Asetek Holdings, Inc et al v. Coolit Systems Inc
Filing
75
STIPULATION AND ORDER re 73 STIPULATION WITH PROPOSED ORDER STIPULATED REQUEST FOR ORDER AMENDING CASE MANAGEMENT ORDER; PROPOSED ORDER filed by Coolit Systems Inc Claims Construction Hearing set for 11/4/2013 02:30 PM. Tutorial Hearing set for 10/21/2013 10:00 AM in Courtroom 5, 17th Floor, San Francisco. Claims Construction Hearing set for 11/5/2013 02:30 PM.. Signed by Judge Edward M. Chen on 3/12/13. (bpf, COURT STAFF) (Filed on 3/12/2013)
1
2
3
4
5
COOLEY LLP
HEIDI L. KEEFE (178960)
(hkeefe@cooley.com)
DANIEL J. KNAUSS (267414)
(dknauss@cooley.com)
Five Palo Alto Square
3000 El Camino Real
Palo Alto, CA 94306-2155
Telephone:
(650) 843-5000
Facsimile:
(650) 849-7400
ROBERT F. McCAULEY (162056)
(robert.mccauley@finnegan.com)
TINA E. HULSE (232936)
(tina.hulse@finnegan.com)
FINNEGAN, HENDERSON, FARABOW,
GARRETT & DUNNER LLP
3300 Hillview Avenue
Palo Alto, CA 94304
Telephone:
(650) 849-6600
Facsimile:
(650) 849-6666
DENNIS McCOOE
(mccooe@blankrome.com)
(admitted Pro Hac Vice)
KATHERINE BARECCHIA
(barecchia@blankrome.com)
(admitted Pro Hac Vice)
JOEL DION (dion-j@blankrome.com)
(admitted Pro Hac Vice)
BLANK ROME LLP
One Logan Square
130 North 18th Street
Philadelphia, PA 19103
Telephone:
(215) 569-5580
Facsimile:
(215) 832-5580
Attorneys for Plaintiffs
ASETEK HOLDINGS, INC. and
ASETEK A/S
6
7
8
9
10
11
12
13
14
Attorneys for Defendant
CoolIT Sysytems, Inc.
15
UNITED STATES DISTRICT COURT
16
NORTHERN DISTRICT OF CALIFORNIA
17
SAN FRANCISCO DIVISION
18
19
ASETEK HOLDINGS, INC. and ASETEK A/S,
20
21
22
Plaintiffs,
v.
COOLIT SYSTEMS INC.,
23
Defendant.
CASE NO. 3:12-CV-04498-EMC
STIPULATED REQUEST FOR ORDER
AMENDING CASE MANAGEMENT
ORDER
[PROPOSED] ORDER
(as modified)
24
25
26
27
28
CASE NO. 3:12-CV-04498-EMC
STIPULATION AND [PROPOSED] ORDER RE
CASE MANAGEMENT ORDER
1
On January 17, 2013, the Court held an Initial Case Management Conference. At the
2
Initial Case Management Conference, the Court adopted the parties’ proposed Case Management
3
Order through the completion of claim construction discovery and set a further case management
4
conference for May 23, 2013 at 10:30 am. On February 26, 2013, CoolIT filed its amended
5
answer to Asetek’s amended complaint and amended counterclaims.
6
counterclaims included a claim for infringement of CoolIT’s U.S. Pat. No. 8,382,456, which
7
issued on February 26, 2013. The parties are preparing to exchange the contentions required by
8
the Patent Local Rules in connection with CoolIT’s patent. The parties agree that, in view of
9
CoolIT’s new counterclaim, coordination of dates for claim construction proceedings for Asetek’s
10
CoolIT’s amended
patents-in-suit and CoolIT’s patent-in-suit would be efficient.
11
Accordingly, the parties submit that good cause exists to amend the Case Management
12
Order in view of the desirability of coordinating claim construction for all patents now involved
13
in this case.
14
The parties propose the following amended schedule:
15
EVENT
16
Last Day for CoolIT to Serve Disclosure of
Asserted Claims and Infringement
Contentions (and accompanying document
production)
17
18
19
20
21
22
23
PROPOSED SCHEDULE
March 19, 2013
Last Day for Asetek to Serve Preliminary
Invalidity Contentions (and accompanying
document production)
May 3, 2013
Last Day for Parties to Exchange List of
“Proposed Terms and Claim Elements for
Construction”
May 17, 2013
Case Management Conference
May 23, 2013 at 10:30 am
24
25
26
27
Meet and confer to identify 10 terms
May 24, 2013
Exchange of Preliminary Claim
Constructions and Extrinsic Evidence
June 7, 2013
28
CASE NO. 3:12-CV-04498-EMC
1
STIPULATION AND [PROPOSED] ORDER RE
CASE MANAGEMENT ORDER
EVENT
1
2
3
4
5
PROPOSED SCHEDULE
Meet and confer re Joint Claim
Construction and Prehearing Statement
June 14, 2013
Joint Claim Construction and Prehearing
Statement
July 2, 2013
Complete claim construction discovery
July 16, 2013
6
7
8
Opening claim construction briefs
July 30, 2013
Responsive Briefs
August 13, 2013
9
10
Reply Briefs
11
- Oct. 21, 2013 at 10:00 a.m.
Tutorial
Claim Construction Hearing - Nov. 4 & 5 at
September 3, 2013, or at the earliest next
2:30 p.m. available date of the Court
12
13
14
15
16
August 20, 2013
Close of Fact Discovery
Last Day to File Motions for Leave to
Amend the Pleadings
December 17, 2013 or sixty days from
issuance of the claim construction order,
whichever is later
Initial Expert Reports (on issues upon
which party bears burden of proof)
January 7, 2014 or 21 days after the close of
fact discovery, whichever is later
Rebuttal Expert Reports
February 6, 2014 or 30 days after initial expert
reports, whichever is later
Close of Expert Discovery
March 10, 2014 or 30 days after rebuttal
expert reports, whichever is later
Last Day to File Dispositive Motions
March 24, 2014 or 14 days after close of
expert discovery, whichever is later
Final Pretrial Conference
TBD
Trial
May 2014 (subject to the Court’s availability)
17
18
19
20
21
22
23
24
25
26
27
28
CASE NO. 3:12-CV-04498-EMC
2
STIPULATION AND [PROPOSED] ORDER RE
CASE MANAGEMENT ORDER
1
By his signature below, counsel for Defendant attests that counsel for Plaintiffs concurs in
2
the filing of this stipulation.
3
Dated: March 8, 2013
4
Respectfully submitted,
BLANK ROME LLP
5
By:
6
7
Dated: March 8, 2013
9
FINNEGAN, HENDERSON, FARABOW,
GARRETT & DUNNER, LLP
10
11
By:
/s/Robert F. McCauley
Robert F. McCauley
Attorneys for Plaintiffs
Asetek A/S and Asetek Holdings, Inc.
12
13
14
15
Respectfully submitted,
[PROPOSED] ORDER
PURSUANT TO STIPULATION, IT IS SO ORDERED.
18
19
20
UNIT
ED
12
Dated: March __, 2013
S DISTRICT
TE
C
TA
RT
U
O
17
S
16
The Honorable Edward M. Chen
United StatesDERED
R District Judge
Northern District ED
of California
S SO O
IT I
DIFI
AS MO
R NIA
8
/s/Dennis P. McCooe
Dennis P. McCooe
Attorneys for Defendant
CoolIT Systems Inc.
22
Stipulated Request for Order Amending Case Management Order. In compliance with General
E
FO
A
H
LI
RT
23
NO
21
ATTESTATION PER GENERAL ORDER 45
en
d M. Ch
e Edwar being used to file this
Judg
I, Daniel J. Knauss, am the ECF User whose ID and password are
C
O F filing.
D IS T IC T
Order 45, X.B., I hereby attest that the counsel listed above have concurred with this
R
RN
24
25
Dated: March 8, 2013
26
27
/s/ Daniel J. Knauss
DANIEL J. KNAUSS
Attorneys for Defendant
CoolIT Systems, Inc.
1105849 v1/HN
28
CASE NO. 3:12-CV-04498-EMC
3
STIPULATION AND [PROPOSED] ORDER RE
CASE MANAGEMENT ORDER
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.