East Bay Municipal Utility District et al v. Balfour Beatty Infrastructure, Inc.
Filing
53
ORDER GRANTING DEFENDANT'S MOTIONS FOR JUDGMENT ON THE PLEADINGS WITHOUT PREJUDICE; DENYING DEFENDANT'S MOTION TO DISMISS; ADDRESSING PARTIES' DISCOVERY DISPUTE by Judge William H. Orrick denying 37 Motion to Dismiss and granting 38 Motion for Judgment on the Pleadings. Balfour Beatty's motion to dismiss is DENIED. Balfour Beatty's motion for judgment on the pleadings is GRANTED, and Qui Tam Plaintiffs' Complaint is DISMISSED WITHOUT PREJUDICE. Any amended complaint shall be filed within 30 days of this order. Further discovery is STAYED until Qui Tam Plaintiffs file a complaint that satisfies Rule 9(b). (jmdS, COURT STAFF) (Filed on 12/19/2013)
1
2
3
4
5
UNITED STATES DISTRICT COURT
6
NORTHERN DISTRICT OF CALIFORNIA
7
EAST BAY MUNICIPAL UTILITY
DISTRICT, et al.,
8
Plaintiffs,
9
v.
10
11
United States District Court
Northern District of California
Case No. 13-cv-02032-WHO
BALFOUR BEATTY INFRASTRUCTURE,
INC.,
12
Defendant.
ORDER GRANTING DEFENDANT’S
MOTIONS FOR JUDGMENT ON THE
PLEADINGS WITHOUT PREJUDICE;
DENYING DEFENDANT’S MOTION
TO DISMISS; ADDRESSING PARTIES’
DISCOVERY DISPUTE
Re: Dkt. Nos. 37, 38, 47
13
INTRODUCTION
14
Qui tam plaintiffs Bill Haley, Harry Rotz, and Lew Long (collectively, “Qui Tam
15
16
Plaintiffs”) filed suit on behalf of the East Bay Municipal Utility District, Sacramento County
17
Water Agency, Freeport Water Authority, and the Cities of Sacramento, Roseville, and Rio Vista
18
(collectively, the “Public Entities”), alleging that defendant Balfour Beatty Infrastructure, Inc., a
19
public works contractor, violated the California False Claims Act.
Balfour Beatty has moved to dismiss the Qui Tam Plaintiffs’ Complaint under Federal
20
21
Rule of Civil Procedure 12(b)(1), arguing that the Complaint is barred by the public disclosure bar
22
in the False Claims Act. Dkt. No. 37. Balfour Beatty has also moved for judgment on the
23
pleadings under Federal Rule 12(c), arguing that the Complaint is not plausible nor pleaded with
24
the requisite particularity.1 Dkt. No. 38. For the reasons stated below, Balfour Beatty’s motion to
25
26
27
28
1
It is not clear to the Court why Balfour Beatty concurrently filed both a motion to dismiss and a
motion for judgment on the pleadings. The Court presumes that this was not an attempt to evade
the page limits imposed by the Local Rules. In any event, should Balfour Beatty move to dismiss
an amended complaint, it will be limited to one motion, whether styled a motion to dismiss or a
motion for judgment on the pleadings, unless the Court grants leave otherwise.
1
dismiss is DENIED and its motion for judgment on the pleadings is GRANTED. Qui Tam
2
Plaintiffs’ Complaint is DISMISSED WITHOUT PREJUDICE. The Court also DENIES Qui
3
Tam Plaintiffs’ request to compel discovery from Balfour Beatty. Dkt. No. 47.
4
BACKGROUND
5
Labor Code Section 1777.5 requires a public-works contractor to employ a minimum
6
number of apprentices, corresponding to the number of journeymen,2 if the public-works
7
contractor “employs workers in any apprenticeable craft or trade” in performing any work under a
8
public-works contract. Cal. Lab. Code § 1777.5(d). The ratio of “work performed by apprentices
9
to journeymen employed in a particular craft or trade on the public work” may not be less than one
hour of apprentice work for every five hours of journeyman work. Cal. Lab. Code § 1777.5(g).
11
United States District Court
Northern District of California
10
Qui Tam Plaintiffs allege that over the last ten years, Balfour Beatty has performed public-works
12
projects where it employed workers to perform “Pipefitter-Steamfitter work processes”3 but failed
13
to employ and train Pipefitter-Steamfitter apprentices, as required by Section 1777.5 and by the
14
public-works contracts governing the projects.4 Dkt. No. 37-2, ECF pages 2-16 (“Compl.”) ¶ 20.
15
2
16
17
18
19
20
21
22
23
24
25
26
27
28
A journeyman is “a person who has either (1) completed an accredited apprenticeship in his/her
craft, or (2) who has completed the equivalent of an apprenticeship in length and content of work
experience.” Cal. Code Regs. tit. 8, § 205(a).
3
The Complaint states that “Pipefitter-Steamfitter work processes” means “layout of process
piping systems; installation of pressurized and process piping for hot and cold water, steam, gas,
chemical process, air and vacuum systems; these work processes include cutting pipe, threading
pipe, bending pipe, beveling pipe, welding pipe, soldering pipe, brazing pipe, grooving pipe, and
cutting and assembling glass, fiberglass and plastic pipe; welding processes in connection with
pipefitting and steamfitting, including arc welding, tungsten inert gas welding, orbital welding and
oxy-acetylene cutting; installation of all equipment appurtenant to process piping, including
pumps, compressors, heat exchangers and boilers; installation of cans, inserts and hangers for
pipe; installation of pneumatic, hydraulic, and instrumentation tubing and control piping, and
calibration of instrumentation tubing; operation and repair of power tools, hand tools and
machinery used for pipefitting and steamfitting; handling construction materials and equipment
used for pipefitting and steamfitting; rigging of pipe and related equipment; testing of piping
systems.” Compl. ¶ 11.
4
Qui Tam Plaintiffs identify only one public-works contract at issue. They allege that Balfour
Beatty violated Section 6 of the public-works contract governing the Vineyard Water Treatment
Plant project with the Sacramento County Water Agency, which provides that “The Contractor
shall comply with Labor Code Section 1777.5, concerning the employment of apprentices. The
Contractor shall be responsible for compliance by all Subcontractors.” Compl. ¶ 19. Qui Tam
Plaintiffs do not identify public-works contracts that impose Section 1777.5’s requirements on
Balfour Beatty for the other projects. Nonetheless, for purposes of this motion, the Court assumes
that Balfour Beatty is required to comply with Section 1777.5 on all alleged projects.
2
1
Qui Tam Plaintiffs allege that Balfour Beatty consequently violated the False Claims Act by
2
billing the Public Entities without disclosing the alleged Section 1777.5 violations, thereby falsely
3
certifying that it was in compliance with the public-works contracts. See, e.g., id. ¶¶ 18-21.
4
The Complaint identifies six Public Entities with whom Balfour Beatty worked on seven projects:
5
Sacramento County Water Agency—Vineyard Water Treatment Plant project
6
Freeport Water Authority—Freeport Regional Water Intake Facilities project
7
East Bay Municipal Utility District—Folsom South Canal Connection project
City of Sacramento—Fairbairn Treatment Plant Expansion project
City of Roseville—Granite Bay Water Treatment Plant project; Dry Creek Wastewater
Treatment Plant Expansion project
City of Rio Vista—Rio Vista Wastewater Treatment Plant project
8
9
10
United States District Court
Northern District of California
11
12
Qui Tam Plaintiffs do not allege specific facts regarding these projects. Rather, they “are
13
informed and believe and thereupon allege that Defendant has violated its public-works contracts
14
and has made false claims for payment on numerous public-works projects throughout California.”
15
Id. ¶ 25.
16
Qui Tam Plaintiffs allege four causes of action, all arising under the False Claims Act, Cal.
17
Govt. Code. § 12650, et seq.: i) submissions of false claims under Section 12651(a)(1); ii) use of
18
false records under Section 12651(a)(2); iii) use of false statements under Section 12651(a)(7);
19
and iv) failure to disclose false claims under Section 12651(a)(8). All of the causes of action are
20
premised on Balfour Beatty’s alleged violation of Labor Code Section 1777.5.
21
LEGAL STANDARD
22
Under Federal Rule of Civil Procedure 12(b)(6), a district court must dismiss a complaint
23
if it fails to state a claim upon which relief can be granted. To survive a Rule 12(b)(6) motion to
24
dismiss, the plaintiff must allege “enough facts to state a claim to relief that is plausible on its
25
face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 556 (2007). A claim is facially plausible when
26
the plaintiff pleads facts that “allow the court to draw the reasonable inference that the defendant
27
is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (citation
28
omitted). There must be “more than a sheer possibility that a defendant has acted unlawfully.” Id.
3
1
While courts do not require “heightened fact pleading of specifics,” a plaintiff must allege facts
2
sufficient to “raise a right to relief above the speculative level.” Twombly, 550 U.S. at 555, 570.
3
In deciding whether the plaintiff has stated a claim upon which relief can be granted, the Court
4
accepts the plaintiff’s allegations as true and draws all reasonable inferences in favor of the
5
plaintiff. Usher v. City of Los Angeles, 828 F.2d 556, 561 (9th Cir. 1987). However, the Court is
6
not required to accept as true “allegations that are merely conclusory, unwarranted deductions of
7
fact, or unreasonable inferences.” In re Gilead Scis. Sec. Litig., 536 F.3d 1049, 1055 (9th Cir.
8
2008). If the court dismisses the complaint, it “should grant leave to amend even if no request to
9
amend the pleading was made, unless it determines that the pleading could not possibly be cured
10
United States District Court
Northern District of California
11
by the allegation of other facts.” Lopez v. Smith, 203 F.3d 1122, 1127 (9th Cir. 2000).
The standard for deciding a motion for judgment on the pleadings under Rule 12(c) “is
12
‘functionally identical’ to [a motion under] Rule 12(b)(6).” Cafasso, United States ex rel. v. Gen.
13
Dynamics C4 Sys., Inc., 637 F.3d 1047, 1055 n.4 (9th Cir. 2011). When deciding such a motion,
14
“the allegations of the non-moving party must be accepted as true, while the allegations of the
15
moving party which have been denied are assumed to be false.” Hal Roach Studios, Inc. v.
16
Richard Feiner & Co., Inc., 896 F.2d 1542, 1550 (9th Cir. 1989). “Judgment on the pleadings
17
should be granted when, accepting all factual allegations in the complaint as true, there is
18
no issue of material fact in dispute and the moving party is entitled to judgment as a matter of
19
law.” Chavez v. United States, 683 F.3d 1102, 1108 (9th Cir. 2012) (internal punctuation and
20
citation omitted).
DISCUSSION
21
22
23
I. MOTION FOR JUDGMENT ON THE PLEADINGS
Balfour Beatty moves for judgment on the pleadings on the grounds that i) the Complaint
24
fails to plead plausible False Claims Act violations and ii) the claims are not pleaded with the
25
particularity required by Federal Rule 9(b).
26
A.
27
Balfour Beatty’s plausibility argument is centered on the parties’ dispute over the proper
28
The plausibility of Qui Tam Plaintiffs’ claims
interpretation of Section 1777.5. Balfour Beatty argues that if a public works contractor elects to
4
1
hire journeymen to work on a project, Section 1777.5 requires the contractor to hire a certain ratio
2
of apprentices from the same occupation as the journeymen (e.g., laborer, pipefitter, carpenter,
3
etc.). Dkt. No. 38 at 7. Qui Tam Plaintiffs respond that Section 1777.5 requires a contractor to
4
hire apprentices whose state-approved apprenticeship programs encompass the type of work
5
performed by the journeymen, irrespective of the journeymen’s “craft or trade.” In short, Balfour
6
Beatty argues that the occupation of the journeymen dictates which apprentices a contractor must
7
hire, whereas Qui Tam Plaintiffs argue that the nature of the work performed by the journeymen
8
dictates which apprentices may be hired.
As noted below, the Court GRANTS Balfour Beatty’s motion for judgment on the
10
pleadings on the grounds that the Complaint is not pleaded with the specificity required by Rule
11
United States District Court
Northern District of California
9
9(b). The Court therefore does not address the proper interpretation of Section 1777.5 at this
12
stage. Qui Tam Plaintiffs are given leave to file an amended complaint. Should Balfour Beatty
13
move to dismiss the amended complaint, the parties at that time may brief the proper interpretation
14
of Section 1777.5. The Court will address the issue then, if appropriate.
15
16
17
18
B.
Qui Tam Plaintiffs’ claims do not satisfy Rule 9(b).
Balfour Beatty asserts that Qui Tam Plaintiffs’ claims are not pleaded with sufficient
particularity. The Court agrees.
Rule 9(b)’s requirement that claims grounded in fraud be pleaded with particularity applies
19
to False Claims Act claims. Cafasso, 637 F.3d at 1054. “To satisfy Rule 9(b), a pleading must
20
identify the ‘who, what, when, where, and how’ of the misconduct charged, as well as what is
21
false or misleading about the purportedly fraudulent statement, and why it is false.” Id. (internal
22
punctuation and citation omitted).
23
i. Qui Tam Plaintiffs’ allegations relating to unspecified projects
24
Qui Tam Plaintiffs allege that Balfour Beatty violated its public-works contracts and made
25
false claims on public-works projects throughout California, including “but not limited to” the
26
seven specific projects undertaken for the six public entities identified in the Complaint. Compl. ¶
27
25. To the extent that Qui Tam Plaintiffs intend to assert claims relating to unspecified projects
28
and public entities, those claims are neither plausible nor pleaded with particularity, and any such
5
1
claims are dismissed.
2
ii. Qui Tam Plaintiffs’ allegations relating to identified projects
3
Qui Tam Plaintiffs are “informed and believe and thereupon allege that Defendant has
violated its public-works contracts and has made false claims for payment . . . .” on the projects
5
identified above. Compl. ¶ 25. Elsewhere the Complaint alleges generally that “[d]uring the time
6
period relevant to this suit, on public-works projects on which Defendant employed workers to
7
perform Pipefitter-Steamfitter work processes, Defendant has failed to employ and train Pipefitter-
8
Steamfitter apprentices . . . .” Id. ¶ 20. The Complaint does not identify when Balfour Beatty
9
allegedly employed workers to perform Pipefitter-Steamfitter work processes, what those work
10
processes were, how many apprentices were required, or what apprentices Balfour Beatty hired.
11
United States District Court
Northern District of California
4
The Complaint thus does not provide the “who, what, when, where, and how” of the misconduct
12
charged and does not satisfy Rule 9(b). In order to defend itself against the allegation that it
13
violated Section 1777.5, Balfour Beatty must be informed of the work that it allegedly performed
14
that triggered the requirement to hire apprentices. The complaint is similarly silent as to the False
15
Claims Act allegations as it does not allege when and in what statements and records Balfour
16
Beatty impliedly certified that it was in compliance with Section 1777.5
17
“Rule 9(b) serves not only to give notice to defendants of the specific fraudulent conduct
18
against which they must defend, but also to deter the filing of complaints as a pretext for the
19
discovery of unknown wrongs, to protect defendants from the harm that comes from being subject
20
to fraud charges, and to prohibit plaintiffs from unilaterally imposing upon the court, the parties
21
and society enormous social and economic costs absent some factual basis.” Bly-Magee v.
22
California, 236 F.3d 1014, 1018 (9th Cir. 2001) (citation and internal punctuation omitted). Rule
23
9(b) is accordingly not satisfied even if Balfour Beatty can determine the general contours of what
24
it stands accused.
25
For the reasons stated, Balbour Beatty’s motion for judgment on the pleadings is
26
GRANTED and the Complaint is DISMISSED WITH LEAVE TO AMEND. Any amended
27
complaint shall address the deficiencies noted above.
28
6
1
II. MOTION TO DISMISS
Balfour Beatty argues that Qui Tam Plaintiffs’ claims are barred by the public disclosure
2
bar in the False Claims Act because the complaint is based on allegations or transactions publicly
3
disclosed prior to the filing of complaint and the Qui Tam Plaintiffs are not the original sources of
4
the information. Balfour Beatty argues that the allegations or transactions in the Complaint were
5
publicly disclosed in four different ways: (1) in a qui tam lawsuit filed on December 28, 2011 in
6
Alameda County Superior Court, East Bay Municipal Utility District, et al. ex rel. Cameron v. C.
7
8
Overaa & Co. (the “East Bay Action”); (2) in a class action lawsuit filed on December 30, 2011 in
Alameda Superior Court, Floyd Henson, et al. v. C. Overaa & Co. (the “Henson Action”); (3) in
9
other cases and published decisions relating to disputes between the Laborer and Pipefitter unions
10
over apprentice hiring; and (4) in reports and investigations connected to Balfour Beatty’s
11
United States District Court
Northern District of California
submission of certified payroll records pursuant to the California Labor Code. The Court finds
12
that the allegations and transactions at issue here were not previously disclosed in the asserted
13
public disclosures and DENIES Balfour Beatty’s motion to dismiss.5
14
The public disclosure bar6 to the False Claims Act is “intended to bar parasitic or
15
opportunistic actions by persons simply taking advantage of public information without
16
17
contributing to or assisting in the exposure of the fraud.” City of Hawthorne ex rel. Wohlner v.
H&C Disposal Co., 1 Cal. Rptr. 3d 312 (Ct. App. 2003). In contrast, “[w]hen a totally different
18
species of fraud has been disclosed or when the facts or documents on their face do not expose
19
fraud, the qui tam complaint serves to alert the government to fraud it otherwise might never have
20
discovered.” State ex rel. Grayson v. Pac. Bell Tel. Co., 48 Cal. Rptr. 3d 427, 436 (Ct. App. 2006)
21
22
5
23
24
25
26
27
28
Given that the allegations and transactions at issue here were not previously disclosed against
Balfour Beatty, the Court does not reach whether the Qui Tam Plaintiffs are the “original sources”
of the information.
6
The False Claims Act was amended in 2012. The relevant public disclosure language previously
read, “No court shall have jurisdiction over an action under this article based upon the public
disclosure . . . .” Cal. Gov. Code § 12652(d)(3)(A) (prior to 2012 amendments). The current
language instead states “The court shall dismiss an action or claim under this section . . . if
substantially the same allegations or transactions as alleged in the action or claim were publicly
disclosed. . . .” The amendment changes the public disclosure bar from a jurisdictional threshold
to an affirmative dismiss, which changes the burden of persuasion. The parties dispute whether
the current or former language applies to this matter. The Court need not resolve that question as
the Court finds no public disclosure irrespective of which version of the statute is at issue.
7
1
(citation omitted). “[T]he public disclosure bar should be applied only as necessary to preclude
2
parasitic or opportunistic actions, but not so broadly as to undermine the Legislature’s intent that
3
relators assist in the prevention, identification, investigation, and prosecution of false claims.”
4
Wohlner, 1 Cal. Rptr. 3d at 312.
5
A. The East Bay and Henson Actions
6
The qui tam complaint in the East Bay Action mirrors the Complaint in this action. See
7
Dkt. No. 37-2, ECF pages 66-80 (“East Bay Compl.”). It names as defendants a contractor named
8
C. Overaa and Company and Does 1-50. East Bay Compl. ¶¶ 2-3. Balfour Beatty is not a
9
defendant in the East Bay Action complaint and is not otherwise referenced in that complaint. The
East Bay Action is brought on behalf of 13 public entities, only one of which, the East Bay
11
United States District Court
Northern District of California
10
Municipal Utility District, is also a putative plaintiff in the present matter. Id. ¶ 1. None of the
12
public-works projects identified in the East Bay Action complaint are at issue in the present
13
action. Compare id. ¶ 25 with Compl. ¶ 25. As in this case, the East Bay Action alleges that
14
“[d]uring the time period relevant to this suit, on public-works projects on which Defendant
15
employed workers to perform Pipefitter-Steamfitter work processes, Defendant has failed to
16
employ and train Pipefitter-Steamfitter apprentices as required by the laws and regulations
17
described above.” East Bay Compl. ¶ 25.
18
The Henson Action is a class action brought by pipefitter apprentices alleging that Overaa
19
and Does 1-50 failed to employ and train apprentices enrolled in the appropriate apprenticeship
20
programs in specific public-works projects where Overaa was the prime contractor. See Dkt. No.
21
37-2, ECF pages 103-20 (“Henson Compl.”). Like the East Bay Action, Balfour Beatty is neither
22
a defendant nor referenced in the Henson complaint. One of the projects at issue was funded by
23
the East Bay Municipal Utility District, but none of the projects identified in the complaint are at
24
issue in the present action. The Henson complaint alleges that Overaa “employed workers to
25
perform Pipefitter-Steamfitter work processes on [a project for the East Bay Municipal District in
26
Oakland], but Defendant’s certified payroll records for that project indicate that Pipefitter-
27
Steamfitter apprentices were not employed or trained as required by law. Henson Compl. ¶ 20(c).
28
Balfour Beatty does not allege that it was accused of participating in the violations alleged
8
1
in the East Bay and Henson Actions or that the prosecution of those actions brought attention to its
2
own alleged violations of Section 1777.5. Rather, Balfour Beatty argues that because the “central
3
allegation” in this case and in the East Bay and Henson Actions is the same—“that Pipefitter
4
apprentices are entitled to perform water treatment plant pipe work (and are entitled to perform
5
that work in the statutory ratios), and violations of the California Labor Code occurred when
6
others performed that work/those ratios were not met”—the allegations in the current Complaint
7
were publicly disclosed in the East Bay and Henson Actions Dkt. No. 37 at 7, 8.
In support, Balfour Beatty argues that “strikingly similar facts” were present in United
8
States v. Alcan Electrical & Engineering, Inc., 197 F.3d 1014 (9th Cir. 1999), in which the Ninth
10
Circuit affirmed the dismissal of a qui tam action under the public disclosure bar even though the
11
United States District Court
Northern District of California
9
qui tam defendants were not identified in the earlier complaint. The Court does not agree that
12
Alcan bears facts similar to those present here.
In Alcan, an IBEW union member filed an application with the District Court for the
13
14
District of Alaska for leave to file a suit against union officials. The union member lodged his
15
proposed complaint with the court.7 The proposed complaint alleged that his local IBEW chapter
16
“has conspired with local contractors, through its Work Recovery Program, to deduct certain sums
17
from the Union members’ paychecks, (2.5% of gross wages), who were working on State and
18
Federally funded projects, and then remit these funds back to the contractor in violation of Federal
19
Law.” Id. at 1016. The proposed complaint did not identify the “local contractors.” The union
20
member subsequently filed a qui tam action against the contractors based on the same allegations
21
stated in his proposed complaint.
22
The Ninth Circuit affirmed the district court’s dismissal of the qui tam action on the
23
grounds that the proposed complaint constituted public disclosure, finding that the prior complaint
24
“alleged a narrow class of suspected wrongdoers-local electrical contractors who worked on
25
federally funded projects over a four-year period.”8 The Circuit concluded that “the government
26
7
27
28
The complaint was lodged, but not filed, and it was not under seal. The district court found that
the proposed complaint was therefore available to the public. Id. at 1016.
8
The plaintiff also failed to establish that he was the “original source” of the information, as
required where there has been prior public disclosure.
9
1
could easily identify the contractors at issue.” Id.
Unlike Alcan, the East Bay and Henson Actions do not relate to the same transactions by
3
the same parties at issue in the qui tam complaint before the Court. Balfour Beatty is correct that
4
the alleged conduct in the East Bay and Henson Actions—failing to hire apprentices in the
5
required ratio—mirrors the conduct alleged in the present complaint. But that different actors, on
6
different projects, allegedly violated the same laws that Balfour Beatty is now accused of
7
violating, does not mean that the government was on notice of Balfour Beatty’s alleged conduct.
8
In addition, unlike Alcan, Balfour Beatty is not part of an easily identifiable “narrow class of
9
suspected wrongdoers.” In Alcan the defendants were local contractors that had contracted with a
10
local IBEW chapter on federally-funded projects over a four year period. Those same contractors
11
United States District Court
Northern District of California
2
and projects were at issue in the proposed complaint and the qui tam action. In contrast, the
12
projects and defendants identified in the East Bay and Henson Actions are different from the
13
projects and defendants at issue in the present matter. Consequently, unlike Alcan, in the present
14
case the government would not have discovered Balfour Beatty’s alleged conduct by investigating
15
the allegations in the East Bay and Henson Actions.
16
Balfour Beatty also cites Grayson, 142 Cal. App. 4th at 748, from the California Court of
17
Appeal for the Third District, and United States ex rel. Findley v. FPC-Boron Employees’ Club
18
105 F.3d 675 (D.C. Cir. 1997), for the proposition that the East Bay and Henson Actions disclosed
19
“general practices” which alerted the government to the alleged conduct at issue in this case and
20
bar the present qui tam action. In response, Qui Tam Plaintiffs cite Wohlner, 1 Cal. Rptr. 3d 312,
21
from the California Court of Appeal for the Second District, where the court found that a prior
22
complaint alleging that a contractor fraudulently billed a city did not bar a subsequent qui tam suit
23
against the same defendant for fraudulently billing the same city because the prior lawsuit related
24
to different instances of fraud.
25
In Wohlner, two prior lawsuits alleged that a city waste contractor improperly billed the
26
city for increases in dumping fees paid by the contractor between 1990 and 1995, even though the
27
contractor never incurred the costs and, under the governing contract, any increased dumping fees
28
were not to be passed on to the city because the contract included automatic inflation adjustments.
10
1
A subsequent qui tam complaint brought claims against the same contractor for improperly billing
2
the same city for different supposed dumping fee increases in 1980. The court ruled that the prior
3
suit did not constitute public disclosure of the allegations in the qui tam complaint because the
4
prior complaints did not relate to the alleged fraudulent billing in 1980, but related to fraudulent
5
billing in 1990 and 1995. The court held that the qui tam complaint “is not based upon the public
6
disclosure of allegations in the [prior] litigation” and, consequently, “does not constitute a
7
‘parasitic’ lawsuit,” and was not barred. Wohlner, 1 Cal. Rptr. 3d at 323.
8
In Grayson, a qui tam plaintiff alleged that Pacific Bell had not turned over the unused
balances on its prepaid telephone cards to the state as required under the Unclaimed Property Law.
10
The court found that prior disclosures of this practice in the news media, including discussions of
11
United States District Court
Northern District of California
9
the practice in a newsletter for unclaimed property administrators and a tax publication, “disclosed
12
the questionable legality” of withholding unused phone card balances from unclaimed property
13
filings. Grayson, 48 Cal. Rptr. 3d at 434. The court found that this disclosure “clearly alerted the
14
government to defendants’ failure to either report or escheat breakage.” The court therefore found
15
that the complaint “merely echoe[d] what the government already knew and chose not to
16
prosecute.” Id. at 435.
17
The Grayson court found a “fitting analogy” for the case before it in Findley. There a qui
18
tam plaintiff alleged that government-employee clubs from the Department of Justice and Bureau
19
of Prisons illegally used federal resources to operate vending machines but kept the revenue from
20
the vending machines. Findley, 105 F.3d at 678. The District of Columbia Circuit held that prior
21
discussions of that practice, dating back over 40 years, in a Comptroller General Opinion, in the
22
legislative history of the Randolph–Sheppard Act (governing vending facilities operated by the
23
blind in federal buildings), and in a Federal Circuit opinion, constituted prior disclosure of the
24
claims. The court affirmed the district court’s holding that based on the prior disclosure of that
25
practice, “before the filing of this action, enough information was in the public domain to expose
26
the allegation that government employees are perpetrating a fraud upon the government by
27
maintaining vending machines on Federal property.” Id. at 679. The court explained that the
28
“complaint reveals allegations which substantially repeat what the public already knows and add
11
1
only the identity of particular employees’ clubs engaged in the questionable and previously
2
documented generic practice.”
3
Of the ostensibly dueling opinions from the sister California courts of appeal, Wohlner and
4
Grayson—and Grayson’s “fitting analogy,” Findley—the Court finds that the facts and reasoning
5
of Wohlner have better application to the facts present here. For the reasons stated above, the East
6
Bay and Henson Actions did not put the government on notice of Balfour Beatty’s allegedly
7
fraudulent conduct. Accordingly, Qui Tam Plaintiffs’ lawsuit is not a “parasitic’ lawsuit” and is
8
not barred by the prior suits. See Wohlner, 1 Cal. Rptr. 3d at 322 (public disclosure bar should not
9
be construed “so broadly as to undermine the Legislature’s intent that relators assist in the
10
United States District Court
Northern District of California
11
prevention, identification, investigation, and prosecution of false claims”).
The Court further finds that the East Bay and Henson Actions, which are as vague and
12
conclusory as the present action, do not constitute sufficient disclosures of a “general practice”
13
relating to the conduct at issue such that it “clearly alerted the government” to Balfour Beatty’s
14
alleged conduct. Grayson, 48 Cal. Rptr. 3d at 436. Similarly, no documented general practice is
15
identified in the East Bay and Henson Actions in remotely the same public way that would alert
16
the government to the fraud alleged here against Balfour Beatty as occurred in Findley.
17
Balfour Beatty argues that “the East Bay and Henson lawsuits disclosed to the State, the
18
named public entities, and the general public the allegation that California water treatment
19
contractors—including contractors labeled “DOES 1 through 50” in the complaint—did not use
20
Pipefitter apprentices or meet ratio requirements on water treatment plant construction projects.”
21
Dkt. No. 37 at 10. Tellingly, Balfour Beatty does not cite the particular portions of the East Bay
22
or Henson complaints that supposedly disclose the allegation that California water treatment
23
contractors in general violate Section 1777.5. The mere fact that those complaints named DOE
24
defendants is not sufficient. To the contrary, the DOE defendants in those suits were allegedly
25
responsible for the violations alleged in those complaints; not for other generalized violations.
26
See, e.g., East Bay Compl. ¶ 3 (“Each fictitiously named Defendant is in some manner responsible
27
or liable for the unlawful acts and omissions alleged herein.”) (emphasis added). Unlike Grayson
28
and Findley, the East Bay and Henson Actions did not give the government any identifiable reason
12
1
to think that Balfour Beatty was guilty of the same conduct as the defendants in those actions.
2
B. Other lawsuits between the Pipefitters and Laborers
3
Balfour Beatty argues that “at least four published federal and state judicial opinions in
4
California arising out of, and thoroughly documenting, the Northern California Pipefitter-versus-
5
Laborer dispute over water treatment plant work” constitute public disclosure of the allegations at
6
issue here. As an example, Balfour Beatty cites Pipe Trades Dist. Council No. 51 v. Aubry, 41
7
Cal. App. 4th 1457, 1461 (1996), which states:
8
Both in Northern California and elsewhere in the nation
jurisdictional disputes have regularly existed between the UA
[Pipefitters] and the Laborers. Focusing on recent times and
Northern California, a long-running dispute has existed between
these unions as to which one has jurisdiction over the installation of
various kinds of piping for various types of water treatment plants.
9
10
United States District Court
Northern District of California
11
Dkt. No. 37 at 11.9
12
As an initial matter, Qui Tam Plaintiffs’ allegations in the present Complaint relate to
13
conduct starting in October 2002. Compl. ¶¶ 2, 5 (alleging conduct within 10 years of filing of
14
Complaint). Given that the various complaints in the cases cited by Balfour Beatty were filed
15
before October 2002, it is not apparent to the Court how those actions can constitute disclosure of
16
alleged Balfour Beatty misconduct that had not yet occurred. In any event, those cases do not
17
constitute public disclosures of the allegations at issue here for the same reasons that the East Bay
18
and Henson Actions do not: the present action alleges misconduct by a different defendant under
19
different contracts with different public entities in connection with different projects than those
20
cases.
21
C. Balfour Beatty’s submission of certified payroll records
22
The public disclosure bar applies if the allegations or transactions were previously
23
24
disclosed in, among other ways, an “investigation of the Legislature, the state, or governing body
of a political subdivision.” Gov. Code. § 12652(d)(3)(A). Balfour Beatty argues that the payroll
25
26
27
28
9
Balfour Beatty also cites, without elaboration, United States ex rel. Local 342 Plumbers v. Dan
Caputo Co., 321 F.3d 926 (9th Cir. 2003); United States ex rel. Plumbers Local Union No. 38 v.
C.W. Roen Constr. Co., 183 F.3d 1088 (9th Cir. 1999); Huber, Hunt & Nichols, Inc. v. United
Ass’n Journeymen & Apprentices Plumbing Indus., Local 38, 282 F.3d 746 (9th Cir. 2002); Pipe
Trades Dist. Council No. 51 v. Aubry, 41 Cal. App. 4th 1457 (1996).
13
1
records it was required to provide to the Public Entities constitute an “investigation” within the
2
meaning of the public disclosure. Balfour Beatty provides no authority for this argument, aside
3
from a dictionary definition of the work “investigation.” Dkt. No. 43 at 12. The Court is not
4
persuaded that payroll records submitted to the Public Entities constitute “investigations” within
5
the meaning of the public disclosure bar.
6
7
8
9
For the reasons stated, Balbour Beatty’s motion to dismiss is DENIED.
III. PARTIES’ DISCOVERY DISPUTE
The parties have submitted a joint discovery dispute regarding Qui Tam Plaintiffs’
inspection demands and interrogatories and Balfour Beatty’s deposition questions about fee
arrangements between Qui Tam Plaintiffs’ counsel and other entities. Dkt. No. 47.
11
United States District Court
Northern District of California
10
Qui Tam Plaintiffs are not entitled to take further discovery until they file a complaint that
12
complies with Rule 9(b). As the Ninth Circuit explained in Bly-Magee, 236 F.3d at 1019, “qui
13
tam suits are meant to encourage insiders privy to a fraud on the government to blow the whistle
14
on the crime. Because insiders privy to a fraud on the government should have adequate
15
knowledge of the wrongdoing at issue, such insiders should be able to comply with Rule 9(b).”
16
Here, Qui Tam Plaintiffs have received discovery regarding the Vineyard Water Treatment
17
plant project. That should be more than adequate to allow them to file a complaint with the
18
necessary specificity if they can. The Court denies Qui Tam Plaintiffs’ request that it compel
19
Balfour Beatty to respond or produce documents in response to Qui Tam Plaintiffs interrogatories
20
and discovery requests. See, e.g., Cafasso, 637 F.3d at 1057 (“This type of allegation, which
21
identifies a general sort of fraudulent conduct but specifies no particular circumstances of any
22
discrete fraudulent statement, is precisely what Rule 9(b) aims to preclude.”); Periguerra v.
23
Meridas Capital, Inc., 09-cv-4748 SBA, 2010 WL 395932, *5 (N.D. Cal. Feb. 1, 2010)
24
(“Allowing Plaintiffs to conduct discovery in order to comport with heightened pleading
25
requirement applicable to fraud-based claims is directly contrary to the purpose of Rule 9(b);
26
namely, that plaintiffs show that there is some substance to their claim of fraud before subjecting a
27
defendant to the rigors of the discovery process.”).
28
Balfour Beatty has asked the Court to allow it to renew depositions of Qui Tam Plaintiffs
14
1
to obtain information regarding the nature of Qui Tam Plaintiffs’ fee arrangements with counsel.
2
Given that further discovery is stayed until Qui Tam Plaintiffs file a complaint that satisfies Rule
3
9(b), Balfour Beatty’s request is moot. Balfour Beatty may renew this request when and if
4
discovery re-commences.
CONCLUSION
5
6
Balfour Beatty’s motion to dismiss is DENIED. Dkt. No. 37. Balfour Beatty’s motion for
7
judgment on the pleadings is GRANTED (Dkt. No. 38) and Qui Tam Plaintiffs’ Complaint is
8
DISMISSED WITHOUT PREJUDICE. Any amended complaint shall be filed within 30 days of
9
this order and shall address the deficiencies noted above.
10
The Court DENIES Qui Tam Plaintiffs’ request that the Court compel Balfour Beatty to
United States District Court
Northern District of California
11
respond to Qui Tam Plaintiffs’ inspection demands and interrogatories. Further discovery is
12
STAYED until Qui Tam Plaintiffs file a complaint that satisfies Rule 9(b).
13
IT IS SO ORDERED.
14
15
16
17
Dated: December 19, 2013
______________________________________
WILLIAM H. ORRICK
United States District Judge
18
19
20
21
22
23
24
25
26
27
28