Colorado and Santa Fe Energy Company, LLC et al-v-Nexant, Inc.
Filing
34
ORDER by Judge Jeffrey S. White GRANTING 13 Motion to Dismiss, with leave to amend. (jswlc3, COURT STAFF) (Filed on 9/25/2012)
1
2
3
4
5
NOT FOR CITATION
6
IN THE UNITED STATES DISTRICT COURT
7
FOR THE NORTHERN DISTRICT OF CALIFORNIA
8
9
COLORADO AND SANTA FE ENERGY
COMPANY, LLC,
10
No. C 12-00011 JSW
11
ORDER GRANTING MOTION TO
DISMISS WITH LEAVE TO
AMEND
v.
For the Northern District of California
United States District Court
Plaintiff,
12
NEXANT, INC.,
13
Defendant.
14
/
15
16
INTRODUCTION
17
This matter comes before the Court upon consideration of the Motion to Dismiss, filed
18
by Defendant Nexant, Inc. (“Nexant”). The Court has considered the parties’ papers, relevant
19
legal authority, and the record in this case, and has had the benefit of oral argument. The Court
20
HEREBY GRANTS Nexant’s motion.1
BACKGROUND
21
The following facts are taken from the Complaint and, for purposes of this motion, are
22
23
accepted as true, unless otherwise noted. Plaintiff, Colorado and Santa Fe Energy Company,
24
LLC (“Colorado”), has an ownership interest in and is a managing member of the Fossil Gulch
25
Facility, a renewable energy facility. For each megawatt hour (“MWh”) of energy it creates,
26
the Fossil Gulch Facility also creates a “Renewable Energy Credit (“REC”).” (Compl. ¶¶ 7-8.)
27
28
Plaintiff’s opposition includes footnote text that does not comply with
Northern District Civil Local Rule 3-4(c)(2). The Court places all parties on notice that,
in the future, it shall strike non-conforming briefs.
1
1
“RECs are non-tangible energy commodities that may be sold to marketers, brokers or asset
2
managers who then resell them at a later date.” (Id. ¶ 9.)
3
On September 8, 2012, Colorado and Nexant entered into a Renewable Energy
4
Certificate Master Sales Agreement, which is governed by California law. (Compl. ¶ 11, Ex. 1
5
(Master Agreement § 18).) Pursuant to the Master Agreement, Colorado agreed to sell RECs to
6
Nexant for an initial five (5) year period. The parties also contemplated that they would enter
7
subsequent Sales Order Agreements during this term. (Compl. ¶¶ 11, 13; Master Agreement §
8
2.) The terms of the Master Agreement provide that Colorado can deliver the RECs to Nexant
9
either by: (1) a commercial tracking system; or (2) a signed Renewable Generator Attestation.
(Master Agreement § 5.) The parties provided that “[i]f the Delivery Method is a tracking
11
For the Northern District of California
United States District Court
10
system, Delivery shall be deemed completed once electronic delivery is made into Nexant’s
12
account in accordance with the operating rules of the system.” (Id.)
13
The parties also provided that the “Contract Quantity associated with each Sales Order
14
Agreement shall be delivered by [Colorado] to Nexant during the Delivery Period identified in
15
the Sales Order Agreement (“Delivery Period”). Delivery shall be deemed completed when
16
[Colorado] delivers the Contract Quantity to Nexant by the Delivery Method defined in the
17
Sales Order Agreement.” (Id.) In addition to identifying the Delivery Method, the Sales Order
18
Agreement also would identify: (1) the time frame during which the RECs would be
19
accumulated (“Production Period”); (2) the quantity of RECs to be delivered (“Contract
20
Quantity”); and (3) the price Nexant agreed to pay for each REC delivered. (Compl. ¶ 14;
21
Master Agreement 2.)
22
The parties executed the first Sales Order Agreement on September 8, 2010. (Compl.
23
¶ 15, Ex. 2 (“September Sales Order”).) It reflects that: (1) the Production Period is January 1,
24
2011 through December 23, 2011; (2) that the Delivery Method is “WREGIS,” which stands for
25
Western Renewable Energy Generation Information System; (3) the Delivery Period would be
26
“on or before” April 15, 2011, July 15, 2011, October 15, 2011, and January 15, 2012; (4) the
27
Contract Quantity was “100% of output from” the Fossil Gulch Facility; and (4) the Base Price
28
would be $8.00 per MWh. (Compl. ¶ 19, Ex. 2.)
2
1
According to Colorado, “[p]ursuant to the Operating Rules of WREGIS, specifically
2
Rule 12.2, ninety (90) days after the end of each generation month, the WREGIS system created
3
RECs for the” megawatt hours of electricity produced by the Fossil Gulch Facility in that
4
generation month. The RECs, once created, were then available for delivery to Nexant.”
5
(Compl. ¶ 20.)
6
On or about May 24, 2011, Colorado logged in to the WREGIS system and transferred
7
to Nexant all RECs that had been created since January 1, 2011. On May 26, 2011, Nexant
8
rejected delivery. (Compl. ¶¶ 22-23.) Colorado alleges that Nexant did not notify it of the
9
rejection until June 16, 2011. Nexant then informed Colorado that it would not accept delivery
of the RECs via WREGIS, because that system would not deliver the RECs within the fifteen
11
For the Northern District of California
United States District Court
10
day period prescribed by the September Sales Order. (Id. ¶ 25.) In response, on July 7, 2011,
12
Colorado delivered the RECs generated in the second fiscal quarter by a signed attestation. (Id.
13
¶ 26.) Nexant also rejected that delivery, on the basis that it was not made via WREGIS. (Id.
14
¶ 27.)
15
Colorado alleges that it “has fully performed all terms, conditions, covenants, and
16
promises of the Master Agreement and September Sales Order, except to the extent that it has
17
been prevented or excused from performing by the acts of Nexant or others.” (Compl. ¶ 32.)
18
To date, Nexant has failed to take delivery of approximately 17,477 RECs for the year 2011,
19
resulting in damages of not less than $139,816.00. (Id. ¶¶ 28, 33-34.) Based on these and other
20
allegations, Colorado brings claims for breach of contract and breach of the implied covenant of
21
good faith and fair dealing.
22
23
24
ANALYSIS
A.
Applicable Legal Standard.
A motion to dismiss is proper under Federal Rule of Civil Procedure 12(b)(6) where the
25
pleadings fail to state a claim upon which relief can be granted. The complaint is construed in
26
the light most favorable to the non-moving party and all material allegations in the complaint
27
are taken to be true. Sanders v. Kennedy, 794 F.2d 478, 481 (9th Cir. 1986). However, even
28
under the liberal pleading standard of Federal Rule of Civil Procedure 8(a)(2), “a plaintiff’s
3
1
obligation to provide the ‘grounds’ of his ‘entitle[ment] to relief’ requires more than labels and
2
conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Bell
3
Atlantic Corp. v. Twombly, 550 U.S. 544, 555 (2007) (citing Papasan v. Allain, 478 U.S. 265,
4
286 (1986)). If the allegations are insufficient to state a claim, a court should grant leave to
5
amend, unless amendment would be futile. See, e.g., Reddy v. Litton Indus., Inc., 912 F.2d 291,
6
296 (9th Cir. 1990); Cook, Perkiss & Liehe, Inc. v. N. Cal. Collection Serv., Inc., 911 F.2d 242,
7
246-47 (9th Cir. 1990).
8
As a general rule, “a district court may not consider any material beyond the pleadings
overruled on other grounds by Galbraith v. County of Santa Clara, 307 F.3d 1119 (9th Cir.
11
For the Northern District of California
in ruling on a Rule 12(b)(6) motion.” Branch v. Tunnell, 14 F.3d 449, 453 (9th Cir. 1994),
10
United States District Court
9
2002) (citation omitted). However, the Court may consider documents attached to the
12
complaint, documents relied upon but not attached to the complaint, when the authenticity of
13
those documents is not questioned, and other matters of which the Court can take judicial
14
notice, without converting a motion to dismiss into a motion for summary judgment. Zucco
15
Partners LLC v. Digimarc Corp., 552 F.3d 981, 990 (9th Cir. 2009).
16
Nexant has asked the Court to take judicial notice of The California Renewables
17
Portfolio Standard Program, California Public Utilities Code §§ 399.11 through 399.31, and
18
California Public Utilities Commission Resolution No. E-4178. Because the Court did not rely
19
on these documents to resolve the motion, the Court DENIES the request for judicial notice as
20
moot.
21
B.
22
Colorado Fails to State a Claim for Breach of Contract.
Nexant moves to dismiss on the basis that Colorado fails to state a claim for relief. The
23
essential elements of a claim for breach of contract under California law are: (1) the existence
24
of a contract, (2) plaintiff’s performance or excuse for nonperformance, (3) defendant’s breach,
25
and (4) resulting damages to plaintiff. Reichert v. General Insurance Co., 68 Cal. 2d 822, 830
26
(1969). Nexant argues that Colorado has failed to allege facts to support the second and third
27
elements. Because the Court finds that Colorado has failed to allege facts to support the second
28
4
1
element, the Court need not and declines to reach the question of whether Colorado pleads
2
sufficient facts in support of the third element.
3
Colorado alleges that WREGIS did not create RECs until ninety days after the end of
4
each generation month, which prevented Colorado from delivering the first quarter RECs to
5
Nexant within the Delivery Period. (Id. ¶ 20.)2 Colorado also alleges that it chose to use
6
delivery via attestation for the second quarter, because Nexant had stated that it would only
7
accept RECs delivered no later than fifteen days after the end of the fiscal quarter in which they
8
were generated. (Id. ¶ 26.) In essence, Colorado argues that, because of the way WREGIS is
9
structured, it was impossible to use WREGIS as the Delivery Method and deliver RECs to
11
For the Northern District of California
United States District Court
10
Nexant within the Delivery Period.
Colorado has not provided, and the Court is not aware of, any authority that stands for
12
the proposition that, where the facts alleged show that the plaintiff is in breach of a contract, the
13
plaintiff still may sue for breach and rely on a theory of impossibility to show it was excused
14
from performing. See, e.g., Northrop Corp. v. Triad Int’s Mktg. S.A., 811 F.2d 1265, 1270-71
15
(9th Cir. 1987) (noting that California Civil Code section 1511 “is a codification of a rule of
16
purely private law embodying a common-law defense in an action between contracting parties
17
for breach”). Colorado relies on People v. McIntosh, 177 Cal. App. 4th 534 (2009), in support
18
of this argument. However, the Court finds McIntosh inapposite.
19
In McIntosh, the defendant moved to withdraw his plea agreement when the judge who
20
presided over its entry was not available to sentence the defendant. Id. at 537. The court held
21
that “when sentencing discretion is expressly constrained by the terms of a plea agreement and
22
the judge who accepted the plea becomes unavailable for reasons beyond the court’s or the
23
prosecutor’s control, the defendant is not automatically entitled to withdraw his or her plea... in
24
the absence of evidence that exercise of individualized judicial discretion was a material
25
element of the consideration for the plea agreement.” Id. The court’s reasoning was premised
26
27
28
2
Colorado argues that at the time Nexant prepared the September Sales Order
WREGIS provided that RECs would be available for transmittal 90 days after the end of
each generation month, and cite to paragraph 20 of the Complaint in support of that
argument. However, paragraph 20 does not clearly stand for that proposition, and Colorado
does not allege that Nexant was aware of the provisions of this rule but that it was not.
5
1
upon general principles of contract law, namely that “partial impossibility of performance by
2
one party excuses the other party from performing under an agreement only if the term that
3
cannot be performed was material to the agreement as a whole.” Id. at 545.
4
Here, unlike the situation in McIntosh, Colorado attempts to use the doctrine of
5
impossibility as a sword rather than as a shield. In McIntosh by contrast, the “claim” was, in
6
effect, a claim to rescind a contract and impossibility of performance was used to defend that
7
claim. Second, although Colorado argues that the Delivery Method and Delivery Period were
8
not material terms, the Complaint does not include any facts that support those arguments.
9
Accordingly, the Court finds that Colorado has failed to allege facts that show it was
excused from performing under the contract.
11
For the Northern District of California
United States District Court
10
D.
Colorado Fails to State a Claim for Breach of the Covenant of Good Faith and Fair
Dealing.
12
Colorado’s second claim, that Nexant breached the implied covenant of good faith and
13
fair dealing, fails for the same reason that its breach of contract claim fails. A claim for breach
14
of the covenant of good faith and fair dealing requires a plaintiff to show performance or excuse
15
for nonperformance. See Rosenfeld v. JP Morgan Chase Bank, N.A., 732 F. Supp. 2d 952, 968
16
(N.D. Cal. 2010) (citing Judicial Council of California Civil Jury Instruction 325) (reciting the
17
elements of a claim for breach of the covenant of good faith and fair dealing). As the Court has
18
already noted, Colorado fails to allege facts sufficient to satisfy this requirement.
19
CONCLUSION
20
21
For the foregoing reasons, the Court GRANTS Nexant’s motion to dismiss. However,
22
the Court cannot say that it would be futile to grant Colorado leave to amend. Accordingly, if
23
Colorado seeks to pursue these claims, it shall file an amended complaint by October 16, 2012.
24
Nexant shall file its answer or otherwise respond within the time required by the Federal Rules.
25
26
IT IS SO ORDERED.
Dated: September 25, 2012
JEFFREY S. WHITE
UNITED STATES DISTRICT JUDGE