Monolithic Power Systems, Inc. v. Silergy Corporation et al
Filing
98
ORDER by Judge Vince Chhabria granting in part and denying in part 35 Motion to Dismiss; granting in part and denying in part 81 Motion to Dismiss and Staying Case. (knm, COURT STAFF) (Filed on 7/15/2014)
1
2
3
4
UNITED STATES DISTRICT COURT
5
NORTHERN DISTRICT OF CALIFORNIA
6
7
MONOLITHIC POWER SYSTEMS, INC.,
Case No. 14-cv-01745-VC
Plaintiff,
8
v.
9
10
SILERGY CORPORATION, et al.,
Defendants.
Re: Dkts. No. 35 and 81
11
United States District Court
Northern District of California
ORDER GRANTING MOTION TO
DISMISS IN PART, DENYING MOTION
TO DISMISS IN PART, AND STAYING
THE CASE
12
13
I.
INTRODUCTION
14
Plaintiff Monolithic Power Systems, Inc. ("MPS") has sued Defendants Silergy
15
Corporation, Silergy Technology, Compal Electronics, Inc., Bizcom Electronics, Inc., and Wei
16
Chen. Silergy Corporation is the parent company of Silergy Technology, and so the two
17
companies will collectively be referred to as "Silergy." Compal is the parent company of Bizcom,
18
and so the two companies will collectively be referred to as "Compal/Bizcom." MPS alleges
19
patent infringement against Silergy and Compal/Bizcom, and breach of contract against Chen and
20
Silergy. Silergy has moved to dismiss the patent infringement claims entirely, based on a
21
settlement agreement that required the parties to meet and confer about any patent infringement
22
allegation, and then mediate the dispute, before litigation. Silergy and Compal/Bizcom have also
23
moved to dismiss the willful infringement and induced infringement claims based on failure to
24
plead facts to support those claims. Chen and Silergy have not yet moved to dismiss the breach of
25
contract claim, which MPS added three days before the hearing on the motion to dismiss. But the
26
parties agree the question whether the breach of contract claim should be dismissed based on the
27
settlement agreement, to which both Chen and Silergy were parties, is ripe for adjudication.
28
The court finds that the settlement agreement prohibits MPS from bringing a patent
1
infringement claim against Silergy, or a breach of contract claim against Chen and Silergy, before
2
following the meet and confer and mediation process. Therefore, the lawsuit is dismissed as to
3
Silergy and Chen, and the case against Compal/Bizcom is stayed while MPS honors its contractual
4
obligation to negotiate with the other parties.
5
6
II.
DISCUSSION
On December 6, 2011, MPS signed a settlement agreement with Silergy and Chen. The
7
Agreement resolved several patent infringement suits involving the parties, and included a
8
schedule for Silergy's payment of $2,000,000 to MPS. The agreement included multiple other
9
provisions, including the following:
10
15
Escalation Path. In the event a party believes that the other party is infringing the party's
patent(s), with the exception of the MPS Patents, or that either party has violated a
provision of this Agreement, the Parties agree to initiate and conduct a good faith meet and
confer, within 90 days of a written request, to discuss resolution of the dispute; and, if the
Parties are unable to resolve the dispute within 90 days of the meet and confer, to submit
the dispute to mediation before JAMS or other mutually agreed upon mediator. During this
90 day period, and during any such dispute mediation, the parties may not commence any
patent opposition proceedings, patent revocation proceedings, declaratory judgment
proceedings, or re-examination proceedings in respect of the mediated patents.
16
MPS argues it was not required to refrain from suing before completing the process set
United States District Court
Northern District of California
11
12
13
14
17
18
19
forth above, because the "escalation path" fails to specify that a patent infringement suit may not
go forward during the process. But the language and purpose of the provision are clear: if "a party
believes that the other party is infringing the party's patent(s)" – which is what MPS believes now
20
21
22
– then the parties agree to conduct a meet and confer and, if that doesn't work, go to mediation.
While that happens, the provision ensures that the party accused of infringement will not, during
23
this "escalation" period, attack the accusing party's patent in other proceedings. It is obvious that
24
this provision contemplates completion of the mediation process before the accusing party can file
25
suit. Otherwise the process set forth in the escalation path would be virtually meaningless, if not
26
completely meaningless.
27
MPS also argues that the "escalation path," which does not include a termination date,
28
2
1
should be deemed terminated under California law. According to MPS, the court must discern the
2
provision's duration based on either the parties' intent or on what the court considers a reasonable
3
time. See McCaksey v. California State Auto. Assn., 118 Cal.Rptr.3d 34, 49 (Cal. App. 2010).
4
MPS argues that the "escalation path" should be construed to have terminated when Silergy
5
completed its payments to MPS. It bases this argument on a subsequent paragraph in the
6
"escalation path," which contemplates that payments from Silergy to MPS to resolve the prior
7
patent disputes should go to an escrow account, instead of directly to MPS, in the event that MPS
8
9
files another patent infringement suit. But this paragraph does not evince an intent by the parties
that the prior paragraph (the paragraph about meet and confer and mediation) apply only for the
11
United States District Court
Northern District of California
10
15-month duration of the payments to MPS. It merely reflects an intent that, if MPS sued Silergy
12
while the latter was still making payments, the payments would go to an escrow account instead of
13
to MPS.
14
Several provisions in the settlement agreement contain explicit termination dates,
15
16
17
indicating that the parties knew what to do when they wanted a provision to terminate before the
remainder of the contract. For example, Section F(4) of the agreement precludes Silergy from
18
copying MPS products "for a period of three years from the effective date." And Section G(2)
19
precludes Silergy from hiring anyone from MPS "for a period of three years from the Effective
20
Date."
21
In contrast, other provisions which lack an express termination date are clearly intended to
22
remain into effect today. For instance, MPS believes, and Silergy could not reasonably dispute,
23
24
that Section G(1) of the agreement, in which Wei Chen "represents and warrants not to use or
25
disclose any document that contains MPS confidential information," is still in effect. (After all,
26
this provision forms the basis of the breach of contract claim MPS added three days before the
27
hearing on the motion to dismiss.) Further, Section F(2) applies "to the extent Silergy continues to
28
make the payments…and thereafter." (emphasis added).
3
Because the parties did not include a termination date for the "escalation path" when they
1
2
knew how to include early termination dates in other provisions, and because the agreement
3
remains operable, there is no basis to conclude the "escalation path" does not remain operable as
4
well.
5
III.
6
CONCLUSION
Because the "escalation path" is in effect, the motion to dismiss the patent infringement
7
action against Silergy is granted, with leave to amend if necessary after the parties follow the
8
9
procedure laid out in the provision. The breach of contract claim against Chen and Silergy is also
dismissed, with leave to amend if necessary, because the "escalation path" also covers disputes
11
United States District Court
Northern District of California
10
concerning a breach of the agreement. The patent infringement action against Compal/Bizcom,
12
who were not parties to the settlement agreement, is stayed pending the outcome of the meet and
13
14
confer process and mediation involving MPS, Silergy and Chen. At the July 10, 2014 hearing on
the motion to dismiss, counsel for Compal/Bizcom committed that, in the event the court
15
16
17
determined that MPS, Silergy, and Chen were required to participate in a meet and confer and
mediation process, Compal/Bizcom would participate in that same process, and the court expects
18
them to do so in lieu of participating in a separate mediation hosted by the Northern District's
19
alternative dispute resolution program. Finally, Silergy and Compal/Bizcom's motion to dismiss
20
the induced and willful infringement claims is denied without prejudice to refiling it if necessary.
21
A case management conference is scheduled for February 10, 2015.
22
23
24
25
26
IT IS SO ORDERED.
Dated: July 15, 2014
______________________________________
VINCE CHHABRIA
United States District Judge
27
28
4
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?