STIPULATION AND ORDER RE 74 TO AMDEND CLAIM CONSTRUCTION SCHEDULE. Claim Construction Hearing set for 2/24/2012 10:00 AM. Tutorial Hearing set for 2/22/2012 10:00 AM in Courtroom 3, 17th Floor, San Francisco.Signed by Judge Richard Seeborg on 12/14/11. (cl, COURT STAFF) (Filed on 12/14/2011)
*E-Filed 12/14/11*
1
2
3
4
5
6
7
Daniel Johnson, Jr. (State Bar No. 57409)
Michael J. Lyons (State Bar No. 202284)
Dion M. Bregman (State Bar No. 208393)
Ahren C. Hsu-Hoffman (State Bar No. 250469)
MORGAN, LEWIS & BOCKIUS LLP
2 Palo Alto Square
3000 El Camino Real, Suite 700
Palo Alto, CA 94306-2122
Tel: 650.843.4000
Fax: 650.843.4001
E-mail: djjohnson@morganlewis.com
E-mail: mlyons@morganlewis.com
E-mail: dbregman@morganlewis.com
E-mail: ahsu-hoffman@morganlewis.com
THOMAS J. FRIEL, JR. (SBN 80065)
101 California Street, 5th Floor
San Francisco, CA 94111-5800
Tel.: 415.693.2000
Fax: 415.693.2222
E-mail: tfriel@cooley.com
Attorneys for Plaintiff
FINISAR CORPORATION
SARAH J. GUSKE (SBN 232467)
WAYNE O. STACY (pro hac vice)
380 Interlocken Crescent, Suite 900
Broomfield, CO 80021-8023
Tel.: 720.566.5000
Fax: 720.566.4099
E-mail: sguske@cooley.com
E-mail: wstacy@cooley.com
MARK T. SMITH (SBN 260845)
Five Palo Alto Square
3000 El Camino Real
Palo Alto, CA 94306
Tel.: 650.843.5122
Fax: 650.857.0663
E-mail: msmith@cooley.com
8
9
10
11
12
13
Attorneys for Defendants
OPLINK COMMUNICATIONS, INC.,
and
OPTICAL COMMUNICATION
PRODUCTS, INC
14
15
16
UNITED STATES DISTRICT COURT
17
NORTHERN DISTRICT OF CALIFORNIA
18
SAN FRANCISCO DIVISION
19
20
CASE NO. 3:10-cv-05617 RS
FINISAR CORPORATION,
21
Plaintiff,
22
v.
STIPULATION AND [PROPOSED]
ORDER TO AMEND CLAIM
CONSTRUCTION SCHEDULE UNDER
CIV. L.R. 6-2
23
24
OPLINK COMMUNICATIONS INC.,
OPTICAL COMMUNICATION
PRODUCTS, INC.,
25
Defendants.
26
27
28
M ORGAN , L EWIS &
B OCKIUS LLP
ATTORNEYS AT LAW
PALO ALTO
STIPULATION TO AMEND CLAIM CONSTRUCTION
SCHEDULE; CASE NO. 3:10-CV-05617 RS
1
Plaintiff FINISAR CORPORATION (“Finisar”) and Defendants OPLINK
2
COMMUNICATIONS INC., OPTICAL COMMUNICATION PRODUCTS, INC. (“Oplink”), by
3
and through their respective counsel, hereby submit, pursuant to Civil L.R. 6-1(b), 6-2 and 7-12,
4
this stipulated and agreed request that the Court delay the Claim Construction Briefing Schedule
5
by two weeks.
6
7
WHEREAS the parties participated in Court-ordered mediation before Mr. Wulff on
November 30, 2011;
8
9
WHEREAS the parties are continuing to participate in good faith in continuing, active
negotiations towards a settlement;
10
11
WHEREAS the parties believe in good faith that this litigation may be settled within the
next two weeks;
12
13
WHEREAS the Court issued its Amended Joint Schedule and Order (Docket No. 54) on
August 2, 2011 (the “Scheduling Order”);
14
15
WHEREAS the Court issued a Stipulation and Order to Amend Claim Construction
Schedule Under Civ. L.R. 6-2 on December 1, 2011;
16
17
WHEREAS the Stipulation and Order requires Finisar to file its Patent L.R. 4-5(a)
Opening Claim Construction Brief on December 14, 2011;
18
19
WHEREAS the Stipulation and Order requires Oplink to file its Patent L.R. 4-5(b)
Responsive Claim Construction Brief on January 4, 2011;
20
21
WHEREAS the Stipulation and Order requires Finisar to file its Patent L.R. 4-5(c) Reply
Claim Construction Brief on January 11, 2011;
22
WHEREAS the Stipulation and Order set a tutorial for the Court on January 18, 2012;
23
WHEREAS the Stipulation and Order set the Claim Construction Hearing on January 20,
24
25
26
27
28
M ORGAN , L EWIS &
B OCKIUS LLP
ATTORNEYS AT LAW
PALO ALTO
2012;
WHEREAS the requested time modification will have minimal effect on any other
scheduled dates;
WHEREAS the parties agree that delaying the claim construction briefing schedule by
about two weeks may prevent unnecessary expense, promote judicial economy, and increase the
1
STIPULATION TO AMEND CLAIM CONSTRUCTION
SCHEDULE; CASE NO. 3:10-CV-05617 RS
1
likelihood of an extra-judicial settlement in this litigation;
2
IT IS HEREBY STIPULATED AND AGREED:
3
Subject to the Court’s approval, the Scheduling Order shall be amended as follows:
4
5
Patent L.R. 4-5(a) Opening Claim Construction Brief
January 6, 2012
6
Patent L.R. 4-5(b) Responsive Claim Construction Brief
January 20, 2012
7
Patent L.R. 4-5(c) Reply Claim Construction Brief
January 27, 2012
8
Tutorial
February 15, 2012 (Court’s schedule
February 22, 2012 at 10:00 am
permitting)
Claim Construction Hearing
February 17, 2012 (Court’s schedule
February 24, 2012 at 10:00 am
permitting)
9
10
11
12
Dated: December 14, 2011
RESPECTFULLY SUBMITTED,
13
MORGAN, LEWIS & BOCKIUS LLP
14
15
By /s/ Michael J. Lyons
Michael J. Lyons
Attorneys for Plaintiff
FINISAR CORPORATION
16
17
18
I, Michael J. Lyons, am the ECF User whose ID and password are being used to file this
19
STIPULATION AND [PROPOSED] ORDER. In compliance with General Order 45, X.B., I
20
hereby attest that the signatory identified below has concurred in this filing.
21
22
Dated: December 14, 2011
COOLEY LLP
23
By /s/ Sarah Guske
Sarah Guske
Attorneys for Defendant
OPLINK COMMUNICATIONS INC.,
OPTICAL COMMUNICATION
PRODUCTS, INC.,
24
25
26
27
28
M ORGAN , L EWIS &
B OCKIUS LLP
ATTORNEYS AT LAW
PALO ALTO
2
STIPULATION TO AMEND CLAIM CONSTRUCTION
SCHEDULE; CASE NO. 3:10-CV-05617 RS
1
2
3
4
ORDER
PURSUANT TO STIPULATION, IT IS SO ORDERED:
That the Stipulation and [Proposed] Order To Amend Claim Construction Schedule Under
Civ. L.R. 6-2 is hereby adopted by the Court. The parties shall comply with this Order.
5
6
12/14
Dated: ________________, 2011
HON. RICHARD SEEBORG
UNITED STATES DISTRICT JUDGE
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
M ORGAN , L EWIS &
B OCKIUS LLP
ATTORNEYS AT LAW
PALO ALTO
3
STIPULATION TO AMEND CLAIM CONSTRUCTION
SCHEDULE; CASE NO. 3:10-CV-05617 RS
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?