Wilderness Act and NEPA by continuing
14
15
to issue Packer Permits without first developing more stringent environmental protections in either
16
the GMP or in an alternative plan. Packer Permits refer collectively to the commercial use
17
authorizations (CUAs) granted annually to stock operators and to the renewal permit issued to the
18
one stock operator located in the parks. Before SEKI staff can issue a CUA, the requesting
19
commercial operator must submit proprietary information about the business and agree to certain
20
conditions. One such condition is a commitment to adhere to the stock use restrictions established
21
both by the SUMMP and the conditions of that particular year. The specific restrictions for each
22
year are derived from a compilation of monitoring data, employee observation, stock use reports,
23
and an evaluation of overall meadow conditions. The HSHA insists that these procedures are
24
deficient and constitute an “about-face” of the NPS’s original promise to conduct additional
25
environmental study before renewing any permits. Relying on twenty-year-old EAs conducted for
26
the SUMMP and the BMP, plaintiff contends, is insufficient under both the Wilderness Act and
27
1
28
In the Complaint, plaintiffs also assert a claim under the Organic Act. They do not address this
claim, however, in either their motion for summary judgment or in their opposition to defendants’
cross-motion for summary judgment. Defendants, therefore, request that the Court conclude
plaintiff has abandoned this claim. Plaintiffs do not object to this request.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
4
1
NEPA. Furthermore, according to plaintiff, the NPS cannot escape liability by insisting that the
2
requisite “more extensive review and analysis” for issuing permits in upcoming years will occur in
3
the detailed WSP.
Plaintiff brings a motion for summary judgment asserting that the NPS violated: (1) The
4
specialized finding required under the Act; and (2) NEPA by issuing Packer Permits and approving
7
the GMP before adequately assessing the environmental impacts of the increase in stock use.
8
Defendants respond with a cross-motion for summary judgment asserting that the GMP is a
9
programmatic document and part of a tiered planning approach and that they are therefore permitted
10
to defer both specialized findings and a full environmental impact assessment as to stock use until a
11
For the Northern District of California
Wilderness Act by issuing Packer Permits and approving the GMP without conducting the type of
6
United States District Court
5
later stage. Defendants further maintain that in issuing CUAs they did not violate NEPA. With
12
regards to Packer Permits and the Wilderness Act, however, defendants concede that they failed to
13
conduct the requisite specialized findings.2
III. LEGAL STANDARD
14
A. Summary Judgment
15
Rule 56(c) of the Federal Rules of Civil Procedure provides that summary judgment “shall
16
17
be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on
18
file, together with the affidavits, if any, show that there is no genuine issue as to any material fact
19
and that the moving party is entitled to a judgment as a matter of law.” The party who seeks
20
summary judgment bears the initial responsibility of identifying an absence of a genuine issue of
21
material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). If the moving party satisfies this
22
initial burden, it shifts to the non-moving party to present specific facts showing that there is a
23
genuine issue for trial. Fed. R. Civ. P. 56(e); Celotex, 477 U.S. at 324. “Only disputes over facts
24
that might affect the outcome of the suit under governing law” are material. Anderson v. Liberty
25
Lobby, Inc., 477 U.S. 242, 248 (1986). A genuine issue exists if the non-moving party presents
26
2
27
28
Defendants also bring a motion for relief from the nondispositive pretrial order of a Magistrate
Judge. In this motion they contest the Judge’s order granting in part and denying in part plaintiff’s
motion to augment and supplement the administrative record. Specifically, they object to the
admission of four of the fifty documents submitted pursuant to the order—Documents 8, 9, 10, and
42. This Order granting in part and denying in part parties’ cross-motions for summary judgment
does not rely on any of these documents. Defendants’ objections are therefore immaterial and need
not be resolved.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
5
1
evidence from which a reasonable factfinder, viewing the evidence in the light most favorable to
2
that party, could resolve the material issue in his or her favor. Id. at 248-49.
3
4
B. Administrative Procedures Act
Plaintiffs bring this challenge under the Wilderness Act and NEPA pursuant to the
only if it is “arbitrary, capricious, an abuse of discretion, or not otherwise in accordance with the
7
law.” 5 U.S.C. § 706. While the arbitrary and capricious standard is “narrow,” judicial review
8
under the APA “must not ‘rubber-stamp’ . . . administrative decisions that [are] inconsistent with a
9
statutory mandate or that frustrate the congressional policy underlying a statute.” Ocean Advocates
10
v. United States Army Corps of Eng’rs., 361 F.3d 1108, 1118 (9th Cir. 2004) (quoting Ariz. Cattle
11
For the Northern District of California
Administrative Procedure Act (“APA”). Under the APA, a court may overrule a final agency action
6
United States District Court
5
Growers’ Ass’n v. United States Fish & Wildlife, 273 F.3d 1229, 1236 (9th Cir. 2001)). Thus, in
12
assessing challenges brought under the Wilderness Act and NEPA, once a court is “satisfied that a
13
proposing agency has taken a ‘hard look’ at a decision’s environmental consequences, the review is
14
at an end.” Oregon Natural Res. Council v. Lowe, 109 F.3d 521, 526 (9th Cir. 1997) (quoting Idaho
15
Conservation League v. Mumma, 956 F.2d 1508, 1519 (9th Cir. 1992) (citations omitted)).
IV. DISCUSSION
16
17
A. The Wilderness Act
18
The HSHA asserts that the NPS violated the Wilderness Act by failing to conduct the
19
requisite finding of necessity before authorizing commercial services in the wilderness. The
20
HSHA’s argument pertains to both the overall GMP and to the NPS’s issuance of Packer Permits.
21
The NPS concedes that it has not yet conducted the type of specialized finding of necessity
22
envisioned by the Ninth Circuit. In this regard, it admits that it violated the Wilderness Act in
23
issuing the Packer Permits and submits that plaintiff’s summary judgment motion should be granted
24
on this issue only. With respect to the GMP, however, the NPS insists that a specialized necessity
25
finding is premature because the Ninth Circuit only requires such a finding for binding
26
implementation documents. The GMP, the NPS maintains, is merely a programmatic plan intended
27
to provide management guidance, not to implement decisions.
28
The Wilderness Act was enacted with the purpose of preserving and protecting the
wilderness in its natural condition. See 16 U.S.C. § 1131(c). With this in mind, the Act charged the
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
6
dominant.” 36 C.F.R. § 293.2(c). Furthermore, the Act largely prohibits commercial enterprises in
3
wilderness areas, authorizing them only “to the extent necessary for activities which are proper for
4
realizing the recreational or other wilderness purposes of the areas.” 16 U.S.C. § 1133(d)(5).
5
Interpreting this language, the Ninth Circuit has held that “the statutory scheme requires, among
6
other things, that the assigned agency make a finding of ‘necessity’ before authorizing commercial
7
activities in wilderness areas.” High Sierra Hikers Ass’n. v. Blackwell, 390 F.3d 630, 646 (9th Cir.
8
2004) (“[A] finding of necessity is required, but not wholly sufficient.”). This finding must be
9
“specialized” and permit commercial activities “no more than [is] necessary to achieve the goals of
10
the Act.” Id. at 647 (describing the goals of the Act as preserving the wilderness and providing the
11
For the Northern District of California
NPS and other agencies, to promulgate regulations which ensure that “wilderness values will be
2
United States District Court
1
public with access to its natural condition).
12
In instituting this requirement, Blackwell recognized that the agency must balance many
13
competing interests in making a necessity finding. Id. at 647; see Wilderness Watch, Inc. v. U.S.
14
Fish and Wildlife Serv., 629 F.3d 1024, 1033, 1039, 1040 (9th Cir. 2010)) (“The Wilderness Act
15
requires a delicate balancing between Congress’ desire to maintain [untouched lands, and its] . . .
16
recognition that such an idealistic view is subject to some practical limitations.”). Consequently,
17
courts must generally defer to the agency’s chosen “form or content” for conducting the specialized
18
finding, ensuring only that the agency has adequately considered the potential consequences of the
19
commercial activity. Blackwell, 390 F.3d at 645, 648 (enforcing the “agency’s obligation under the
20
Wilderness Act to protect and preserve wilderness areas”). Despite this deference to the agency’s
21
chosen form, courts have emphasized that the prohibition against commercial activity is “one of the
22
strictest prohibitions of the Act.” Californians for Alternatives to Toxics v. U.S. Fish and Wildlife,
23
No. CIV. S–10–1477 FCD/CMK, 2011 WL 3915966, at *20 (E.D. Cal. Sept. 6, 2011) (citing
24
Wilderness Watch, Inc., 629 F.3d at 1040). Thus, if an agency determines that a commercial use
25
should trump the Act’s general policy of wilderness preservation, it has the burden of showing the
26
court that, in balancing competing interests, it prepared the “requisite findings” of necessity. Id. at
27
*21; see High Sierra Hikers Ass’n v. U.S. Forest Serv., 436 F. Supp. 2d 1117, 1131 (E.D. Cal. 2006)
28
(“[W]hen there is a conflict between maintaining the primitive character of the area and between
any other use . . . the general policy of maintaining the primitive character of the area must be
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
7
1
supreme.”); see also Wolf Recovery Found v. U.S. Forest Serv., 692 F. Supp. 2d 1264, 1268 (D.
2
Idaho 2010).
The HSHA argues that it is entitled to summary judgment because the NPS acknowledges it
3
4
did not make the requisite specialized necessity findings for the GMP. The NPS responds that the
5
absence of such a finding does not render the GMP invalid. Rather, it contends that Blackwell and
6
the Act’s necessity finding requirement only apply to binding agency decisions which expressly
7
permit commercial activity, not to programmatic plans like the GMP, which merely provide
8
guidance as to a variety of issues respecting park management.3 Unlike the plan considered in
9
Blackwell, the NPS emphasizes, the GMP “does not permit any operator to provide commercial
services in the wilderness, but merely authorizes continuing use up to current levels, subject to the
11
For the Northern District of California
United States District Court
10
regulatory and permitting review process.” (Def’s. Cross-Mot. for Summ. J. at 8) (emphasis added).
12
Defendants stress that pursuant to the GMP, the NPS will not authorize new types of commercial
13
activities until a full necessity finding is completed in the WSP. Until that time, the NPS will
14
simply continue to issue commercial permits by the same methods, and at the same levels, as before
15
the GMP was issued.
The NPS bases much of its argument on the difference between “providing commercial
16
17
services” and “authorizing continuing use of [existing] commercial services.” While the WSP in
18
Blackwell permitted commercial activity, the GMP here only authorizes stock use at current levels.
19
No such distinction, however, exists in either the language of the Wilderness Act or Ninth Circuit
20
precedent. In fact, Blackwell explicitly declined to differentiate, for purposes of the Wilderness Act,
21
between an agency maintaining current levels of commercial activity and increasing such activity.
22
Rather, the Court, in holding that the Forest Service did not conduct an adequate necessity test,
23
stated that “[a]t best when the Forest Service simply continued preexisting permit levels, it failed to
24
balance the impact that level of commercial activity was having on the wilderness character of the
25
3
26
27
28
At oral argument, the NPS emphasized that Blackwell is inapposite because there the Court was
considering an implementation document. At no point, defendant asserts, has the Ninth Circuit
required a necessity finding under the Wilderness Act for a programmatic document such as the
GMP. The NPS, however, puts too much emphasis on this distinction; the Blackwell Court
provided little discussion as to whether the Forest Service’s purported plan was binding or merely
advisory. Rather, the Court focused on the environmental impact of the agency’s plan and whether
the agency had completed the requisite balancing. As stated, per the NPS’s own concession, it has
failed to complete this balancing.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
8
1
land. At worst, the Forest Service elevated recreational activity over the long-term preservation of
2
the wilderness.” 390 F.3d at 647-48. As evident from this language, it was immaterial to the Court
3
whether the agency was escalating the amount of commercial activity or simply maintaining activity
4
at its preexisting levels. What was material to the Court’s analysis, however, was whether the
5
agency balanced all relevant factors and potential consequences in permitting continued commercial
6
activity. Such balance is essential, the Court stated, because the agency’s primary responsibility is
7
to protect the wilderness, not cede to commercial needs. An agency can only override this
8
responsibility and promote competing interests such as those related to commercial activity, if it first
9
engages in a “comparative and qualitative analysis where the variables are considered in relation to
one another and the interests at stake are weighed.” Californians for Alternatives to Toxics, 2011
11
For the Northern District of California
United States District Court
10
WL 3915966, at *25 (citing Blackwell, 690 F.3d at 646). Once this analysis is complete, “the
12
administering agency must determine the most important value and [justify] its decision to protect
13
that value.” Id. at *21 (quoting Blackwell, 690 F.3d at 646). Thus, contrary to the NPS’s assertions,
14
the crucial inquiry is not whether the agency is increasing or maintaining—permitting or
15
authorizing—current levels of commercial activity, but rather whether the agency has conducted a
16
sufficient comparative and qualitative analysis.
17
Here, the NPS admits to promulgating the GMP without this requisite balancing. It does not
18
argue that its analysis was adequate or that its evaluation concluded that preexisting commercial
19
activity was necessary. Rather, it simply states that the agency is currently conducting a finding of
20
necessity and a determination is forthcoming in a WSP. In the meantime, however, by the NPS’s
21
own admission, the GMP is providing guidance to wilderness management on a “wide array of
22
issues.” This “guidance” is partially based on the GMP’s findings with regards to commercial use,
23
the very findings that have yet to be subjected to the requisite determination of necessity. This
24
constitutes a direct violation of the Wilderness Act as interpreted in Blackwell. As that precedent
25
mandates, the NPS must balance these new “wide array of issues” and their potential consequences
26
with the effects of preexisting levels of commercial activity.
27
The NPS’s stated intention to complete the necessary balancing in a forthcoming WSP is
28
similarly insufficient. Moreover, the fact that the NPS has committed to forego authorizing new
types of commercial activities until after the WSP is inadequate. Blackwell, 390 F.3d at 647-48.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
9
1
The NPS has issued a GMP which, programmatic or not, at the very least, provides for the
2
continuation of stock use at its current levels. Pursuant to the Wilderness Act, a necessity finding is
3
required.4 Because the NPS has yet to complete this finding, the GMP violates the Act.5
B. National Environment Policy Act
4
NEPA is a procedural statute which does not “mandate particular results but simply provides
5
6
the necessary process to ensure that federal agencies take a hard look at the environmental
7
consequences of their actions.” Neighbors of Cuddy Mtn. v. Alexander, 303 F.3d 1059, 1070 (9th
8
Cir. 2002); see Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989) (“[I]t is now
9
well settled that NEPA itself does not mandate particular results, but simply prescribes the necessary
process.”). It was enacted with two goals mind: “(1) to ensure the agency will have detailed
11
For the Northern District of California
United States District Court
10
information on significant environmental impacts when it makes its decisions; and (2) to guarantee
12
that this information will be available to a larger audience.” Inland Empire Public Lands Council v.
13
U.S. Forest Serv., 88 F.3d 754, 758 (9th Cir. 1996). These goals are satisfied once the agency
14
completes its evaluation; the statute therefore “exists to ensure a process, not to ensure any result.”
15
Id. at 758 (emphasis in original); see Metcalf, 214 F.3d at 1141 (9th Cir. 2000) (“NEPA does not set
16
out substantive environmental standards, but instead establishes ‘action-forcing’ procedures that
17
require agencies to take a ‘hard look’ at environmental consequences.”). Among other
18
requirements, the agency must prepare an Environmental Impact Statement (“EIS”) for all actions
19
which significantly affect the quality of the human environment. See 42 U.S.C. § 4332(2)(C).6 An
20
EIS must include a comprehensive discussion of all substantial environmental impacts and inform
21
the public of any reasonable alternatives which could avoid or minimize these adverse impacts. See
22
40 C.F.R. § 1502.1. In assessing the adequacy of an agency’s EIS, courts apply the “rule of reason”
23
4
24
25
26
27
28
Because the NPS violated the Wilderness Act by foregoing the requisite specialized finding, the
Court need not address the dispute over whether the ongoing commercial stock use currently
permitted in SEKI’s wilderness is unnecessary under the Act.
5
Both parties agree that further briefing is necessary for the purpose of determining an appropriate
remedy. The NPS asserts that the proper remedy is to remand the matter to the agency, not to vacate
the GMP in its entirety, because plaintiff is only challenging the GMP with respect to stock use, a
small component of the large programmatic document. The HSHA, while stipulating to a future
briefing schedule to address remedy, insists that injunctive relief is necessary.
6
Before issuing an EIS, an agency may choose to prepare an Environmental Assessment (“EA”) to
determine whether the environmental impact of a project is significant enough to warrant an EIS.
Under this process, only if the EA concludes that an EIS is necessary, must the agency prepare one.
40 C.F.R. § 1508.9.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
10
1
standard which determines whether the EIS contains a “reasonably thorough discussion” of the
2
“probable environmental consequences.” Cal v. Block, 690 F.2d 753, 761 (9th Cir. 1982); Friends
3
of Yosemite Valley v. Norton, 348 F.3d 789, 801 (9th Cir. 2003) (equating the “rule of reason”
4
standard to an abuse of discretion review).
5
Here, the NPA prepared an EIS accompanying the GMP. Regardless, the HSHA asserts that
6
the NPA violated NEPA by: (1) failing to consider a range of reasonable alternatives before issuing
7
Packer Permits or approving the GMP; (2) neglecting to take the required hard look at the
8
environmental impacts of the levels of stock use permitted under the GMP; and (3) improperly
9
relying on outdated environmental assessments and categorical exclusions in issuing Packer
Permits.
11
For the Northern District of California
United States District Court
10
As a threshold matter, the parties dispute whether the EIS should be considered
12
programmatic or site-specific. This distinction is significant because courts assess NEPA
13
compliance differently depending on the type of EIS at issue. A programmatic EIS need only
14
provide “sufficient detail to foster informed decision making,” while a site-specific EIS must
15
include “data-gathering and analysis of system-wide impacts.” 'Ilio'ulaokalani Coalition v.
16
Rumsfeld, 464 F.3d 1083 (9th Cir. 2006); see also Block, 690 F.2d at 761 (explaining that
17
considerations regarding the adequacy of a programmatic EIS may differ from those for a site-
18
specific EIS). Under certain circumstances, programmatic EIS are encouraged to promote
19
efficiency and to “eliminate repetitive discussions of the same issues and to focus on the actual
20
issues ripe for decision at each level of the environmental review.” 40 C.F.R. § 1502.20; Friends of
21
Yosemite Valley v. Norton, 348 F.3d 789 (9th Cir. 2003) (recognizing that programmatic EIS permit
22
agencies to “defer detailed analysis until a concrete development proposal crystallizes”). When
23
utilizing the programmatic approach, agencies must engage in a “tiered” process; the agency will
24
first issue the programmatic EIS and then follow up with one or more site-specific EIS as necessary
25
to assess adequately all environmental consequences. 'Ilio'ulaokalani Coalition, 464 F.3d at 1094;
26
see 40 C.F.R. § 1502.20; Block, 690 F.2d at 761 (“[T]he crucial inquiry in considering the adequacy
27
of [a programmatic] EIS . . . is not whether the project’s site-specific impact should be evaluated in
28
detail, but when such detailed evaluation should occur.”). Such a tiered process is only appropriate,
however, when the EIS at issue is not evaluating an agency’s “critical decision” with regards to site
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
11
1
development. Block, 690 F.2d at 761(“When a programmatic EIS has already been prepared, we
2
have held that site-specific impacts need not be fully evaluated until a ‘critical decision’ has been
3
made to act.”). A “critical decision” is defined as one that “constitutes an irreversible and
4
irretrievable commitment of the availability of resources” to a project at a specific site. Norton, 348
5
F.3d at 801 (quoting Block, 690 F.2d at 761). Thus, the crucial inquiry in determining whether the
6
EIS should be evaluated as one of a programmatic or site-specific nature is whether the GMP makes
7
an irretrievable commitment of resources that affects stock use.
8
9
The HSHA contends that the EIS should be regarded as site-specific, not programmatic. The
Association argues, contrary to the NPS’s assertions, that the GMP is more than a guiding
document, but rather, an implementation plan which provides critical and binding decisions as to
11
For the Northern District of California
United States District Court
10
“grazing, monitoring, and capacity-related issues for stock.” Such critical decisions are reflected
12
where the GMP: (1) allows stock use at preexisting levels and; (2) constrains future agency choices
13
which cause the expansion of stock use. In short, the HSHA argues that, due to these critical
14
decisions, the NPS is not permitted to characterize its EIS as programmatic in an effort to avoid the
15
detailed analysis required by NEPA. In response, the NPS discusses the HSHA’s characterization
16
of the GMP and insists there are no critical decisions made in that planning document. The NPS
17
notes that its determination in the ROD and GMP to continue stock use up to current levels and
18
under current policies flows from its earlier decisions made in the SUMMP and BMP. Additionally,
19
the GMP does nothing to constrain the NPS’s future choices with regards to the implementation of
20
stock use projects. Consequently, the NPS asserts, the GMP should be treated as programmatic and
21
the accompanying EIS need not meet the requirements of a site-specific evaluation.
22
Determining an answer to that dispute “begins with an accurate description of the NPS’s
23
proposed action.” Norton, 348 F.3d at 801. Here, the ROD, implementing the GMP, explains that
24
the latter simply “provides conceptual guidance for park managers . . . that the parks may wish to
25
consider at some point in the future.” (GMP 0021661). As to stock use, it specifically advises
26
SEKI to maintain current levels according to the previous policies of SUMMP and BMP. With
27
regard to future stock use, neither the ROD nor the GMP makes any binding decisions. Rather, the
28
ROD anticipates the development of a Wilderness Stewardship and Stock Use Plan (“WSSUP”) to
make critical determinations regarding stock use. The WSSUP will “be developed—with formal
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
12
1
opportunities for review and comment as well as informal public meetings—to regulate use and
2
protect wilderness areas.” (GMP 0021661).7 It will also be accompanied by its own site-specific
3
EA or EIS pursuant to a regulatory tiered approach. Notably, nothing in the ROD appears to limit
4
the NPS in future decisions. Rather, the ROD provides for the precise sort of multi-stepped
5
approach permitted by the regulations. To this point, the ROD states that the “GMP does not
6
address site specific design and location attributes for [stock support] facilities,” thereby inferring
7
that these issues will be addressed in upcoming site-specific EIS.
permitted, evaluating if the NPS’s proposed action constituted a critical decision for purposes of
10
NEPA. In determining that no critical decision had yet been made, the Court emphasized that the
11
For the Northern District of California
In Norton, the Ninth Circuit similarly considered whether a programmatic EIS was
9
United States District Court
8
Comprehensive Management Plan (“CMP”) itself provided that it was a guiding document.
12
Furthermore, the Court held that “because a subsequent and full environmental review is
13
contemplated . . . neither function constitutes ‘an irreversible and irretrievable commitment of the
14
availability of resources.”’ 348 F.3d at 801.
Analogously here, the NPS’s own assertions and the ROD language support that no
15
16
irretrievable commitment has been made with respect to stock use. The mere continuing issuance of
17
Packer Permits according to prior policies under the GMP, does not constitute a renewed
18
irretrievable commitment. See, e.g. Center for Environ. Law & Policy v. U.S. Bureau of
19
Reclamation, 655 F.3d 1000 (9th Cir. 2011) (stating that issuing permits did not constitute an
20
irretrievable commitment of resources). Rather, the NPS has promulgated a programmatic plan for
21
its parks with an accompanying programmatic EIS. When critical decisions with regard to site-
22
specific acts are made in the future, the NPS must then prepare more detailed EIS. For purposes of
23
this NEPA challenge, the EIS will consequently be analyzed pursuant to the requirements of a
24
programmatic EIS. See Block, 690 F.2d at 761 (“The standards normally applied to assess an EIS
25
require further refinement when a largely programmatic EIS is reviewed.”).
1. The NPS’s Consideration of Reasonable Alternatives
26
27
28
7
At oral argument, plaintiff focused on the inadequacies of the forthcoming WSP, stating the plan’s
Notice of Intent restricted its implementation only to the 96.8% of SEKI designated as wilderness
areas. Importantly, this scoping document is merely an initial draft and the NPS is fully in its
discretion to expand the final WSP to address all areas of the park. Plaintiff, however, may request
within the upcoming briefing on remedy, a court order regulating the scope of the WSP.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
13
1
The HSHA’s first NEPA challenge concerns the NPS’s alleged failure to consider a proper
2
range of alternatives. Specifically, the HSHA argues that the NPS should have analyzed both the
3
“no grazing” alternative and the alternative which would have completely banned stock usage at
4
higher elevations, before issuing the GMP. In response, the NPS contends it has not violated
5
NEPA, that while it did not consider the two alternatives raised by the HSHA, both will be
6
examined during the WSP process. Furthermore, the NPS asserts that the ROD and the GMP
7
analyzed five reasonable alternatives, thereby, providing the public and the decision-makers with a
8
range of different approaches to stock use. This range, the NPS insists, is more than sufficient given
9
the policy goals and programmatic nature of the GMP.
NEPA requires agencies “to inform decisionmakers and the public of the reasonable
11
For the Northern District of California
United States District Court
10
alternatives which would avoid or minimize adverse impacts or enhance the quality of the human
12
environment.” 40 C.F.R. § 1502.1. “Judicial review of the range of alternatives considered by an
13
agency is governed by a ‘rule of reason’ that requires an agency to set forth only those alternatives
14
necessary to permit a ‘reasoned choice.”’ Block, 690 F.2d at 767 (quoting Save Lake Washington v.
15
Frank, 641 F.2d 1330, 1334 (9th Cir. 1981)); see also 'Ilio'ulaokalani Coalition, 464 F.3d at 1094,
16
(“The scope of reasonable alternatives that an agency must consider is shaped by the purpose and
17
need statement articulated by that agency.”). Substantial deference, therefore, is given to the
18
agency’s articulated purpose and objectives for the planned project. 'Ilio'ulaokalani Coalition, 464
19
F.3d at 1095. The crucial inquiry for courts applying the rule of reason “is whether an EIS’s
20
selection and discussion of alternatives fosters informed decision-making and informed public
21
participation.” Block, 690 F.2d at 767. It follows that there is no requirement under NEPA that an
22
agency consider every possible alternative to a proposed action. See Westlands Water Dist. v. U.S.
23
Dept. of Interior, 376 F.3d 853, 871 (9th Cir. 2004) (reversing the district court’s holding that the
24
range of alternatives considered was unreasonable because the agency reviewed sufficient
25
alternatives to meet the goals of NEPA to provide for an “open, thorough public discussion”).
26
Rather, an agency need only analyze alternatives which do not appear to be “too remote or
27
speculative” to accomplish the project’s purpose. Block, 690 F.2d at 767; see City of Angoon v.
28
Hodel, 803 F.2d 1016, 1021 (9th Cir. 1986) (“When the purpose (of a project) is to accomplish one
thing, it makes no sense to consider the alternative ways by which another thing might be
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
14
1
achieved.”). An agency, however, must, at least, “briefly discuss the reasons” for eliminating any
2
alternative. 40 C.F.R. § 1502.14.
3
As stated above, courts must defer to the agency’s proffered statement of purpose in
4
assessing whether the NEPA document sufficiently considered all reasonable alternatives. Federal
5
courts in the Ninth Circuit embrace this deference wholeheartedly and consistently refuse to
6
determine that an agency’s articulated purpose is too narrow. Kettle Range Conservation Group v.
7
U.S. Forest Serv., 148 F. Supp. 2d 1107 (E.D. Wash 2001) (“This court is not aware of any case in
8
which the Ninth Circuit found a statement of purpose to be unreasonably narrow.”); see
9
Muckleshoot Indian Tribe v. United States Forest Serv., 177 F.3d 800, 812-13 (9th Cir. 1999)
(adopting the agency’s narrow purpose even though it essentially ruled out any alternatives which
11
For the Northern District of California
United States District Court
10
did not resemble the preexisting plan); Friends of Se’s. Future v. Morrison, 153 F.3d 1059, 1066-67
12
(9th Cir. 1998) (upholding a narrow purpose which excluded consideration of any alternative which
13
would provide less timber to the market). Here, the NPS presents as the GMP’s stated objective,
14
“set[ting] forth the basic management philosophy for the parks and provid[ing] strategies for
15
addressing issues and achieving management objectives” so as to develop a “conceptual framework
16
for formulating the[] alternatives” presented. (GMP 00001-00002). As evidenced by this language,
17
the purpose of the GMP was not to provide a detailed assessment of management options for stock
18
use in the parks; such a detailed assessment will be a part of future WSPs. The alternatives
19
considered, therefore, need only be appropriate for this stated purpose, not for the anticipated WSP
20
to come.
21
Notably, this conclusion fits with the purpose of NEPA’s “reasonable alternative”
22
requirement of ensuring that the “most intelligent, optimally beneficial decision will ultimately be
23
made.” N. Alaska Environ. Center v. Kempthorne, 457 F.3d 969, 978 (9th Cir. 2006) (quoting
24
Calvert Cliffs’ Coordinating Comm., Inc. v. United States Atomic Energy Comm’n, 449 F.2d 1109,
25
1114 (D.C. Cir. 1971)); Westlands Water Dist. v. United States Dept. of the Interior, 376 F.3d 853,
26
871 (9th Cir. 2004) (requiring only that the EIS’s considered alternatives fulfill NEPA’s purpose of
27
providing an “open, thorough discussion promoting informed decision-making”). This is because, if
28
the NPS is not using the GMP to make any new decisions that alter current or future stock use, it is
premature to insist that the GMP should consider detailed alternatives to these unmade decisions—
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
15
1
they will be evaluated in the upcoming WSPs. Furthermore, the agency did, in fact, assess five
2
alternatives in the GMP, ranging from a no-stock approach to a number of options suggesting that
3
stock use be monitored to prevent resources impairment.8 The NPS’s consideration of five
4
alternatives, with the expectation that it will assess more in the future, is sufficient to demonstrate
5
NEPA compliance at this time. See, e.g., Kempthorne , 457 F.3d at 978 (rejecting plaintiffs’
6
argument that the EIS which considered five alternatives was insufficient); Westlands Water Dist.,
7
376 F.3d at 871 (“The EIS was not required to consider more mid-range alternatives to comply with
8
NEPA.”).
2. NPS’s Consideration of Environmental Impacts9
9
NEPA requires that an agency take a “hard look” at mitigation measures which may offset
11
For the Northern District of California
United States District Court
10
any adverse environmental consequences of an agency’s proposed action. See 40 C.F.R. § 1502.16.
12
The agency must utilize the EIS to discuss such mitigation measures “in sufficient detail to ensure
13
there has been a fair evaluation” of the consequences. Robertson v. Methow Valley Citizens
14
Council, 490 U.S. 332, 352 (1989). An agency’s compliance with this NEPA requirement is also
15
analyzed under the “rule of reason” standard. Block, 690 F.2d at 761 (quoting Trout Unlimited, Inc.
16
v. Morton, 509 F.2d 1276, 1283 (9th Cir. 1974)). This standard of review “inquires whether an EIS
17
contains a ‘reasonably thorough discussion of the significant aspects of the probable environmental
18
consequences.”’ Id. The level of detail required in each EIS depends on the objectives and scope of
19
the proposed action. Aberdeen & Rockfish R.R. Co. v. Students Challenging Regulatory Agency
20
Procedures, 422 U.S. 289, 322 (1975). Thus, the Ninth Circuit has determined that the distinction
21
between inadequate and adequate impact and mitigation discussions “appears to be one of degree.”
22
Compare Okanogan Highlands Alliance v. Williams, 236 F.3d 468, 473 (9th Cir. 2000) (holding that
23
the Forest Service complied with NEPA’s “hard look” requirements even though the agency
24
described the mitigating measures in general terms) with Neighbors of Cuddy Mountain v. U.S.
25
26
27
28
8
The HSHA’s argument that three of these options will raise stock levels is purely speculative as
the critical decisions with regards to stock use will be made within the forthcoming WSPs.
9
The parties consolidate the discussion of the adequacy of the EIS as it pertains to both the
evaluation of environmental impacts and the consideration of mitigating measures despite the fact
that these components are often analyzed separately. Following the parties’ approach, the Court
similarly combines the analyses. This combination is appropriate as the controlling law for these
issues largely overlaps.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
16
1
Forest Service, 137 F.3d 1372, 1381 (determining that an EIS did not fully consider all necessary
2
mitigating measures which could ameliorate consequences stemming from timber sales).
3
Although the standard for evaluating the requisite “hard look” scope is fact-specific, the
4
Ninth Circuit has established some bright-line rules. Most importantly, the EIS must provide easily-
5
accessible detailed information about probable environmental consequences and potential mitigation
6
measures. Block, 690 F.2d at 761. This information must be conveyed within the EIS in plain
7
language so that the general public can “readily understand” the effects of the proposed plan. 40
8
C.F.R. § 1502.8. Relatedly, the EIS cannot merely assert a perfunctory description of mitigating
9
measures. Neighbors of Cuddy Mountain, 137 F.3d at 1380. “A mere listing of mitigation measures
is insufficient to qualify as the reasoned discussion required by NEPA.” Id. (quoting Northwest
11
For the Northern District of California
United States District Court
10
Indian Cemetery Protective Ass’n v. Peterson, 795 F.2d 688, 697 (9th Cir. 1986)). Rather,
12
mitigation must be detailed with enough specificity to “ensure that environmental consequences
13
have been fairly evaluated.” Carmel-By-the-Sea v. U.S. Dep’t of Transp., 123 F.3d 1142, 1154 (9th
14
Cir. 1997).
15
This specificity is required even when an agency is merely writing a programmatic EIS in
16
which “the precise contours of the proposed action ha[s] not yet been determined.” League to Save
17
Lake Tahoe v. Tahoe Regional Planning Agency, 739 F. Supp. 2d 1260, 1283 (E.D. Cal. 2010)
18
(citing N. Alaska Envtl. v. Kempthorne, 457 F.3d 966 (9th Cir. 2006), in which the Court determined
19
that even though the agency’s plan was not yet site-specific, the mitigation analysis necessarily
20
included a range of mitigating measures and their respective effectiveness)). An agency cannot,
21
therefore, avoid a detailed mitigation analysis simply by postponing it on the basis that the
22
“[f]easilibity and success of mitigation would depend on site specific conditions.” S. Fork Band
23
Council of W. Shoshone of Nevada v. United States Dep’t of Interior, 588 F.3d 718 (9th Cir. 2009)
24
(concluding that the EIS did not sufficiently address the mitigation measures related to groundwater
25
removal). Importantly, however, although at the programmatic stage an EIS must provide sufficient
26
detail “to foster informed decision-making [,]. . . site-specific impacts need not be fully evaluated”
27
until the agency decides to undertake a site-specific project. Norton, 348 F.3d at 800.
28
Finally, the Ninth Circuit has determined that, even though an agency need not actually
mitigate the identified harms, it must perform some assessment of whether the mitigation measures
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
17
1
would be effective. Id. at 727 (“An essential component of a reasonably complete mitigation
2
discussion is an assessment of whether the proposed mitigation measures can be effective.”). This
3
assessment must include “an estimate of how effective mitigation measures would be if adopted” or
4
a “reasoned explanation as to why such an estimate is not possible.” Neighbors of Cuddy Mountain,
5
137 F.3d at 1381. It must also provide supporting analytical data discussing the effectiveness of the
6
relevant mitigation measure. See Sierra Club v. Bosworth, 510 F.3d 1016, 1027 (9th Cir. 2007).
7
Here, the HSHA claims that the NPS violated NEPA by continuing to allow stock use at
8
current levels and by issuing Packer Permits, without taking the necessary hard look at the
9
environmental impacts of stock use. Specifically, it asserts that the NPS neglected to assess: (1) the
inadequacies of SEKI’s own mitigation measures; (2) stock contamination of water resources; (3)
11
For the Northern District of California
United States District Court
10
harm to native animal populations caused by stock use; (4) the introduction of invasive non-native
12
weeds via stock grazing; and (5) the aesthetic impact of stock. In response, the NPS asserts there is
13
no statutory or Ninth Circuit requirement to provide such detailed assessment. Rather, it insists that
14
such site-specific detailed analysis of impact and mitigation measures will be addressed in the
15
upcoming WSP as required in a properly tiered NEPA process.
16
a. The EIS’s Discussion of SEKI’s Mitigation Measures
17
The HSHA contends the NPS failed to assess the inadequacies of SEKI’s mitigation
18
measures. Specifically, the HSHA asserts that instead of conducting the requisite hard look
19
analysis, the NPS merely listed potential mitigation measures, focusing in detail on two measures
20
only: the temporary meadow closure program under the SUMMP and BMP and the Residual
21
Biomass Monitoring Program (“RBM”). Even with regard to these more detailed measures, the
22
HSHA insists that the NPS’s analysis is lacking; the agency neglected to take a hard look at how
23
both the temporary closure program and the RBM fail effectively to offset the adverse impacts of
24
stock use. The HSHA explains how both measures are ineffective. It first maintains that the
25
temporary meadow closure program is an ad hoc approach providing a remedy only after damage
26
has occurred. As a consequence, the NPS has never been forced to create a proactive system for
27
closing meadows at the point when the threshold for stock use is reached. The agency has therefore
28
not implemented a permanent closure since 1986. As an example, the HSHA refers to the McClure
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
18
1
Meadow which is still open for stock despite multiple recommendations from rangers that the area
2
should be closed to grazing animals.
3
The HSHA also addresses the inadequacies of the RBM. This program operates by
4
comparing the amount of above-ground plant material in ungrazed areas with that in grazed areas. It
5
is flawed, according to the HSHA, because it is subject to observer bias: the rangers collect data
6
through sight rather than through scientific analysis, SEKI staff are often unable to find a reference
7
plot that is wholly ungrazed, and the program does not consider either aesthetic or mechanical
8
impacts. The HSHA concludes that the NPS has overlooked the programs’ flaws and thereby
9
neglected its duty to take a hard look at potentially more effective mitigating measures.
The NPS maintains that the level of detail required with regard to mitigating measures must
11
For the Northern District of California
United States District Court
10
reflect the programmatic document at issue; the GMP’s discussion of mitigation is more than
12
sufficient. Additionally, the NPS explains that neither the temporary closure program nor the RBM
13
should be labeled inadequate. As to the temporary meadow closure program, the NPS asserts that
14
the document on which the HSHA relies for the proposition that a more proactive program for
15
meadow closure is needed, predated the GMP by eleven years. Within that period, according to the
16
NPS, SEKI has developed and implemented an adaptive and effective program for meadow
17
management. This program includes measures such as: (1) Management Directive (“MD”) 9,
18
adopted in 2003, which authorizes rangers to recommend timelines for opening and closing
19
meadows for grazing in order to provide for resource protection; (2) a letter from the SEKI
20
Superintendent outlining how best to implement SUMMP and BMP in order to provide an effective
21
method for protecting meadows; and (3) efforts by the Meadow Management Committee to meet
22
annually to analyze monitoring results, stock use reports, and staff directives in order to prevent
23
meadow harm before it occurs. The NPS insists these measures together sufficiently protect the
24
meadows. The HSHA is incorrect, therefore, in asserting that the temporary meadow closure
25
program provides relief only after damage occurs; rather, it appears to work in conjunction with
26
these other programs to prevent meadow damage.
27
28
As to the RMB program, the NPS maintains plaintiff’s objections are similarly unfounded.
It first asserts that the residual biomass estimation used by the program is a scientifically valid
indicator of meadow status “which warrants the greatest degree of judicial deference.” (Id. at 16)
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
19
1
(citing Lands Council v. McNair, 537 F.3d 981, 1000 (9th Cir. 2008)). It additionally states that the
2
RBM has been evaluated by the NPS-commissioned Abbott report which concluded that the
3
program produces “long-term databases capable of providing management with information that is
4
robust with respect to short-term fluctuations. Thus we recommend that the biomass monitoring be
5
continued, with refinements.” (GMP 0037548). From this language, the NPS concludes it justly
6
determined to utilize biomass monitoring until a more detailed analysis is conducted in the WSSUP.
7
Based on these assessments of the two mitigation measures, the NPS concludes that, for a
8
programmatic plan, the EIS at issue is more than sufficient.10
scope of the EIS at issue. The EIS and ROD repeatedly state that the purpose of the GMP is simply
11
For the Northern District of California
As the NPS accurately asserts, the level of detail required in a hard look analysis reflects the
10
United States District Court
9
to “provide management direction” and a “vision” for what SEKI should become in the future.
12
(GMP 0020243). The details of this vision are to be ironed out in subsequent WSPs as permitted
13
under the tiered NEPA method. The EIS clearly explains this tiered strategy to the public
14
throughout the document and more specifically in the section discussing mitigation measures. For
15
example, in response to a comment expressing concern as to a lack of such measures, the GMP
16
urges “[i]t is beyond the scope of this general management plan to analyze all the details of stock (or
17
hiker) use. A detailed analysis of stock and other wilderness activities will be conducted for the
18
future” WSSUP. (GMP 0020928).
19
10
20
21
22
23
24
25
26
27
28
The HSHA contends that even under programmatic plan standards, the GMP does not contain a
sufficient discussion of environmental impacts or potential mitigation measures. Plaintiff
emphasizes that the purpose of an EIS is to use plain language to inform the public of the agency’s
action. Thus, the NPS cannot just point to the entire administrative record and require both the
public and the Court to “hunt through nearly 52,000 pages of administrative record for evidence that
NPS took a hard look.” (Pl’s. Repl. to Cross-Mot. for Summ. J. at 17). To this effect, the HSHA
states that the GMP does not even mention MD 9, one of the measures cited by the NPS in its
briefings; to expect the public to search for MD 9 in an effort to uncover sufficient mitigating
measures defeats the purpose of the EIS. The HSHA is correct that an agency cannot fulfill NEPA’s
hard look requirement by presenting a discussion which is “so diffuse, scattered, or opaque that a
court must play Humpty Dumpty to put the [administrative] pieces together in a coherent fashion.”
Center for Environ. Law & Policy, 655 F.3d at 1009. An agency also fails to comply with NEPA by
merely listing mitigation measures, without further discussion. See Neighbors of Cuddy Mtn., 137
F.3d at 1380. Contrary to the HSHA’s assertions, however, the NPS has done neither of these
things. Rather, it simply postpones more detailed discussions until the WSSUP is complete. While
the NPS mitigation discussion and reliance on the administrative record would be deficient if the
EIS was site-specific, it meets the threshold for a programmatic EIS.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
20
1
The EIS also includes a generalized discussion of the mitigation measures as is appropriate
2
for a programmatic EIS. It mentions a number of continuing efforts such as “controlling access
3
based on soil moisture conditions, restricting use numbers, timing use and closing meadows to
4
grazing, improving trails . . . requesting weed-free feed, and continuing ongoing educational
5
efforts.” While, as the HSHA contends, this list appears to violate Neighbors of Cuddy Mountain by
6
merely mentioning mitigation measures without further explanation, the HSHA, in making this
7
contention, seemingly neglects to consider the mitigation discussion located in both the description
8
of the alternatives and the explanation of environmental impacts. Such a bifurcated discussion of
9
mitigation measures is permitted within a programmatic EIS. 40 C.F.R. §§ 1502.14(g) &
1502.16(h); see generally Center for Environ. Law & Policy, 655 F.3d at 1009 (emphasizing that “it
11
For the Northern District of California
United States District Court
10
would impermissibly elevate form over substance” to require the NEPA document to repeat its
12
cumulative effects analysis under a particular heading when it was adequately considered
13
throughout the extensive record).
14
Furthermore, subsequent to this generalized discussion of a number of mitigation measures,
15
the EIS describes the residual biomass process and how it works in conjunction with other plans.
16
Applying the rule of reason standard, the Court therefore cannot conclude that the NPS failed
17
adequately to take a hard look at the mitigation measures necessary for a programmatic guiding
18
document. At the time the GMP was prepared, MD 9, MD 38, and a number of other science-based
19
management techniques were in effect to assess the levels of current stock use. The fact that the
20
GMP did not implement any new stock use or alter the policy for issuing permits, means that a study
21
of mitigating measures for an increase in stock use is not yet necessary. These measures, however,
22
must be closely analyzed in a properly tailored study within the WSSUP. See Norton, 348 F.3d at
23
802 (permitting a broad programmatic EIS, but insisting that the NPS must “prepare appropriate
24
environmental review” for all “future actions” guided by the programmatic NEPA document).
25
26
b. The EIS’s Discussion of Water Resource Impacts
The HSHA next contends that the NPS failed to take the required hard look at impacts
27
resulting from the discharge of stock manure and urine. Instead, the HSHA maintains, the EIS
28
ignores the scientific reports indicating a relationship between stock use and water contamination.
Plaintiff specifically refers to a number of studies by Dr. Robert Derlet which allegedly demonstrate
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
21
mistaken in asserting that the agency failed to discuss mitigating measures for the impacts of stock
3
use on water resources. First, the NPS contends that in preparing the GMP it relied on a prior SEKI
4
plan specifically addressing water, the Aquatic/Water Resources Management Plan. According to
5
the NPS, this plan provides “the parks’ water resources information database and specific objectives
6
for managing aquatic and water resources.” (Defs’. Cross-Mot. for Summ. J. at 17). The NPS
7
issued the GMP knowing that these regulations were already in place. Furthermore, the NPS insists
8
that it did consider the Derlet reports in preparing the GMP. For support, defendants refer to the
9
EIS which discusses the 2004 study by Dr. Robert Derlet and Dr. James Carlson. (GMP 0020929).
10
The EIS explains that this study “failed to show any detectable correlation between increased water-
11
For the Northern District of California
the correlation between fecal matter in the water and grazing. The NPS counters that the HSHA is
2
United States District Court
1
borne pathogens and high-use stock areas.” (Id.). The EIS further insists that although there have
12
been complaints of stock discharge into streams, the “water quality is excellent when compared to
13
the standards in the Water Quality Control Plan for the Central Valley Regional Water Quality
14
Control Board.” Id. Despite this EIS discussion, the HSHA contends that the NPS did not
15
sufficiently consider all the Derlet studies—it only cited the 2004 study in the referenced portion. It
16
neglected, therefore, to incorporate Dr. Derlet’s 2006 study into the GMP which confirmed the
17
correlation between grazing and water contamination.
18
NEPA does not require courts to “decide whether an [EIS] is based on the best scientific
19
methodology available.” McNair, 537 F.3d at 1003 (quoting Friends of Endangered Species, Inc. v.
20
Jantzen, 760 F.2d 976, 986 (9th Cir. 1985)). Nor does it insist that courts resolve disagreements
21
between scientists as to methodology or outcome. See Jantzen, 760 F.2d at 986. Rather, the rule of
22
reason standard simply involves ensuring that the agency followed a procedure which “resulted in a
23
reasoned analysis of the evidence before it,” regardless of the outcome. Id.; see 5 U.S.C. §
24
706(2)(D); Lanthan v. Brinegar, 506 F.2d 677, 693 (9th Cir. 1974) (emphasizing that NEPA is a
25
procedural statute and that the adequacy of an EIS depends on whether it was prepared in
26
observance of proper procedures). Here, the NPS demonstrates that it considered at least the 1989
27
SEKI Water Resources Management Plan, the 2005 Water Resources Information and Issues
28
Overview Report, and the 2004 Derlet study in concluding that: (1) there are some reports of water
contamination, but water quality is excellent compared to the Central Valley standards; and (2) the
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
22
1
2004 study failed to establish a correlation between stock use and water contamination. These
2
conclusions, in addition to the agency’s promise to conduct a detailed water analysis in the WSP,
3
satisfy NEPA.11
c. The EIS’s Discussion of Native Animal Populations
4
The HSHA insists that the NPS also did not take the requisite hard look at damage to native
5
6
populations. Specifically, it maintains that the EIS neglected to assess the impacts and potential
7
mitigating measures with regard to the bighorn sheep, the mountain yellow-legged frog (“MYLF”),
8
and the Yosemite toad. According to plaintiff, evidence of this neglect is demonstrated by the U.S.
9
Fish & Wildlife Service’s (“USFWS”) determination that the Draft GMP did not provide sufficient
information regarding the potential impact on certain endangered species. The NPS does not
11
For the Northern District of California
United States District Court
10
dispute that the USFWS was “unable to concur” with a number of the NPS’s conclusions about
12
endangered species. (GMP 0021692). The NPS does however remark that the USFWS opinion is
13
of little importance to the determination of whether there is a NEPA violation because the USFWS
14
was commenting as to the Draft GMP. As a result of this comment, the NPS engaged in discussions
15
with the USFWS on November 5, 2004, which “resulted in an agreement that the NPS will complete
16
site-specific data collection at the project level to determine” if the project specific actions would
17
violate the Endangered Species Act. (GMP 0020915). To this effect, the NPS states that such a
18
tiered consultation approach is appropriate under the Act.
19
As to the specific species mentioned by the HSHA, the NPS further insists that it adequately
20
considered all impacts and mitigation measures for purposes of a programmatic document. The EIS
21
determined that the Preferred Alternative was not likely to result in adverse effects to the Sierra
22
Nevada bighorn sheep. There was consequently no need to consider a full scale mitigation plan.
23
The NPS arrived at this conclusion after the NPS wildlife biologist determined that the primary
24
threat to bighorn sheep was not the preferred alternative, but rather, predators, production of less-fit
25
lambs, domestic sheep presence, and a number of natural occurrences. The agency, in so
26
concluding, also considered the fact that recent monitoring reflected expanding sheep population
27
11
28
The mere fact that the HSHA can present a 2006 study by Dr. Derlet is insufficient to establish
that the NPS failed to take the requisite hard look at water contamination. This is especially the case
because the two parties interpret the study differently. The HSHA maintains that Dr. Derlet found a
correlation between water contamination and stock grazing while the NPS asserts that the study only
notes areas of stock use that are at risk of contamination.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
23
1
within SEKI. No need, therefore, arose for immediate mitigation measures. Rather, the NPS would
2
work with USFWS on future WSPs and instruct park managers to take precautions as necessary.
The HSHA contends that this analysis is insufficient because the decision in Sierra Hikers
3
informed the agency that bighorn sheep are displaced when stock approach sheep forage sites and
6
this displacement can lead to loss of essential nutrients. Plaintiff, however, cannot expect the NPS
7
to rely on the Kennedy decision for purposes of its hard look analysis because the decision has been
8
vacated. Instead, the Court must defer to the NPS’s determination that the bighorn sheep will not
9
likely be adversely affected by the EIS, particularly as the NPS represents it considered a number of
10
other sources in reaching its conclusion. See Jantzen, 760 F.2d at 986 (emphasizing that it was not
11
For the Northern District of California
Ass'n v. Kennedy, No. C–94–3570 CW, 1995 WL 382369, at *15 (N.D. Cal. June 14, 1995),
5
United States District Court
4
for the Court to assess an agency’s scientific methodology or to determine which expert opinion is
12
accurate).
The NPS further asserts that it sufficiently considered the impacts on the MYLF and the
13
14
Yosemite toad. After considering all the information available, the EIS determined that the
15
Preferred Alternative would not likely have an adverse effect on either amphibian. As to the MYLF,
16
the NPS examined the 2005 Water Resources Information and Issues Overview Report which
17
emphasized that the suspected primary cause of the species’ decline was the introduction of trout
18
and airborne contaminants. The NPS also considered the existing stock use restriction at Sixty
19
Lakes Basin, the location of one of the park’s largest remaining MYLF populations. As to the toad,
20
the NPS similarly scrutinized the 2005 Report which summarized various studies and concluded that
21
a number of factors contribute to the species’ decline; while these factors include grazing, the
22
Report mainly emphasized the threat posed by trout. To this point, the Report explained that the
23
NPS is developing long-term monitoring plans for amphibians which include wide-range surveys to
24
assess how best to preserve the species.12 Based on these scientific studies and the decision to
25
26
12
27
28
The HSHA points to a decision from this district that the Forest Service failed to provide
sufficient detail with regards to mitigation measures to protect the Yosemite toad. HSHA v.
Weingardt, 521 F. Supp. 2d 1065, 1087 (N.D. Ca. 2007). The HSHA maintains that in Weingardt,
the agency provided more detail than the EIS at issue here; thus, this EIS must also fail under NEPA
analysis. The analysis in Weingardt, however, is not controlling because the EIS in Weingardt was
a site-specific document while the EIS here is a programmatic one.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
24
1
cooperate with the USFWS to assess further impacts in the WSP, the NPS determined that no
2
specific mitigation measures need be adopted at the programmatic GMP stage.
3
The HSHA argues the NPS was aware chytrid fungus destroys MYLF populations and that
4
hoofs can carry such fungus into the park, but neglected sufficiently to discuss such impacts in
5
either the EIS or the 2005 Report. For support, the HSHA refers to two documents within the
6
record which mention the potential threat of the fungus on MYLF populations. These documents,
7
however, are insufficient to overcome the NPS’s assurances that it considered all impacts on
8
endangered species. One of plaintiff’s references is to a memo from a field ranger who, with no
9
scientific basis, concluded that chytrid fungus endangered MYLFs. The other is to one line in the
extensive 2004 SEKI Natural Resources Annual Report which states that the Sierra Nevada Aquatic
11
For the Northern District of California
United States District Court
10
Research Lab surveys “found continued decline of significant populations of mountain yellow-
12
legged frogs due to chytrid fungus.” (GMP 0039815). This negligible showing is insufficient to
13
demonstrate that for purposes of a programmatic EIS, the NPS acted capriciously in determining
14
that no further mitigation measures were required at the time of the GMP. Under the rule of reason
15
standard, the NPS took a hard look at the impacts on endangered species, identified the relevant
16
areas of concern, and reasonably decided that further site-specific analysis would be postponed to
17
the implementation stage.
18
19
d. The EIS’s Discussion of Invasive Weeds
The HSHA next asserts that the EIS overlooks documents in the record which demonstrate
20
that stock introduces harmful non-native weeds into SEKI. It thereby violated NEPA by neglecting
21
to assess environmental impacts or to consider potential mitigating measures such as no-grazing or
22
weed-free feed options. For support, plaintiff refers to a 1996 study from the Center for Water and
23
Windland Resources which determined that improper grazing methods “exacerbate the spread of
24
invasive weeds.” (GMP 0031645). Plaintiff also invokes the NPS’s own annual warnings that
25
weeds may be transported by stock. Finally, the HSHA mentions that the NPS’s own restoration
26
ecologist commented that more studies on invasive plants were necessary if stock use continued at
27
current levels. The HSHA contends the NPS ignored this research demonstrating the dangers of
28
stock use and weeds, and consequently failed to implement effective strategies.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
25
The NPS contests much of the HSHA’s argument. First, it insists that many of the
1
2
documents plaintiff relies on are either outdated or irrelevant to NEPA analysis. For example,
3
exhibit 70 refers to “east-side sagebrush steppe rangelands,” a condition not applicable to SEKI’s
4
ecosystems.13 Second, the NPS maintains the very fact that it issues annual warnings about weeds
5
to stock users demonstrates it has taken steps to mitigate the damage and inform the public of the
6
harms of weeds.14 Third, the NPS insists that it indeed has taken steps in response to the ecologist’s
7
recommendation invoked by the HSHA. Since that time, the agency has begun conducting early
8
detection surveys for non-native plants, trained wilderness rangers to recognize non-native plants,
9
and implemented programs to detect and treat non-native plants at Cedar Grove Pack Station and
trailheads frequented by stock animals. Lastly, the NPS claims that the EIS does more than merely
11
For the Northern District of California
United States District Court
10
list potential mitigation measures without addressing their effectiveness; rather, the EIS considered
12
the numerous SEKI plans in effect and determined that resulting use impacts stemming from the
13
Preferred Alternative “would likely be negligible to minor.” (GMP 0020604). This is because the
14
increased use would be confined to areas which already receive high to moderate levels of use. The
15
NPS therefore determined that no new mitigating measures were immediately necessary to address
16
such negligible impacts.15 The NPS further states that although it has not completed all possible
17
mitigation measures with regard to invasive plants, NEPA does not require mitigation; it simply
18
insists that agencies consider the impacts and inform the public of the harms associated with
19
invasive weeds.
Admittedly, the EIS fails to include a thorough discussion of invasive weeds despite the
20
21
documents in the record which attest to such dangers. As the NPS points out, however, many of the
22
documents identified are inapplicable in SEKI. Furthermore, the NPS is currently engaged in a
23
comprehensive plan to prevent an increase in the levels of non-native weeds; the agency fulfills its
24
13
25
26
27
28
The HSHA does not contest the NPS’s arguments with regards to the inapplicability of Exhibits
70, 71, or 72.
14
The NPS also insists that the HSHA improperly and selectively quotes from SEKI’s 1999 Natural
and Cultural Resources Management Plan. The NPS specifically objects to the truncated quotation
provided in plaintiff’s summary judgment motion stating that stock “provides a potential vector for
the introduction of exotic plants.” (GMP 0030635). Defendants maintain that this quote is taken
out of context because the entire plan demonstrates that many stressors, not just stock, affect the
levels of invasive weeds.
15
With regard to low use front-country areas, the EIS suggests “removing invasive plants” as a
management prescription to mitigate any impacts. (GMP 0020321).
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
26
1
burden of demonstrating the effectiveness of this plan throughout the paper discussing the Velvet
2
Grass in the Kern Canyon. (CUA 002267-68). With this plan in place, the NPS reasonably
3
concluded that the Preferred Alternative would have little to no new impact on vegetation. Whether
4
this conclusion is correct is not for the Court to decide: “NEPA itself does not mandate particular
5
results, but simply prescribes the necessary process.” Robertson, 490 U.S. at 350.
6
As a further note, the HSHA places much emphasis on the fact that the EIS suggests a
7
potential mitigation measure of removing invasive species in front-country areas, insisting that such
8
a “listing” contravenes the Ninth Circuit’s holding in Neighbors of Cuddy Mountain. This,
9
however, is an inaccurate characterization of the EIS. The GMP mentions the measure simply to
provide a management prescription to be considered in the WSP. At the time the GMP was
11
For the Northern District of California
United States District Court
10
prepared, the NPS had already determined that mitigation measures were unnecessary for invasive
12
weeds; the effects of stock use and invasive weeds were being addressed elsewhere and this EIS
13
would have “negligible” impact on these weeds. Consequently, the mention of invasive weeds in
14
the EIS combined with the NPS’s active program to educate the public and to combat the invasion
15
of non-native plants satisfies the agency’s NEPA obligations.
16
e. The EIS’s Discussion of Aesthetic Impacts
17
The HSHA asserts that the NPS failed to take a hard look at the impacts of stock use on
18
aesthetics and opportunities for spiritual refreshment. It claims that the NPS was put on notice of
19
these impacts from a number of documents which span a period of twenty-five years: (1) a 1989
20
Chief Ranger memo requesting further consideration of stock effects on aesthetics; (2) an undated
21
letter from a park visitor who complained of the dust from stock animals; and (3) two letters
22
expressing displeasure with stock use in the park and describing the impacts of such use on the park
23
experience. Despite these documents, the HSHA contends that the NPS made no attempt to
24
evaluate the impacts or adopt mitigation measures, thereby, rendering the procedural requirements
25
of NEPA meaningless. The NPS recognizes that it received a number of letters objecting to stock
26
use and complaining of the aesthetic impact of animals in the park. It explains, however, that the
27
Draft GMP also garnered numerous comments from visitors and organizations demanding increased
28
stock use and asserting that they could only appreciate the aesthetic beauty of the park if stock was
permitted. The NPS responded to all of these comments on both sides of the argument and took
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
27
1
them into account in preparing the EIS. In crafting it, the agency also considered evidence
2
demonstrating: (1) that stock use had declined in the past five years; and (2) the existence of
3
ongoing attempts to facilitate communication and cooperation between backpackers and stock users.
4
After evaluating all of this evidence, the EIS concluded that the impact of stock use “would continue
5
to cause minor, adverse, long-term impacts to some backcountry hikers, but increased regulation and
6
stock-free areas which would be determined in the forthcoming wilderness stewardship and stock
7
use plan, would mitigate this impact.” (GMP 0020762). In other words it determined that based on
8
the programmatic nature of the EIS and the fact that stock use would remain at current levels, there
9
was no need currently for further debate over aesthetic impacts.
The HSHA maintains that this determination was both arbitrary and capricious. In fact, the
11
For the Northern District of California
United States District Court
10
HSHA asserts that it has for years requested that the NPS create a system of foot only trails. The
12
agency has repeatedly denied this request, closing to stock only two short trail segments which are
13
difficult to access, the Whitney and Sawtooth trails. The HSHA’s arguments, however, are
14
insufficient to demonstrate that the NPS should have taken a harder look. First, the simple fact that
15
the HSHA disagrees with the merits of the NPS’s conclusions of where to provide stock free trails is
16
immaterial to NEPA analysis. Robertson, 490 U.S. at 351; Sierra Club v. Kimbell, 623 F.3d 549,
17
561 (8th Cir. 2010) (“Although Sierra Club may disagree with the merits of the Forest Service's
18
conclusion, the agency's discussion demonstrates that it made an informed decision, and NEPA
19
requires nothing more.”). Second, the HSHA’s objections as to the two specific trails are
20
inappropriate for a programmatic EIS. As defendants indicate, analysis as to access to individual
21
trails is more appropriate for the upcoming site-specific EIS. Based on the record, the agency’s
22
analysis is sufficient to demonstrate the type of NEPA compliance necessary for a programmatic
23
EIS and its conclusion is neither arbitrary nor capricious.
24
5. Issuance of Annual Packer Permits
25
The HSHA asserts that the NPS improperly relied on the SUMMP, BMP, GMP or
26
categorical exclusions to issue Packer Permits. The HSHA explains the NPS initially represented
27
that further NEPA compliance was necessary before it would issue or renew Packer Permits. This
28
representation was based on the agency’s belief that more stringent environmental policies were
necessary to regulate stock permits and that the SUMMP and BMP were outdated. Despite these
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
28
that further “review and consultation demonstrated to us that the compliance conducted in the mid-
3
1980s [in the SUMMP and BMP], and their accompanying Environmental Assessments was
4
appropriate and is still valid.” (GMP 0021311). According to the HSHA, this reversal was
5
improper because NPS cannot depend on EAs conducted over twenty years ago to meet its NEPA
6
obligations; rather it must take a hard look at the impact of Packer Permits now before issuing or
7
renewing any further Permits. As per the NPS’s own concession, this hard look will not be
8
completed until the upcoming WSP. Furthermore, the HSHA argues that the NPS cannot rely in the
9
alternative, on categorical exclusions to issue the permits. This is because the use of such
10
exclusions is limited solely to situations where there has been an insignificant or limited
11
For the Northern District of California
assurances, the NPS backtracked on this promise to stay the issuance of new permits in 2005, stating
2
United States District Court
1
environmental effect. Packer Permits, insists the HSHA, undoubtedly have a significant effect.
12
The NPS asserts that is has fully complied with NEPA both in relying on the SUMMP, BMP
13
and GMP to issue permits, and in taking the additional step of providing environmental review
14
through the categorical exclusion process. It insists that the 2009 CUAs and Contract Extension
15
were issued pursuant to: (1) the 2007 GMP which had an EIS level of review for purposes of
16
maintaining stock use at current levels; and (2) the SUMMP and BMP which were both
17
accompanied by EA level NEPA reviews. These documents contain sufficient environmental
18
review regarding current stock levels to permit the agency to continue issuing permits, at these same
19
levels, until the completion of the upcoming WSP.
20
The HSHA bases much of its argument on the contention that both the SUMMP and BMP
21
are outdated and therefore cannot be relied upon for NEPA compliance. In support, plaintiff refers
22
to documents in the record which note that the plans are either outdated or in need of revision.
23
Some of these documents were propounded by SEKI employees themselves. For example, in 2001,
24
SEKI’s Plant Ecologist, in an informal email, stated that the SUMMP was “overdue for revision.”
25
(GMP 0016740). Notably, however, within this same document the ecologist attached the SUMMP
26
for reference and explained that the plan “does a good job of lining up what we are doing where and
27
why.” (GMP 0016739). Additionally, contrary to the HSHA’s assertions, the mere fact that some
28
staff and community members were concerned that the previous EAs were out-dated, does not
preclude the NPS from altering its position and deciding to retain stock use at current levels for the
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
29
1
time being. In fact, the NPS did comply with the proper procedures. As to the SUMMP and BMP
2
the agency did backtrack, but only after determining based on “review and consultation” that the
3
EAs in both plans were fully NEPA compliant and “still valid.” (GMP 0021311). In so
4
determining, the agency acknowledged its prior misstatements and concluded that pursuant to the
5
EAs of the SUMMP and BMP, it planned “on continuing to issue the permits in the same manner
6
until such time as we are able to conduct more extensive review and analysis of this activity during
7
the development and implementation of a Wilderness Stewardship Plan.”16 (GMP 0021311).
Furthermore, as to the GMP, the NPS conducted a full EIS. Based on this EIS, the NPS
8
9
concluded that until the WSP, stock use should not be increased but remain at current levels—
thereby permitting the issuance of Packer Permits at these levels. The HSHA insists that the NPS
11
For the Northern District of California
United States District Court
10
has repeatedly maintained the GMP is a programmatic document, lacking a detailed assessment as
12
to stock use and thus, by the NPS’s own concession, cannot be relied on to issue Packer Permits.
13
The HSHA further insists that the NPS has “admitted that the GMP does not contain a detailed
14
environmental assessment of stock use,” referring to a memo from the SEKI Superintendent. (GMP
15
003268). This memo, however, does not support the assertion the HSHA suggests. Rather, the
16
memo simply states that while GMP would continue current stock use, the upcoming WSSUP
17
would more specifically “address grazing, monitoring and capacity-related issues for stock.” (CUA
18
0003268). Notably, this memo also provides, with regards to Packer Permits, that the SUMMP and
19
BMP “have established a system of adaptive management standards based on monitoring and
20
analysis of field conditions . . . . This system has proven to be effective in protecting resources.”
21
(CUA 0003268). Based on the administrative record, the HSHA is unable to demonstrate a
22
substantive basis for the conclusion that the EAs for the SUMMP and BMP are outdated. The NPS,
23
therefore, did not violate NEPA in continuing to issue Packer Permits at current levels pursuant to
24
the environmental findings in the older plans and in the GMP.17
25
16
26
27
28
The HSHA objects to the agency’s conclusion, stating it could not possibly have determined that
the prior EAs were sufficient after the requisite hard look; it must have therefore failed to comply
with the hard look requirement. In support of this contention, the HSHA repeatedly invokes the
vacated decision in Kennedy, 1995 WL 382369, which stated that “the SUMMP and the BMP
allowed unacceptable impacts to the parks’ natural resources.” (Pl’s. Mot. for Summ. J. at 23). The
HSHA cannot, however, rely on this vacated order even for factual background.
17
As an alternative basis to justify the Packer Permits, the NPS maintains that it provided additional
environmental review through a categorical exclusion. As stated above, the HSHA maintains that
such exclusions are inappropriate because the Packer Permits had significant effects on the
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
30
IV. CONCLUSION
1
2
Plaintiff’s motion for summary judgment is granted as to the Wilderness Act. Defendants’
3
cross-motion for summary judgment is granted as to the NEPA claim. A Further Case Management
4
Conference is set for March 1, 2012, at which the parties should be prepared to discuss scheduling
5
further proceedings on the issue of remedy.
6
7
IT IS SO ORDERED.
8
9
RICHARD SEEBORG
UNITED STATES DISTRICT JUDGE
11
For the Northern District of California
United States District Court
10
Dated: 1/24/12
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
environment. The NPS argues, however, that exclusions are permitted for actions which did not
entail potential for environmental impact which was not already reviewed under the EAs or the EIS.
The SEKI Superintendent determined that the Packer Permits for 2008 and 2009 “involve[ed] no
construction or potential for new environmental impact” and were therefore entitled to categorical
exclusions. (CUA 002323-2347; CUA 002348-2359). Because the NPS demonstrated NEPA
compliance in relying on the SUMMP, BMP, and GMP in issuing permits, the Court need not assess
whether categorical exclusions were appropriate for these permits.
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT
31
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?