CSR Technology, Inc. v. Freescale Semiconductor, Inc.
Filing
61
CASE MANAGEMENT ORDER NO. 2; ORDER SETTING CASE MANAGEMENT CONFERENCE re 58 STIPULATION WITH PROPOSED ORDER re 60 Joint Case Management Statement. Initial Case Management Conference set for 3/27/2013 at 2:00 PM in Courtroom 9, 19th Floor, San Francisco. Signed by Judge Jon S. Tigar on March 6, 2013. (wsn, COURT STAFF) (Filed on 3/7/2013)
1
2
UNITED STATES DISTRICT COURT
3
NORTHERN DISTRICT OF CALIFORNIA
4
5
CSR TECHNOLOGY, INC.,
Plaintiff,
6
v.
7
8
FREESCALE SEMICONDUCTOR, INC.,
Defendant.
9
10
Case No. 12-cv-02619-JST
CASE MANAGEMENT ORDER NO. 2;
ORDER SETTING CASE
MANAGEMENT CONFERENCE
Re: Dkt. Nos. 58, 60
Date: March 27, 2013
Time: 2:00 P.M.
Hon. Jon S. Tigar
Courtroom 9, 19th Floor
United States District Court
Northern District of California
11
Before the Court are competing case schedules proposed by the parties in their Joint Case
12
Management Statement, Dkt. No. 60. The Court now adopts the following case schedule, which
13
extends the prior schedule to account for the additional time required by Defendant Freescale to
14
file a motion to receive adequate infringement contentions. See Order Granting in Part and
15
Denying in Part Motion to Compel, Dkt. No. 56 (Feb. 8, 2013) (“Plaintiff’s contentions consist of
16
nothing more than a conclusion based ‘on information and belief’ that since calibration in the Accused
17
Products occurs, it must occur according to the claimed method”).
18
The parties shall appear for a case management conference on Wednesday, March 27,
19
2013, at 2:00 P.M., in Courtroom 9, 19th Floor, 450 Golden Gate Ave., San Francisco, California,
20
at which time the Court will set firm dates for the last two items on the case schedule and address
21
any other issues related to the management of the case.
22
Event
Date
24
Deadline to Supplement Infringement Contentions
(Patent L.R. 3-1 & 3-2)
03/11/13
25
Deadline to Supplement Invalidity Contentions
(Patent L.R. 3-3 & 3-4)
04/25/13
Parties to Exchange Terms for Construction (Patent L.R. 4-1)
05/09/13
Parties to Exchange Proposed Constructions (Patent L.R. 4-2)
05/30/13
23
26
27
28
1
Event
Date
2
Joint Claim Construction and Pre-Hearing Statement
(Patent L.R. 4-3)
06/24/13
3
Completion of Claim Construction Discovery (Patent L.R. 4-4)
07/24/13
4
CSR’s Opening Claim Construction Brief (Patent L.R. 4-5)
08/08/13
5
Freescale’s Responsive Claim Construction Brief
(Patent L.R. 4-5)
08/22/13
CSR’s Reply Claim Construction Brief (Patent L.R. 4-5)
08/29/13
Technology Tutorial
September, 2013
Claim Construction Hearing (Patent L.R. 4-6)
September, 2013
6
7
8
9
10
United States District Court
Northern District of California
11
12
13
14
IT IS SO ORDERED.
Dated: March 6, 2013
______________________________________
Jon S. Tigar
United States District Judge
15
16
17
18
19
20
21
22
23
24
25
26
27
28
2
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?