STIPULATION AND ORDER re 62 STIPULATION WITH PROPOSED ORDER - Stipulation to Modify Claims Construction Briefing Schedule. Signed by Judge Jon S. Tigar on March 25, 2013. (wsn, COURT STAFF) (Filed on 3/25/2013)
1
2
3
4
5
6
7
8
9
10
11
12
SQUIRE SANDERS (US) LLP
Nathan Lane, III (State Bar # 50961)
Email: nathan.lane@squiresanders.com
Joseph Meckes (Stat Bar # 190279)
Email: joseph.meckes@squiresanders.com
Jeremy Dutra (admitted pro hac vice)
Email: jeremy.dutra@squiresanders.com
275 Battery Street, Suite 2600
San Francisco, CA 94111
Telephone: +1 415 954 0200
Facsimile: +1 415 393 9887
Attorneys for Plaintiff
Breville Pty Limited and Breville USA, Inc.
LAW OFFICES OF JEFFREY P. WIDMAN
Jeffrey P. Widman (State Bar #58628)
Email: jpwidman@comcast.net
Timothy D. Widman (State Bar # 189182)
Email: tdwidmanesq@comcast.net
101 Race Street, Suite 100
San Jose, CA 95126-3041
Telephone:
+1 408 288 6777
Facsimile:
+1 408 288 7668
GRAHAM CURTIN, P.A.
Glen Diehl (admitted pro hac vice)
gdiehl@grahamcurtin.com
4 Headquarters Plaza
P.O. Box 1991
Morristown, NJ 07962-1991
Telephone: +1 973 401 7138
Attorneys for Defendant
Storebound LLC
13
14
UNITED STATES DISTRICT COURT
15
NORTHERN DISTRICT OF CALIFORNIA
16
17
18
BREVILLE PTY LIMITED, an Australia
proprietary company, and BREVILLE
USA, INC., a California Corporation,
Plaintiff,
19
20
21
vs.
STOREBOUND LLC, a New York limited
liability company,
Case No. CV-12-01783 JST
The Honorable Jon S. Tigar
Courtroom 9
STIPULATION TO MODIFY CLAIMS
CONSTRUCTION BRIEFING SCHEDULE;
[PROPOSED] ORDER
22
Defendant.
Complaint Filed: April 10, 2012
23
24
AND RELATED COUNTERCLAIMS.
25
26
27
28
SQUIRE SANDERS (US) LLP
275 Battery Street, Suite 2600
San Francisco, California 94111
STIPULATION MODIFYING CLAIMS
CONSTRUCTION BRIEFING SCHEDULE
Case No. CV-12-01783 JST
1
To accommodate the schedule of counsel for Breville, the parties have agreed, subject to
2
Court approval, to postpone the briefing schedule on claims construction by one week. Breville
3
filed its Opening Claims Construction Statement on March 21, 2013, as previously ordered.
4
Storebound’s Response Brief is currently due on April 4, 2013 and Breville’s Reply Brief is due
5
on April 11, 2013. The Claims Construction Hearing is currently set for June 18, 2013 with a
6
tutorial set for June 4, 2013.
7
The parties hereby stipulate and request that the Court permit the parties to postpone the
8
briefing schedule by one week, such that Storebound’s Response Brief will be due on April 11,
9
2013 and Breville’s Reply Brief will be due on April 18, 2103. This will not affect any other
10
dates currently scheduled.
11
SO STIPULATED:
12
Dated: March 22, 2013
13
SQUIRE SANDERS (US) LLP
By:
/s/ Joseph A. Meckes
Joseph A. Meckes
Attorneys for Plaintiff
BREVILLE PTY LIMITED AND
BREVILLE USA, INC.
14
15
16
Dated: March 22, 2013
GRAHAM CURTIN P.A.
17
By:
/s/ Glen Diehl
Glen Diehl
Attorneys for Defendant
STOREBOUND LLC
18
19
20
21
[PROPOSED] ORDER
22
Having considered the Parties’ stipulation, and good cause appearing, the Court hereby
23
grants the parties’ Stipulation. Storebound’s Claims Construction Response Brief is due on April
24
11, 2013 and Breville’s Reply Brief is due on April 18, 2103.
25
PURSUANT TO STIPULATION, IT IS SO ORDERED.
26
27
DATED: March 25, 2013
Judge Jon S. Tigar
28
SQUIRE SANDERS (US) LLP
275 Battery Street, Suite 2600
San Francisco, California 94111
STIPULATION MODIFYING CLAIMS
CONSTRUCTION BRIEFING SCHEDULE
Case No. CV-12-01783 JST
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?