STIPULATION AND ORDER EXTENDING TIME TO ANSWER re 115 Stipulation, filed by Southwestern Power Group II, LLC, MMR Power Solutions, LLC, MMR Group Inc. Signed by Judge Edward M. Chen on 12/19/11. (bpf, COURT STAFF) (Filed on 12/19/2011)
1
2
3
4
5
6
7
8
9
10
11
12
13
Jerry L. Marks (SBN 135395)
Email: jmarks@milbank.com
Aaron Renenger (SBN 222675)
Email: arenenger@milbank.com
MILBANK, TWEED, HADLEY & McCLOY LLP
601 S. Figueroa Street, 30th Floor
Los Angeles, California 90017
Telephone: (213) 892-4000
Facsimile: (213) 629-5063
David R. Gelfand (admitted pro hac vice)
Email: dgelfand@milbank.com
Rachel Penski Fissell (admitted pro hac vice)
Email: rfissell@milbank.com
MILBANK, TWEED, HADLEY & McCLOY LLP
1 Chase Manhattan Plaza
New York, NY 10005
Telephone: (212) 530-5000
Facsimile: (212) 822-5661
Attorneys for Defendants STA Development, LLC,
Solar Trust of America, LLC, Solar Millennium, Inc.,
CA I-10 Solar, LLC, Palo Verde Solar I, LLC,
Palo Verde Solar II, LLC, Blythe Solar Power Project
Unit 1, LLC, Blythe Solar Power Project Unit 2, LLC,
Blythe Solar Power Project Unit 3, LLC and
Blythe Solar Power Project Unit 4, LLC
14
15
UNITED STATES DISTRICT COURT
16
NORTHERN DISTRICT OF CALIFORNIA
17
SAN FRANCISCO DIVISION
19
MMR GROUP, INC.,
MMR POWER SOLUTIONS, LLC and
SOUTHWESTERN POWER GROUP II, LLC,
20
Plaintiffs,
18
21
22
23
24
25
26
27
28
vs.
STA DEVELOPMENT, LLC (F/K/A SOLAR
MILLENNIUM, LLC), SOLAR TRUST OF
AMERICA, LLC, SOLAR MILLENNIUM AG,
SOLAR MILLENNIUM, INC., CA I-10
SOLAR, LLC, PALO VERDE SOLAR I, LLC,
PALO VERDE SOLAR II, LLC, BLYTHE
SOLAR POWER PROJECT UNIT 1, LLC,
BLYTHE SOLAR POWER PROJECT UNIT 2,
LLC, BLYTHE SOLAR POWER PROJECT
UNIT 3, LLC AND BLY,THE SOLAR POWER
PROJECT UNIT 4, LLC
Defendants.
Case No. 3:11-cv-01521-EMC
CORRECTED FIFTH STIPULATION
TO EXTEND DEFENDANTS’ TIME
TO RESPOND TO AMENDED
COMPLAINT AND [PROPOSED]
ORDER
The Honorable Judge
Edward M. Chen
CORRECTED FIFTH STIPULATION TO EXTEND DEFENDANTS’ TIME TO RESPOND TO AMENDED
COMPLAINT
1
2
STIPULATION
Plaintiffs MMR GROUP, INC., MMR POWER SOLUTIONS, LLC and
3
SOUTHWESTERN POWER GROUP II, LLC (collectively, “MMR”) and Defendants STA
4
DEVELOPMENT, LLC, SOLAR TRUST OF AMERICA, LLC, SOLAR MILLENNIUM, INC.,
5
CA I-10 SOLAR, LLC, PALO VERDE SOLAR I, LLC, PALO VERDE SOLAR II, LLC,
6
BLYTHE SOLAR POWER PROJECT UNIT 1, LLC, BLYTHE SOLAR POWER PROJECT
7
UNIT 2, LLC, BLYTHE SOLAR POWER PROJECT UNIT 3, LLC AND BLYTHE SOLAR
8
POWER PROJECT UNIT 4, LLC (collectively, the “STAD Defendants”) respectfully request
9
that the Court extend the time for the STAD Defendants to respond to the Amended Complaint,
10
filed on October 4, 2011 (ECF No. 102) and served on the STAD Defendants on October 7, 2011,
11
by eight days from December 19, 2011 to December 27, 2012.
12
On November 4th and 14th, the parties requested, and this Court later granted, a one-week
13
extension of time for the STAD Defendants to respond to the Amended Complaint because the
14
parties were in advanced stages of settlement discussions. On November 22nd and December 1st,
15
the parties requested, and this Court later granted, extensions of two weeks due to continued
16
progress in settlement negotiations. The timing of finalizing a settlement has been impacted by
17
several complex factors, but the parties continue to be hopeful that they will execute a settlement
18
agreement forthwith. Due to the upcoming holidays and the continued progress in reaching a
19
settlement, the parties request an eight day extension of the time for the STAD Defendants to
20
respond to the Amended Complaint. The parties’ request will have a de minimis, if any, impact
21
on the schedule. In the interests of judicial economy, the parties therefore request that Court
22
extend the STAD Defendants’ time to respond to the Amended Complaint by eight days from
23
December 19, 2011 to December 27, 2012.
24
25
26
27
28
1
CORRECTED FIFTH STIPULATION TO EXTEND TIME TO RESPOND TO AMENDED COMPLAINT AND
[PROPOSED] ORDER
1
MILBANK, TWEED, HADLEY & McCLOY LLP
Dated: December 19, 2011
2
By: /s/ Rachel Penski Fissell
Jerry L. Marks (SBN 135395)
Aaron Renenger (SBN 222675)
601 S. Figueroa Street, 30th Floor
Los Angeles, California 90017
Telephone: (213) 892-4000
Facsimile: (213) 629-5063
3
4
5
6
David R. Gelfand (admitted pro hac vice)
Rachel Penski Fissell (admitted pro hac vice)
1 Chase Manhattan Plaza
New York, NY 10005
Telephone: (212) 530-5000
Facsimile: (212) 822-5661
7
8
9
Attorneys for Defendants STA Development, LLC,
Solar Trust of America, LLC, Solar Millennium, Inc.,
CA I-10 Solar, LLC, Palo Verde Solar I, LLC,
Palo Verde Solar II, LLC, Blythe Solar Power Project
Unit 1, LLC, Blythe Solar Power Project Unit 2, LLC,
Blythe Solar Power Project Unit 3, LLC and
Blythe Solar Power Project Unit 4, LLC
10
11
12
13
14
Dated: December 19, 2011
15
16
WATT, TIEDER, HOFFAR
& FITZGERALD, LLP
By: /s/ Nicholas A. Merrell
Bennett J. Lee (CA Bar No. 230482)
Nicholas A. Merrell (CA Bar No. 240795)
Regina A. Verducci (CA Bar No. 264996)
333 Bush Street, Suite 1500
San Francisco, CA 94104
Telephone: 415-623-7000
Facsimile: 415-623-7001
17
18
19
20
21
Attorneys for Plaintiffs MMR Group, Inc., MMR Power
Solutions, LLC and Southwestern Power Group II, LLC
23
12/19/11
Dated: ______________________
ERED
O ORDJUDGE
UNITED STATES DISTRICT COURT
IT IS S
27
hen
rd M. C
NO
H
ER
LI
RT
2
dwa
Judge E
A
28
R NIA
26
UNIT
ED
25
S
PURSUANT TO STIPULATION, IT IS SO ORDERED.
RT
U
O
24
S DISTRICT
TE
C
TA
FO
22
C
OF
D I S T ICOMPLAINT AND
CORRECTED FIFTH STIPULATION TO EXTEND TIME TO RESPOND TO AMENDED C T
R
[PROPOSED] ORDER
N
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?