ORDER re 16 MOTION for Default Judgment by the Court as to Defendant AC Square, Inc. filed by Xerox Corporation, Request for Supplemental Evidence. Signed by Magistrate Judge Donna M. Ryu on 03/30/2016. (dmrlc1, COURT STAFF) (Filed on 3/30/2016)
1
2
3
4
UNITED STATES DISTRICT COURT
5
NORTHERN DISTRICT OF CALIFORNIA
6
7
XEROX CORPORATION,
Case No. 15-cv-04816-DMR
Plaintiff,
8
v.
REQUEST FOR SUPPLEMENTAL
EVIDENCE
9
10
AC SQUARE, INC.,
Re: Dkt. No. 16
Defendant.
United States District Court
Northern District of California
11
12
In this breach of contract action, Plaintiff Xerox Corporation moves the court for entry of
13
default judgment against Defendant AC Square, Inc. pursuant to Federal Rule of Civil Procedure
14
55(b)(2). [Docket No. 16.] Plaintiff seeks actual damages, interest, the immediate return of its
15
property in Defendant’s possession or payment of its full market value, and attorneys’ fees and
16
costs. For the reasons stated below, the court orders Plaintiff to submit supplemental evidence in
17
support of its request for damages.
18
I.
BACKGROUND
From 2009 to 2014, the parties entered into seven product lease contracts for copier
19
20
equipment and one product maintenance contract. In connection with its Motion for Default
21
Judgment, Plaintiff submitted the eight written contracts, each of which indicates the length of the
22
agreement (in months) and the minimum monthly payments due. Declaration of Janet Atkinson
23
(“Atkinson Decl.”), Dec. 30, 2015, Exs. 1, 4, 7, 10, 12, 15, 18, 21 (Lease Agreements and
24
Maintenance Agreement). Plaintiff alleges that Defendant breached all contracts on April 18,
25
2015.
26
On October 19, 2015, Plaintiff filed this lawsuit seeking contract damages in the form of
27
the “principal sum” remaining under each of the eight contracts, an interest rate of 18% per year
28
(or 1.5% per month), recovery and possession of all leased property or its fair market value, and
1
attorneys’ fees and costs.
2
Plaintiff served Defendant with the summons and Complaint by substitute service on
3
November 13, 2015. [Docket No. 9 (Proof of Service).] Defendant did not file a responsive
4
pleading or otherwise appear. The Clerk entered Defendant’s default on December 28, 2015.
5
[Docket No. 13.] After Plaintiff filed its Motion for Default Judgment, the court ordered Plaintiff
6
to submit supplemental briefing, which Plaintiff timely filed. [Docket No. 18 (Suppl. Br.).] The
7
court determines that this matter is suitable for resolution without oral argument. See N.D. Cal.
8
Civ. L. R. 7-1(b).
9
10
II.
LEGAL STANDARDS
Federal Rule of Civil Procedure 55(b)(2) permits a court to enter a final judgment in a case
United States District Court
Northern District of California
11
following a defendant’s default. Shanghai Automation Instrument Co. v. Kuei, 194 F. Supp. 2d
12
995, 999 (N.D. Cal. 2001). Whether to enter a judgment lies within the court’s discretion.
13
Pepsico, Inc. v. Cal. Sec. Cans, 238 F. Supp. 2d 1172, 1174 (C.D. Cal. 2002) (citing Draper v.
14
Coombs, 792 F.2d 915, 924-25 (9th Cir. 1986)) (“A defendant’s default does not automatically
15
entitle the plaintiff to a court-ordered judgment.”)
16
Before assessing the merits of a default judgment, a court must ensure the adequacy of
17
service on the defendant, as well as confirm that it has subject matter jurisdiction over the case and
18
personal jurisdiction over the parties. See In re Tuli, 172 F.3d 707, 712 (9th Cir. 1999). If the
19
court finds these elements satisfied, it turns to the following factors (“the Eitel factors”) to
20
23
determine whether it should grant a default judgment:
(1) the possibility of prejudice to the plaintiff, (2) the merits of
plaintiff’s substantive claim, (3) the sufficiency of the complaint, (4)
the sum of money at stake in the action[,] (5) the possibility of a
dispute concerning material facts[,] (6) whether the default was due
to excusable neglect, and (7) the strong policy underlying the
Federal Rules of Civil Procedure favoring decision on the merits.
24
Eitel v. McCool, 782 F.2d 1470, 1471-72 (9th Cir. 1986) (citation omitted). In this analysis, “the
25
well-pleaded allegations of the complaint relating to a defendant’s liability are taken as true.”
26
Pepsico, Inc., 238 F. Supp. 2d at 1175 (citing Televideo Sys., Inc. v. Heidenthal, 826 F.2d 915,
27
917-18 (9th Cir. 1987)). Nevertheless, default does not compensate for essential facts not within
28
the pleadings and those legally insufficient to prove a claim. Cripps v. Life Ins. Co. of N. Am., 980
21
22
2
1
F.2d 1261, 1267 (9th Cir. 1992).
2
III.
ANALYSIS
3
A.
4
Plaintiff asserts the existence of federal diversity jurisdiction. Compl. ¶ 1. Plaintiff is
Jurisdiction
5
incorporated in the state of New York with a principal place of business in Connecticut.
6
Defendant is incorporated in California with a principal place of business in California. Compl.
7
¶¶ 3-4. Plaintiff alleges that the amount in controversy exceeds $75,000. Compl. ¶ 2. These
8
allegations establish a basis for diversity jurisdiction, as well as personal jurisdiction over
9
Defendant. Goodyear Dunlop Tires Ops., S.A., v. Brown, 131 S.Ct. 2846, 2853-54 (2011) (“the
paradigm forum for the exercise of general jurisdiction . . . for a corporation . . . [is] one in which
11
United States District Court
Northern District of California
10
the corporation is fairly regarded as at home”).
12
B.
13
Plaintiff served Defendant with the summons and Complaint by substitute service on
14
Adequacy of Service
Afshin Ghaneh, Defendant’s agent for service of process.
Under the Federal Rules of Civil Procedure, a domestic or foreign corporation must be
15
16
served in a judicial district of the United States, and may be served in the manner prescribed for
17
serving individuals under Rule 4(e)(1). Fed. R. Civ. P. 4(h)(1)(A). A defendant may be served by
18
“following state law for serving a summons in an action brought in courts of general jurisdiction
19
in the state where the district court is located or where service is made.” Fed. R. Civ. P. 4(e)(1).
20
In connection with its request for default judgment, Plaintiff asserts that service of the summons
21
and complaint on Defendant complied with California Code of Civil Procedure section 415.20(a),
22
which provides:
23
[i]n lieu of personal delivery of a copy of the summons and
complaint to the person to be served as specified in Section 416.10,
416.20, 416.30, 416.40, or 416.50,1 a summons may be served by
24
25
26
27
28
1
California Code of Civil Procedure sections 416.10, 416.20, 416.30, 416.40, and 416.50 set forth
permissible methods of serving corporations, joint stock companies or associations,
unincorporated associations, and public entities. Under section 416.10, a corporation may be
served by delivering a copy of the summons and complaint to “a person authorized by the
corporation to receive service of process.” Cal. Civ. Code § 416.10(b).
3
leaving a copy of the summons and complaint during usual office
hours in his or her office or, if no physical address is known, at his
or her usual mailing address, other than a United States Postal
Service post office box, with the person who is apparently in charge
thereof, and by thereafter mailing a copy of the summons and
complaint by first-class mail, postage prepaid to the person to be
served at the place where a copy of the summons and complaint
were left. When service is affected by leaving a copy of the
summons and complaint at a mailing address, it shall be left with a
person at least 18 years of age, who shall be informed of the
contents thereof. Service of a summons in this manner is deemed
complete on the 10th day after the mailing.
1
2
3
4
5
6
7
Cal. Civ. Proc. Code § 415.20(a).
Plaintiff submitted evidence that Afshin Ghaneh is Defendant’s agent for service of
9
process. Suppl. Br. at 1-2, Ex. 2. Plaintiff did not personally serve Ghaneh but left the summons
10
and complaint with Jane Doe, “a person at least 18 years of age apparently in charge at [Ghaneh’s]
11
United States District Court
Northern District of California
8
office or usual place of business,” who refused to give her name. Plaintiff also mailed Ghaneh a
12
copy of the documents the same day. [Docket No. 9] (Proof of Service). In light of these facts
13
and supporting documentation, the court finds that service of process in this case was adequately
14
effected.
15
C.
16
Turning to the first Eitel factor, Plaintiff will suffer prejudice if the court does not enter a
Application of the Eitel Factors
17
default judgment against Defendant because Plaintiff otherwise has no means to recover the
18
money and property at issue. Pepsico, Inc., 238 F. Supp. 2d at 1177. Therefore, the first factor
19
weighs in favor of granting Plaintiff’s motion.
20
Plaintiff also fulfills the second and third Eitel factors. For each of the eight contracts,
21
Plaintiff alleges claims for: (1) breach of contract, (2) account stated, and (3) claim and delivery.
22
A breach of contract claim under California law requires that a plaintiff show: (1) a contract; (2)
23
plaintiff’s performance or excuse for nonperformance; (3) the defendant’s breach; (4) and
24
resulting damage to plaintiff. Wall St. Network Ltd. v. N.Y. Times Co., 164 Cal. App. 4th 1171,
25
1178 (2008). Plaintiff demonstrates the existence of eight contracts, as well as performance on its
26
part. Plaintiff also alleges that Defendant breached all eight contracts on April 18, 2015. Finally,
27
Plaintiff alleges damages from Defendant’s breach in the form of property and money. Plaintiff
28
has sufficiently pled meritorious claims for breach of contract.
4
1
Account stated is a common count that is a “simplified form of pleading normally used to
2
aver the existence of various forms of monetary indebtedness.” McBride v. Boughton, 123 Cal.
3
App. 4th 379, 394 (2004). Account stated is not a specific cause of action but an alternative way
4
of seeking the same recovery demanded in a specific cause of action. Id. As discussed above,
5
Plaintiff has sufficiently pled breach of contract so account stated is sufficient as well.
Plaintiff also alleges claim and delivery for all products under each contract. Claim and
7
delivery is not a separate action but a remedy to return specific property and to award incidental
8
damages. Adler v. Taylor, No. 04-8472-RGK(FMOX), 2005 WL 4658511, at *3 (C.D. Cal. Feb.
9
2, 2005). In California, courts use claim and delivery which is identical to the federal remedy of
10
replevin. Id. An action for claim and delivery requires a plaintiff to show a right to possession
11
United States District Court
Northern District of California
6
and the defendant’s wrongful possession of the property at issue. Id; see Stalcup v. Liu, No. 11-
12
00002-JSW, 2011 WL 1753493, at *6 (N.D. Cal. April 22, 2011); Cal. Civ. Code § 3379; Cal.
13
Civ. Proc. Code § 512.010. Since Plaintiff adequately pled breach of contract, it has sufficiently
14
stated claim and delivery for all contracts concerning leased products. However, the contract
15
entitled “Maintenance Agreement” appears to govern repair services and “consumable supplies”
16
(such as ink). Atkinson Decl., Ex. 7. The complaint does not make clear what property is in
17
Defendant’s possession that may be subject to claim and delivery.
18
19
In sum, Plaintiff has submitted a legally sufficient and meritorious complaint except with
respect to claim and delivery based on the maintenance contract.
20
As to the fourth factor, “[w]hen the money at stake in the litigation is substantial or
21
unreasonable, default judgment is discouraged.” Bd. of Trs. v. Core Concrete Const., Inc., No. 11-
22
2532 LB, 2012 WL 380304, at *4 (N.D. Cal. Jan. 17, 2012) (citing Eitel, 782 F.2d at 1472).
23
However, when “the sum of money at stake is tailored to the specific misconduct of the defendant,
24
default judgment may be appropriate.” Id. (citations omitted). The sum of damages, interest,
25
attorneys’ fees, and costs that Plaintiff requests is $126,869.43 as of January 4, 2016. Mot. at 6.
26
Plaintiff also seeks return of its property in Defendant’s possession or fair market value of such
27
property. Plaintiff estimates the fair market value to be $44,716.00. Atkinson Decl. ¶ 138. As
28
discussed below, while the court finds deficiencies with respect to Plaintiff’s damage calculations,
5
1
the sum of money appears to be “tailored to the specific misconduct” of Defendant. Therefore, the
2
fourth factor weighs in favor of granting Plaintiff’s motion.
3
Under the fifth Eitel factor, the court assesses the likelihood of dispute between the parties
regarding the material facts of the case. Where a plaintiff has filed a well-pleaded complaint
5
alleging the elements necessary to establish its claims, and the Clerk has entered default upon
6
defendant’s failure to answer, a court may find the possibility of a dispute as to material facts is
7
unlikely. See Capitol Records v. Barrera, Case No. 06-07212-JSW, 2007 WL 1113949, at *3
8
(N.D. Cal. April 13, 2007); Elektra Entm't Group, Inc. v. Crawford, 226 F.R.D. 388, 393 (C.D.
9
Cal. 2005). Here, Defendant failed to appear and respond to the Complaint and the Clerk entered
10
default accordingly. Because Plaintiff’s well-pled allegations, except as to damages, are presumed
11
United States District Court
Northern District of California
4
to be true, TeleVideo, 826 F.2d at 917-18, it adequately alleged its claims against Defendant, as set
12
forth above. Plaintiff served Defendant with its motion for default judgment as well as its
13
supplemental briefing. [Docket Nos. 6, 9, 18 (Proofs of Service).] Nevertheless, Defendant did
14
not appear or file any opposition to Plaintiff’s motion. Accordingly, the record reflects
15
Defendant’s silence despite notice of the proceedings and several opportunities to respond.
16
Therefore, the court finds there is little possibility of a dispute of material facts.
17
Finally, under the sixth Eitel factor, nothing in the record suggests that Defendant
18
defaulted due to excusable neglect. As noted earlier, Plaintiff served Defendant with submissions
19
relating to the case throughout the pendency of this action and Defendant still failed to participate
20
in the litigation. The default of Defendant cannot be attributed to excusable neglect, so the sixth
21
factor weighs in favor of Plaintiff.
22
The final Eitel factor examines whether the policy of favoring a decision on the merits
23
precludes entry of default judgment. Eitel, 782 F.2d at 1472 (“[c]ases should be decided on their
24
merits whenever reasonably possible”). However, “the mere existence of Fed.R.Civ.P. 55(b)
25
indicates that this preference, standing alone, is not dispositive.” PepsiCo, 238 F. Supp. 2d at
26
1177 (internal quotation and citation omitted). Because Defendant failed to defend against this
27
action, a decision on the merits would be “impracticable, if not impossible.” Truong, 2007 WL
28
1545173, at *13 (citation omitted). Therefore, the court finds this factor, though it weighs against
6
1
default judgment, does not preclude granting it. See Kloepping v. Fireman's Fund, No. C 94-2684
2
TEH, 1996 WL 75314, at *3 (N.D. Cal. Feb. 13, 1996).
3
In sum, the Eitel factors weigh in favor of granting Plaintiff’s motion for default judgment.
4
D.
5
Although the factual contentions of the operative complaint are accepted as true when
Remedies
6
determining the liability of a defaulting defendant, this rule does not apply to statements regarding
7
damages. See TeleVideo, 826 F.2d at 917-18. To recover damages after securing a default
8
judgment, a plaintiff must prove the relief it seeks through testimony or written affidavit. Bd. of
9
Trs. of the Boilermaker Vacation Trust v. Skelly, Inc., 389 F. Supp. 2d 1222, 1226 (N.D. Cal.
2005); see PepsiCo, Inc., 238 F. Supp. 2d at 1175 (citing Televideo Sys., Inc., 826 F.2d at 917-18).
11
United States District Court
Northern District of California
10
Plaintiff moves for default judgment on all three of its claims for relief: breach of contract,
12
account stated, and claim and delivery. Plaintiff submitted the Declaration of Janet Atkinson in
13
support of its prayer for relief. [Docket No. 16-1.] As explained below, it is unclear whether the
14
evidence in the record supports Plaintiff’s damage calculations and request for relief.
15
Accordingly, although the Eitel factors weigh in favor of granting default judgment, the court
16
orders Plaintiff to submit supplemental evidence to support and clarify its request for damages.
17
1.
Contract Damages
18
Plaintiff failed to submit sufficient proof or explanation in support of its contract damage
19
calculations. There are discrepancies between Plaintiff’s pleadings and the actual contract terms.
20
Plaintiff has not provided enough support for the court to conduct a proper assessment to
21
determine whether Plaintiff is entitled to the damages it seeks.
22
For example, Plaintiff’s first claim for relief regarding the contract in Exhibit 1 to the
23
Atkinson Declaration states that “Pursuant to the terms of the Agreement, Plaintiff has elected to
24
accelerate the balance of the Agreement. The balance of the rental payments under the Agreement
25
is $39,115.75. Additionally, pursuant to the agreement, Defendant is liable for interest on all sums
26
due from the date of default at 1.5% per month”. Compl. ¶¶ 10-11. However, the “default and
27
remedies” provision of the contract itself states, in relevant part, that in the event of default,
28
“Xerox may. . . remove equipment at your expense and require immediate payment. . . of (a) all
7
1
amounts then due, plus interest from the due date until paid at a rate of 1.5% per month [and] (b)
2
minimum payments remaining in the term, discounted at 4% per annum. . .” Atkinson Decl., Ex.
3
1 (at ECF p. 8, § 19).
4
Plaintiff’s Complaint and submissions fail to track the terms set forth in the contract. For
5
this reason, the court is unable to determine the relationship between its request for the “balance of
6
rental payments under the Agreement” in the sum of $39,115.75 alleged in its Complaint, and “all
7
amounts then due” and “minimum payments remaining in the term, discounted at 4% per annum,”
8
as specified in the contract term.
Additionally, Plaintiff alleges that it is entitled to the 1.5% interest rate for the entire
10
“principal sum.” Mot. at 4-6. This appears inconsistent with the contract provision outlining a 4%
11
United States District Court
Northern District of California
9
discount on remaining minimum payments in the event of default. Based on the conclusory nature
12
of Plaintiff’s calculations, the court cannot determine if Plaintiff applied the 4% discount to the
13
amount requested, or if Plaintiff has reason to not apply the discounted interest rate provision.
14
Similar problems exist for all other product contracts.
15
In addition, Plaintiff’s seventh claim relates to breach of a maintenance contract. Compl.
16
¶¶ 43-51. Plaintiff requests the “principal sum” of the contract, which allegedly equals
17
“$2,182.75” plus 1.5% interest per month to total “$2,463.70.” Mot. at 4. However, the contract
18
“default and remedies” provision states that Plaintiff may only recover “(a) all amounts then due,
19
plus interest from the date due date until paid at the rate of 1.5% per month [and] (b) the remaining
20
Minimum Payments, not to exceed 6 such payments if this Agreement is for a one-year Term and
21
12 such payments for a multi-year Term. . . ” Atkinson Decl., Ex. 7 (at ECF p. 8, § 13). The
22
contract “called for monthly payments in the amount of $11.00, plus print charges,” (Compl. ¶
23
45), which does not appear to bear any relation to Plaintiff’s calculation of its loss. Again,
24
Plaintiff’s conclusory calculations do not provide sufficient evidence that it is entitled to the
25
amount it requests.
26
As a final example, Plaintiff alleges that Defendant breached all eight contracts on April
27
18, 2015. The contract provisions state that “any partial months in the Term will be billed on a
28
pro rata basis.” See, e.g. Atkinson Decl., Ex. 1 (at ECF p. 8 §12). Again, Plaintiff’s conclusory
8
1
calculations do not indicate if it applied this pro rata calculation, or whether Plaintiff had reason to
2
disregard this rate.
3
In sum, Plaintiff fails to provide sufficient evidence and explanation for the court to
4
determine if its calculations are proper. Plaintiff must submit additional evidence and explain its
5
calculations for each breach of contract claim.
6
7
2.
Account Stated
Account stated is not a standalone cause of action but an alternate way of seeking the same
recovery demanded in a specific cause of action. Thus, Plaintiff’s prayer for relief for each
9
account stated claim is identical to its prayer for relief for each breach of contract claim. The
10
same deficiencies identified with Plaintiff’s contract damage claims apply to these requests for
11
United States District Court
Northern District of California
8
relief under the account stated claims.
12
13
3.
Claim and Delivery of Personal Property
Plaintiff requests claim and delivery for property leased under each of the eight contracts
14
or “its market value in case delivery cannot be had, or any deficiency due to sale after
15
repossession.” Mot. at 4. Plaintiff claims that $44,716.00 is the total fair market value of the
16
property. See Atkinson Decl. ¶ 138. The only basis for the fair market valuation is Atkinson’s
17
declaration that she is “required to know the market price for used equipment and to keep in
18
constant contact with equipment re-marketers.” She states that she is “informed and believe[s]
19
and thereon alleges” that the lump sum fair market value of the equipment at issue is $44,716.00.
20
Atkinson Decl. ¶ 138. This is a conclusory statement of the value of Plaintiff’s property. It does
21
not provide the basis for her knowledge, nor does it provide the fair market value for each product,
22
and how it was derived.
23
Additionally, the contract for claim nine is titled “Maintenance Agreement” and appears to
24
govern repair services and “consumable supplies,” such as ink. Atkinson Decl., Ex. 7 (at ECF p.
25
6). Plaintiff did not indicate what tangible property exists under the Maintenance Agreement to
26
support this form of relief.
27
28
These flaws may well be curable. Plaintiff may submit additional evidence to support its
claim for relief.
9
IV.
1
CONCLUSION
For the foregoing reasons, the court concludes that the first six Eitel factors outweigh the
2
Federal Rules of Civil Procedure’s strong preference for a decision on the merits. However,
3
Plaintiff did not submit sufficient evidence to establish its entitlement to the relief sought.
4
Accordingly, Plaintiff shall submit additional evidence and briefing within thirty days of this
5
order. Plaintiff shall immediately serve this Order on Defendant, and shall also serve the
6
additional evidence and briefing at the time of filing. Plaintiff is ordered to file proofs of service.
7
8
S
ED
RT
13
ER
15
16
17
18
19
20
21
22
23
24
25
26
27
28
10
A
H
14
FO
. Ryu
onna M
Judge D
LI
12
R NIA
RDER
______________________________________
IS SO O
IT
Donna M. Ryu
United States Magistrate Judge
NO
United States District Court
Northern District of California
11
UNIT
ED
Dated: March 30, 2016
10
RT
U
O
IT IS SO ORDERED.
9
S DISTRICT
TE
C
TA
N
F
D IS T IC T O
R
C
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.