Winding Creek Solar LLC v. California Public Utilities Commission

Filing 161

FINDINGS OF FACT AND CONCLUSIONS OF LAW; AND ORDER ON SUMMARY JUDGMENT. Signed by Judge James Donato on 12/6/2017. (jdlc2S, COURT STAFF) (Filed on 12/6/2017)

Download PDF
1 2 3 UNITED STATES DISTRICT COURT 4 NORTHERN DISTRICT OF CALIFORNIA 5 6 WINDING CREEK SOLAR LLC, Plaintiff, 7 8 9 10 Case No. 13-cv-04934-JD v. MICHAEL PEEVEY, et al., FINDINGS OF FACT AND CONCLUSIONS OF LAW, AND ORDER ON SUMMARY JUDGMENT Defendants. United States District Court Northern District of California 11 12 Plaintiff Winding Creek Solar LLC has sued the Commissioners of the California Public 13 Utilities Commission (“CPUC”) for a declaration that three CPUC orders conflict with federal law 14 and consequently violate the Supremacy Clause of the United States Constitution. The CPUC 15 orders set up a procurement program called “Re-MAT” (short for “Renewable Market-Adjusting 16 Tariff”), and regulate the terms on which utility companies like the Pacific Gas and Electric 17 Company (“PG&E”) must purchase power from alternative energy power production facilities like 18 small wind farms and solar projects. Winding Creek intends to build such a solar project in Lodi, 19 California, and it seeks a long-term contract to sell the energy from the proposed facility to PG&E. 20 It sued because it believes the CPUC orders in dispute prevented it from getting a contract 21 entitlement under the Public Utility Regulatory Policies Act (“PURPA”). 22 This order brings to a close a case that has been fought hard over a number of years. After 23 three rounds of motions to dismiss, the parties filed cross-requests for summary judgment which 24 were heavily briefed and included submission of an amicus brief from PG&E and other third-party 25 utility companies. Disputes over material facts compelled the Court to hold a one-day bench trial. 26 Both sides presented witnesses and expert testimony, and filed substantial post-trial briefs. The 27 Court makes these findings of fact and conclusions of law, and grants summary judgment in favor 28 of Winding Creek. 1 BACKGROUND 2 To frame the rather technical dispute between the parties, the Court summarizes the 3 statutory context set out in a prior order. Dkt. No. 60. Under the Federal Power Act (“FPA”), 16 4 U.S.C. § 791a et seq., the interstate commerce of electric energy at wholesale is subject to 5 regulation by the Federal Energy Regulatory Commission (“FERC”). In 1978, Congress enacted 6 the Public Utility Regulatory Policies Act (“PURPA”), which amended the FPA. PURPA was 7 enacted to encourage the development of renewable sources of energy, and “thus to reduce 8 American dependence on fossil fuels by promoting increased energy efficiency.” Indep. Energy 9 Producers Ass’n, Inc. v. Cal. Pub. Util. Comm’n, 36 F.3d 848, 850 (9th Cir. 1994). To that end, PURPA directs FERC to prescribe “such rules as it determines necessary to encourage 11 United States District Court Northern District of California 10 cogeneration and small power production,” including rules that require electric utilities to offer to 12 “purchase electric energy from [qualifying cogeneration and small power production facilities].” 13 16 U.S.C. § 824a-3(a). The Court found in a prior order that plaintiff Winding Creek’s proposed 14 Lodi facility is a “qualifying small power production facility” under PURPA. Dkt. No. 75 at 9. 15 PURPA requires State regulatory authorities such as CPUC to implement the rules prescribed by 16 FERC. 16 U.S.C. § 824a-3(f)(1). 17 The outcome of this case turns on three key requirements under PURPA and its 18 implementing FERC regulations. The first is what the parties have referred to as the “must-take 19 obligation,” see, e.g., Dkt. No. 152 (Trial Tr.) at 127:8-128:9, which is industry short-hand for the 20 proposition that PURPA requires FERC to encourage small power production with rules that 21 “require electric utilities to offer to . . . purchase electric energy from [qualifying] facilities.” 16 22 U.S.C. § 824a-3(a). FERC’s implementing regulations state that “[e]ach electric utility shall 23 purchase . . . any energy and capacity which is made available from a qualifying facility . . . 24 [d]irectly to the electric utility.” 18 C.F.R. § 292.303(a)(1). A few exceptions exist for this 25 mandatory purchase obligation, but the parties agree that they do not apply here. Trial Tr. at 26 130:14-131:7 (CPUC witness Michael Colvin testifying that “the must-take obligation for 20 27 megawatts and under remains”). 28 2 1 The second and third legal requirements that are critical to this case have to do with 2 pricing. PURPA and FERC’s regulations not only mandate that electric utilities must purchase 3 energy and capacity from qualifying facilities, they also set certain required terms for those 4 purchases. Under 18 C.F.R. § 292.304(b)(2), utilities must purchase energy and capacity from 5 qualifying facilities at a rate that “equals the avoided costs” of the utility. Under the regulations, 6 “avoided costs” means “the incremental costs to an electric utility of electric energy or capacity or 7 both which, but for the purchase from the qualifying facility or qualifying facilities, such utility 8 would generate itself or purchase from another source.” 18 C.F.R. § 292.101(b)(6). 9 10 The regulations also require that qualifying facilities be given a choice in the pricing of the energy sales to the utilities. Under 18 C.F.R. § 292.304(d): United States District Court Northern District of California 11 Each qualifying facility shall have the option either: 12 (1) To provide energy as the qualifying facility determines such energy to be available for such purchases, in which case the rates for such purchases shall be based on the purchasing utility’s avoided costs calculated at the time of delivery; or 13 14 15 16 17 18 (2) To provide energy or capacity pursuant to a legally enforceable obligation for the delivery of energy or capacity over a specified term, in which case the rates for such purchases shall, at the option of the qualifying facility exercised prior to the beginning of the term, be based on either: (i) The avoided costs calculated at the time of delivery; or 19 (ii) The avoided costs calculated at the time the obligation is incurred. 20 The parties agree that section (d)(2) is the pertinent provision in this case because Winding Creek 21 sought a “legally enforceable obligation for the delivery of energy or capacity over a specified 22 term” to secure financing for its planned but unbuilt solar facility. 23 The Court’s prior motion to dismiss orders settled the proper parties in the case, the 24 facilities at issue and the plausible legal claims, all of which have mutated to some degree over the 25 life of this case. Dkt. Nos. 39, 60, 75. The operative complaint is plaintiff’s second amended 26 complaint for declaratory and injunctive relief. Dkt. No. 61. Plaintiff is Winding Creek Solar 27 LLC, an owner and developer of solar projects, and Allco Finance Limited is its only member. Id. 28 ¶ 10. Defendants are the five Commissioners of the California Public Utilities Commission who 3 1 were sued in their official capacities. Id. ¶¶ 11-15. The facility at issue is an unbuilt, 1.0- 2 megawatt solar project that Winding Creek plans to construct in Lodi, California (the “Lodi 3 facility”). Id. ¶¶ 10, 75. Winding Creek’s only remaining legal claim is for “preemption” based 4 on alleged violations of the Supremacy Clause (and not under 42 U.S.C. § 1983). Dkt. No. 75 at 5 10-11. The Supremacy Clause theory alleges conflicts between the challenged CPUC orders and 6 PURPA. Id. 7 The three specific CPUC orders that plaintiff challenges are: D.12-05-035 (the “May 2012 8 Order”), D.13-01-041 (the “January 2013 Order”) and D.13-05-034 (the “May 2013 Order”). Dkt. 9 No. 61 ¶ 6. As Winding Creek alleges, these orders set the terms on which California’s investorowned utilities such as PG&E must enter into long-term, fixed-price contracts with qualifying 11 United States District Court Northern District of California 10 facilities such as Winding Creek’s Lodi facility. Id. ¶¶ 1, 6. The overall procurement program 12 established by these orders is known as the “Re-MAT Program,” see, e.g., id. ¶ 45 (the 13 “Renewable Market-Adjusting Tariff” or “‘Re-MAT’ for short”), and Winding Creek focuses its 14 attack on two aspects of the program. It challenges the 750-megawatt statewide cap that the 15 program places on the electric utilities’ collective obligation to purchase electricity from 16 qualifying facilities. Id. ¶¶ 7, 50-54. It also alleges that “the Orders provide for a purchase price 17 that is different than the utilities’ avoided costs.” Id. ¶ 8. Winding Creek asserts that both of these 18 aspects of the Re-MAT program conflict with PURPA and the regulations enacted by FERC 19 pursuant to PURPA. See id. ¶¶ 78-101. 20 Both sides filed for summary judgment (Dkt. Nos. 89, 90) following the Court’s third 21 motion to dismiss order, which granted in part and denied in part defendants’ motion to dismiss 22 without further leave to amend. Dkt. No. 75. Tracking its complaint, Winding Creek sought 23 summary judgment on the grounds that the Re-MAT Program violates PURPA because (i) it caps 24 the amount of electricity that utilities must purchase from qualifying facilities, and (ii) the rate 25 offered under the program is not based on the utilities’ avoided costs. Dkt. No. 89. 26 Defendants sought summary judgment in their favor on the same issues, but in doing so, 27 they relied heavily on a different CPUC procurement program: the “mandatory Standard Contract 28 that California utilities must offer smaller QFs of 20 MW or less generation capacity under 4 1 PURPA.” Dkt. No. 90 at 1. Defendants argued that the Re-MAT program’s caps did not violate 2 the utilities’ purchase obligation under PURPA because “the Standard Contract is available to 3 Winding Creek.” Id. at 16. Defendants also argued that Re-MAT pricing is properly based on 4 utilities’ avoided cost rates, and that the Standard Contract satisfies the pricing requirements under 5 18 C.F.R. § 292.304(d)(2). Id. at 17-25. Defendants argued that because the Standard Contract 6 fully satisfies PURPA, the CPUC was free to have alternative programs like Re-MAT even if 7 those additional programs may not be PURPA-compliant. Dkt. No. 105 at 15:5-19. The parties’ 8 disagreement has now crystallized around the compliance of the Re-MAT Program and the 9 Standard Contract with PURPA and implementing regulations. 10 Needless to say, this dispute takes place in a complex regulatory context. While the United States District Court Northern District of California 11 dispositive facts turned out to be relatively straightforward, the parties had a marked tendency to 12 resort to industry jargon and inside-baseball arguments in ways that sometimes obscured the basic 13 issues. Consequently, after the summary judgment motion hearing, the Court invited and received 14 an amicus brief jointly filed by PG&E, Southern California Edison Company and San Diego Gas 15 & Electric Company, to which both plaintiff and defendants filed responses. Dkt. Nos. 109, 110, 16 112. Even then, the Court determined that summary judgment could not be resolved on the papers 17 and held a one-day bench trial on the question of “whether the CPUC’s standard contract complies 18 with 18 C.F.R. § 292.304(d)(2).” Dkt. Nos. 117, 148. The parties subsequently submitted post- 19 trial materials. Dkt. Nos. 153-159. This order sets out the Court’s findings of fact and 20 conclusions of law from the bench trial, and resolves the pending summary judgment motions with 21 the benefit of those findings and conclusions. 22 23 FINDINGS OF FACT AND CONCLUSIONS OF LAW Rule 42(b) of the Federal Rules of Civil Procedure provides that “[f]or convenience, to 24 avoid prejudice, or to expedite and economize, the court may order a separate trial of one or more 25 separate issues, claims, crossclaims, counterclaims, or third-party claims.” Rule 1 directs that the 26 Rules should generally “be construed, administered, and employed by the court and the parties to 27 secure the just, speedy, and inexpensive determination of every action and proceeding.” Our 28 circuit has affirmed that “[u]nder Rule 42(b), the district court has broad discretion to bifurcate a 5 1 trial to permit deferral of costly and possibly unnecessary proceedings pending resolution of 2 potentially dispositive preliminary issues.” Jinro America Inc. v. Secure Investments, Inc., 266 3 F.3d 993, 998 (9th Cir. 2001).1 The Court held the bench trial under these provisions, with no 4 objection by either side. The parties also agreed to try disputed issues to the Court and not a jury. 5 See, e.g., Dkt. No. 82 at 16. The Court consequently states its findings and conclusions below 6 under Rule 52(a)(1). 7 I. 1. 8 9 THE RE-MAT PROGRAM California has an extensive Renewables Portfolio Standard (“RPS”) program that requires investor-owned utilities, electric service providers, and community choice aggregators to significantly increase procurement from eligible renewable energy resources in the coming 11 United States District Court Northern District of California 10 decades. Dkt. No. 130 ¶ 10.2 The California legislature established the program in 2002, and 12 expanded it in 2006, 2011 and 2015. Id. Many of the legal requirements for the RPS program are 13 codified at California Public Utilities Code Section 399.11 et seq. Id. at n.2. 2. 14 The CPUC implements and administers RPS compliance rules for California’s 15 retail sellers of electricity, and this includes establishing the terms and conditions of procurement. 16 Dkt. No. 130 ¶ 9. 17 3. Re-MAT is a market-based RPS program that provides a feed-in tariff for 18 renewable generators sized up to 3 megawatts. Dkt. No. 130 ¶ 11. A feed-in tariff is a policy 19 mechanism designed to accelerate investment in and deployment of renewable energy, and it 20 achieves this by offering long-term contracts to renewable energy producers. Id. ¶ 12. 4. 21 The Re-MAT program became operational in October 2013. Dkt. No. 130 ¶ 17. 22 23 24 25 26 27 1 See also Stewart v. RCA Corp., 790 F.2d 624, 629 (7th Cir. 1986) (“Stewart’s complaint did not request a jury trial. If the judge was entitled to resolve disputes at trial, he was entitled to try a single issue under Fed. R. Civ. P. 42(b). There is little point in holding a full trial if a surgical approach can cut away needless disputes. A judge on top of a case can identify dispositive issues, and often these issues can be tried quickly and economically. Thoughtfully used, the trial limited to a single issue can assist litigants, witnesses, and courts alike.”); United States v. Berry, 862 F.2d 567, 568 (6th Cir. 1988) (affirming district court’s grant of United States’ motion for summary judgment, “which the district court held in abeyance pending an evidentiary hearing”). 2 28 This document, defendants’ unretained expert report of CPUC employee Cheryl Lee, was admitted as Trial Exhibit 113. Dkt. No. 144 at 8-9; Trial Tr. at 223:10-18. 6 1 5. The Re-MAT program offers three different prices for each of these different 2 product types: (1) baseload (i.e., providing firm energy deliveries at all hours; e.g., geothermal), 3 (2) peaking as-available (i.e., providing non-firm energy deliveries during peak use hours; e.g., 4 solar), and (3) non-peaking as-available (providing non-firm energy deliveries during non-peak 5 use hours; e.g., wind and hydro). The prices for each product type also vary by the utility making 6 the purchase. Dkt. No. 130 ¶¶ 20-24. 7 6. Within each of these categories, the price (again, by utility and by method of 8 energy generation) can change based on what is essentially an auction that is held every two 9 months. Dkt. No. 130 ¶¶ 40-43; Trial Tr. at 36:16-37:4. 10 7. After every two-month program period, the Re-MAT price can be adjusted in United States District Court Northern District of California 11 $4/MWh increments (up to $12/MWh) up or down based on the outcome and price adjustments of 12 the previous program period. The price is designed to respond to changes in generator interest and 13 costs to construct and operate generation facilities, which are understood to be “market supply 14 signals.” If there is decreased generator interest in accepting the offer price, the price is adjusted 15 upward to encourage more generators to enter the market; conversely, when more generators are 16 willing to sell at the offer price, the Re-MAT price is adjusted downwards so that ratepayers can 17 benefit from what appear to be increased supply and falling prices. Dkt. No. 130 ¶¶ 40-42; see 18 also Dkt. No. 153 ¶ 18 (“Under the design of the Re-MAT program, after the price for the initial 19 program period is set, the price for subsequent periods will adjust up or down based on QFs’ 20 willingness to accept the previous period’s offer price.”). 21 8. If at least five unaffiliated projects are in the utility’s product category queue and 22 the total capacity of the price-accepting project applicants is < 20% of the capacity allocation in 23 that period, then the price is adjusted upward by $4/MWh. If at least five unaffiliated projects are 24 in the utility’s product category queue and the total capacity of the price-accepting project 25 applicants is ≥ 100% of the capacity allocation in that period, then the Re-MAT price is adjusted 26 downward. If the two conditions for either increasing or decreasing the price do not exist, then the 27 price stays the same for the next program period. Dkt. No. 130 ¶¶ 41-43; see also Dkt. No. 153 28 ¶¶ 19-21. 7 1 9. The size of the price adjustment (between $4/MWh to $12/MWh) depends on the 2 number of consecutive program periods for which the increase or decrease conditions have been 3 met, and whether or not a contract has been executed in the prior period. Dkt. No. 130 ¶ 45. 4 10. There was no reasoned basis for CPUC’s choice of increments in multiples of $4 5 for these price adjustments as opposed to any other number; the size of these price adjustments 6 was arbitrary. Trial Tr. at 179:13-180:7. 7 11. As the CPUC’s own expert declared, the “adjustment component of the ReMAT program ensures that IOUs are not entering into contracts on their ratepayers’ behalf that are 9 higher than the market price, while also not setting a price that is lower than what the market will 10 bear.” Dkt. No. 130 ¶ 46; see also Trial Tr. at 182:13-21 (idea behind Re-MAT price adjustments 11 United States District Court Northern District of California 8 is that ratepayers “should pay no more than the market or . . . opportunities to procure a similar 12 product elsewhere.”). 13 12. During PG&E’s first Re-MAT program period, the offer price for peaking as- 14 available facilities like Winding Creek was $89.23 per megawatt hour. Dkt. No. 153 ¶ 16; Dkt. 15 No. 156 ¶ 8; Trial Tr. at 36:1-7. The CPUC established $89.23 as the starting price based on the 16 most recent Renewable Auction Mechanism solicitation at the time of the Re-MAT program’s 17 adoption. $89.23/MWh was the weighted average of each of the investor-owned utilities’ highest 18 -priced executed Renewable Auction Mechanism contracts. Dkt. No. 130 ¶¶ 38-39; see also Dkt. 19 No. 153 ¶¶ 16-17. Since then, the price has changed based on the auction mechanism described 20 above, and it has consistently fallen over time. 21 13. Re-MAT contracts are long-term contracts of 10, 15 or 20 years in duration. The 22 price is fixed for the entire length of the contract, with an all-in (or combined) capacity, energy 23 and renewable energy credit payment based on the offered price, which is adjusted by time-of- 24 delivery factors based on time of year and day that the electricity is generated. Dkt. No. 130 ¶ 32. 25 The contract price and time-of-delivery factors are known at the time of contract execution and 26 they do not change. Id. ¶ 49. 27 28 14. It is undisputed that the Re-MAT program caps the amount of energy a utility must procure through it. There is a statewide program cap of 750MW for all publicly owned utilities. 8 1 Dkt. No. 130 ¶ 15; see also Dkt. No. 153 ¶ 5 (“California has placed a 750 MW overall cap on the 2 quantity of Qualifying Facility generation utilities are obligated to purchase under the Re-MAT 3 program.”). 15. 4 Public Utilities Code § 399.20(f) sets the program cap and how the MWs are to be 5 allocated among California’s three largest investor-owned utilities. Dkt. No. 130 ¶ 25 & n.7. The 6 750 MW is allocated among the utilities proportionate to their customers’ share of the state-wide 7 peak electricity demand. Dkt. No. 153 ¶ 6. 16. 8 PG&E’s share of the total cap is 218.8MW. Dkt. No. 130 ¶ 25; Dkt. No. 153 ¶ 7. This program capacity is then divided equally among the three product categories: as-available 10 peaking, as-available non-peaking, and baseload. Dkt. No. 130 ¶ 26; Dkt. No. 153 ¶ 9. So for 11 United States District Court Northern District of California 9 peaking as-available QFs like Winding Creek’s proposed solar facility, PG&E’s total purchase 12 obligation under the Re-MAT is 49.949 MW. Dkt. No. 153 ¶ 10. 17. 13 PG&E offers a limited amount of MWs in every Re-MAT program period. Each 14 Re-MAT program period is two months in duration, and the predetermined maximum amount that 15 PG&E may offer in each period is 5 MWs. Dkt. No. 130 ¶¶ 29-30; Dkt. No. 153 ¶ 12 (“the Re- 16 MAT program also places a cap of 5 MW on PG&E’s procurement obligation for each category of 17 QF in each program period”). 18. 18 The soonest that PG&E’s Re-MAT program can be fully subscribed in the peaking 19 as-available category is approximately July 2018. Dkt. No. 130 ¶ 3. 20 II. THE STANDARD CONTRACT 19. 21 The Standard Contract for QFs of 20 MW or less is a product of the QF Settlement, 22 which resolved years of litigation between QFs and their trade associations, utilities, the CPUC 23 and other parties. Dkt. No. 156 ¶¶ 17, 19. The agreement settled disputes over the terms and 24 availability of contracts between QFs and utilities, and took effect in December 2010. Dkt. 25 No. 153 ¶ 32. 20. 26 Winding Creek is not a party to the QF Settlement. Dkt. No. 156 ¶ 18; Dkt. 27 No. 153 ¶ 33. It can, however, enter into a Standard Contract if it so desires. Trial Tr. at 38:17- 28 19. 9 1 2 3 21. The average term for a Standard Contract is 10 years. Trial Tr. at 41:1-4; see also id. at 111:8-12 (term can be up to 7 or 12 years). 22. The pricing for the Standard Contract has two components -- one for capacity, for 4 which the price is fixed, and another for energy. Trial Tr. at 22:4-23; Dkt. No. 156 at ¶¶ 20-21. 5 The capacity payment is essentially a payment for the amount of energy a facility could deliver at 6 any given time, as having that energy available to it increases a utility’s ability to meet an 7 increased demand for electricity more quickly. Trial Tr. at 21:4-15. The energy payment on the 8 other hand is for the actual energy that is delivered from the QF to the utility. Id. at 21:16-18. For 9 intermittent resources like solar, it is the energy component that counts for probably 80 percent of 10 United States District Court Northern District of California 11 the revenues. Id. at 42:13-15. 23. The energy price for the Standard Contract is a formula rate for which some inputs 12 are known, but at least three of the inputs are not known at the time the contract is signed. Trial 13 Tr. at 22:4-23. The three market-based variable inputs are: a gas index (or burner tip gas price), a 14 market heat rate, and a location adjustment factor. Dkt. No. 156 ¶ 21. (The other three inputs for 15 the formula are: variable operations and maintenance, a time of use factor, and greenhouse gas 16 compliance costs. Dkt. No. 153 ¶ 38.) 17 24. The burner tip gas price is essentially the price for natural gas, which can vary 18 significantly over time. Trial Tr. at 35:18-20, 27:8-25. The gas input is based on a monthly index 19 updated on the first business day of each month, based on the last week of the previous month. 20 Dkt. No. 156 ¶ 21; Dkt. No. 153 ¶ 42. 21 25. The market heat rate is a measure of the efficiency of the assumed avoided gas- 22 fired generator. Trial Tr. at 35:7-9. The market heat rate varies monthly and its value for 23 purposes of the formula is updated on the 5th business day of each month. Dkt. No. 153 ¶ 41. 24 26. The third key variable is the locational difference. Trial Tr. at 28:17-19. That 25 factor is based on locational marginal prices, and consequently does not yet exist for an unbuilt 26 facility like the Lodi facility at issue in this case. Trial Tr. at 29:3-23. The location adjustment 27 factor is a site-specific factor that varies to reflect the fact that the cost of energy from a particular 28 10 1 location varies due to changes in the local energy markets. It varies monthly and is identified 30 2 days after generation occurs and is then applied to the prior month’s payment. Dkt. No. 153 ¶ 43. 27. 3 This formula is the only way that the price of energy is calculated for a QF under 4 the Standard Offer Contract. Trial Tr. at 34:9-15. The output of the formula can exhibit 5 significant volatility over time. Trial Tr. at 30:9-31:21. 28. 6 The CPUC cannot say what the output of the formula, i.e., the energy price, will be for any given time in the future during a utility’s contract period with a QF without knowing how 8 the variables will be filled in on a month-by-month basis with actual market data. Trial Tr. at 9 116:13-17. 10 29. 11 United States District Court Northern District of California 7 Dkt. No. 156 ¶ 19. 12 III. 13 Procurement through the Standard Contract for QFs 20MW or Less is not capped. WINDING CREEK 30. Plaintiff Winding Creek Solar LLC is a developer of solar generating facilities and 14 currently seeks to develop a 1-megawatt solar generating facility in Lodi, California. Dkt. No. 156 15 ¶ 1; Dkt. No. 153 ¶ 1. 16 31. During PG&E’s first Re-MAT program period, when the offer price was $89.23 17 per megawatt hour, Winding Creek could not participate because it was not among the projects at 18 or near enough the head of the queue. Dkt. No. 156 ¶ 8. The order for this first queue was 19 determined randomly for all the generators that had submitted timely applications; subsequently 20 the queue has formed on a first-come, first-served basis. Dkt. No. 153 ¶ 14. For each program 21 period, PG&E proceeds in order of the queue, asking each generator if it will accept a contract at 22 the program price for that period. Id. ¶ 15. 23 32. Winding Creek was offered a contract at $77.23/MWh in March 2014, but it 24 declined. It was offered another contract at $65.23/MWh in May 2014, but Winding Creek 25 declined that also. Dkt. No. 156 ¶ 9; Dkt. No. 153 ¶ 30. Winding Creek has since remained 26 eligible during every Re-MAT period to accept an offer but it has chosen not to do so. Dkt. 27 No. 156 ¶¶ 9, 15. Winding Creek currently occupies the first place in PG&E’s Re-MAT queue for 28 peaking as-available facilities. Dkt. No. 153 ¶ 31. 11 33. 1 2 Winding Creek has the option of entering into a Standard Contract if it so desires. Trial Tr. at 38:17-19. SUMMARY JUDGMENT 3 4 5 I. LEGAL STANDARDS Under Rule 56 of the Federal Rules of Civil Procedure, a “party may move for summary 6 judgment, identifying each claim or defense -- or the part of each claim or defense -- on which 7 summary judgment is sought. The court shall grant summary judgment if the movant shows that 8 there is no genuine dispute as to any material fact and the movant is entitled to judgment as a 9 matter of law.” Fed. R. Civ. P. 56(a). 10 The party moving for summary judgment always bears the initial burden of demonstrating United States District Court Northern District of California 11 the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 12 (1986). When the moving party also bears the ultimate burden of proof at trial, it can meet this 13 initial burden by “com[ing] forward with evidence which would entitle it to a directed verdict if 14 the evidence went uncontroverted at trial.” C.A.R. Transp. Brokerage Co. v. Darden Rests., Inc., 15 213 F.3d 474, 480 (9th Cir. 2000). When the moving party does not bear the ultimate burden of 16 proof, it can meet its initial burden on summary judgment by “‘showing’ -- that is, pointing out to 17 the district court -- that there is an absence of evidence to support the nonmoving party’s case.” 18 Celotex, 477 U.S. at 325. Once this initial burden of production has been met by the moving 19 party, the burden then shifts to the nonmoving party to “produce evidence to support its claim or 20 defense.” Nissan Fire & Marine Ins. Co., Ltd. v. Fritz Cos., Inc., 210 F.3d 1099, 1103 (9th Cir. 21 2000); see also C.A.R., 213 F.3d at 480. “If the nonmoving party fails to produce enough 22 evidence to create a genuine issue of material fact, the moving party wins the motion for summary 23 judgment.” Nissan Fire, 210 F.3d at 1103 (citing Celotex, 477 U.S. at 322). Conversely, if the 24 nonmoving party “produces enough evidence to create a genuine issue of material fact, the 25 nonmoving party defeats the motion.” Id. 26 A dispute is genuine “if the evidence is such that a reasonable jury could return a verdict” 27 for either party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A fact is material if it 28 could affect the outcome of the suit under the governing law. Id. at 248-49. To determine 12 1 whether there exists a genuine dispute as to any material fact, a court must view the evidence in 2 the light most favorable to the non-moving party, drawing all justifable inferences in that party’s 3 favor. Id. at 255. A principal purpose of summary judgment “is to isolate and dispose of factually 4 unsupported claims.” Celotex, 477 U.S. at 323-24. In resolving a summary judgment motion, it is not the Court’s task “to scour the record in 5 6 search of a genuine issue of triable fact.” Keenan v. Allan, 91 F.3d 1275, 1279 (9th Cir. 1996) 7 (quotations omitted). Rather, it is entitled to rely on the nonmoving party to “identify with 8 reasonable particularity the evidence that precludes summary judgment.” Id.; see also Fed. R. 9 Civ. P. 56(c)(3) (“The court need consider only the cited materials, but it may consider other materials in the record.”). 11 United States District Court Northern District of California 10 II. THE RE-MAT PROGRAM IS NOT COMPLIANT WITH PURPA 12 Despite the complex regulatory and factual background here, the key legal issues turned 13 out to be straightforward, and the scope of the parties’ actual dispute quite narrow. As an initial 14 matter, the Court concludes that the Re-MAT Program is not PURPA-compliant in at least two 15 independent ways. Defendants implicitly recognize this non-compliance in the heavy emphasis 16 they place on the Standard Contract Program. 17 One area of Re-MAT’s non-compliance is the program cap. It is undisputed that the 18 CPUC imposed a 750 MW statewide cap for the program overall, which is further subdivided into 19 a 5 MW cap for PG&E for each category of QF in each Re-MAT program period. See Findings of 20 Fact and Conclusions of Law (“FFCL”), supra, ¶¶ 14-17. At the same time, it is also undisputed 21 that PURPA and the implementing FERC regulations contain a “must-take obligation” -- a 22 mandatory purchase obligation on the part of utilities to buy “any energy and capacity which is 23 made available from a qualifying facility” -- which remains in place for facilities like the Lodi 24 facility. See p. 2, supra; see also 16 U.S.C. § 824a-3(a), 18 C.F.R. § 292.303(a)(1), and Trial Tr. 25 at 130:14-131:7. The plain meaning of this requirement is that utilities must buy all of the energy 26 and capacity offered by QFs. It does not require significant legal analysis to conclude that 27 CPUC’s imposition of caps in the Re-MAT program violates the must-take obligation. 28 13 The other area of non-compliance involves pricing. Here, too, the Court finds that the 1 2 issue is straightforward. Prices generated by the Re-MAT program’s reverse auction procedure do 3 not satisfy the definition of “avoided costs” in FERC’s regulations. Under 18 C.F.R. 4 § 292.101(b)(6), “avoided costs” means “the incremental costs to an electric utility of electric 5 energy or capacity or both which, but for the purchase from the qualifying facility or qualifying 6 facilities, such utility would generate itself or purchase from another source.” PURPA itself 7 requires that in prescribing rules for utilities to purchase electric energy from a qualifying facility, 8 the rates may not “exceed[] the incremental cost to the electric utility of alternative electric 9 energy.” 16 U.S.C. § 824a-3(b). The “incremental cost of alternative electric energy” is in turn defined as “the cost to the electric utility of the electric energy which, but for the purchase from [a 11 United States District Court Northern District of California 10 QF], such utility would generate or purchase from another source.” 16 U.S.C. § 824a-3(d). 12 In light of these definitions, it would make sense to look to a spot market price or similar 13 indicator for electricity. It makes much less sense to use a complex auction procedure burdened 14 with arbitrary rules, such as a randomly selected two-month time period (as opposed to any other) 15 and price adjustments applied in $4 increments -- a method that even the CPUC witness 16 acknowledged was without a reasoned basis. See FFCL ¶¶ 5-10. The reverse auction procedure 17 strays too far from basing prices on a utility’s but-for cost, which the statute and regulations 18 require. 19 III. 20 THE STANDARD CONTRACT DOES NOT EXCUSE RE-MAT NONCOMPLIANCE 21 Because Winding Creek has shown the Re-MAT program’s non-compliance on these two 22 requirements, the burden shifts to defendants to demonstrate why summary judgment should not 23 be entered for Winding Creek. They do not meet their burden. 24 As defendants acknowledge, only two programs are at issue in this case: “The CPUC has 25 developed numerous programs that are compliant with [PURPA], but have identified only two of 26 these programs for which WCS can qualify: the Renewable Market Adjusting Tariff (Re-MAT) 27 program; and the Standard Contract for QFs 20 MW or Less.” Dkt. No. 156 ¶ 5 (citing Lee 28 Unretained Expert Report, ¶¶ 55-59). Defendants’ primary defense in this case is that the 14 1 Standard Contract satisfies PURPA, and so the CPUC is free to have additional programs that are 2 not PURPA-compliant, including a non-compliant Re-MAT Program. Dkt. No. 90. That point 3 makes some analytical sense, and for summary judgment purposes the Court accepts it as true. 4 But it does not save defendants because they have not shown that PURPA and its implementing 5 FERC regulations are fully satisfied through the Standard Contract in and of itself, or even in 6 combination with Re-MAT. Here is why. The text of 18 C.F.R. § 292.304(d)(2) clearly states that, “at the option of the 7 8 qualifying facility exercised prior to the beginning of the term,” the QF may sell energy or 9 capacity at a rate determined by either “(i) [t]he avoided costs calculated at the time of delivery; or (ii) [t]he avoided costs calculated at the time the obligation is incurred.” Winding Creek agrees 11 United States District Court Northern District of California 10 that the Standard Contract provides a rate based on an “avoided cost.” See Dkt. No. 153 ¶ 35 12 (“The rate contained in the Standard Contract is an ‘avoided cost’ rate, which is defined as a cost 13 that the utility would otherwise incur if it had to buy power from a non-QF source.”). But the 14 Standard Contract does not -- and cannot -- offer both of the pricing options that PURPA gives to 15 QFs. 16 The evidence against the CPUC emerges directly from the defendants’ own trial testimony 17 and post-trial submissions. At trial, Michael Colvin, a CPUC employee, expressly testified that 18 the Standard Contract complies with both 18 C.F.R. § 292.304(d)(2)(i) and (d)(2)(ii). Trial Tr. at 19 119:21-121:15; see also Dkt. No. 155 at 6. This testimony effectively acknowledged that the 20 Standard Contract does not offer the legally required price option choice to QFs. See Trial Tr. at 21 121:10-15 (Q: “So in your mind, in your view, there is no meaningful difference between (d)(2)(i) 22 and (d)(2)(ii) in the way that the price paid to the QF would be calculated, is that right?” 23 A: “Correct. For purposes of this contract.”). 24 In post-trial briefing, defendants tried to escape from this testimony by declaring Colvin to 25 be “in error,” and stating that “[t]he CPUC here concedes that the Standard Contract for 20 MW or 26 Less is a contract under 18 C.F.R. § 292.304(d)(2)(ii), but is not a contract under 18 C.F.R. 27 § 292.304(d)(2)(i).” Dkt. No. 155 at 6. This effort to bury Colvin’s testimony is wholly 28 unpersuasive. As an initial matter, defendants championed Colvin as an expert on contract pricing 15 1 for QFs, and relied heavily on his statements before his testimony in court. See, e.g., Dkt. No. 2 134. After taking evidence about Colvin’s long experience at the CPUC, and hearing his 3 testimony on the stand, the Court has no doubt that he was a knowledgeable and competent 4 witness who fully understood the questions posed to him and the answers he gave at trial. The 5 Court also finds his testimony was credible. Defendants’ about-face on Colvin as a witness and 6 his testimony is not well-taken. 7 In addition, defendants’ post-trial attacks on Colvin are all in the form of statements by 8 lawyers and not based on evidence before the Court. A lawyer’s argument does not trump a fact 9 witness’s testimony at trial. That is all the more true here because other facts undermine defendants’ contentions. Under 18 C.F.R. § 292.304(d)(2), there are two pricing options that must 11 United States District Court Northern District of California 10 be provided, and defendants have not identified how those two options are on offer through one or 12 more programs that are available to Winding Creek. Defendants acknowledge, as they must, that 13 “a single formula or pricing mechanism does not comply with both 18 C.F.R. § 292.304(d)(2)(i) 14 and (d)(2)(ii) under PURPA.” Dkt. No. 159 at 2. And yet they go on to say that both Re-MAT 15 and the Standard Contract “satisfy 18 C.F.R. § 292.304(d)(2)(ii).” Id. They do not identify any 16 program that even arguably satisfies 18 C.F.R. § 292.304(d)(2)(i). This violates PURPA and 17 FERC’s implementing regulations. See Allco Renewable Energy Ltd. v. Mass. Elec. Co., 208 F. 18 Supp. 3d 390, 398 (D. Mass. 2016) (“The MDPU rule, by providing only the spot market rate, 19 eliminates the QF’s ability to choose the latter pricing option [i.e., ‘calculated at the time the 20 obligation is incurred’]. As such, the MDPU rule fails to properly implement FERC’s regulations, 21 as mandated by PURPA section 210(f)(1). 16 U.S.C. § 824a-3(f)(1).”). 22 Defendants make several post-trial arguments about why the programs available to 23 Winding Creek still satisfy PURPA. None of them are persuasive. Defendants suggest that they 24 need not comply with FERC regulations at all because “PURPA itself does not mandate the 25 requirements under 18 C.F.R. § 292.304(d)(2)(i) and (ii).” Dkt. No. 155 at 6. In a similar vein, 26 they repeatedly invoke the “broad authority and wide discretion” that should be afforded to the 27 CPUC. See, e.g., id. at 1. But as the Allco court noted, whatever latitude the state agency is to be 28 given “to implement FERC’s PURPA rules does not justify an implementation that plainly 16 1 conflicts with those rules.” 208 F. Supp. 3d at 399. Our circuit has also underscored this 2 uncontroversial principle in a case that defendants repeatedly cite. In Independent Energy 3 Producers Association v. California Public Utilities Commission, 36 F.3d 848 (9th Cir. 1994), the 4 court carefully examined FERC’s regulations and concluded that a CPUC program is preempted 5 “under federal law” citing to a FERC regulation. See 36 F.3d at 859 (concluding that CPUC 6 program is “also preempted under federal law. See 18 C.F.R. § 292.303(c)”). Even the snippet 7 defendants quote from a Supreme Court case states that a State commission can comply with 8 PURPA “by issuing regulations, by resolving disputes on a case-by-case basis, or by taking any 9 other action reasonably designed to give effect to FERC’s rules.” FERC v. Mississippi, 456 U.S. 742, 751 (1982) (emphasis added; quoted by defendants at Dkt. No. 155 at 1). FERC’s 11 United States District Court Northern District of California 10 regulations undeniably carry the force of law, and defendants are not free to ignore them just 12 because the regulatory requirements do not appear in the text of PURPA itself. 13 Defendants also make much of two FERC decisions that addressed Winding Creek’s 14 challenges to the Re-MAT program. See, e.g., Dkt. No. 155 at 7 (citing Winding Creek Solar 15 LLC, 151 FERC ¶ 61,103, 2015 WL 2151303 (May 8, 2015), and Winding Creek Solar LLC, 153 16 FERC ¶ 61,027, 2015 WL 6083932 (Oct. 15, 2015)). These decisions do not speak to the salient 17 issues here. The May 2015 “Notice of Intent Not to Act and Declaratory Order” simply states that 18 the Standard Contract provides a “long-term PURPA contract at an avoided cost rate.” 2015 WL 19 2151303, at *2. And the October 15, 2015 “Order Denying Request for Reconsideration” states 20 that FERC sees no reason to change its prior decision that “the Re-MAT program is consistent 21 with PURPA, because it is an alternative to a primary PURPA program, the Standard Contract for 22 QFs 20 MW or Under, which is consistent with PURPA.” 2015 WL 6083932, at *2. Neither 23 order even mentions, let alone meaningfully discusses, the two pricing options that are required 24 under 18 C.F.R. § 292.304(d)(2)(i) and (ii), or how the Standard Contract, the Re-MAT program, 25 or some combination of the two, satisfies those requirements. And because the FERC decisions 26 are consequently not germane, the Court finds that it need not reach questions of the level of 27 deference it must afford to these decisions. 28 17 Rather than attempting to show how the Standard Contract (by itself or with the Re-MAT 1 2 program) might satisfy the price option requirements for QFs, defendants actually put both 3 programs -- the only programs available to Winding Creek -- in the same pricing category, and 4 then insist that the CPUC need not satisfy the regulations at all. This is a misguided approach and 5 the Court rejects it. As a consequence, defendants’ argument that it does not matter that the Re- 6 MAT program is not PURPA-complaint because the Standard Contract already does all that is 7 required under PURPA must also be rejected. Returning to the cap issue, there is no dispute that participation in the Re-MAT program is 8 9 capped. Participation in the Standard Contract program is not capped. But because the Standard Contract program does not by itself fully satisfy the pricing requirements under PURPA, the 11 United States District Court Northern District of California 10 absence of caps in the Standard Contract program does not give the CPUC leeway to violate 12 PURPA with a Re-MAT cap. Put differently, even if the Standard Contract program and the Re- 13 MAT program in combination provided the two different pricing options under 18 C.F.R. 14 § 292.304(d)(2)(i) or (d)(2)(ii), that would not be enough because of the Re-MAT program’s caps. 15 Winding Creek does not, as the law mandates, have access to an uncapped program offering, at its 16 election, either a rate under 18 C.F.R. § 292.304(d)(2)(i) or (d)(2)(ii). Consequently, defendants 17 have not carried their burden against summary judgment for Winding Creek.3 18 IV. STANDING AND ADMINISTRATIVE EXHAUSTION Defendants have again raised Article III standing and administrative exhaustion arguments, 19 20 which were previously denied and are denied again here. Defendants say that “WCS could have 21 accepted an offer of $77.23/MWh on March 1, 2014, and it declined to do so,” and argue on that 22 basis that “self-inflicted harm is not an injury for constitutional standing purposes.” Dkt. No. 155 23 24 25 26 27 28 3 Defendants’ motion to reopen the summary judgment proceedings is denied. Dkt. No. 131. The request is based on “newly-understood facts that (1) plaintiff Winding Creek Solar LLC (WCS) will not face a cap on PG&E’s Re-MAT program for at least sixteen months, and (2) the Re-MAT program’s performance demonstrates that solar developers will accept Re-MAT contracts at lower avoided cost rates as their costs have fallen.” Id. at 1. These arguments have no bearing on the issues that drive the Court’s resolution of Winding Creek’s summary judgment motion. Winding Creek has shown that it is being denied an option to sell energy to PG&E on terms required by federal law. That other solar developers have opted not to complain about the same options has no bearing on Winding Creek’s correctness in doing so. 18 1 at 21-22. This is nothing more than an ill-taken request for reconsideration of the Court’s prior 2 standing decision. The Court has already found that Winding Creek has Article III standing for 3 this litigation. See Dkt. No. 75 at 11-12 (finding sufficient plaintiff’s allegations that its lost 4 “opportunity to enter into a contract with [PG&E] on terms required by federal law” is its injury in 5 fact, as well as the allegation that the “current impermissible price offered . . . ‘is the only 6 remaining barrier to plaintiff’s ability to obtain the financing needed to construct the Lodi 7 facility”). Defendants make no effort to establish a proper basis for reconsideration of this ruling, 8 see Civil L.R. 7-9, and the Court declines to do so. Defendants also raise an administrative exhaustion argument against Winding Creek’s 10 “attack” on the Standard Contract. Dkt. No. 159 at 5. In general, PURPA provides qualifying 11 United States District Court Northern District of California 9 facilities with the right to file suit in the United States district courts if State agencies like the 12 CPUC fail to properly implement FERC’s rules. 16 U.S.C. § 824a-3(h)(2)(B). But this right to 13 file suit arises only after the “electric utility, qualifying cogenerator or qualifying small power 14 producer” has first “petition[ed] the Commission [i.e., FERC] to enforce the requirements of 15 subsection (f)” and FERC has not initiated an enforcement action itself within 60 days of the 16 petition. Id. Defendants believe that “WCS’s failure to challenge the validity of the CPUC’s 17 primary PURPA program pursuant to 18 C.F.R. § 292.301 raises a new failure of WCS to exhaust 18 its administrative remedies.” Dkt. No. 159 at 5. This is unavailing. The Standard Contract is not a program Winding Creek affirmatively 19 20 challenged in the first instance. Rather, it became an issue in the case -- and plaintiff raised a 21 challenge to it -- only because defendants put the program forward in opposition to Winding 22 Creek’s summary judgment motion. There is no administrative exhaustion bar here. 23 V. RELIEF 24 Consequently, on the record before the Court, summary judgment is appropriate for 25 Winding Creek. The question of relief is now ripe. Winding Creek asks the Court to find that it is 26 entitled to a contract with PG&E under the Re-MAT program at the initial offering price of 27 $89.23/MWh. See Dkt. No. 154 at 16 (requesting that the Court order “the CPUC to award 28 Winding Creek with a contract for $89.23 per MWh”). 19 1 That goes too far. There is a difference between an implementation claim and an as- 2 applied challenge. See Solutions for Utilities, Inc v. Cal. Pub. Util. Comm’n, No. CV 11-04975 3 SJO (JCGx), 2016 WL 7613906, at *15 (C.D. Cal. Dec. 28, 2016) (“An implementation claim is a 4 claim that a state agency has failed to implement FERC’s PURPA regulations or has implemented 5 them in a way that is inconsistent with FERC’s regulations. Such claims are brought in federal 6 court . . . . Meanwhile, an as-applied claim challenges the application of a state agency’s rules to 7 an individual petitioner and is reserved to the state courts.”) (quotations omitted); see also Allco, 8 208 F. Supp. 3d at 397 (“Allco’s remedy for the MDPU’s allegedly improper implementation of 9 the FERC regulations is an implementation claim against the MDPU and, once the FERC regulations are properly implemented by the state, an as-applied claim against the utility to enforce 11 United States District Court Northern District of California 10 the state implementation.”). 12 In this case, while an implementation challenge was properly brought and is now upheld, 13 the request for a specific contract at a specific price is an as-applied challenge that does not belong 14 in this forum. The Court grants only the declaratory and injunctive relief requested by plaintiff 15 (Dkt. No. 61 at 24, Prayer for Relief, subsections (a)-(d)), and goes no further. CONCLUSION 16 17 Summary judgment is granted for plaintiff and against defendants. 18 IT IS SO ORDERED. 19 Dated: December 6, 2017 20 21 JAMES DONATO United States District Judge 22 23 24 25 26 27 28 20

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?