Verinata Health, Inc. et al v. Ariosa Diagnostics, Inc et al
Filing
38
ORDER setting claim construction schedule re #36 . Signed by Judge Susan Illston on 2/27/13. (tfS, COURT STAFF) (Filed on 2/28/2013) Modified on 3/1/2013 (ysS, COURT STAFF).
1 WEIL, GOTSHAL & MANGES LLP
Edward R. Reines (135960)
2 (edward.reines@weil.com)
Derek C. Walter (246322)
3 (derek.walter@weil.com)
Michele A. Gauger (281769)
4 (michele.gauger@weil.com)
Aaron Y. Huang (261903)
5 (aaron.huang@weil.com)
IRELL & MANELLA LLP
David I. Gindler (117824) (dgindler @irell.com)
Andrei Iancu (184973) (aiancu@irell.com)
Amir Naini (226627) (anaini@irell.com)
1800 Avenue of the Stars, Suite 900
Los Angeles, California 90067-4276
Telephone:
(310) 277-1010
Facsimile:
(310) 203-7199
Attorneys for Defendants
ARIOSA DIAGNOSTICS, INC.
and
LABORATORY CORPORATION OF
AMERICA HOLDINGS
6 Silicon Valley Office
201 Redwood Shores Parkway
7 Redwood Shores, CA 94065
Telephone: (650) 802-3000
8 Facsimile: (650) 802-3100
9 Attorneys for Plaintiffs
VERINATA HEALTH, INC.
10 and
THE BOARD OF TRUSTEES OF THE
11 LELAND STANFORD JUNIOR
UNIVERSITY
UNITED STATES DISTRICT COURT
12
13
NORTHERN DISTRICT OF CALIFORNIA
14
SAN FRANCISCO DIVISION
I
us
Judge S
24
25
A
H
ER
LI
RT
23
n
an Illsto
NO
22
ERED
ORD
T IS SO
R NIA
Defendants.
21
S DISTRICT
TE
C
TA
RT
U
O
19 ARIOSA DIAGNOSTICS, INC. and
LABORATORY CORPORATION OF
20 AMERICA HOLDINGS,
STIPULATED CLAIM CONSTRUCTION
SCHEDULE
FO
v.
18
Case No. 3:12-cv-05501-SI
S
Plaintiffs,
17
)
)
)
)
)
)
)
)
)
)
)
)
)
)
UNIT
ED
15 VERINATA HEALTH, INC. and THE
BOARD OF TRUSTEES OF THE LELAND
16 STANFORD JUNIOR UNIVERSITY,
N
F
D IS T IC T O
R
C
26
27
28
Stipulated Claim Construction Schedule
2775819
Case No. 12-CV-05501-SI
Pursuant to the Court’s February 13, 2013 docket entry resetting the claim construction
1
2 hearing date and the Amended Civil Minutes ordering the submission of a patent schedule in this
3 case, Plaintiffs Verinata Health, Inc. (“Verinata”) and The Board of Trustees of the Leland
4 Stanford Junior University (“Stanford”), and Defendants Ariosa Diagnostics, Inc. (“Ariosa”) and
5 Laboratory Corporation of America Holdings (“LabCorp”), jointly submit this statement and
6 stipulation regarding the claim construction schedule.
7 I.
PRELIMINARY STATEMENT
8
The parties in this action have met and conferred, and have agreed to the claim
9 construction schedule presented below. The schedule is based upon the technology tutorial and
10 claim construction hearing dates set by the Court, and largely follows the Patent Local Rules for
11 the interim deadlines.
12 II.
STIPULATED CLAIM CONSTRUCTION SCHEDULE
13
Event
Date
14
16
Invalidity Contentions and
accompanying document production by
accused infringer
17
Patent L.R. 3-3 & 3-4
18
Exchange of Proposed Terms and Claim
Elements for Construction
15
19
March 22, 2013
April 5, 2013
Patent L.R. 4-1
20
21
Exchange of Preliminary Claim
Constructions and Extrinsic Evidence
22
April 19, 2013
Patent L.R. 4-2
23
24
25
26
27
28
Stipulated Claim Construction Schedule
2775819
-2-
Case No. 12-CV-05501-SI
1
Event
Date
2
3
Filing of Joint Claim Construction and
Pre-Hearing Statement
4
Patent L.R. 4-3
5
May 3, 2013
Status Conference
- Discuss Tutorial Mechanics
6
7
May 24, 2013 at 3:00 p.m., subject to the
Court’s availability1
- Discuss Markman Hearing Mechanics
8
Completion of Claim Construction
Discovery
9
10
Patent L.R. 4-4
11
May 31, 2013
Opening Claim Construction Brief by
Patentee
12
June 5, 2013
Patent L.R. 4-5(a)
13
14
Responsive Claim Construction Brief by
Accused Infringer(s)
15
Patent L.R. 4-5(b)
16
Reply Claim Construction Brief by
Patentee
17
July 3, 2013
July 17, 2013
Patent L.R. 4-5(c)
18
Technology Tutorial
July 31, 2013 at 3:30 p.m.
Claim Construction Hearing
August 7, 2013 at 3:30 p.m.
19
20
21
Patent L.R. 4-6
22
23
24
25
26
27
28
//
1
The parties understand that the Court has ordered that the claim construction-related
issued raised in the parties’ February 20 and 21, 2013 letters to the Court will be addressed at a
Case Management Conference on April 19, 2013. Dkt. No. 35. The parties to the instant action
respectfully propose a status conference to discuss tutorial and claim construction hearing
mechanics following the filing of the joint claim construction and pre-hearing statement on May 3,
2013 in this action. Such conference may be, at the discretion of the Court, in lieu of or in
addition to the April 19 conference. Of course, if the Court wishes to discuss tutorial and claim
construction hearing mechanics on April 19 in light of the information available by that date, the
parties will be prepared to do so.
Stipulated Claim Construction Schedule
2775819
-3-
Case No. 12-CV-05501-SI
1
Respectfully submitted,
2 Dated: February 27, 2013
IRELL & MANELLA LLP
3
By:
4
5
6
7
Dated: February 27, 2013
/s/ Andrei Iancu
Andrei Iancu
Attorneys for Defendants Ariosa
Diagnostics, Inc. and Laboratory
Corporation of America Holdings
WEIL, GOTSHAL & MANGES LLP
8
By:
9
10
11
/s/ Edward R. Reines
Edward R. Reines
Attorneys for Plaintiffs
Verinata Health, Inc. and The Board
of Trustees of the Leland Stanford
Junior University
12
CERTIFICATION
13
I, Andrei Iancu, am the ECF User whose identification and password are being used to file
14
15 this Stipulation. In compliance with General Order 45.X.B, I hereby attest that Edward R. Reines
16 has concurred in this filing.
17
18
19
20
21
22
23
24
25
26
27
28
Stipulated Claim Construction Schedule
2775819
-4-
Case No. 12-CV-05501-SI
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?