ORDER Granting Modification of Case Management Dates re 144 Stipulation. Close of Claim Construction Discovery due by 3/19/2012. Interim Case Management Statement due by 4/10/2012. Interim Case Management Conference set for 4/20/2012 10:00 AM in C ourtroom 1, 5th Floor, San Jose. Tutorial and Claim Construction Hearing set for 5/30/2012 in Courtroom 1, 5th Floor, San Jose. B&N agrees to withdraw its pending motion to stay (Docket No. 143) without prejudice and may re-notice and re-file such motion at its discretion. The Clerk shall terminate Docket Item No. 143. Motions terminated: 143 MOTION to Stay filed by Barnesandnoble.com, LLC. Signed by Judge Edward J. Davila on 11/1/2011. (ecg, COURT STAFF) (Filed on 11/1/2011)
8
9
10
S
Krista M. Carter (State Bar No. 225229)
carterk@dicksteinshapiro.com
DICKSTEIN SHAPIRO LLP
700 Hansen Way
Palo Alto, CA 94304
Telephone: (650) 632-4208
Facsimile: (650) 632-4533
ER
a rd J . D
R NIA
dw
J u d ge E
H
7
RT
6
Attorneys for Plaintiff
OLYMPIC DEVELOPMENTS AG, LLC
NO
5
avila
FO
4
DERED
SO OR
IT IS
DIFIED
AS MO
A
3
S DISTRICT
TE
C
TA
RT
U
O
2
Steven Ritcheson, Esq. (SBN 174062)
WHITE FIELD, INC.
9800 D Topanga Canyon Blvd., #347
Chatsworth, CA 91311
Telephone: (818) 882-1030
Facsimile: (818) 337-0383
UNIT
ED
1
Filed10/31/11 Page1 of 4
LI
Case5:11-cv-01655-EJD Document144
N
F
D IS T IC T O
R
C
Attorneys for Defendant
BARNESANDNOBLE.COM LLC.
11
12
13
UNITED STATES DISTRICT COURT
14
FOR THE NORTHERN DISTRICT OF CALIFORNIA
15
SAN JOSE DIVISION
16
17
OLYMPIC DEVELOPMENTS AG, LLC,
18
19
20
21
Plaintiff,
v.
Case No. C 11-01655 EJD
Honorable Judge Edward J. Davila
STIPULATION FOR MODIFICATION OF
CASE MANAGEMENT DATES
BARNESANDNOBLE.COM, LLC,
Defendant.
22
23
24
25
26
27
28
1
STIPULATION FOR MODIFICATION OF CASE MANAGEMENT DATES
Case No. C 11-01655 EJD
Case5:11-cv-01655-EJD Document144
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Filed10/31/11 Page2 of 4
WHEREAS, by Order dated September 13, 2011 (Docket No. 141), the Court has ordered the
parties to comply with certain case management dates, including: Infringement Contentions
(September 30, 201); Invalidity Contentions (November 14, 2011); Joint Claim Construction and
Prehearing Statement (January 13, 2012); Close of Claim Construction Discovery (February 13,
2012); Joint Case Management Statement for Interim Conference (March 6, 2012); Interim Case
Management Conference (March 16, 2012); Last Day to Complete ADR Session (March 22, 2012);
Case Tutorial (April 10, 2012); and Claim Construction Hearing (April 10, 2012) (collectively, the
“Case Management Dates”).
WHEREAS, Plaintiff Olympic Developments AG, LLC (“Olympic”) and Defendant
barnesandnoble.com, llc (“B&N”), are engaged in settlement discussions; and
WHEREAS, (a) B&N filed a motion to stay the above entitled action on October 17, 2011
(Docket No. 143), and (b) it appears from the Court’s website that Plaintiff’s counsel was
inadvertently removed from the Court’s email service list and Plaintiff did not receive notice of
B&N’s motion; and
WHEREAS, the parties wish to continue their settlement discussions and resolve the issues
surrounding notice of B&N’s motion;
The Parties, by and through their respective counsel, subject to the Court’s approval, stipulate
as follows:
1.
The Case Management Dates shall be reset as follows:
a. Infringement Contentions (COMPLETED);
b. Invalidity Contentions: from November 14, 2011 to December 20, 2011;
c. Joint Claim Construction and Prehearing Statement: from January 13, 2012 to
February 17, 2012;
d. Close of Claim Construction Discovery: from February 13, 2012 to March 19,
2012;
e. Joint Case Management Statement for Interim Conference: from March 6, 2012 to
April 10, 2012;
28
2
STIPULATION FOR MODIFICATION OF CASE MANAGEMENT DATES
Case No. C 11-01655 EJD
Case5:11-cv-01655-EJD Document144
1
f. Interim Case Management Conference: from March 16, 2012 to April 20, 2012;
2
g. Last Day to Complete ADR Session: from March 22, 2012 to April 26, 2012;
3
30, 2012 at 9:00 a.m.
h. Case Tutorial: from April 10, 2012 to May 15, 2012 at 9:00 a.m.; and
4
i. Claim Construction Hearing: from April 10, 2012 to May 15, 2012 following
30, 2012 following
5
6
7
8
9
Filed10/31/11 Page3 of 4
Tutorial.
2.
B&N agrees to withdraw its pending motion to stay (Docket No. 143) without
prejudice and may re-notice and re-file such motion at its discretion. The Clerk shall
terminate Docket
Item No. 143.
SO STIPULATED.
Dated: October 31, 2011.
10
Respectfully submitted,
WHITE FIELD, INC.
11
12
By:
/s/ Steven W. Ritcheson
Steven W. Ritcheson
Attorneys for Plaintiff OLYMPIC DEVELOPMENTS
AG, LLC
13
14
15
16
Dated: October 31, 2011.
Respectfully submitted,
DICKSTEIN SHAPIRO LLP
17
18
19
By:
/s/ Krista M. Carter
Krista M. Carter
Attorney for Defendant BARNESANDNOBLE.COM
LLC
20
21
22
23
24
25
26
27
28
3
STIPULATION FOR MODIFICATION OF CASE MANAGEMENT DATES
Case No. C 11-01655 EJD
Case5:11-cv-01655-EJD Document144
1
2
3
Filed10/31/11 Page4 of 4
SIGNATURE ATTESTATION
Pursuant to General Order 45.X(B), I hereby attest that concurrence has been obtained from
the above-named counsel indicated by a “conformed” signature (/s/) within this e-filed document.
4
/s/ Steven W. Ritcheson
Steven W. Ritcheson
5
6
7
PURSUANT TO STIPULATION, IT IS SO ORDERED.
8
9
10
DATED:
November 1, 2011
HONORABLE EDWARD J. DAVILA
United States District Court Judge
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
4
STIPULATION FOR MODIFICATION OF CASE MANAGEMENT DATES
Case No. C 11-01655 EJD
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?