ORDER denying 1 request to issue vessel arrest warrant. Signed by Judge Joseph C. Spero on February 23, 2015. (jcslc2S, COURT STAFF) (Filed on 2/23/2015)
1
2
3
4
UNITED STATES DISTRICT COURT
5
NORTHERN DISTRICT OF CALIFORNIA
6
7
JOSEPH ROBERT SPOONER,
Case No. 15-cv-00692-JCS
Plaintiff,
8
v.
ORDER DENYING REQUEST TO
ISSUE VESSEL ARREST WARRANT
9
10
MULTI HULL FOILING AC45 VESSEL 4
ORACLE TEAM USA, et al.,
Defendants.
11
United States District Court
Northern District of California
Re: Dkt. No. 1
12
13
I.
INTRODUCTION
Plaintiff Joseph Spooner brings this admiralty action for wrongful termination of a
14
15
16
17
18
―maritime services contract,‖ both in personam against Defendant Oracle Racing, Inc. (―Oracle
Racing‖) and in rem against 4 Oracle Team USA, a hydrofoiling AC45-class racing catamaran (the
―Vessel‖). The Court requested supplemental briefing from both parties as to whether a warrant
should issue for arrest of the Vessel. Having reviewed the parties‘ arguments, the Court concludes
that no basis for a maritime lien is apparent from Spooner‘s Complaint, and therefore declines to
19
issue a warrant to arrest the Vessel.
20
21
22
II.
BACKGROUND
A.
Factual Allegations
As relevant background to this action, the Court takes notice of the undisputed facts that
23
24
25
26
27
28
(1) the America‘s Cup is a long-established international sailing competition; and (2) Oracle
Racing, in conjunction with the Golden Gate Yacht Club, is the defending America‘s Cup
champion after winning the 34th America‘s Cup on San Francisco Bay in 2013.
Spooner‘s Complaint alleges as follows. In December of 2013, Spooner entered into a
maritime services contract with Oracle Racing to serve ―as a member of the sailing team of
ORACLE TEAM USA.‖ Compl. (dkt. 1) ¶ 10. Spooner alleges that as a result of this contract, he
2
―was employed by defendants as a member of the crew aboard [the Vessel], in the service of the
3
vessel, and in the course and scope of his duties as a seaman in furtherance of the mission and
4
commerce of the vessel [Spooner] crewed, maintained, and repaired said vessel.‖ Id. ¶ 9. The
5
contract ―commenced on February 1, 2014, for the fixed term of over three (3) and a half years,‖
6
to expire seven days following the last race of the 35th America‘s Cup Finals. Id. ¶ 10. From July
7
1, 2014 through the expiration of the contract, Spooner was to be paid $25,000 per calendar
8
month. Id. ¶ 11. The contract also provided that Spooner would receive a bonus of not less than
9
six months‘ pay if Oracle Team USA successfully defended its title at the 35th America‘s Cup,
10
and that he would be reimbursed for ―any other business expenses . . . properly and necessarily
11
United States District Court
Northern District of California
1
incur[red].‖ Id. ¶¶ 12−13.
12
Spooner alleges that by letter dated January 16, 2015, ―Oracle Racing, Inc. wrongfully and
13
without cause, breached its contractual obligations to [Spooner] by discharging [him] from
14
performing his contractual services.‖ Id. ¶ 14. Oracle Racing paid Spooner through January 31,
15
2015, but has not paid him for any period since that date, despite Spooner‘s demand that Oracle
16
Racing pay him the full amount due under the remaining term of the contract. Id. ¶¶ 15−17. In
17
satisfaction of wages purportedly owed, Spooner asks the Court to declare that Spooner holds a
18
maritime lien against the Vessel, and to arrest the Vessel for potential condemnation and sale. Id.
19
at 5 (Itemized Demand for Judgment ¶¶ 1−2).
20
B.
21
Spooner filed his Verified Complaint on February 13, 2015 and sought expedited review of
Procedural History
22
his request for a warrant to arrest the Vessel. See generally id.; Notice of Request for Review
23
(―Request,‖ dkt. 1-4). The Request argues that an arrest warrant should issue because Spooner is
24
entitled to a maritime lien both for seaman‘s wages and for necessary repairs and maintenance.
25
Request at 4−5. Spooner also filed a short ―Amended Notice of Request‖ the same day, consisting
26
of legal arguments as to ―whether a yacht is a vessel for the purpose of a maritime lien.‖ See Am.
27
Notice of Request (―Am. Request,‖ dkt. 4). The Court was unable to determine from these
28
documents whether a warrant should issue, and on February 17, 2015 issued an Order directing
2
1
Spooner to file a supplemental brief and permitting Oracle Racing to file a simultaneous brief in
2
opposition. See Order (dkt. 6). Specifically, the Court asked Spooner to address, among any other
3
relevant issues, the following:
4
(1) whether it is proper for the Court to review whether a complaint
sufficiently states a claim before issuing an arrest warrant for a
vessel; (2) if so, whether Spooner‘s Complaint sufficiently alleges
that Defendant Oracle Racing, Inc. (―Oracle Racing‖) lacked
authority to terminate Spooner‘s contract; and (3) whether wrongful
termination of an employment contract—as opposed to nonpayment
of wages for work already completed—gives rise to a maritime lien
in these circumstances.
5
6
7
8
Id. at 1.
9
10
Spooner‘s Supplemental Brief changes tack from his original Request. Instead of arguing
that Oracle Racing failed to pay seaman‘s wages or reimburse necessities, Spooner now argues
11
United States District Court
Northern District of California
that any breach of a maritime contract is sufficient to create a maritime lien, and that his contract
12
with Oracle Racing meets the criteria of a maritime contract. Pl.‘s Supp‘l Br. (dkt. 9) at 3−4, 9
13
(citing Norfolk S. Ry. v. Kirby, 543 U.S. 14, 24 (2004); Kossick v. United Fruit Co., 365 U.S. 731,
14
735−36 (1961); The Resolute, 168 U.S. 437, 439−40 (1897); Wilkens v. CIT Corp., 153 F.3d 1273,
15
16
17
1276 (11th Cir. 1998)). Spooner acknowledges that the Court ―must review the complaint and
supporting papers‖ to determine whether ―the conditions for an in rem action appear to exist,‖ but
argues that such review ―is not meant to be ‗rigorous.‘‖ Id. at 7 (citing Admiralty Rule1 C(3)(a)(i);
18
Weeks Marine Inc. v. Cargo of Scrap Metal Ladened Aboard Sunken Barge Cape Race, 571 F.
19
Supp. 2d 334 (D. Conn. 2008)). Thus, according to Spooner, his allegation that Oracle Racing
20
breached a ―maritime services contract‖ is sufficient to issue an arrest warrant for the Vessel—and
21
any arguments against the propriety of arrest are better suited for a post-arrest hearing. See id. at
22
6.
23
24
25
Oracle Racing‘s brief opposing arrest of the Vessel relies in large part on factual
contentions outside the scope of the Complaint, including a declaration by Oracle Racing‘s general
manager Grant Simmer and a copy of contract that grants either party the right to terminate it ―for
26
27
28
1
The rules governing admiralty proceedings in federal court are set forth in the Federal Rules
of Civil Procedure‘s Supplemental Rules for Admiralty or Maritime Claims and Asset Forfeiture
Actions. For convenience, this Order refers to those rules as ―Admiralty Rules.‖
3
1
any reason whatsoever at any time by giving no less than two (2) weeks‘ prior written notice of
2
termination.‖ Simmer Decl. (dkt. 10-1) Ex. A ¶ 12; see generally Oracle Br. (dkt. 10). Oracle
3
Racing argues that under Admiralty Rule C, it is proper for the Court to examine whether the
4
conditions for an in rem action exist before issuing a warrant. Oracle Br. at 3. According to
5
Oracle Racing, (1) there is no maritime lien for breach of a maritime contract because Oracle
6
Racing was within its rights in terminating the contract, id. at 4; (2) there is no maritime lien for
7
unpaid wages because Spooner has not alleged that he was not paid for any services rendered and
8
because relevant provisions of the Seaman‘s Wages Act exclude yachts, id. at 4−5; and (3) there is
9
no maritime lien for necessaries because Spooner has not alleged that he was not reimbursed for
repair work that he actually performed and because the Vessel was not launched until after
11
United States District Court
Northern District of California
10
Spooner‘s contract was terminated, id. at 5−6. The Court disregards Oracle Racing‘s contentions
12
that rely on purported facts outside of the Complaint, except to the extent, as discussed below, that
13
the contract itself is properly subject to judicial notice.
Spooner filed a second supplemental brief asserting that there is no party with standing to
14
15
speak for the Vessel because Oracle Racing‘s brief ―was not filed on behalf of the owner of the
16
[Vessel],‖ and no ―Claim of Owner‖ has been filed.2 Pl.‘s 2d Supp‘l Br. (dkt. 12) at 1. Spooner
17
also filed a declaration disputing Oracle Racing‘s contention that the Vessel had not been launched
18
during his tenure with Oracle Racing. See generally Spooner Decl. (dkt. 14). Spooner‘s
19
Declaration attaches photographs and internet links to videos that purport to show Spooner sailing
20
and repairing the Vessel. Spooner Decl. Exs. A−G. Spooner later filed an amended declaration
21
attaching additional evidence that the Vessel was launched, and Spooner crewed on it, before the
22
contract was terminated. See generally Spooner Am. Decl. (dkt. 15).
23
III.
ANALYSIS
24
A.
25
―In any action in rem the complaint must: (a) be verified; (b) describe with reasonable
Legal Standard
26
2
27
28
This issue is immaterial for present purposes. Whether or not Oracle Racing‘s counsel is
entitled to speak for the Vessel, Oracle Racing is itself a party to the case and the Court
specifically permitted Oracle Racing to file a brief addressing the propriety of an arrest warrant.
See dkt. 6.
4
1
particularity the property that is the subject of the action; and (c) state that the property is within
2
the district or will be within the district while the action is pending.‖ Admiralty Rule C(2). The
3
Admiralty Rules further provide that when such a complaint is filed:
4
The court must review the complaint and any supporting papers. If
the conditions for an in rem action appear to exist, the court must
issue an order directing the clerk to issue a warrant for the arrest of
the vessel or other property that is the subject of the action.
5
6
Admiralty Rule C(3)(a)(i).
7
The Ninth Circuit has described the standard for bringing a maritime action in rem as
8
follows:
9
A maritime action in rem has traditionally been available only in
connection with a maritime lien. Claims not creating a maritime lien
must be pursued in personam. The Resolute, 168 U.S. 437, 440–42,
18 S. Ct. 112, 113–14, 42 L. Ed. 533 (1897). Maritime liens must be
construed ―stricti juris, and cannot be extended by construction,
analogy, or inference.‖ Osaka Shosen Kaisha v. Pacific Export
Lumber Co., 260 U.S. 490, 499, 43 S. Ct. 172, 174, 67 L. Ed. 364
(1923). Consequently, ―[t]he only liens recognized today are those
created by statute and those historically recognized in maritime
law.‖ In re Admiralty Lines, Ltd., 280 F. Supp. 601, 604−05 (E.D.
La.1968), aff’d mem., 410 F.2d 398 (5th Cir. 1969).
10
United States District Court
Northern District of California
11
12
13
14
15
Melwire Trading Co. v. M/V Cape Antibes, 811 F.2d 1271, 1273 (9th Cir.) amended, 830 F.2d
16
1083 (9th Cir. 1987). In determining whether ―the conditions for an in rem action appear to exist‖
17
in this case, see Admiralty Rule C(3)(a)(i), the Court therefore considers whether Spooner appears
18
to have a maritime lien ―created by statute or historically recognized in maritime law‖ against the
19
Vessel. See Melwire Trading Co., 811 F.2d at 1273 (quoting Admiralty Lines, 280 F. Supp. at
20
604−05).
21
22
B.
Spooner’s Complaint Fails to Establish a Lien for Wages or Necessaries
Although Spooner‘s Complaint invokes a maritime lien for seaman‘s wages and
23
necessaries (specifically, repairs and maintenance), see Compl. ¶¶ 16−18, his allegations do not
24
support the existence of a lien on either of those bases. The Complaint explicitly alleges that he
25
was paid his contractual rate through January 31, 2015—fifteen days after Oracle Racing
26
―discharg[ed] [him] from performing his contractual services.‖ Id. ¶ 13. The Complaint does not
27
allege that Spooner provided any services whatsoever, whether as a sailor or a repairman, for
28
5
1
which he was not compensated. As Judge Sweigert stated in a 1967 decision of this Court:
2
From the earliest period of maritime commerce the test in admiralty
courts for determining whether there is a seaman‘s wage lien has
been: Has a maritime service been performed? If such service has
been performed, then whatever constitutes the compensation for the
service, if reducible to money, may be enforced by a maritime lien
against the vessel upon which those services were performed.
3
4
5
Long Island Tankers Corp. v. S. S. Kaimana, 265 F. Supp. 723, 726 (N.D. Cal. 1967) (emphasis
6
7
added) aff’d without opinion sub nom. Cross v. S. S. Kaimana, 401 F.2d 182 (9th Cir. 1968) (per
curiam). It follows that where all services performed have been fully compensated, no seaman‘s
8
wage lien arises. The Court concludes that the same principle applies to necessaries such as
9
repairs and maintenance.
10
Because wages and necessaries were the only grounds for a maritime lien discussed in
United States District Court
Northern District of California
11
12
13
Spooner‘s Complaint and contemporaneous supporting papers, the Court was unable to find that
―the conditions for an in rem action appear[ed] to exist,‖ and declined to direct the clerk to issue a
warrant. See Admiralty Rule C(3)(a)(i). The Court instead requested further briefing. Spooner‘s
14
supplemental briefs do not appear to pursue the argument that a maritime lien arises in this case
15
from unpaid wages or uncompensated necessaries. The Court therefore turns to whether the
16
purportedly wrongful termination of Spooner‘s ―maritime services contract‖ gives rise to a
17
maritime lien.
18
19
C.
Under Ninth Circuit Authority, Wrongful Termination of a Seaman’s Contract
Can Give Rise to a Maritime Lien
20
Spooner relies on the Supreme Court‘s 1897 statement in The Resolute that ―the only
21
requirements necessary to give jurisdiction‖ for ―a suit in rem for the breach of a maritime contract
22
[are] [f]irst, that the contract sued upon is a maritime contract; and, second, that the property
23
proceeded against is within the lawful custody of the court.‖ 168 U.S. at 439; see Pl.‘s Supp‘l Br.
24
at 3. To the extent that The Resolute can be read as holding that any breach of any maritime
25
contract gives rise to a maritime lien, the statement is dicta—the case before the Supreme Court
26
dealt with unpaid wages for services rendered as crew on a tugboat—and inconsistent with other
27
case law. Courts have long held, for example, that a ―claim for breach of an executory contract
28
cannot . . . give rise to a maritime lien enforceable in rem against a vessel.‖ European-Am.
6
1
Banking Corp. v. M/S Rosaria, 486 F. Supp. 245, 255 (S.D. Miss. 1978); see also, e.g., Osaka
2
Shosen Kaisha v. Pac. Export Lumber Co., 260 U.S. 490, 500 (1923); The Yankee Blade, 60 U.S.
3
(19 How.) 82, 90 (1857); 8-VII Benedict on Admiralty § 7.01(C)(1)(c). The issue in this case is
4
therefore whether a seaman3 can claim a maritime lien for damages owed for wrongful discharge
5
in breach of contract, even though he has been paid for services rendered prior to termination.
Case law on that issue is inconsistent and surprisingly sparse. Although some cases have
6
7
held that wrongful termination claims do not give rise to maritime liens, the Court understands
8
controlling Ninth Circuit authority to hold that they can.
At least one district court has held that a wrongfully terminated seaman ―cannot proceed in
9
rem even if improper discharge be assumed but must resort to whatever remedy he may have, if
11
United States District Court
Northern District of California
10
any, in personam.‖ The Golden Kauri, 28 F. Supp. 288, 290 (E.D. La. 1939). That court stated
12
that ―it is settled that where services have not, in fact, been rendered, there can be no lien as for
13
wages, except [as provided by statute],‖ based on the ―the settled rule that unexecuted4 maritime
14
contracts carry no lien.‖ Id. at 289−90. That holding is consistent with the general rule that a
15
maritime lien ―aris[es] out of services rendered to or injuries caused by‖ a vessel. See 1 Admiralty
16
& Mar. Law § 9-1. In the case of wrongful termination or discharge, no uncompensated services
17
have yet been rendered, and the harm is caused by the discharging party as opposed to the vessel.
18
The Fifth Circuit has cited The Golden Kauri with approval for the proposition that a ―seaman
19
does not have a claim against the vessel for the wages he would have earned had he not been
20
improperly discharged‖ unless such a remedy is provided by statute,5 and thus ―can proceed only
21
3
22
23
24
25
26
27
28
At least one court has held that a crew member in a yacht race is a seaman for the purpose of
admiralty law, albeit in the context of a claim for injury rather than breach of contract or unpaid
wages. In re Read, 224 F. Supp. 241, 246 (S.D. Fla. 1963). The reasoning of that court—that a
race crew ―c[omes] aboard for the very purpose of aiding in the navigation of a vessel,‖ id.—is
persuasive, particularly in this case where, unlike in Read, there was a contract and consideration
paid for Spooner to serve as crew.
4
It is clear in the context of the case that the court used the term ―unexecuted‖ in the sense of
something not ―done, given, or performed,‖ rather than not signed by the parties. See Black‘s Law
Dictionary 1650 (9th ed. 2009) (second listed definition of ―executed‖). The opinion previously
stated that the plaintiff had signed a written agreement that he believed mandated his continued
employment. The Golden Kauri, 28 F. Supp. at 289.
5
The current statute that provides for such a remedy in some circumstances is 46 U.S.C.
§ 10313(c). Spooner has not invoked this statute, and it is not applicable here because the chapter
7
1
against the owner or master of the vessel for the wages he would have earned and may not use the
2
summary in rem procedures Congress has provided seamen for the collection of their earned
3
wages.‖ Bunn v. Global Marine, Inc., 428 F.2d 40, 48 n.10 (5th Cir. 1970).
4
A respected treatise on admiralty law takes the opposite view, stating that a ―principle
5
exception to the [executory contract] rule is that a crewmember can assert a lien for unearned
6
wages.‖ 8-VII Benedict on Admiralty § 7.01(C)(1)(c) (citing Todd Shipyards Corp. v. City of
7
Athens, 83 F. Supp. 67, 90 (D. Md. 1949)). The only case cited, however, does not appear to
8
support that rule. The page of Todd Shipyards cited by Benedict discusses a lien for a provision
9
master‘s wages that had ―accumulated‖ during various voyages, as well as for the cost of supplies
he had purchased. Todd Shipyards, 83 F. Supp. at 90. The Court finds no indication that the
11
United States District Court
Northern District of California
10
provision master‘s lien was based on unearned wages. See id.
12
Other courts have in fact recognized maritime liens arising from wrongful discharge
13
claims. Most significantly, the Ninth Circuit appears to have taken that approach in Putnam v.
14
Lower, 236 F.2d 561 (9th Cir. 1956). In that case, the ―holders of a valid recorded preferred ship
15
mortgage on the oil screw vessel Silver Spray‖ appealed ―a decree of the district court . . .
16
foreclosing said mortgage and subordinating it to the wage liens of appellees,‖ the ship‘s crew. Id.
17
at 563. The Ninth Circuit identified ―an inconsistency . . . in the theory of recovery‖ applied by
18
the district court: the district court had found the seamen‘s liens superior to the mortgage based on
19
their favored status as wage liens, but the ship was arrested before the voyage commenced, and
20
―no maritime lien can be allowed to seamen for wages accruing subsequent to the time the ship is
21
taken into custodia legis.‖ Id. at 570. The Ninth Circuit resolved the inconsistency by construing
22
the crew‘s claims as for wrongful discharge damages rather than wages:
23
24
25
[I]t is clear that any compensation recoverable to appellees, as
wages, must have accrued at or prior to the time that appellee Lower
libeled the ‗Silver Spray.‘ While not unquestioned,6 courts have, in
similar situations, allowed recovery not for wages, but as damages
for breach of the seaman’s employment contract by wrongful
26
27
28
containing it applies only to vessels on international or intercoastal voyages. See id. § 10301(a).
There is no allegation that the Vessel in this case undertook or is even capable of undertaking such
a voyage. See generally Compl.
6
―Old Point Fish Co. v. Haywood, 4 Cir., 1940, 109 F.2d 703, 706.‖
8
discharge. This, on the theory that such claim becomes matured at
the time of the wrongful discharge,7 or, in our case, by the
abandonment of the contract by [the ship‘s owner].
1
2
Applying this reasoning to the instant case, since [the owner] had
wrongfully abandoned his contracts for the tuna venture before the
date of the libel, appellees‘ claims for damages had accrued before
the vessel entered custodia legis, and did not depend upon facts
occurring subsequent to that time. We conclude that the appellees,
claims existed at or before the time the ship was libeled, and were in
no way cut off by said libel.
3
4
5
6
Id. at 570−71 (emphasis added; footnotes in original but renumbered for consistency with this
7
8
9
Order). Although the Ninth Circuit found the district court‘s award of expectation damages overly
speculative, it held that the crew members were entitled to reliance damages, including ―a fair
allowance for their time and services in sailing the Silver Spray to Alaska and back‖ in preparation
10
for the aborted primary voyage (a tuna fishing expedition). Id. at 573. Because such damages
United States District Court
Northern District of California
11
were ―in the nature of seaman‘s wages,‖ they took priority over the mortgage. Id.
12
Putnam could be clearer as to whether the damages ultimately approved took the form of
13
maritime liens, but the Court understands the opinion to hold that they did. That case is therefore
14
controlling authority in this district that wrongful termination of a seaman‘s employment contract
15
can support a maritime lien.
16
D.
17
Spooner’s Complaint Fails to Establish That He Is Entitled to a Maritime Lien
for Wrongful Discharge
Having determined that wrongful discharge can create a maritime lien, the Court now turns
18
19
to whether Spooner‘s Complaint adequately states such a claim. Because the contract grants
20
Oracle Racing the right to terminate it ―for any reason whatsoever at any time,‖ the Court holds
21
that Spooner has failed to state a claim for wrongful termination, and thus has no maritime lien on
22
the Vessel.
23
1. The Contract is Subject to Judicial Notice
24
A threshold issue is whether the Court may take judicial notice of the contract, which was
25
submitted by Oracle Racing in response to the Court‘s request for briefing. The Court is aware of
26
no authority discussing when judicial notice is appropriate in determining whether a vessel arrest
27
28
7
―The Wanderer, C.C.La.1880, 20 F. 655; The Lakeport, D.C.W.D.N.Y.1926, 15 F.2d 575.‖
9
1
2
warrant should issue.
The federal Admiralty Rules state that absent exigent circumstances, a ―court must review
3
the complaint and any supporting papers‖ before directing the clerk to issue an arrest warrant.
4
Admiralty Rule C(3)(a)(i). It is well established in civil non-admiralty cases that even when a
5
court‘s review is otherwise limited the allegations of a complaint, the doctrine of incorporation by
6
reference permits the court ―to take into account documents whose contents are alleged in a
7
complaint and whose authenticity no party questions, but which are not physically attached to the
8
plaintiff‘s pleading.‖ Knievel v. ESPN, 393 F.3d 1068, 1076 (9th Cir. 2005) (internal quotation
9
marks, brackets, and citations omitted). At the time when the court decides whether a warrant
should issue, the record for a typical in rem admiralty case likely will not contain documents
11
United States District Court
Northern District of California
10
beyond what the plaintiff himself or herself has submitted. But in the rare case where additional
12
documents are filed—and perhaps rarer still, where a court can be satisfied that authenticity is not
13
contested—this Court finds no reason why the incorporation by reference doctrine should not
14
apply. Where such documents make clear that no maritime lien exists, turning a blind eye to them
15
would require a court to set in motion potentially significant efforts by the United States Marshall,
16
the parties, and the court system to effect a baseless arrest, a post-arrest hearing, and the inevitable
17
release of the vessel once the arrest is vacated.
18
Incorporation by reference is appropriate in this case. The contents of Spooner‘s contract
19
are alleged in, and indeed integral to, his Complaint. Spooner alleges that he ―entered into a
20
maritime services contract entitled ‗Heads of Terms for AC35—Sailing Team—Joseph Spooner.‘‖
21
Compl. ¶ 10. The Complaint recounts the commencement date of the contract, its term, and its
22
provisions regarding Spooner‘s compensation. Id. ¶¶ 10−12. The Complaint also quotes
23
provisions of the contract setting forth Spooner‘s duties as a member of Oracle Racing‘s sailing
24
team and the terms by which he would be reimbursed for expenses. Id. ¶¶ 10, 13.
25
The Court is further satisfied that Spooner does not contest the authenticity of the contract
26
submitted by Oracle Racing. After Oracle Racing filed its brief (which set forth its arguments
27
regarding the contract‘s terminability) and Grant Simmer‘s declaration (which included the
28
contract as an attachment), Spooner filed a declaration disputing a number of Simmer‘s assertions
10
1
but conspicuously silent as to the authenticity of the contract. See generally Spooner Decl.
2
Spooner‘s amended declaration, filed several days after Oracle Racing submitted the contract,
3
adds further evidence addressing when the boat was launched, but again does not dispute the
4
contract‘s authenticity. See generally Spooner Am. Decl. Although Spooner was not required to
5
file any response to Oracle Racing‘s brief, it is not plausible that, having felt it necessary to
6
dispute factual contentions regarding when the Vessel was launched, Spooner would withhold a
7
contention that Oracle Racing had submitted a false copy of the contract. Thus, because the
8
Complaint alleges the contents of the contract and no party disputes its authenticity, the Court
9
takes judicial notice of its terms as if it were incorporated into the Complaint.8
10
2. Viewed in Conjunction with the Contract, the Complaint Fails to State a
Claim for Wrongful Termination
11
United States District Court
Northern District of California
Taking into consideration the terms of the contract itself, the Court now considers whether
12
13
Spooner‘s Complaint states a claim for its breach—if there is no breach, then there is no maritime
lien, the ―conditions for an in rem action‖ would not ―appear to exist,‖ and it would thus be
14
improper for the Court to direct that a warrant should issue. See Admiralty Rule C(3)(a)(i).
15
16
17
18
The contract is between Oracle Racing, referenced therein as ―OTUSA‖ (an abbreviation
of Oracle Team USA), and Allegro Yachting Ltd. (the ―Company‖), ―to procure the services of
Joseph Spooner (the ‗Consultant‘) as a member of the Sailing Team of OTUSA for the 35th
America‘s Cup.‖9 Simmer Decl. Ex. A at 1. Spooner signed the contract on behalf of the
19
Company, id. at 6, and the Court assumes for the sake of argument that he has standing to bring
20
this action in his personal capacity.
21
The contract plainly grants both parties discretion to terminate the contract on two weeks‘
22
notice:
23
24
8
25
26
27
28
In the alternative, the Court construes the contract as among the ―supporting papers‖ to the
Complaint and thus subject to review before issuing a warrant. See Admiralty Rule C(3)(a)(i).
9
Although the contract anticipated its eventual ―substitution with a long-form employment
agreement,‖ that later agreement was to ―be based on the material terms agreed and included in
[the] Heads of Terms,‖ Simmer Decl. Ex. A ¶ 20, and the parties appear to agree that the contract
had not been replaced before its recent termination. See Compl. ¶ 10 (describing the operative
contract as the ―Heads of Terms for AC35—Sailing Team—Joseph Spooner‖ entered on or about
December 9, 2013).
11
Notice Period: Either OTUSA or the Company may terminate this
Heads of Terms for any reason whatsoever at any time by giving no
less than two (2) weeks‘ prior written notice of termination.
1
2
3
4
5
6
Simmer Decl. Ex. A ¶ 12 (emphasis added). Although Spooner‘s Complaint correctly describes
the contract as expiring seven days following the 35th America‘s Cup Finals, the Complaint
neglects to include the first clause of the contract‘s expiry date paragraph: ―Unless terminated
earlier in accordance with this Heads of Terms.‖ Id. ¶ 3. Thus, while the contract provides for
monthly compensation ―through the expiry date stated above,‖ id. ¶ 7(b), the definition of that date
7
specifically contemplates the possibility of early termination, id. ¶ 3.
8
Spooner alleges that ―on January 16, 2015‖ Oracle Racing ―breached its contractual
9
obligations to plaintiff by discharging plaintiff . . . by sending plaintiff a letter of discharge dated
10
January 16, 2015,‖ and failed to pay him after January 31, 2015. Compl. ¶¶ 14−15. The contract
11
United States District Court
Northern District of California
makes clear that either party had the right to terminate the contract in this manner, i.e., on two
12
13
14
weeks‘ written notice. Simmer Decl. Ex. A ¶ 12. Oracle Racing‘s termination of the contract was
therefore not a breach. With no breach, there is no basis for a maritime lien, and the ―conditions
for an in rem action‖ do not ―appear to exist.‖ See Admiralty Rule C(3)(a)(i). The Court
15
accordingly DECLINES to direct the clerk to issue a warrant to arrest the Vessel.
16
17
IV.
CONCLUSION
Although wrongful discharge in breach of a maritime contract can give rise to a maritime
18
lien in the Ninth Circuit, the record before the Court does not indicate that any such breach
19
occurred. The Court finds no basis for an in rem action apparent, and DECLINES to direct the
20
clerk to issue a warrant for the arrest of the vessel 4 Oracle Team USA. If Spooner is aware of
21
additional facts to show that a warrant should issue, he may file an amended complaint pursuant to
22
Rule 15(a) of the Federal Rules of Civil Procedure. Fed. R. Civ. P. 15(a); see also Admiralty Rule
23
A(2) (providing that the Federal Rules of Civil Procedure apply to admiralty proceedings except
24
///
25
///
26
///
27
///
28
12
1
2
3
4
5
6
7
where inconsistent with the Admiralty Rules).
This Order has no effect on Spooner‘s in personam claim against Oracle Racing, which is
not properly before the Court at this time.
IT IS SO ORDERED.
Dated: February 23, 2015
______________________________________
JOSEPH C. SPERO
Chief Magistrate Judge
8
9
10
United States District Court
Northern District of California
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
13
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?