SCHEDULING ORDER RE CLAIM CONSTRUCTION. Signed by Judge Jeremy Fogel on 6/17/2010. (jflc3, COURT STAFF) (Filed on 6/17/2010)
1 2 3 4 5 6 7
**E-Filed 6/17/10**
IN THE UNITED STATES DISTRICT COURT 8 FOR THE NORTHERN DISTRICT OF CALIFORNIA 9 SAN JOSE DIVISION 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1
UPEK, INC., a Delaware corporation, Plaintiff, v. AUTHENTEC, INC., a Delaware corporation, Defendant. AUTHENTEC, INC., a Delaware corporation, Counterclaimant, v. UPEK, INC., a Delaware Corporation, Counterdefendant.
Case No. 10-424-JF (PVT) SCHEDULING ORDER1 RE CLAIM CONSTRUCTION
At a case management conference on May 28, 2010, the Court scheduled a claim construction hearing for October 28, 2010. The parties have been unable to reach agreement on a schedule leading up to the claim construction hearing. AuthenTec has submitted a proposed schedule; UPEK has neither responded nor submitted an alternative proposal. Having considered
This disposition is not designated for publication and may not be cited.
C a se No. C-10-424 JF (PVT) O R D E R (1) GRANTING AUTHENTEC'S ADMINISTRATIVE MOTIONS TO SEAL, ETC. ( JF E X 1 )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
AuthenTec's proposed schedule, and good cause therefor appearing, the Court will enter a scheduling order as set forth below. Discovery is to proceed with respect to claim construction issues only. Event Initial Case Management Conference Rule 26 Initial Disclosures Deadline for modified Patent L.R. 3-1 and 3-2 disclosures Deadline Friday, May 28, 2010, 10:30 a.m. Friday, June 11, 2010 Tuesday, June 22, 2010 1. 2. Identify which claims are asserted against which products; Create one chart for one asserted independent claim against one product; Identify the claimed priority and invention dates for the asserted patent; and Produce the documents required by Patent L.R. 3-2 concurrently with the infringement disclosures
3.
4.
Deadline for modified Patent L.R. 3-3 and 3-4 disclosures
Tuesday, July 20, 2010 1. Identify which prior art the party asserts against which claims and the basis for the assertion; Chart one dependent claim for each reference or combination thereof; and Produce the documents required by Patent L.R. 3-4 concurrently with the invalidity disclosures
2. 3.
Exchange of proposed claim terms for construction pursuant to Patent L.R. 4-1 Exchange of preliminary claim construction and extrinsic evidence pursuant to Patent L.R. 4-2 Joint claim construction and prehearing statement pursuant to Patent L.R. 4-3 Close of claim construction discovery pursuant to Patent L.R. 4-4
Tuesday, August 3, 2010 Tuesday, August 10, 2010
Tuesday, August 24, 2010 Wednesday, September 8, 2010
2
C a se No. C-10-424 JF (PVT) O R D E R (1) GRANTING AUTHENTEC'S ADMINISTRATIVE MOTIONS TO SEAL, ETC. ( JF E X 1 )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Opening claim construction briefs pursuant to Patent L.R. 4-5(a) Responsive claim construction briefs pursuant to Patent L.R. 4-5(b) Reply claim construction briefs pursuant to Patent L.R. 4-5(c) Case tutorial Claim construction hearing pursuant to Patent L.R. 4-6 Further case management conference IT IS SO ORDERED. DATED: 6/17/10
Thursday, September 23, 2010 Thursday, October 7, 2010 Thursday, October 14, 2010 October 28, 2010, 10:00 a.m. October 28, 2010, 10:00 a.m. October 28, 2010, 10:00 a.m.
____________________________ JEREMY FOGEL United States District Judge
3
C a se No. C-10-424 JF (PVT) O R D E R (1) GRANTING AUTHENTEC'S ADMINISTRATIVE MOTIONS TO SEAL, ETC. ( JF E X 1 )