CASE MANAGEMENT ORDER. Signed by Judge Paul S. Grewal on March 13, 2012. (psglc1, COURT STAFF) (Filed on 3/13/2012)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
NORTHERN DISTRICT OF CALIFORNIA
10
SAN JOSE DIVISION
11
12
13
14
15
16
DYNETIX DESIGN SOLUTIONS, INC., )
)
Plaintiff,
)
)
v.
)
)
SYNOPSYS, INC.,
)
)
Defendant.
)
___________________________________ )
Case No.: C 11-05973 PSG
CASE MANAGEMENT ORDER
17
18
On March 6, 2012, the parties appeared before Magistrate Judge Paul S. Grewal for a case
19
management conference. Based on the parties’ Joint Case Management Statement and the
20
discussions held at the case management conference,
21
22
23
IT IS HEREBY ORDERED that the deadline for joinder of any additional parties, or other
amendments to the pleadings, is sixty days after the date of the claim construction order.
IT IS FURTHER ORDERED that the presumptive limits on discovery set forth in the
24
Federal Rules of Civil Procedure apply with one exception: Each party may serve no more than 50
25
requests for admission related to substantive issues.
26
27
28
IT IS FURTHER ORDERED that the parties shall meet and confer regarding the form of
production of electronically stored information.
IT IS FURTHER ORDERED that the parties shall participate in private mediation no later
Case No.: 11-5973 PSG
CASE MANAGEMENT ORDER
1
than 30 days after the claim construction hearing.
2
IT IS FURTHER ORDERED that the following schedule shall apply to this case:
3
Last Day for Plaintiff’s Disclosure of Asserted Claims and Infringement Contentions (Patent
L.R. 3-1) and Related Documents (Patent L.R. 3-2) . . . . . . . . . . . . . . . . . . . . .March 20, 2012
4
5
Last Day for Defendant’s Invalidity Contentions (Patent L.R. 3-3) and Related Document
Production (Patent L.R. 3-4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . May 4, 2012
6
Last Day for the Exchange of Proposed Terms and Claim Elements for Construction (Patent
L.R. 4-1(a)) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .May 18, 2012
7
8
Last Day for the Exchange of Preliminary Proposed Claim Construction and Extrinsic
Evidence (Patent L.R. 4-2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .June 8, 2012
9
File Joint Claim Construction Statement (Patent L.R. 4-3)– limited to 10 terms unless leave
of court granted . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .July 3, 2012
10
Completion of Claim Construction Discovery (Patent L.R. 4-4) . . . . . . . . . . . .August 2, 2012
11
Last Day for Plaintiff’s Opening Claim Construction Brief (Patent L.R. 4-5(a))Aug. 17, 2012
12
13
Last Day for Defendant’s Opposing Claim Construction Brief
(Patent L.R. 4-5(b)). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Aug. 31, 2012
14
Last Day for Plaintiff’s Reply Claim Construction Brief (Patent L.R. 4-5()) . . . .Sept. 7, 2012
15
Tutorial and Claims Construction Hearing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sept. 12, 2012
16
Further Joint Case Management Report . . . . . . . . within 30 days of claim construction ruling
17
Advice of Counsel Disclosure . . . . . . . . . . . . . . . . . . . 50 days after claim construction ruling
18
Fact Discovery Cutoff . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . April 19, 2013
19
Designation of Opening Experts with Reports . . . . . . . . . . . . . . . . . . . . . . . . . . May 3, 2013
20
Designation of Rebuttal Experts with Reports . . . . . . . . . . . . . . . . . . . . . . . . . May 17, 2013
21
Expert Discovery Cutoff . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . May 31, 2013
22
Deadline(s) for Filing Discovery Motions . . . . . . . . . . . . . . . . . . . . See Civil Local Rule 37-3
23
Last Day for Dispositive Motion Hearing1 . . . . . . . . . . . . . . . . . 10:00 a.m. on July 30, 2013
24
Final Pretrial Conference.............................................................2:00 p.m. on August 27, 2013
25
Trial . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9:30 a.m. on Sept. 16, 2013
26
IT IS FURTHER ORDERED that the parties shall comply with the Standing Order for Civil
27
1
28
This is the last date for hearing dispositive motions. Any such motions must be noticed
in compliance with Civil Local Rule 7-2(a).
Case No.: 11-5973 PSG
CASE MANAGEMENT ORDER
1
Practice in Cases Assigned for All Purposes to Magistrate Judge Paul S. Grewal (Dec. 2010), a copy
2
of which is available from the Clerk of the Court,2 with regard to the timing and content of the Joint
3
Pretrial Statement, and all other pretrial submissions.
4
Dated: 3/13/2012
5
PAUL S. GREWAL
United States Magistrate Judge
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
2
27
28
A copy of Judge Grewal's standing order is also available on the court's website at
www.cand.uscourts.gov by clicking first on the "Judges" button, then on Judge Grewal's name, then on
the link for "Magistrate Judge Grewal's Standing Orders," and finally on the link for "Judge Grewal's
Civil Standing Order."
Case No.: 11-5973 PSG
CASE MANAGEMENT ORDER
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Case No.: 11-5973 PSG
CASE MANAGEMENT ORDER
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?