Center For Biological Diversity et al v. Federal Highway Administration et al
Filing
148
ORDER by Judge JEFFREY S. WHITE denying 132 Motion for Summary Judgment; granting 135 Motion for Summary Judgment; granting 137 Motion for Summary Judgment (jjoS, COURT STAFF) (Filed on 12/19/2013)
1
2
3
4
5
NOT FOR PUBLICATION
6
UNITED STATES DISTRICT COURT
7
NORTHERN DISTRICT OF CALIFORNIA
8
9
CENTER FOR BIOLOGICAL DIVERSITY,
et al.,
v.
United States District Court
Northern District of California
11
12
13
ORDER DENYING PLAINTIFFS’
MOTION FOR SUMMARY JUDGMENT
AND GRANTING DEFENDANTS’
CROSS-MOTIONS FOR SUMMARY
JUDGMENT
Plaintiffs,
10
Case No. 12-cv-02172-JSW
CALIFORNIA DEPARTMENT OF
TRANSPORTATION, et al.,
Re: Dkt. Nos. 132, 135, 137
Defendants.
14
INTRODUCTION
15
This matter comes before the Court upon consideration of Plaintiffs’ Motion for Summary
16
17
Judgment, filed by the Center for Biological Diversity ( “CBD”), the Sierra Club, the Willits
18
Environmental Center (“WEC”), and the Environmental Protection Information Center (“EPIC”)
19
(collectively “Plaintiffs”) (Docket No. 132, “Plaintiffs’ MSJ”), as well as Defendants’ Cross-
20
Motions for Summary Judgment, filed by the California Department of Transportation and
21
Malcolm Dougherty (collectively “Caltrans”) (Docket No. 137, “Caltrans’ Cross-MSJ”) and the
22
United States Army Corps of Engineers (the “Corps”) (Docket No. 135, “Corps’ Cross-MSJ”).
23
The Court has considered the parties’ papers, relevant legal authority, the record in this
24
case, and had the benefit of oral argument. The Court HEREBY DENIES Plaintiffs’ Motion for
25
Summary Judgment, GRANTS Caltrans’ Cross-Motion for Summary Judgment, and GRANTS
26
the Corps’ Cross-Motion for Summary Judgment.
27
///
28
///
BACKGROUND
1
2
CBD, Sierra Club, and EPIC (the “NEPA Plaintiffs”) allege that Caltrans failed to comply
3
with the requirements of the National Environmental Policy Act, 42 U.S.C. Sections 4321, et seq.
4
(the “NEPA Claim”). Plaintiffs allege that the Corps violated the Clean Water Act, 33 U.S.C.
5
Sections 1251, et seq. (the “CWA Claim”).1 Both claims arise out of the construction of a
6
highway bypass project around the community of Willits, California (the “Willits Bypass
7
Project”), the origin of which dates back to the mid-1950s. The parties agree that some form of a
8
bypass is necessary. The crux of their dispute is whether the bypass should be composed of two
9
lanes or four lanes.
In May 2002, Caltrans and the Federal Highway Administration (“FHWA”)2 issued a
10
United States District Court
Northern District of California
11
combined draft Environmental Impact Statement (“EIS”) and Environmental Impact Report
12
(“EIR”) (“Draft EIS”). (See Caltrans’ Administrative Record (“Caltrans AR”) 12; Army Corps of
13
Engineers’ Administrative Record (“Corps AR”) 18:2175-2742.)3 Caltrans and FHWA issued the
14
Final EIS in October 2006. (See Caltrans AR 1-1928.) In both the Draft EIS and the Final EIS,
15
Caltrans considered variations of a four-lane freeway and a no-build alternative, but it also
16
discussed the issue of a two-lane bypass.4 For example, in the Draft EIS it stated that:
17
FHWA regulations do not allow development of a facility that
would be functionally obsolete within its design life. In 1992,
Caltrans staff studied a two-lane bypass of Willits and determined
that a two-lane bypass would not achieve a satisfactory level of
service or improve safety. In 2000, after all technical studies were
completed for the current range of alternatives, [WEC] asked
Caltrans to reconsider a two-lane alternative for the proposed bypass
18
19
20
21
1
22
On May 1, 2012, Plaintiffs filed the original complaint and, on June 25, 2012, filed the
First Amended Complaint, which is the operative pleading.
23
2
24
The Court granted the FHWA’s motion to dismiss on September 10, 2012. (Docket No.
58.)
3
25
26
27
Both Caltrans and the Corps have numbered the pages of their administrative records using
six digits starting with “000001.” The Court eliminates the preliminary “0s” when citing to the
record, and it cites to Caltrans Administrative Record as follows: Caltrans’ Administrative Record
as “Caltrans AR page number.” The Court cites to the Corps’ Administrative Record as “Corps
AR exhibit number:page number.”
4
28
Since the inception of the Willits Bypass Project, Caltrans has considered approximately
thirty different bypass alternatives. (Corps AR 16:1187, 16:1201-05.)
2
project. In response, Caltrans analyzed the concept but chose not to
add a two-lane alternative because, foremost, a two-lane alternative
would not meet the “purpose and need” for the project. The
“purpose and need” calls for a facility that would provide a LOS
“C” through the 20-year design period (i.e., 2028). A two-lane
facility would provide a LOS “D” at peak hour upon construction
(2008), and would diminish to LOS “E” within the 20-year period.
LOS “E” exists when a facility is at capacity during peak traffic
flows. Thus, a new two-lane highway would be functionally
obsolete within the design period. This issue is discussed in detail in
Section 3.6.2.
1
2
3
4
5
6
7
(Caltrans AR 1349.)
Caltrans also noted that “[i]t is important to recognize that a LOS of ‘C’ on a four-lane
8
9
highway is substantially different than LOS ‘C’ on a two-lane highway, in that a freeway offers
continuous passing opportunities. On a 2-lane road, passing opportunities are affected by volume
11
United States District Court
Northern District of California
10
and sight distance. Average operating speeds are directly affected by slower traffic.” (Id. 1349
12
n.2.)
Caltrans ultimately designated “Modified Alternative J1T” as the Least Environmentally
13
14
Damaging Practicable Alternative (“LEDPA”). (Caltrans AR 16.) The Corps agreed with that
15
conclusion. (Id.) In the Final EIS, Caltrans again noted that many individuals and organizations
16
argued that it should have considered a two-lane bypass. Caltrans stated that it had analyzed the
17
concept of a two-lane bypass, but it concluded that a two-lane bypass would not meet the purpose
18
and need of the project. (Caltrans AR 29; see also Corps AR 17:1577-1590.) Caltrans also noted
19
that “[u]pon environmental approval and appropriation of funding, [it] could design and construct
20
all of the proposed project depending on funding availability. In an effort to balance potential
21
funding limitations and the need for the project,” the Willits Bypass Project “could be constructed
22
in phases, whereby a functional interim facility would be constructed initially….” (Caltrans AR
23
37.)
24
In December 2006, Caltrans signed a Record of Decision (“ROD”) for the Willits Bypass
25
Project, approving Modified Alternative J1T. (Caltrans AR 2000-2020.) Plaintiffs did not file a
26
legal challenge to that decision. In 2007, Caltrans decided to proceed with phased construction,
27
because of funding constraints. During the first phase of the project, which is now under
28
construction, Caltrans plans to complete a two-lane bypass, and it plans to complete the remaining
3
1
two lanes as funding becomes available. (See generally Caltrans AR 23082; Corps AR 299:9521-
2
9531.)
3
After it issued the FEIS and the ROD, Caltrans made several design changes to the Willits
4
Bypass Project. In June 2010, Caltrans prepared a re-evaluation to examine those changes and
5
their potential environmental impacts (the “2010 Re-Evaluation”). (Caltrans AR 2215-2254;
6
Corps AR 22:2868-2907.) Caltrans specifically addressed the issue of phasing in the 2010 Re-
7
Evaluation. (Caltrans AR 2217.) In June 2011, Caltrans prepared a second re-evaluation to
8
evaluate impacts on Baker’s Meadowfoam and farmlands (the “2011 Re-Evaluation”). (Caltrans
9
AR 2509-2596; Corps AR 23:2908-2995.) Caltrans specifically noted that phasing was one of the
major changes that affected Baker’s Meadowfoam habitat. (Caltrans AR 2511.) Ultimately,
11
United States District Court
Northern District of California
10
Caltrans concluded that the changes discussed in the 2010 and 2011 Re-Validations did not
12
require it to issue a supplemental EIS. (Id. 2215, 2509.)
13
It is undisputed that constructing the Willits Bypass Project will result in the discharge of
14
fill material in designated wetlands and waters of the United States. (Corps AR 305:9758-9764.)
15
Accordingly, on March 1, 2010, Caltrans applied for a permit pursuant to Section 404 of the
16
CWA, and it submitted a Mitigation and Management Plan (“MMP”). (See, e.g., Corps AR 7:452,
17
303:9601.) The Corps initially rejected Caltrans’ application, because “the Willits Bypass Project
18
will result in alteration and/or destruction of wetlands to a magnitude that would contribute to
19
significant degradation of waters of the United States.” (Corps AR 7:452.) The Corps also
20
rejected the initial MMP. (Corps AR 303:9579.) With respect to the Section 404 Permit
21
application, the Corps noted that Caltrans planned to proceed in phases and concluded that “there
22
are other practicable alternatives to the project with less adverse impact on the aquatic ecosystem
23
or without other significant adverse environmental consequences.” (Id. 7:453; see generally id.
24
7:452-455.)
25
The Corps noted that it had “not exercised an option to re-open consideration of the project
26
purpose and need. However, [Caltrans’] pursuit of presenting a four lane bypass project to your
27
funding partner that proposes a fill discharge for full project construction but only two lanes of
28
roadway construction (without assurance that the other two lanes of roadway will be constructed),
4
1
raises significant concerns regarding the extent of the public need for the project.” (Id. 7:454.)
2
The Corps noted that it could be possible to obtain a Section 404 permit, if Caltrans’ proposal
3
included specific revisions. By way of example, the Corps noted that “[a] two-lane bypass was
4
last examined in 1992. Several comments received in response to the Public Notice requested
5
updated traffic studies and questioned the overall project purpose and need. The Corps requires
6
updated traffic studies and a reexamination of these factors to ensure the overall project purpose
7
and need are still current and valid.” (Id.)
In January 2012, Caltrans submitted a revised MMP to the Corps. (Corps AR 272:8644-
8
8965; see also id. 269:7500-8317 through 271:8452-8643, 273:8966-9028.) In February 2012, the
10
Corps issued a Permit Evaluation and Decision Document (the “Section 404 Permit”), in which it
11
United States District Court
Northern District of California
9
also evaluated information and circumstances that developed after Caltrans issued the Final EIS
12
and ROD. (Id. 303:9575-9752.) The Corps determined that a supplemental environmental
13
assessment (“EA”), rather than a supplemental EIS, was appropriate, because “the new
14
information presented did not rise to the level of significant impact on the human environment.”
15
(Id. 303:9576.) The Corps also found that Modified Alternative J1T was the LEDPA, and it
16
issued the Section 404 Permit with twenty-two special conditions. (Id. 303:9611-9616.)
17
Pursuant to the Section 404 Permit, 51.07 acres of wetlands and other waters of the United
18
States can be permanently filled and 30.89 acres of wetlands and other waters of the United States
19
can be temporarily filled during construction of the Willits Bypass Project. (Id. 305:9758-9764.)
20
Phase I construction “shall permanently fill 42.76 acres of waters of the United States and
21
temporarily fill 22.91 acres of waters of the United States. … Phase II construction would
22
permanently fill 8.31 acres of waters of the United Sates and temporarily fill 8.07 acres of waters
23
of the United States.” (Id. 305:9758.) However, Caltrans “is not authorized to commence fill or
24
construction activities associated with Phase II of the [Willits Bypass] Project until after the Corps
25
has provided a written notice to proceed with Phase II.” (Id. 303:9615.) Caltrans will be required
26
to submit a proposed MMP for Phase II, which “must allow two (2) years of development and
27
review such that the final mitigation plan is developed prior to the start of Phase II construction.”
28
(Id.)
5
On July 26, 2012, Caltrans selected a contractor for the Willits Bypass Project, and the
1
2
contractor began construction in January 2013. (See Docket No. 138-1, Declaration of Mauricio
3
Serrano (“Serrano Decl.”), ¶¶ 5-7.)
The Court shall address specific additional facts as necessary to the analysis in the
4
5
remainder of this Order.
ANALYSIS
6
7
A.
A principal purpose of the summary judgment procedure is to identify and dispose of
8
9
Legal Standards Applicable to Motions for Summary Judgment.
factually unsupported claims. Celotex v. Cattrett, 477 U.S. 317, 323-24 (1986). Summary
judgment is proper when “the movant shows that there is no genuine dispute as to any material
11
United States District Court
Northern District of California
10
fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “In
12
considering a motion for summary judgment, the court may not weigh the evidence or make
13
credibility determinations, and is required to draw all inferences in a light most favorable to the
14
non-moving party.” Freeman v. Arpaio, 125 F.3d 732, 735 (9th Cir. 1997). The party moving for
15
summary judgment bears the initial burden of identifying those portions of the pleadings,
16
discovery, and affidavits which demonstrate the absence of a genuine issue of material fact.
17
Celotex, 477 U.S. at 323; see also Fed. R. Civ. P. 56(c).
Once the moving party meets this initial burden, the non-moving party must go beyond the
18
19
pleadings and “identify with reasonable particularity the evidence that precludes summary
20
judgment.” Keenan v. Allan, 91 F.3d 1275, 1279 (9th Cir. 1996) (quoting Richards v. Combined
21
Ins. Co., 55 F.3d 247, 251 (7th Cir. 1995) (stating that it is not a district court’s task to “scour the
22
record in search of a genuine issue of triable fact”); see also Fed. R. Civ. P. 56(e). If the non-
23
moving party fails to make this showing, the moving party is entitled to judgment as a matter of
24
law. Celotex, 477 U.S. at 323; Fed. R. Civ. P. 56(e)(3).
25
B.
The NEPA Claim.
26
1.
27
NEPA “establishes a ‘national policy [to] encourage productive and enjoyable harmony
28
NEPA Requirements.
between man and his environment,’ and was intended to reduce or eliminate environmental
6
1
damage and to promote ‘the understanding of the ecological systems and natural resources
2
important to’ the United States.” Department of Transportation v. Public Citizen, 541 U.S. 752,
3
756 (2004) (quoting 42 U.S.C. § 4321). NEPA does not mandate particular results. Rather “it
4
imposes only procedural requirements on federal agencies with a particular focus on requiring
5
agencies to undertake analyses of the environmental impact of their proposals and actions.” Id.
6
(citing Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349-51 (1989)); see also Blue
7
Mountains Biodiversity Project v. Blackwood, 161 F.3d 1208, 1212 (9th Cir. 1998) (“Blue
8
Mountains”) (“NEPA ensures that the agency ... will have available, and will carefully consider,
9
detailed information concerning significant environmental impacts; it also guarantees that the
relevant information will be made available to the larger [public] audience.”) (internal quotation
11
United States District Court
Northern District of California
10
marks and citation omitted). “NEPA merely prohibits uninformed - rather than unwise-agency
12
action.” Robertson, 490 U.S. at 351.
13
NEPA requires federal agencies to prepare a detailed EIS for all “‘major Federal actions
14
significantly affecting the quality of the human environment.’” Blue Mountains, 161 F.3d at
15
1211-12 (quoting 42 U.S.C. § 4332(2)(C)). “NEPA also imposes a continuing duty to supplement
16
previous environmental documents.” Price Road Neighborhood Ass’n v. United States Dep’t of
17
Transportation, 113 F.3d 1505, 1509 (9th Cir. 1997) (hereinafter “Price Road”). “[T]he decision
18
whether to prepare a supplemental EIS is similar to the decision to prepare an EIS in the first
19
instance: if there remains major Federal action to occur, and if ... new information is sufficient to
20
show that the remaining action will affect the quality of the human environment in a significant
21
manner or to a significant extent not already considered, a supplemental EIS must be prepared.”
22
Marsh, 490 U.S. at 374 (internal quotations and brackets omitted).
23
Under regulations promulgated by the FHWA, a supplemental EIS is required where
24
“changes to the proposed action would result in significant environmental impacts that were not
25
evaluated in the EIS; or new information or circumstances relevant to environmental concerns and
26
bearing on the proposed action or its impacts would result in significant environmental impacts
27
28
7
1
not evaluated in the EIS.” 23 C.F.R. § 771.130(a)(1)-(2).5 “Where the Administration is
2
uncertain of the significance of the new impacts, the applicant will develop appropriate
3
environmental studies or, if the Administration deems appropriate, an EA to assess the impacts of
4
the changes, new information, or new circumstances.” 23 C.F.R. § 771.130(c).
The FHWA regulations also provide for re-evaluation of environmental documents. 23
5
6
C.F.R. § 771.129. Those regulations provide, in relevant part, that “[a]fter approval of the ROD,
7
... the applicant shall consult with the Administration prior to requesting any major federal
8
approvals or grants to establish whether or not the approved environmental document ... remains
9
valid for the requested Administration action.” Id. § 771.129(c). In addition, the FHWA
regulations provide that “a supplemental EIS will not be necessary where: (1) the changes to the
11
United States District Court
Northern District of California
10
proposed action, new information, or new circumstances result in a lessening of adverse
12
environmental impacts evaluated in the EIS without causing other environmental impacts that are
13
significant and were not evaluated in the EIS....” Id. § 771.130(b)(1); see also Price Road, 113
14
F.3d at 1509-10.
Regulations promulgated by the CEQ, in turn, guide a court’s review of an agency’s
15
16
determination of “significance” and include two components: context and intensity. Blue
17
Mountains, 161 F.3d at 1212; see also Ocean Advocates v. United States Army Corps of
18
Engineers, 402 F.3d 846, 865 (9th Cir. 2005) (citing 40 C.F.R. § 1508.27). “Context refers to the
19
setting in which the proposed action takes place.” Id.; see also 40 C.F.R. § 1508.27(a) (“the
20
significance of an action must be analyzed in several contexts, such as society as a whole (human,
21
national), the affected region, the affected interests and the locality”). “Intensity means ‘the
22
severity of the impact.’” Ocean Advocates, 402 F.3d at 865 (quoting 40 C.F.R. § 1508.27(b)); see
23
also 40 C.F.R. § 1508.27(b)(1)-10 (setting forth factors to be considered when evaluating
24
intensity).
25
26
27
28
5
This regulation is similar to regulations promulgated by the Council on Environmental
Quality (“CEQ”), which require an agency to prepare a supplemental EIS when it “makes
substantial changes in the proposed action that are relevant to environmental concerns; or ...
[t]here are significant new circumstances or information relevant to environmental concerns and
bearing on the proposed action or its impacts.” 40 C.F.R. § 1502.9(c)(1)(i)-(ii).
8
1
2.
Standard of Review.
2
The NEPA Plaintiffs bring their claim pursuant to the Administrative Procedure Act (the
3
“APA”), which permits a court to “compel agency action unlawfully withheld or unreasonably
4
delayed,” or to “hold unlawful and set aside agency action, findings and conclusions found to be -
5
arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C.
6
§§ 706(1)-(2)(A). Review of an agency’s decision not to supplement an EIS is “controlled by the
7
‘arbitrary and capricious’ standard of” Section 706(2)(A). Marsh v. Oregon Natural Resources
8
Council, 490 U.S. 360, 376 (1989); see also Friends of the Clearwater v. Dombeck, 222 F.3d 552,
9
556 (9th Cir. 2000) (“Dombeck”) (“The Forest Service’s decision to forego an SEIS should not be
set aside unless it was arbitrary or capricious.”). However, “[a]n action to compel an agency to
11
United States District Court
Northern District of California
10
prepare a [supplemental EIS] … is not a challenge to a final agency decision, but rather an action
12
arising under 5 U.S.C. § 706(1).” Dombeck, 222 F.3d at 560.
In their opening brief, the NEPA Plaintiffs argue that they are proceeding against Caltrans
13
14
under Section 706(1). Caltrans argues in opposition that the NEPA Plaintiffs discuss why the
15
2010 and 2011 Re-Evaluations are inadequate, and it contends the NEPA Plaintiffs cannot
16
“circumvent the procedural bars to bringing a 706(2) action,” which challenges those two
17
documents, by framing their claim under as a claim under Section 706(1). In reply, the NEPA
18
Plaintiffs “hedg[e] their bets.” Native Songbird Care and Conservation v. LaHood, 2013 WL
19
335567, at *6 (N.D. Cal. July 2, 2013). 6 Specifically, Plaintiffs argue that: (1) the 2010 and 2011
20
21
22
23
24
25
26
27
28
6
This aspect of the parties’ dispute first arose in connection with the NEPA Plaintiffs’
motion for a preliminary injunction. When it denied the NEPA Plaintiffs’ motion, the Court
characterized the NEPA Claim as having been brought under Section 706(1), relying on Dombeck.
See Center for Biological Diversity v. California Dep’t of Transportation, 2012 WL 5383290, at
*8 n.12 (N.D. Cal. Nov. 1, 2012). In Dombeck, the court concluded that even though the
defendant had been presented with new information after it issued a final EIS, it “failed to timely
prepare, or even sufficiently to consider and evaluate the need for an SEIS,” until after the
plaintiffs filed suit. Therefore, the court found it violated NEPA. Dombeck, 222 F.3d at 558.
After the plaintiffs filed suit, the defendant prepared two supplemental information reports, which
were the defendant’s “formal instruments for documenting whether new information is sufficiently
significant to trigger the need for” a supplemental EIS. Id. at 555. That fact distinguishes this
case from Dombeck, because Caltrans prepared the Re-Evaluation documents before the NEPA
Plaintiffs filed suit.
9
1
Re-Evaluations are not final agency actions7; (2) if the 2010 and 2011 Re-Evaluations are final
2
agency actions, the NEPA Plaintiffs have stated a timely claim under Section 706(2); and (3) if the
3
Court rejects those arguments, it should grant the NEPA Plaintiffs leave to file a second amended
4
complaint that pleads a claim that challenges those actions under Section 706(2).8
In the Native Songbird case, the plaintiffs, like the NEPA Plaintiffs here, argued that the
5
6
defendants should have prepared a supplemental EIS, and they invoked both provisions of the
7
APA to support that claim. See, e.g., Native Songbird, 2013 WL 3355657 at *5. The court
8
explained why it viewed the plaintiffs’ decision to do so to be prudent. “When the agency has
9
prepared a written determination that a court can review, the distinction between” Sections 706(1)
and 706(2) “makes little difference. Either the determination itself is a final agency action
11
United States District Court
Northern District of California
10
reviewable,” under Section 706(2)(A), “or else the court reviews the [written determination] to
12
determine whether the agency has ‘unlawfully withheld’ the preparation of a Supplemental EIS
13
pursuant to” Section 706(1). Id., 2013 WL 3355657, at *6; see also id., 2013 WL 3355657, at *6
14
n.6 (noting that “published authority on this issue generally demonstrates that in considering an
15
agency’s failure to prepare a Supplemental EIS, courts review a written determination or at least
16
an expert determination”).9
The Court finds that this is a case where the distinction between Sections 706(1) and
17
18
19
20
21
22
23
24
7
The NEPA Plaintiffs’ current argument is not consistent with the position they advocated
at the hearing on the motion for a preliminary injunction. At that hearing, they argued that the
2011 Re-Validation was a final agency action and that they challenged its adequacy.
8
Both parties have “hedged their bets” in this case. Native Songbird, 2013 WL 3355657, at
*6. On July 12, 2012, well after the 2010 and 2011 Re-Evaluations were issued and well after
Plaintiffs filed the original complaint, the FHWA published a notice in the federal register
announcing that Caltrans conducted the two Re-Evaluations and determined that preparation of a
Supplemental EIS was not warranted. According to this notice, those actions were deemed “final
within the meaning of 23 U.S.C. 139(l)(1).” (Caltrans AR 2618-2620.)
9
25
26
27
28
Indeed, in Dombeck, the Ninth Circuit stated that a claim to compel the preparation of a
supplemental EIS is a claim under Section 706(1) in connection with plaintiffs’ argument that the
court should not have considered the defendant’s post-litigation supplemental reports. The Ninth
Circuit rejected that argument, noting that, in Section 706(1) cases, “review is not limited to the
record as it existed at any single point in time, because there is no final agency action to demarcate
the limits of the record.” Id. Therefore, it was entitled to consider the supplemental reports,
which it concluded supported the defendant’s decision not to prepare a supplemental EIS. Id. at
560-61.
10
1
706(2) is one without a difference. Although the Court previously characterized the NEPA
2
Plaintiffs’ claim as a “failure to act” claim arising under Section 706(1), it also is not a case where
3
Caltrans stood silent in the face of new information. See Center for Biodiversity, 2012 WL
4
5383290, at *8. Rather, Caltrans prepared the 2010 and 2011 Re-Evaluations and documented its
5
conclusion that a supplemental EIS was not required, as it is permitted to do. See Idaho Sporting
6
Congress v. Alexander, 222 F.3d 562, 566 (9th Cir. 2000); see also Price Road, 113 F.3d at 1510.
7
Therefore, whether the Re-Evaluations are final agency actions or whether the Court must
8
review those documents to determine if Caltrans unlawfully withheld the preparation of a
9
supplemental EIS, the Court applies standard set forth Marsh:
[T]he … court “must consider whether the decision was based on a
consideration of the relevant factors and whether there has been a
clear error of judgment.” This inquiry must be “searching and
careful,” but “the ultimate standard of review is a narrow one.” …
When specialists express conflicting views, an agency must have
discretion to rely on the reasonable opinions of its own qualified
experts even if, as an original matter, a court might find contrary
views more persuasive. On the other hand, in the context of
reviewing a decision not to supplement an EIS, courts should not
automatically defer to the agency’s express reliance on an interest in
finality without carefully reviewing the record and satisfying
themselves that the agency has made a reasoned decision based on
its evaluation of the significance - or lack of significance - of the
new information.
10
United States District Court
Northern District of California
11
12
13
14
15
16
17
18
Marsh, 490 U.S. at 378 (quoting Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402,
19
416 (1971)).
Under this standard, a court “will reverse a decision as arbitrary and capricious only if the
20
21
agency relied on factors Congress did not intend it to consider, entirely failed to consider an
22
important aspect of the problem, or offered an explanation that runs counter to the evidence before
23
the agency or is so implausible that it could not be ascribed to a difference in view or the product
24
of agency expertise.” The Lands Council v. McNair, 537 F.3d 981, 987 (9th Cir. 2008), overruled
25
on other grounds by Winter v. Natural Resources Defense Council, Inc., 555 U.S. 7 (2008),
26
(internal quotations and citations omitted).10
27
10
28
In light of this conclusion, the Court does not reach the issue of whether the 2010 and 2010
Re-Validations are “final agency actions.” Because the Court has reviewed these documents to
11
1
3.
Analysis.
2
In support of their motion for summary judgment, the NEPA Plaintiffs argue that Caltrans
3
is required to prepare a supplemental EIS, because phased construction and the changes in the
4
design of the Willits Bypass Project will result in: (1) significant impacts to rare plants; (2) greater
5
destruction of wetlands; (3) significant impacts to threatened species of fish and their habitats; and
6
(4) significant impacts to agricultural land.
a.
7
The NEPA Plaintiffs argue that the changes to the Willits Bypass Project will result in
8
9
Rare Plants.
greater impacts to two rare plants: Baker’s Meadowfoam and North Coast semaphore grass.
i.
10
Baker’s Meadowfoam.
United States District Court
Northern District of California
11
It is undisputed that after Caltrans published the Final EIS, the impacts to Baker’s
12
Meadowfoam habitat increased. (Caltrans AR 2240.) According to the NEPA Plaintiffs, Baker’s
13
Meadowfoam is a “unique characteristic” of the area in which the Willits Bypass Project is
14
located. They argue that, because the impacts have increased, Caltrans was required to address
15
this issue in a supplemental EIS. One factor to consider when evaluating “intensity,” is the
16
“[u]nique characteristics of the geographic area such as proximity to historic or cultural resources,
17
park lands, prime farmlands, wetlands, wild and scenic rivers, or ecologically critical areas.” 40
18
C.F.R. § 1508.27(b)(3).
19
According to the 2011 Re-Evaluation, “[t]he ultimate 4-lane Willits Bypass project will …
20
result in a total of 26.26 acres of permanent impacts, 31.16 acres of temporary impacts, and 58.78
21
acres of indirect impacts to” Baker’s Meadowfoam habitat. (Id. 2530.)11 Caltrans also
22
acknowledged the fact that Baker’s Meadowfoam has a limited population, and it considered that
23
fact when it evaluated the potential impacts to both its observed habitat and areas of potential
24
25
26
27
determine whether the decision not to prepare a Supplemental EIS was arbitrary or capricious, the
Court also does not reach the issue of whether it should grant the NEPA Plaintiffs leave to amend
the FAC to include a direct challenge to each of those documents. In addition, because the Court
finds in favor of Caltrans on the merits of the NEPA Claim, it does not reach its arguments that the
NEPA Plaintiffs’ claims are barred by the doctrines of unclean hands and laches.
11
28
Caltrans addressed impacts to Baker’s Meadowfoam in the Final EIS and in the 2010 and
2011 Re-Validation documents. (See, e.g., Caltrans AR 30, 65-68, 2219, 2228, 2231, 2510.)
12
1
2
habitat. (See, e.g., id. 2538.)
The NEPA Plaintiffs argue that “the plant’s few remaining habitats are ‘stressed or in
decline,’” a statement made in the Technical Memo attached to the 2011 Re-Validation. (See id.
4
2528-2565.) That statement actually reads that “[i]t is hypothesized that many remaining
5
populations of Baker’s Meadowfoam are stressed or in decline.” (Id. 2538 (emphasis added).)
6
The NEPA Plaintiffs do not put forth any evidence to suggest that this hypothesis is fact. Caltrans
7
does acknowledge that, “[b]ecause of hydrologic alterations in Little Lake Valley, such as stream
8
diversions, impoundments, and conversion of wetlands to other uses, it is likely that the real extent
9
of habitat for [Baker’s Meadowfoam] has been substantially reduced. The primary threat to
10
Baker’s [M]eadowfoam has been the conversion of habitat to various types of development.
11
United States District Court
Northern District of California
3
Inappropriate grazing by livestock could also pose a threat to the remaining populations.” (Id.)
12
However, “it does not follow that the presence of some negative effects necessarily rises to
13
the level of demonstrating a significant effect on the environment.” Native Ecosystems, 428 F.3d
14
at 1240. Although the impacts to number of acres of Baker’s Meadowfoam have increased,
15
Caltrans stated the impacts were the same type of impacts that it previously analyzed and did “not
16
represent a major increase of impacts.” (Caltrans AR 2511.) It also noted that the impacts would
17
be “fully mitigated by enhancing, preserving and restoring Baker’s Meadowfoam within the
18
proposed mitigation parcels,” which would result in a mitigation ratio of 5:1. (Id.; see also id.
19
2522-23; 2528-2565 (Technical Memo Baker’s Meadowfoam Impacts and Mitigation).) The
20
NEPA Plaintiffs do not dispute that the type of impacts were the same. They also have not
21
pointed to any evidence in the record that would contradict these conclusions or render them
22
implausible.
23
The NEPA Plaintiffs also argue that Caltrans should have prepared a supplemental EIS,
24
because, when it prepared the 2011 Re-Evaluation, Caltrans had not yet completed its mitigation
25
plan for Baker’s Meadowfoam. Contrary to the NEPA Plaintiffs’ argument, Caltrans did not
26
ignore the issue of mitigation in the Final EIS or the 2010 and 2011 Re-Evaluation documents.
27
(See, e.g., id. 121-22, 2219, 2511-12.) “There is a fundamental distinction … between a
28
requirement that mitigation be discussed in sufficient detail to ensure that environmental
13
1
consequences have been fairly evaluated, on the one hand, and a substantive requirement that a
2
complete mitigation plan be actually formulated and adopted, on the other.” Robertson, 490 U.S.
3
at 352. Upon review of the record, the Court finds that Caltrans’ decision to forego preparing a
4
supplemental EIS in light of new impacts to Baker’s Meadowfoam was neither arbitrary nor
5
capricious.
ii.
6
North Coast semaphore grass.
The NEPA Plaintiffs also focus on alleged impacts to NCSG, which is listed as a
7
8
threatened species under California’s Endangered Species Act and is a “federal species of
9
concern.”12 (Caltrans AR 2107-2108, 2156.) It is undisputed that Caltrans did not discuss impacts
on NCSG in the Final EIS, because it did not discover that the plant was located within the
11
United States District Court
Northern District of California
10
footprint of the Willits Bypass Project until after it issued that document. (See id.) It also is
12
undisputed that, as a result of the discovery, Caltrans prepared a supplemental EIR under the
13
California Environmental Quality Act.” (Caltrans AR 2151; see generally id. 2147-2198.)
Although Plaintiffs argue that the Willits Bypass Project will affect 19% of NCSG habitat,
14
15
the record shows these figures pertain to one occurrence. The record also shows that the Willits
16
Bypass Project will not affect most of the known occurrences of NCSG, and that the actual impact
17
would be to approximately 5.6% of the total occupied habitat. Caltrans acknowledged that, “[i]n
18
the absence of mitigation, the loss of up to 5% of the occupied habitat (2,826 plants on 0.401 acre)
19
within NCSG’s range potentially could have a substantial impact on the species.” (Id. 2227.)
20
Caltrans then described the mitigation measures that would be implemented to address those
21
impacts, and it stated that the mitigation ratio would be approximately “12.7:1 (5.094 acres
22
preserved to approximately 0.401 acre affected).” (Id.) As a result of these mitigation efforts,
23
Caltrans concluded “the Willits Bypass Project will not affect NCSG’s ability to survive and
24
reproduce and is not likely to result in jeopardy to the species.” (Id.) The NEPA Plaintiffs do not
25
suggest that Caltrans’ mitigation efforts would be ineffective, and they have not pointed to any
26
27
28
12
Although NCSG is a “federal species of concern,” it is not an “endangered species or
threatened species ... that has been determined to be critical under the Endangered Species Act of
1974. See, e.g., 40 C.F.R. § 1508.27(9).
14
1
2
evidence in the record that would render this explanation implausible.
The Court concludes that the record does not support a conclusion that Caltrans relied on
3
factors that Congress did not intend it to consider. The Court also concludes that Caltrans’
4
explanation about why a Supplemental EIS was not required is not contradicted by the evidence
5
Caltrans had before it at the time it prepared the 2010 and 2011 Re-Evaluations or that its
6
explanations about why a Supplemental EIS was not warranted are “so implausible that it could
7
not be ascribed to a diffrence in view or the product of agency expertise.” See Lands Council, 537
8
F.3d at 987.
9
10
b.
Wetlands.
It is undisputed that changes to the Willits Bypass Project will result in additional impacts
United States District Court
Northern District of California
11
to wetlands and other waters of the United States. (See, e.g., Caltrans AR 2240, 27389.) One of
12
the factors to consider in evaluating whether an impact is significant is the “unique characteristics
13
of the geographic area such as proximity to … wetlands.” 40 C.F.R. § 1508.27(b)(3). All parties
14
acknowledge that some of these impacts will be temporary, although that does not necessarily
15
negate a finding of significance. Id. § 1508.27(b)(7) (“Significance cannot be avoided by terming
16
an action temporary….”). The NEPA Plaintiffs again appear to take the position that any
17
additional impacts must be significant and, thus, Caltrans was required to prepare a Supplemental
18
EIS. The Court is not persuaded.
19
Caltrans did not ignore the fact that the changes to the Willits Bypass Project would have
20
impacts on wetlands, and it documented the efforts that would be taken to minimize the impacts,
21
which include mitigation efforts. (See, e.g., Caltrans AR 2223-2224, 2229-2230.) Although the
22
NEPA Plaintiffs may disagree with Caltrans’ conclusion that the additional impacts were not
23
significant, they do not cite to any evidence that suggests Caltrans’ “offer[ed] an explanation” for
24
its decision that ran “counter to the evidence before” it. Lands Council, 537 F.3d at 987.
25
Similarly, they have not pointed the Court to anything in the record that suggests Caltrans’
26
explanation for its decision “is so implausible that it could not be ascribed to a difference in view
27
or the product of agency expertise.” Id.
28
On this record, the Court concludes that Caltrans’ conclusion that the additional impacts to
15
1
2
3
wetlands did not give rise to the need for a Supplemental EIS was neither arbitrary nor capricious.
c.
Impacts on species of fish and essential fish habitat.
The NEPA Plaintiffs also argue that the design changes and phased construction will have
4
significant impacts on California Coastal Chinook Salmon (“CC Chinook Salmon”), Southern
5
Oregon/Northern California Coasts Coho Salmon (“SONCC Coho Salmon”), and Northern
6
California Steelhead (“NC Steelhead”) that require Caltrans to prepare a Supplemental EIS. They
7
also note that NMFS required Caltrans to re-initiate consultation under the ESA, which they
8
contend demonstrates that Caltrans should have prepared an EIS.
One factor to consider in terms of intensity is “the degree to which the action may
10
adversely affect an endangered or threatened species or its habitat that has been determined to be
11
United States District Court
Northern District of California
9
critical under the Endangered Species Act of 1973.” 40 C.F.R. § 1508.27(b)(9). It is undisputed
12
that the CC Chinook Salmon, SONCC Coho Salmon, and the NC Steelhead are recognized as
13
“threatened” species under federal law. It also is undisputed that various creeks within the
14
footprint of the Willits Bypass project are “designated critical habitat” for these species. (See, e.g.,
15
Caltrans AR 2313.)
16
The NEPA Plaintiffs argue that, because NMFS stated that new impacts “may adversely
17
affect,” these species and will adversely affect their habitat, Caltrans must prepare a Supplemental
18
EIS. The NEPA Plaintiffs do not specify the “degree” to which these species may be adversely
19
impacted. See 40 C.F.R. § 1508.27(b)(9). In addition, after it decided to proceed in phases,
20
Caltrans consulted with the NMFS to consider the impacts of phased construction on these
21
species. The NMFS issued Biological Opinions in 2010 and 2012. In 2012, the NMFS concluded
22
that “the proposed Willits Bypass Project is not likely to jeopardize the continued existence of”
23
those species, and is “not likely to adversely modify or destroy designated critical habitat for”
24
these species. (Caltrans AR 23079; see generally id. 23078-23178.) The NEPA Plaintiffs fail to
25
articulate how or why, in light of these opinions, Caltrans’ conclusion that a Supplemental EIS
26
was not required was arbitrary or capricious, and the Court finds it was not.
27
28
d.
Agricultural Lands.
Finally, the NEPA Plaintiffs argue that “significant new impacts to agricultural land have
16
1
been adopted without adequate supplemental environmental review.” (Plaintiffs MSJ at 25:17-
2
19.) As noted above, the term significantly “requires consideration of context and intensity.” 40
3
C.F.R. § 1508.27. With a site-specific project such as the Willits Bypass Project, in evaluating
4
context, “significance would usually depend upon the effects in the locale rather than in the world
5
as a whole. Both short- and long-term effects are relevant.” Id. § 1508.27(a). In addition, when
6
evaluating intensity, one factor to consider is the “[u]nique characteristics of the geographic area
7
such as proximity to … prime farmlands[.]” Id. § 1508.27(b)(3).
8
The NEPA Plaintiffs argue that the land management practices adopted as part of the
9
mitigation efforts will cause a loss to farmlands and will decrease agricultural activities in the area.
From that conclusion, the NEPA Plaintiffs presume that these changes were “significant” and
11
United States District Court
Northern District of California
10
argue that Caltrans should have prepared a Supplemental EIS. In the 2011 Re-Evaluation,
12
Caltrans noted that “[w]ith the multiplier effect the economic effect of reduced cattle grazing from
13
the wetland rehabilitation efforts in the October 2011 draft MMP are estimated at $300,000
14
annually.” (Caltrans AR 2575.) As a result of mitigation requirements, Caltrans also noted that
15
there would be a reduction in grazing on the mitigation parcels. However, none of those acres
16
were designated as “Prime Farmland, Farmland of Statewide Importance, Unique Farmland, or
17
Farmland of Local Importance,” and none of those acres were being used for row crops. (Id.
18
2513-14.)13
Caltrans also stated that, when it issued the Final EIS, it had considered the impacts to
19
20
farmlands and concluded that no significant impacts would occur. (Id. 2513.) Caltrans
21
determined that “[c]urrent conclusions remain the same, even in view of the increases in
22
agricultural land acquired for mitigation purposes and changes to the potential uses on a limited
23
number of such parcels.” (Id. 2513-14.) Caltrans also explained the bases for its conclusion. By
24
way of example, it noted that:
25
13
26
27
28
The Court notes that the record also demonstrates that, during the Section 404 Permit
process, the Corps considered direct and indirect impacts to prime and unique agricultural lands
and food and fiber production, it noted that those impacts did “not rise to the level of significant,
since the amount is a small fraction” of the total acreage and level of production within
Mendocino County as a whole. (Corps AR 303:9592.) Plaintiffs did not challenge those
conclusions in connection with their CWA Claim.
17
1
[a]gricultural production will be limited only in the areas that will be
receiving credits from [the Corps] for wetland mitigation. Pursuant
to its responsibilities under CEQA and NEPA, Caltrans completed a
Farmland Conversion Impact Rating for Corridor Type Projects
form … for submittal to the [National Resource Conservation
Service (“NRCS”)]. The form uses a Land Evaluation and Site
Assessment model (LESA) developed by the U.S. Soil Conservation
Service and recognized by the California Resources Agency. The
LESA provides lead agencies with a methodology to ensure that
potentially significant effects on the environment of agricultural
conversion are quantitatively and consistently considered in the
environmental review process, including CEQA reviews. … The
LESA evaluates measures of soil resource quality (representing
potential farming practices as opposed to actual current uses), a
given project’s size, water resource availability, surrounding
agricultural lands, and surrounding protected resource lands. For a
given project, the factors are rated, weighted and combined,
resulting in a numeric score. The LESA score becomes a basis for
making a determination of the project’s potential significance.
2
3
4
5
6
7
8
9
10
United States District Court
Northern District of California
11
For the Willits Bypass Project, the NRCS completed parts IV, V,
and VII of the form. As result of the combined assessment, the
Willits Bypass Project (including the Ultimate Project alignment and
mitigation) scored just under 147 points. According to the
[Farmland Protection Policy Act (“FPPA”)], sites receiving a total
score of less than 160, need not be given further consideration for
protection, and no additional sites need to be evaluated.
12
13
14
15
Since the submittal of the LESA to NRCS in May 2011, the amount
of grazing to be eliminated has been reduced from nearly 1,000
acres to roughly 500. The LESA score would be reduced
commensurately.
16
17
18
19
(Id. 2513 (emphasis added).)
The NEPA Plaintiffs do not suggest that, in reaching this conclusion, Caltrans relied on
20
impermissible factors. Nor do they suggest that the LESA model is flawed, either in general or as
21
it was applied to the Willits Bypass Project or that Caltrans’ conclusion were contrary to the actual
22
evidence before it.
23
4.
Conclusion on NEPA Claim.
24
It is clear that “an agency need not supplement an EIS every time new information comes
25
to light after the EIS is finalized.” Marsh, 490 U.S. at 373. Rather, the duty to prepare a
26
supplemental EIS arises only when there are changes to a project or new information which result
27
in environmental impacts that “reach a certain threshold,” i.e., they are significant or uncertain.
28
Price Road, 116 F.3d at 1509. It also is clear that NEPA requires agencies “to take a ‘hard look’
18
1
at the environmental effects of their planned action, even after a proposal has received initial
2
approval.” Marsh, 490 U.S. at 374. The Court has carefully considered the Administrative
3
Record, and it concludes that Caltrans took the requisite hard look at the changes to the Willits
4
Bypass Project and the information that developed after it issued the Final EIS.
5
Accordingly, the Court concludes that Caltrans decision not to prepare an EIS was neither
6
arbitrary nor capricious and it DENIES the NEPA Plaintiffs’ motion for summary judgment, and
7
GRANTS Caltrans’ cross-motion for summary judgment.
8
C.
9
The CWA Claim.
1.
CWA Requirements.
The objective of the CWA is to “restore and maintain the chemical, physical, and
11
United States District Court
Northern District of California
10
biological integrity of the Nation’s waters.” 33 U.S.C. § 1251(a). The CWA generally prohibits
12
the discharge of dredged or fill materials into the waters of the United States, which include
13
wetlands, except as in compliance with the CWA. Id. §§ 1311(a), 1362(6)-(7); 33 C.F.R. §
14
328.3(a)-(b). However, the CWA allows the Secretary of the Army to “issue permits, after notice
15
and opportunity for public hearings for the discharge of dredged or fill material into the navigable
16
waters at specified disposal sites” (hereinafter a “Section 404 permit”), in compliance with
17
regulations promulgated by the Corps and guidelines promulgated by the Corps and the
18
Environmental Protection Agency. 33 U.S.C. § 1344; see also 33 C.F.R. §§ 320.1, et seq.; 40
19
C.F.R. §§ 230.1, et seq. The Corps must observe “’[b]oth sets of rules,’” when it considers an
20
application for a Section 404 permit. Bering Strait Citizens for Responsible Resource
21
Development v. United States Army Corps of Engineers, 524 F.3d 938, 947 (9th Cir. 2008)
22
(quoting Friends of the Earth v. Hintz, 800 F.2d 822, 829 (9th Cir. 1986)).
23
24
25
26
27
28
The decision whether to issue a permit will be based on an
evaluation of the probable impacts, including cumulative impacts, of
the proposed activity and its intended use on the public interest.
Evaluation of the probable impact which the proposed activity may
have on the public interest requires a careful weighing of all those
factors which become relevant in a particular case. The benefits
which may be expected to accrue from the proposal must be
balanced against its reasonably foreseeable detriments. The decision
whether to authorize a proposal, and if so, the conditions under
which it will be allowed to occur, are therefore determined by the
outcome of this general balancing process. That decision should
19
reflect the national concern for both protection and utilization of
important resources. All factors which may be relevant to the
proposal must be considered including the cumulative effects
thereof[.] … For activities involving 404 discharges, a permit will
be denied if the discharge that would be authorized by such permit
would not comply with [EPA guidelines.] Subject to the preceding
sentence and any other applicable guidelines and criteria (see
[sections] 302.2 and 320.3), a permit will be granted unless the
district engineer determines that it would be contrary to the public
interest.
1
2
3
4
5
6
33 C.F.R. § 320.4(a)(1).
The regulations and guidelines provide that “[n]o discharge of dredged or fill material shall
7
be permitted if there is a practicable alternative to the proposed discharge which would have less
9
adverse impact on the aquatic ecosystem, so long as the alternative does not have other significant
10
adverse environmental consequences.” 40 C.F.R. § 230.10(a); see also Bering Strait, 524 F.3d at
11
United States District Court
Northern District of California
8
947. “‘In evaluating whether a given alternative site is practicable, the Corps may legitimately
12
consider such facts as cost to the applicant and logistics. In addition, the Corps has a duty to
13
consider the applicant’s purpose.’” Bering Strait, 524 F.3d at 947 (quoting Sylvester v. United
14
States Army Corps of Engineers, 882 F.2d 407, 409 (9th Cir. 1989)); see also 40 C.F.R. §
15
230.10(a)(2).
The guidelines also provide that “no discharge of dredged or fill material shall be permitted
16
17
which will cause or contribute to significant degradation of the waters of the United States,”
18
including “significantly adverse effects of the pollutants on human health or welfare, … aquatic
19
life and other wildlife dependent on aquatic ecosystems, … aquatic ecosystem diversity, … or
20
recreational, aesthetic, and economic values.” 40 C.F.R. § 230.10(c)(1)-(4). Further, “no
21
discharge of dredged or fill material shall be permitted unless appropriate and practicable steps
22
have been taken which will minimize potential adverse impacts of the discharge on the aquatic
23
ecosystem.” Id. § 230.10(d.) Finally, “[m]itigation is an important aspect of the review and
24
balancing process on many … permit applications. Consideration of mitigation will occur
25
throughout the permit application review process and includes avoiding, minimizing, rectifying,
26
reducing, or compensating for resource losses….” 33 C.F.R. § 320.4(r)(1); see also id. §
27
325.4(a)(3) (Corps may condition issuance of permit on mitigation.).
28
///
20
1
2.
Standard of Review.
2
Unlike the NEPA Plaintiffs’ claim, it is clear that the CWA claim is a challenge to a final
3
agency action, specifically the decision to issue the Section 404 Permit. Accordingly, the Court
4
analyzes this claim under the arbitrary and capricious standard. 5 U.S.C. § 706(2). The Court will
5
overturn the Corps’ decision only if the Corps “relied on factors Congress did not intend it to
6
consider, entirely failed to consider an important aspect of the problem, or offered an explanation
7
that runs counter to the evidence before the agency or is so implausible that it could not be
8
ascribed to a difference in view or the product of agency expertise.” Lands Council, 537 F.3d at
9
987.
3.
11
United States District Court
Northern District of California
10
Analysis.
It is undisputed that: (1) the wetlands in the Willits Bypass Project area qualify as
12
“navigable waters” under the CWA; (2) the project is not “water dependent;” (3) the Willits
13
Bypass Project will involve the discharge of dredged or fill materials into those waters; and (4)
14
that a Section 404(a) Permit is required. Plaintiffs argue that the Corps violated the CWA when it
15
approved the Section 404(a) Permit, because it: (1) improperly rejected less damaging practicable
16
alternatives; (2) failed to independently select the LEDPA; and (3) relied on and approved an
17
inadequate and incomplete MMP.
18
19
a.
Improper rejection of less damaging practicable alternatives.
Plaintiffs argue that the Corps improperly conflated the “purpose and need” requirements
20
of NEPA with the CWA’s requirement to consider the “overall project purposes.” Compare 40
21
C.F.R. § 230.10(a)(2) with 40 C.F.R. § 1502.13; 33 C.F.R. § 325, App. B, ¶ 9(b)(4). In its
22
decision to grant the Section 404 Permit, the Corps stated that “[t]he overall project purpose is to
23
reduce traffic congestion and increase pedestrian safety” and it concluded that Modified
24
Alternative JIT was the LEDPA. The Corps also considered Caltrans’ view that a “minimum level
25
of LOS C” was required to fulfill the Willits Bypass Project’s purpose and need. (See Corps AR
26
at 24:2998, 303:9581.) Plaintiffs argue that this decision was arbitrary and capricious, because
27
two-lane alternatives would have satisfied the overall project purpose.
28
The Corps did accept Caltrans view of the purpose and need for the Willits Bypass Project.
21
1
However, there is nothing inherently improper in that conclusion, i.e. the Corps was not relying on
2
factors that Congress did not intend it to consider. See, e.g., Butte Environmental Council v.
3
United States Army Corps of Engineers, 620 F.3d 936 (9th Cir. 2010). In Butte Environmental
4
Council, the plaintiff challenged the decision to grant a Section 404 permit for a proposed business
5
park to the city of Redding (“the City”). The plaintiff argued that the Corps acted arbitrarily and
6
capriciously by deferring to the City’s judgment that it required a site large enough to
7
accommodate at least one 100-acre parcel. The Ninth Circuit rejected this argument.
8
9
10
United States District Court
Northern District of California
11
12
13
14
Far from blindly accepting the project’s stated purpose, the Corps
initially expressed skepticism that the City needed a site large
enough to accommodate a 100-acre parcel[.] In response, the City
revised its EIS to clarify that “a medium to large parcel business
park” was necessary to meet the manufacturing and distribution
needs of interested business-park users and to create the desired
“synergy” among the park’s occupants. It is true that the Corps
ultimately accepted the City’s revised statement of purpose and
conducted its analysis in light of it. But “the Corps has a duty to
consider the applicant’s purpose,” where, as here, that purpose is
“genuine and legitimate.”
Id. at 946 (quoting Sylvester, 882 F.2d at 409) (emphasis added).
15
In this case, as in Butte Council, when phased construction became a reality, the Corps did
16
not blindly accept that Modified Alternative JIT remained the LEDPA. Rather, the Corps rejected
17
Caltrans’ initial application for a Section 404 Permit. It specifically cited phased construction and
18
stated that it “conclude[d] there are other practicable alternatives to the [Willits Bypass Project]
19
with less adverse impact on the aquatic ecosystem or without other significant adverse
20
environmental impacts.” (Corps AR 7:453; see also id. 7:452-453 (rejecting application because
21
“the Willits Bypass Project will result in alteration and/or destruction of wetlands to a magnitude
22
that would contribute to significant degradation of waters of the United States,” and because “the
23
proposed MMP does not provide the necessary assurances to allow the Corps to determine the
24
proposed MMP will be adequate, self-sustaining, or feasible enough to replace the wetlands
25
functions lost to project construction”).)
26
The Corps then advised Caltrans it could possibly issue a permit if certain revisions were
27
made. It set forth five conditions that, at a minimum, Caltrans would be required to address in a
28
revised application, including updated traffic studies to support the purpose and need of the
22
1
project. (Id. 7:453-454.) After it considered the revised traffic studies, the Corps accepted
2
Caltrans’ conclusion that a minimum level service of LOS C was required. Although Plaintiffs
3
disagree with this conclusion, they do not point to anything in the record to suggest that Caltrans’
4
stated “purpose and need” was not genuine or legitimate. Thus, the Corps had a duty to consider
5
that purpose. Butte County, 620 F.3d at 946.
6
Furthermore, Caltrans maintained that part of the purpose and need for the Willits Bypass
7
Project was to construct a bypass that “would provide at least [an LOS C] through the 20-year
8
design period (i.e. 2028). A two-lane facility would provide a LOS ‘D’ at peak hour upon
9
construction and throughout the 20-year design period.” (Corps AR 16:889; see also id. 16:897,
17:1581 (noting that a two-lane facility would be “functionally obsolete within 20 year design
11
United States District Court
Northern District of California
10
period”; 303:9581 (noting that even with updated traffic studies, a two-lane bypass would only
12
provide LOS D).) Based on this record, the Court cannot say an LOS C level of service was
13
incidental to the Willits Bypass Project. See, e.g., Sylvester, 882 F.2d at 409 (noting that an
14
alternative site for project did “not have to accommodate components … that are merely incidental
15
to the applicant’s basic purpose”) (emphasis in original).
16
The Corps relied on factors that it was entitled to and required to consider. After carefully
17
evaluating the other alternatives, the Corps concluded that Modified Alternative JT1 remained the
18
LEPDA. The Court finds that decision was neither arbitrary nor capricious.
b.
19
Failure to independently select the LEDPA.
20
Plaintiffs also argue that the Corps failed to independently select the LEDPA, relying on a
21
series of letters that Caltrans sent to the Corps in January and February of 2012, in response to the
22
Corps’ request for additional information on traffic patterns. (See Corps AR 215:4882-4916,
23
394:10416, 301:9568-9570, 395:10417-419.) Plaintiffs argue that these letters provide
24
contradictory information about whether traffic patterns had increased or decreased over specific
25
periods and include unsupported information about whether or not local traffic would utilize the
26
Willits Bypass Project. Plaintiffs further argue Corps should have requested additional
27
information from Caltrans about these studies. The Court does not find Plaintiffs’ arguments
28
persuasive.
23
1
When it initially rejected Caltrans’ Section 404 Permit application, the Corps stated that it
2
would “require[] updated traffic studies.” (Corps AR 7:454.) It is not clear from the record that
3
Caltrans’ information on updated studies on traffic patterns and usage are “directly contradictory,”
4
such that it would have raised a red flag that might have required the Corps to request further
5
information. Caltrans also advised the Corps that it had “modeled and analyzed” a “two-lane,
6
controlled access, at-grade Willits Bypass Alternative (modified JT-1 [sic]),” and that it used the
7
Highway Capacity Manual published by the Transportation Research Board of the National
8
Academies (“HCM”) to analyze the “proposed signalized intersections, … as well as the mainline
9
segment.” (Id. 394:10416; see also id. 301:9569.) Caltrans noted that, although there had been
some “decrease in peak hour traffic along US 101 over the previous twelve years[,] … [u]sing the
11
United States District Court
Northern District of California
10
current lower traffic volumes” the intersections operated at an LOS C and the mainline operated at
12
an LOS D, “regardless of striping.” (Id. 394:10416)
13
Caltrans later clarified that the HCM relies on the “mainline” level of service to determine
14
“the number of lanes that are required to be built for streets or highways,” that Caltrans had used
15
Highway Capacity Software (“HCS”) to determine the mainline level of service, and that HCS is
16
“widely used in the traffic engineering industry for level of service calculation.” (Id. 301:9569.)
17
Caltrans also advised the Corps that, even with a reduction in traffic volume in the short term, the
18
mainline of the Willits Bypass Project would operate only at an LOS D, which was why a two-
19
lane option was not sufficient. (Id. 301:9568-70.) Plaintiffs have not questioned the validity of, or
20
the propriety of Caltrans’ reliance on, the HCM or HCS.
21
As discussed above, Caltrans has maintained consistently that it must be able to maintain a
22
minimum LOS Cover the 20 year design period of the Willits Bypass Project. (See, e.g., id.
23
(16:889, 16:897, 17:1581, 215:4894, 303:9581.) In response to comments about the traffic
24
studies, Caltrans noted the “short-term decline in traffic on US 101” and stated that “[t]he current
25
economic recession has affected traffic levels throughout the country.” (Id. 303:9658.) Caltrans
26
also cited research that indicated this trend was beginning to reverse in urban areas, and that rural
27
areas tend to “lag behind when it comes to economic recovery.” Caltrans also cited studies that
28
suggested the population in the vicinity of the Willits Bypass Project would grow. (Id. 303:965824
1
59.) Thus, notwithstanding a short-term decrease in traffic volume, Caltrans offered the Corps
2
information that suggested traffic volume would increase over the 20 year design period.
3
Plaintiffs may disagree with these studies, but they do not point Court to any evidence in the
4
record that contradicts the studies upon which Caltrans relied. Thus, they do not point the Court to
5
any evidence that suggests that the Corps’ decision to grant the Section 404 Permit was contrary to
6
the evidence it had before it.
7
In responding to the Corps’ concerns, Caltrans also concluded that the Willits Bypass
8
Project would require four lanes, rather than two, because local traffic would use the Willits
9
Bypass Project to “get around town.” (See id. 395:10417-10418.) Plaintiffs argue that this
10
conclusion is not supported. However, Caltrans explained its rationale for this conclusion:
United States District Court
Northern District of California
11
12
13
14
15
The methodology used to generate the estimated numbers of bypass
users are based on well-established rules used in modeling. The
primary rule is the concept of “least cost.” When all other factors
are equal a driver will follow a path of least cost. In traffic
modeling, least cost equates to time savings. Intuitively it makes
perfect sense when a driver is given two options to reach a
destination (on takes more time and one takes less) the driver will
choose the one that takes less time even if it requires traveling
further in distance.
16
17
(Id. 303:9658-59.)
18
Plaintiffs may argue that Caltrans’ analogy to more urbanized areas is flawed, but they do
19
not point to anything in the record to contradict Caltrans’ reliance on the “least cost” principle. In
20
sum, Plaintiffs have not pointed to anything in the record that would suggest that the Corps’
21
conclusions regarding Caltrans’ updated traffic studies ran contrary to the evidence before it or are
22
so implausible that they could not be ascribed to a difference in view or the product of agency
23
expertise. Lands Council, 537 F.3d at 987.
24
The Court concludes the Corps did not arbitrarily and capriciously conclude that Modified
25
Alternative J1T was the LEDPA.
26
c.
27
28
Mitigation and Monitoring Plan.
Finally, Plaintiffs argue that the MMP is missing information and fails to analyze
mitigation for the second phase of the Willits Bypass Project.
25
i.
1
Missing information.
Plaintiffs argue that the MMP lacks information on flood control and treatment of the flood
2
3
plain, construction related temporary impacts, and grazing on mitigation parcels. The Corps is
4
“required to develop … proposed mitigation measures ‘to a reasonable degree,’” and is “not
5
required to develop a complete mitigation plan detailing the ‘precise nature … of the mitigation
6
measures[.]’” Tillamook County v. United States Army Corps of Engineers, 288 F.3d 1140, 1144
7
(9th Cir. 2002) (quoting Wetlands Action Network v. United States Army Corps of Engineers, 222
8
F.3d 1105, 1121 (9th Cir. 2000), abrogated on other grounds by Wilderness Society v. United
9
States Forest Service, 630 F.3d 1173 (9th Cir. 2011)). The Corps also is not required to
“‘completely compensate for adverse environmental impacts.’” Id. (quoting Wetlands Action
11
United States District Court
Northern District of California
10
Network, 222 F.3d at 1121).
The MMP contains a statement that wetlands in the vicinity of the Willits Bypass Project
12
13
function to attenuate “floodflow” and describes the history of flooding in the area as well as the
14
factors that contribute to flooding. (Corps AR 303:8663-8664, 8717-8718, 8724-8725.) To
15
address that issue, the MMP provides for, inter alia, establishing vegetated wetlands “in riparian
16
habitat established adjacent to stream channels.” (Id. 303:8693; see also id. 303:8698 (noting that
17
rehabilitation as mitigation measure will “enhance wetlands through increase in biomass,” which
18
will “decrease water velocity during high-flow events”).) The MMP also contains detailed
19
information about the overall mitigation plan, a plan for each mitigation parcel of land, and the
20
reasons a certain type of mitigation was chosen for those parcels. (See, e.g., Corps AR 272:8816-
21
8895.)
22
Plaintiffs do not challenge those mitigation efforts. Rather, they focus on the fact that
23
Caltrans stated that “there may be a need to address sedimentation accumulation in streams such
24
as Outlet and Davis Creek if it … threatens to induce flooding of a neighboring property.” (Corps
25
AR 303:9710 (response to comments on “concern regarding resolution if conflict occurs between
26
neighboring parcels managed for agriculture and wetlands”).) After acknowledging this fact,
27
Caltrans stated that it “has added a section in the adaptive management chapter that will allow the
28
land manager the flexibility to work with the stakeholder regulatory agencies to perform
26
1
maintenance on the streams if needed.” (Id.; see also id. 272:8936-8937 (discussing changes in
2
hydrology, including flooding, that might require adaptive management and type of actions that
3
would be taken).)
4
The adaptive management chapter of the MMP describes what type of actions will be taken
5
in the event of flooding in the mitigation areas and notes that “where it is clear that an action taken
6
by the land manager … in order to comply with the mitigation commitments threatens to flood a
7
neighboring property, immediate action will be taken to prevent such flooding.” (Id. 272:8949.)
8
In addition, the MMP contains erosion schedules, and Plaintiffs do not challenge the figures and
9
information set forth in those schedules. (Id. 270:8410-8416.) The record shows that the Corps
has made a genuine effort to develop a detailed mitigation plan, and “the mere fact that one aspect
11
United States District Court
Northern District of California
10
of the plan is not yet finalized [does not] lead to the conclusion that the Corps’ decision was
12
arbitrary and capricious.” Bering Strait, 524 F.3d at 950-51.
13
Plaintiffs also argue that the MMP lacks information and analysis about construction
14
related impacts. However, the MMP contains information about which construction-related
15
impacts would be considered permanent and which construction-related impacts were temporary,
16
i.e. “areas that are filled temporarily during construction.” (Corps AR 272:8678.) In addition, the
17
MMP states that in order to monitor groundwater, wells were installed “in wet meadows in the
18
haul road alignment to determine whether project impacts from the haul roads would be
19
temporary, as expected, or permanent.” (Id. 272:8730.) The MMP also requires Caltrans and its
20
contractor to use Best Management Practices during construction. Although Plaintiffs argue that
21
the Corps should not have deferred to Caltrans’ reliance on the BMPs, Plaintiffs do not challenge
22
the validity of those practices. (See id. 8691-92, 8875-76.)
23
Finally, with respect to grazing, there are approximately 2000 acres of land subject to
24
mitigation, 400 of which are covered by the MMP. Plaintiffs argue that the Corps should not have
25
approved the MMP until the State mitigation plan for the remaining 1600 acres was complete.
26
“Processing of an application for a [Section 404] permit normally will proceed concurrently with
27
the processing of other required Federal, state, and/or local authorizations or certifications. Final
28
action on the … permit will not normally be delayed pending action by another Federal, state or
27
1
local agency.” 33 C.F.R. § 320.4(j)(1); see also Robertson, 490 U.S. at 352-53 (noting that it
2
would be incongruous to conclude that a federal agency “has not power to act until the local
3
agencies have reached a final conclusion on what mitigating measures they consider necessary”).
4
The Court concludes that the MMP is reasonably developed as to the grazing issues and
5
concludes that the Corps’ decision to issue the Section 404(b) permit in the absence of final
6
grazing plan from the State was neither arbitrary nor capricious.
7
ii.
Failure to analyze mitigation for Phase II.
8
It is undisputed that the MMP does not include mitigation for Phase II of the Willits
9
Bypass Project. However, the Section 404 Permit includes a special condition regarding Phase II,
10
United States District Court
Northern District of California
11
12
13
14
15
16
17
18
19
20
21
22
23
24
which provides as follows:
The Permittee (Caltrans) is not authorized to commence fill or
construction activities associated with Phase II of the Project until
after the Corps has provided a written notice to proceed with Phase
II. Design-level drawings for Phase II shall be submitted to the
Corps a minimum of two years prior to the anticipated
commencement of construction. In addition, a draft mitigation plan
in accordance with the requirements of 33 C.F.R. § 332.4(c) must be
submitted to the Corps to address Phase II project impacts. The
draft submittal must allow two (2) years of development and review
such that the final mitigation plan is developed prior to the proposed
start of Phase II construction. The draft mitigation plan shall
address the 8.31 acres of permanent and 8.07 acres of temporary
impacts to waters of the U.S. associated with Phase II through
restoration/establishment/enhancement of waters of the U.S. and
shall ensure that there will not be a net loss of aquatic resource
functions and services resulting from Phase II. The Phase II final
mitigation plan will be submitted for public review and comment via
Public Notice, and the Permittee shall adequately respond to all
comments prior to Corps approval of the plan. No work in waters of
the U.S. associated with Phase II is authorized until the Permittee
receives, in writing, Corps approval of the final mitigation plan and
Corps acknowledgement of the receipt of the Phase II design-level
drawings. The Permittee shall fully implement this Phase II final
mitigation plan concurrently with, or prior to, Phase II impacts to
waters of the U.S.
Although the MMP does not include mitigation for Phase II, when it prepared the MMP,
25
Caltrans calculated the total number of acres that would be permanently and temporarily impacted
26
by the “ultimate four-lane project.” (Corps AR 272:8679.) The Corps also did not ignore the fact
27
of phased construction or its impacts. (See, e.g., Corps AR 303:9576-9577, 9581.) “That the
28
Corps intends to pursue additional mitigation opportunities at a later time does not conflict with
28
1
the requirement of the CWA unless the mitigation measures that have been fully developed are
2
inadequate.” Bering Strait, 524 F.3d at 951. For the reasons discussed in the preceding section,
3
the Court cannot say that the mitigation measures that have been fully developed are inadequate.
4
As such, the Court concludes that the Corps’ decision to develop mitigation measures for Phase II
5
of the Willits Bypass Project at a later time was neither arbitrary nor capricious.
6
4.
Conclusion on CWA Claim.
7
The Court has carefully considered the Administrative Record, and it concludes that the
8
Corps’ decision to grant the Section 404 Permit was neither arbitrary nor capricious, and it
9
DENIES Plaintiffs’ motion for summary judgment, and GRANTS the Corps’ cross-motion for
10
summary judgment.
United States District Court
Northern District of California
11
The Court shall enter a separate judgment, and the Clerk shall close the file.
12
IT IS SO ORDERED.
13
14
15
Dated: December 19, 2013
______________________________________
JEFFREY S. WHITE
United States District Judge
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?