United States of America for the use of San Benito Supply v. KISAQ-RQ 8A 2 JV et al
Filing
101
MEMORANDUM OF DECISION, FINDINGS OF FACT AND CONCLUSIONS OF LAW. Signed by Magistrate Judge Howard R. Lloyd on 1/28/2015. (hrllc1, COURT STAFF) (Filed on 1/28/2015)
1
*E-Filed: January 28, 2015*
2
3
4
5
6
IN THE UNITED STATES DISTRICT COURT
9
FOR THE NORTHERN DISTRICT OF CALIFORNIA
10
For the Northern District of California
NOT FOR CITATION
8
United States District Court
7
SAN JOSE DIVISION
11
UNITED STATES OF AMERICA FOR
THE USE OF SAN BENITO SUPPLY,
12
MEMORANDUM OF DECISION,
FINDINGS OF FACT AND
CONCLUSIONS OF LAW
Plaintiff,
v.
13
No. C13-00469 HRL
14
KISAQ-RQ 8A 2 JV; et al.,
15
Defendants.
____________________________________/
16
MEMORANDUM OF DECISION
17
A.
18
INTRODUCTION
This case was tried to the court for nine days between November 17 and December 2, 2014.
19
Many witnesses were called and hundreds of exhibits admitted. At the conclusion of their
20
21
presentations, counsel argued, and the matter was taken under submission. The court now issues its
Memorandum of Decision (Memorandum), Findings of Fact (Findings), and Conclusions of Law
22
(Conclusions). 1
23
24
///
///
25
1
26
27
28
The Memorandum fleshes out and gives context to the Findings and includes some explanation of
why the court made the Findings that it did. No attempt has been made to describe all the evidence
or every issue the parties raised, or to name all the witnesses and give the substance of their
testimony. Likewise, the court has not mentioned all the evidence that supports its Findings and
Conclusions. Finally, the court tried to avoid commingling Findings with Conclusions. However, if
any Conclusion has been inadvertently labeled as a Finding (or vice versa), it should be considered
in its true light regardless of the label on it.
This is a Miller Act case. San Benito Supply (“SBS”), 2 a concrete ready-mix supplier, was a
3
sub-subcontractor on a government construction project at Fort Hunter Liggett in southern Monterey
4
County. It sues to recover about $300,000 it claims it is owed for concrete supplied for the project.
5
Defendants are the project’s general contractor/designer KISAQ-RZ 8A 2 JV (“KISAQ”), its
6
concrete subcontractor Frazier Masonry Company (“Frazier”), and two surety companies: Federal
7
Insurance Company (“Federal”) and Western Surety Company (“Western”). The dispute is between
8
SBS and Frazier. The other defendants are named in case a judgment in favor of SBS needs to be
9
For the Northern District of California
B.
2
United States District Court
1
STATEMENT OF THE CASE
paid.
Frazier does not dispute that there are unpaid SBS invoices, but argues that SBS supplied
10
11
nonconforming ready-mix concrete that ultimately had to be torn out by Frazier and replaced at
12
substantial expense. It counterclaims against SBS for about $300,000, and argues that any monies it
13
lawfully owes to SBS (excluding, of course, the price for the nonconforming concrete) should be set
14
off against Frazier’s damage recovery.
In late 2009 the U.S. Army Corps of Engineers (“ACOE”) entered into a contract with
15
16
KISAQ for it to design and build a Tactical Equipment Maintenance Facility (“TMEF”) at Fort
17
Hunter Liggett. This was to be a rectangular, one story structure with tilt up concrete walls, a
18
concrete slab floor, and several large doors so that military vehicles could be brought inside for
19
maintenance and repairs. Because some of the vehicles were extremely heavy, a section of the floor
20
slab was specified to be heavy duty 6000 psi concrete (meaning the concrete had to have a
21
compressive strength of 6000 pounds per square inch so that it would not fail under extra heavy
22
loads). Exh. 50.7, 50.8. This case is about 6000 psi concrete.
KISAQ awarded the subcontract for the masonry work on the TEMF project to Frazier.
23
24
Thereupon, Frazier invited proposals from prospective suppliers of ready-mix concrete. This would
25
be a big job, and SBS was very interested in obtaining it. Preliminary discussions between Charles
26
2
27
28
Because of a peculiarity in the Miller Act, the plaintiff in a claim arising over a government
construction contract must nominally bring suit in the name of the United States (hence the name in
the case caption: “United States of America, For the Use of San Benito Supply...”). For
convenience, the Court will simply refer to the plaintiff as SBS.
2
1
Benford (“Benford”), Frazier’s Project Manager, and Teddy Schipper Jr. (“Teddy”), 3 SBS’s Mine
2
Manager and one of its managing officers, began in the late fall of 2011. Teddy was SBS’s mix
3
designer.
4
Ready-mix concrete is a blend of aggregates, sand, cement, additives (sometimes), and
5
water. The TEMF project called for 3000, 4000, and 6000 psi concrete. Each would require a
6
different mix design. A mix design is the recipe for creating concrete of a particular strength with
7
certain specified properties.
The ACOE’s specifications for the TEMF project did not spell out any mix designs. Rather,
8
For the Northern District of California
United States District Court
9
they called out the ultimate strength required, noted some limitations (e.g. no more than a certain
10
percentage of fly ash), some specific requirements (e.g. add steel fibers), and several permissible
11
ranges of variations in the concrete’s properties (e.g. design air volume, water/cementitious ratio,
12
etc.).
There are so many variables in mix design that no one can look at an unproven design, for
13
14
6000 psi concrete for example, and say for sure that—when put to the test—it will actually result in
15
concrete with a compressive strength of 6000 psi. The “Standard Specifications for Structural
16
Concrete” promulgated by Committee 301 of the American Concrete Institute (“ACI 301”) is
17
viewed by the concrete industry as the “bible” for qualifying concrete mix designs. That is, in a
18
situation such as the present, will the mix design achieve the strength result you need? Under ACI
19
301 there are two ways to qualify a mix design. One: someone comes up with his best judgment for
20
a design for the desired concrete strength, and mixes up trial batches (each with slight differences in
21
air/water volume). Then, using the detailed ACI 301 protocol, cure the samples the required number
22
of days and test each for compressive strength. Finally, evaluate the resulting data by a complex
23
mathematical formula to see if the mix qualifies. Alternatively: if one has actually used the mix (or,
24
one virtually like it) in the field for a number of jobs over a certain period of time and has historic
25
26
27
28
3
The court intends no disrespect in referring to Mr. Schipper Jr. as Teddy. The extended Schipper
family operates and apparently owns SBS. Since Teddy, Ted, Ben, and Mark Schipper each
testified at trial, it seems expedient to refer to any of them here by their first name.
3
1
field test data on compressive strength from those jobs, then tally and analyze that data per the step
2
by step procedure in ACI 301 to see if the mix qualifies.
3
On December 21, 2011, Teddy sent Benford preliminary mix designs, including one for the
4
6000 psi concrete. Exh. 6.7. They went to KISAQ and then to the project structural engineer, who
5
gave them preliminary approval. Exh. 56.3. At this point, SBS had not submitted any back up data
6
on compressive strength.
7
Then, on December 28, 2011, Teddy e-mailed Benford compression data on the 3000, 4000,
For the Northern District of California
and 6000 mixes. Exh. 55.1. The data pdfs were labeled “mix... history.” The history for the 6000
9
United States District Court
8
psi mix showed 21 individual test results after 28 days of curing that were well in excess of 6000
10
psi. Exh. 55.6-7. The word “history” meant that this was historical data from past jobs and not data
11
from batch testing.
12
On February 8, 2012, SBS sent Frazier a form “Proposal” quoting its prices for the concrete
13
and other material Frazier needed for the TEMF project. Then, SBS and Frazier met on March 30,
14
2012 at Frazier’s office to hash out pricing. Benford wanted lower prices, and he and Ted Schipper
15
(“Ted”) haggled back and forth using the Proposal as a worksheet. They ultimately agreed on prices
16
that were then circled and initialed on the worksheet and both signed. Exh. 152. That same day
17
Frazier sent SBS a letter stating that it intended to enter into a purchase order with SBS for the
18
concrete on the TEMF project. Exh. 525. On April 6, SBS prepared a “clean” copy of the Proposal
19
with the agreed upon pricing. Exh. 512.4. Several months later, on July 30, Frazier did issue the
20
Purchase Order. Exh. 516.1.
21
In the intervening time between April 6 and July 30, the mix designs went up the line
22
through an approval process, which ultimately put them on the desk of Karl Mai, the ACOE
23
materials engineer. And, during this process Mai directed some slight changes in the specifications.
24
Originally, they called for steel fibers to be added to the mix. Then, synthetic fibers were
25
substituted. Finally, back to steel fibers. The fly ash content, originally at zero percent, went to
26
10%. The second submission of mix designs went from KISAQ to Mai on May 25, 2012. Mai’s
27
only comments upon reviewing them was to increase fly ash above the current 10%. Exh. 25.1-2,
28
.38-39. SBS changed each mix to 15% fly ash, and all revised mix designs that KISAQ had were
4
1
resubmitted on July 6 and approved. Exh. 524. The revised 6000 psi mix design, which had been
2
approved by the structural engineer along with the others, came to KISAQ after the others had been
3
submitted to Mai and was never forwarded to Mai, who never noticed it was missing. Exhs. 11.2,
4
710.1, 30.1-2. The word came down from the ACOE to pour the concrete for the slab.
5
Beginning about 3:00 a.m. on August 24, 2012 and continuing until about noon that day,
personnel placed the concrete and began the multi-step process of “finishing” it. During this same
8
time period SBS also delivered 254 cubic yards of the 6000 psi mix but without steel fibers. These
9
For the Northern District of California
SBS trucks delivered 280 cubic yards (28 truckloads) of the 6000 psi concrete mix. Frazier
7
United States District Court
6
254 yards were placed by Frazier on the area of the slab that was specified for 4000 psi concrete.
10
(There was no need there for the extra strength provided by steel fibers.) Frazier figured it was
11
more convenient to buy the 6000 psi concrete (without fibers) than at some other time to place 4000
12
psi concrete adjoining the 6000 and have to fuss with the “joint” between the two.
13
While the pouring was going on, SBS took samples of the wet cement coming from some of
14
the trucks. (This is typical practice. The samples are called “companion cylinders.”) Also,
15
Frazier’s quality assurance and inspection lab, CTE, took samples.
16
As the concrete finishing was being concluded, softball-sized delaminations were observed.
17
That is, in a few areas a thin top layer of the concrete peeled or flaked away. This often meant some
18
aspect of the finishing was not done properly.
19
The specification “6000 psi” means that the concrete will have that compressive strength 28
20
days after it is poured and finished. Compressive strength is determined by subjecting a sample to
21
controlled, measured compression until it breaks. CTE “broke” some of its cast samples (with steel
22
fiber) after 28 days, and their average compressive strength was only 4570 ± 370 psi. It broke other
23
samples after 56 days, but the average compressive strength had only risen to 5150 ± 160 psi. Exh.
24
820. SBS’s testing of some of its companion cylinders produced equally disappointing results.
25
Exh. 534.1.
26
Since the compressive strength of concrete increases—up to a point—as time goes by, it was
27
hoped that eventually it would achieve the specified 6000 psi strength. But, it did not. SBS’s
28
expert, Geoffrey Hichborn, drilled out core samples from seven locations on the slab and tested
5
1
them at 101 days of age. Exh. 822. The adjusted average strength was only 5050 psi. The heavy
2
duty slab on grade was never going to get to 6000 psi.
3
On September 30, 2012, Frazier sent to SBS a “formal notice and documentation of non-
replace it would be passed on to SBS. Exh.534.1. Between then and early December 2012, while
6
waiting to see if the passage of time would solve the low compression problem, the parties met
7
several times and exchanged frequent e-mails about how to fix the problem if time did not.
8
Hichborn proposed grinding off the top 1" or so of the slab (it was 7" thick) and topping it with a
9
For the Northern District of California
compliance,” which warned that, if slab strength did not get up to 6000 psi, any cost to rework or
5
United States District Court
4
super-strong epoxy. He never prepared plans or specs or did supporting calculations, and the
10
proposal did not generate widespread interest (at least in part because it would have cost about the
11
same as the sure fix of removing and replacing the slab). Exhs. 558, 586.
12
Discussions about alternate remedies ended when the ACOE, as was its right, directed that
13
the area of the slab requiring 6000 psi concrete be removed and replaced with concrete that
14
complied with the specifications. Exhs. 559.1, 717, 781, 783, 795. SBS declined to participate in
15
any of that work, and Frazier did the job using concrete from another supplier. Frazier’s costs were
16
$312,430.90, and its Counterclaim sought that sum minus what it owed SBS for conforming
17
concrete and material. Exh. 817.
DISCUSSION
18
19
SBS wants judgment for its unpaid invoices and denies any responsibility for the failure of
20
the “6000 psi” concrete to achieve 6000 psi. Frazier acknowledges that it owes for some unpaid
21
invoices, but claims that what it owes is less than what SBS owes for the costs to remove and
22
replace the nonconforming concrete. The court begins by considering whether SBS was
23
contractually required to provide concrete which, if properly placed and finished, would achieve
24
6000 psi after 28 days.
25
SBS’s February 8, 2012 Proposal “offer[ed]” to sell Frazier 6000 psi concrete for $122.84
26
per cubic yard. At the meeting on March 30, 2012, the two negotiated the price down to an agreed
27
$121.00. Frazier’s letter of March 30 advised of its intent to buy. The negotiated prices were
28
confirmed in a clean copy of the Proposal that SBS sent on April 6, 2012. Frazier’s Purchase Order
6
1
of July 30, 2012 formally accepted the offer, and SBS subsequently performed by making deliveries
2
of what was supposed to be 6000 psi concrete.
3
In its Complaint, filed February 4, 2013, SBS alleged the “contract” between it and Frazier
Frazier had filled out and signed on April 4, 2012. However, by the time of the July 2014 Pretrial
6
Conference in this case, SBS had decided that the “contract” was actually formed when the two
7
parties initialed and signed the SBS Proposal after the negotiation over prices at the March 30, 2012
8
meeting. The court denied SBS’s request to formally amend its complaint but told its counsel he
9
For the Northern District of California
consisted of Frazier’s Purchase Order as well as a separate SBS form Credit Application, which
5
United States District Court
4
could offer whatever proof he wanted to try to show the “contract” was really something other than
10
what had been originally pleaded. And, it is plain why he wanted to try, since the boilerplate
11
language in the Proposal says: “Quality Assurance program by others.” Here was language that, if it
12
was part of the “contract,” could possibly be the foundation for an argument that SBS had no
13
obligation to design a mix that would produce 6000 psi concrete.
14
SBS officers who were at the March 30, 2012 meeting with Frazier’s people testified that
15
“Quality Assurance program by others” was fully discussed. Reportedly, they told Benford that
16
language was there because SBS had no experience with 6000 psi concrete and would require
17
someone else, at Frazier’s expense, to qualify that mix. Once that was done, SBS would be happy
18
to use the design to batch and deliver the concrete to the worksite.
19
In direct contradiction, Frazier’s Mike Prascsak and Benford both testified that all they
20
discussed on March 30 was prices, and the initials and signatures were affixed to confirm the
21
penciled-in prices that were agreed upon. No discussion took place about the quality assurance
22
language. No one told them that SBS had no experience with 6000 psi concrete. (Indeed, Teddy
23
had months before sent Benford a design for a 6000 psi mix and historical data supporting it!) And,
24
Frazier was not asked to pay for batch testing, and would not have done so if asked. Designing and
25
qualifying the mix is the supplier’s job, not the buyer’s. The court found Prascsak’s and Benford’s
26
testimony credible. It rejects the testimony of the SBS witnesses.
27
28
Furthermore, Benford and at least one of Frazier’s experts testified that Quality Assurance
has nothing to do with concrete mix design. It is something that the project owner does or delegates
7
1
to someone else to do as work is done at the job site: sampling or testing at the point of placement.
2
(The company referred to as CTE was doing quality assurance when it took samples of the wet
3
concrete as it arrived on SBS trucks for the TEMF pour the morning of August 24, 2012.) The court
4
found this testimony credible as well. 4
One reason the court rejects SBS’s version of discussions at the March 30 meeting is that
5
for mix design. The e-mails between Teddy and Benford over the next four and a half months make
8
that clear. Teddy is the mix designer. He is not telling Benford that he is waiting on someone else’s
9
For the Northern District of California
nothing SBS said or did afterward was consistent with having washed its hands of any responsibility
7
United States District Court
6
design. There is no one else. Teddy is doing the designing and making mix refinements to address
10
some tweaking by the ACOE in the contract specifications.
Even more telling is the reaction of SBS when the problem with compressive strength arose
11
12
in September after some of the 28 day samples were broken. Recall Frazier’s September 30, 2012
13
letter advising SBS that the purported 6000 psi concrete it had supplied was not in compliance with
14
the project specifications and warning, if the strength did not go up in 56 days, that SBS would be
15
responsible for any costs to remedy. Exh. 534. Ted e-mailed his reply on October 5, 2012. He
16
said: “[w]e too are committed to giving our customers the materials and service we promise.” He
17
went on to question whether the compression break tests by CTE were done correctly. He wondered
18
whether steel fibers in the mix may have made a difference. He noted that fly ash could slow down
19
curing and suggested waiting for 56 days or longer and test again. Finally, he asked for payment on
20
current invoices except for the 6000 psi “. . . which is currently in question.” Exh. 536. In a later
21
letter to Benford, Ted stated that SBS may offer to put up a warranty bond in favor of KISAQ and
22
the ACOE to dissuade either from precipitously requiring the removal of the slab. Exh. 69.2.
23
24
25
26
27
28
4
At the same time as the TEMF project, another ACOE project was underway at Fort Hunter
Liggett: the “ECS Warehouse.” Neither KISAQ nor Frazier was involved. But, SBS was. It had
the subcontract to supply ready-mix concrete. The ECS Warehouse project, unlike TEMF, had
concrete specifications that required a complex series of batch testings to qualify the mixes. Exh.
600. For that job, SBS’s Proposal had the usual boiler plate about “Quality Assurance program by
others.” It also said: “SBS is not responsible for mix development.” Exh. 620.3. The absence of
the not-responsible-for-mix-development language in its Proposal for the TEMF job, Exh. 152, is
support for the court’s finding that “Quality Assurance program by others” does not apply to mix
design.
8
1
Nowhere did Ted contend that SBS had no responsibility for mix design of the 6000 psi concrete.
2
There is no hint of a belief that low compression was someone else’s fault and problem.
3
In an October 12, 2012 e-mail from Russell Frazier to Ted, Frazier joined Ted in hoping that
4
the slab’s strength would increase over time to the desired level, but with the prospect of liquidated
5
damages being assessed by KISAQ for delay, asked for a statement of SBS’s intentions if something
6
needed to be done to fix the problem. Exh. 540.2. Ted replied on October 29: “[W]e stand behind
7
our product . . . . Please be assured of our continuing diligence to find a fix which will be more
8
expedient than R and R [removal and replacement] of the slab.” Exh. 540.1.
For the Northern District of California
United States District Court
9
KISAQ, Frazier, and SBS had a meeting on October 16, 2012 at the jobsite to discuss how to
10
deal with the low compression strength results on the heavy duty slab. Exh. 671. SBS indicated at
11
the meeting it had no knowledge that anything Frazier did in the placement and finishing of the
12
concrete caused the low results. Exh. 587. KISAQ told Frazier to come up with a plan of action in
13
case the strength did not increase to an acceptable level. Exh. 671.3. (By industry standards, core
14
samples that reach an average of 85% of the designed strength, so long as no sample is less than
15
75%, would satisfy the strength requirement.)
16
As the court observed before, SBS’s efforts to find a remedy other than removal of the slab
17
were unsuccessful, and Frazier did the work using a different supplier. SBS sued, Frazier
18
countersued, and sometime thereafter SBS changed its tune. The problem with low compressive
19
strength was not the fault of the mix design; it was because Frazier did not place and finish it
20
properly. The court heard much testimony from Ted and Hichborn about how Frazier’s placement
21
of the concrete was bad; how Frazier failed to adequately consolidate it; why it was wrong to add
22
water to the mix at the site; the slump was off; precautions were not taken to account for the heat (it
23
had been a hot day); the elapsed time from batching at the plant to placement at the site was too long
24
for some of the truckloads; and so on. Ted said he observed all these problems when he was present
25
for a few hours during the long pour. The court finds this testimony to not be credible, and, if there
26
were crumbs of truth to these assertions, they were not a contributing cause of the low compression
27
strength. There was persuasive testimony from more than one well qualified witness that all of the
28
9
1
claimed failures of Frazier to properly place and finish, even if true, would not have affected the
2
slab’s compressive strength. 5
So, what was the cause of the low compression? Let’s begin with the fact the mix design for
3
4
the 6000 psi concrete was not properly qualified.
Even Hichborn, SBS’s fiercely partisan expert witness, agreed that a ready-mix supplier that
5
Teddy gave Benford a history to go along with his 6000 psi design. Benford was entitled to rely on
8
what he was told: here was a proven mix. However, it was later discovered that this was, in fact, not
9
For the Northern District of California
gives a mix history to a customer is representing that the mix had worked. And, as noted above,
7
United States District Court
6
historical data gathered in accordance with the protocol in ACI 301. In fact, it was not historical at
10
all. It was a test batch done by Teddy of a 6000 psi mix he had designed in 2011 for a project at a
11
Target store location. SBS did not get the Target job, so it never, ever had actual field experience
12
with 6000 psi concrete. (It is not clear to the court whether Teddy prepared a test batch of this mix
13
in anticipation of SBS getting the Target job or because they were out to get the TEMF project.)
14
However, this was not trial batching following the complicated trial batching protocol called for by
15
ACI 301. It was something much more informal and incomplete. Indeed, this may be why Teddy
16
doctored and packaged the data to look like it was historical rather than from a trial batching.
17
Compare Exhs. 59.6-7, 69.1, with Exhs. 11.5, 55.6, 29.92, 25.39, 30.13. Benford thought he was
18
getting properly qualified concrete. Instead, he was getting a seat-of-the-pants mix that had never
19
been validated. 6
We will never know if that final mix design (absent any last minute change) would have
20
21
produced actual 6000 psi concrete. The third and final submission of mix designs for formal
22
approval was supposed to do nothing more than increase fly ash from 10% to 15%. As the designs
23
went up the review chain, reviewers were looking for 15% fly ash. It was there, and they added
24
their approval. What no one noticed was that Teddy had made an additional change. He had added
25
26
27
28
5
Indeed, samples taken of the wet mix in the trucks before placement and finishing did not come
close to the required compressive strength.
6
Hichborn himself acknowledged that Teddy’s mix design was no good. It had not been qualified
by either genuine historical data or by ACI 301 batch testing. It should not have been used. He said
the unqualified mix design was the “central reason” the heavy duty slab did not reach 6000 psi.
10
1
entrained air. Entrained air is a liquid product that, when added to a batch mix, creates microscopic
2
air bubbles in the mix. This additive (an “admixture” in concrete parlance) is often used in ready-
3
mix concrete that will be exposed to the weather. But the TEMF slab was indoors. And, everyone
4
in the concrete business knew that entrained air reduces compressive strength. Plus, the contract
5
specifications did not call for entrained air. The admixture is listed in Teddy’s final mix recipes, but
6
no one noticed it because no one was looking for anything other than increased fly ash.
7
Teddy testified that Benford called him and told him someone higher up the chain wanted
For the Northern District of California
“air” added. (That meant entrained air as distinguished from the entrapped air that occurs when any
9
United States District Court
8
batch of concrete is mixed. Entrapped air is mostly eliminated when concrete is vibrated during
10
consolidation.) Teddy was opposed to adding air. Reportedly, he told his dad, Ted, who agreed it
11
was a “huge problem.” According to Teddy, Benford was also opposed, but orders were orders. So,
12
Teddy added air.
13
The court rejects Teddy’s testimony about being directed to add entrained air. First, it makes
14
no sense for anyone to want entrained air in mixes not exposed to the weather. Certainly not at the
15
final approval stage. Certainly not without doing batch testing. It was not in the specifications.
16
Benford strenuously denied that anyone told him to add air (indeed, there is no evidence
17
anyone did so) and likewise denied that he told Teddy to add air. The court believes Benford. In
18
part, the court believes Benford because when, earlier, Teddy had been told to make a design change
19
in the mix to add more fly ash, he asked for and received an e-mail from the ACOE confirming the
20
change. Exhs. 60, 61. The fly ash was a minor change to which Teddy had no an objection. Surely,
21
if Teddy had been told to add something he objected to, he would have insisted on seeing it in
22
writing. At the very least, he would have documented his objection. He did neither. Teddy added
23
entrained air on his own.
24
So, the next question is: if Benford did not tell Teddy to add air, why did he do it? The court
25
cannot say for sure, but Teddy may have been confused about which mix design he was dealing
26
with. The concrete specifications for the ECS Warehouse project did require entrained air, and SBS
27
was filling that order. How likely is it that he mixed up the mixes on two separate jobs? Normally
28
one would not expect that to happen. Here, though, Hichborn, while at the October 16, 2012
11
1
meeting about low compressive strength, distributed to everyone a memorandum he had prepared
2
which stated that the TEMF specifications called for entrained air in the concrete. The startled
3
Frazier participants at the meeting pointed out that Hichborn had mixed up the Warehouse
4
specifications with the TEMF’s! Teddy denied he got confused over which specifications were for
5
what, but, if a high-powered expert like Hichborn could get confused going over SBS’s mix design
6
paperwork, so probably could Teddy.
What we do know for sure is that SBS’s mix (with air entrainment) failed to achieve 6000
7
For the Northern District of California
psi strength. David Rothstein, a PhD geologist and concrete petrographer, conducted a petrographic
9
United States District Court
8
examination of two core samples from the TEMF heavy duty slab. He found excessive air in the
10
samples, more than the mix design called for. At most, the mix design called for 4% air. Rothstein
11
found 6 to 7.4%. That excess air would result in a 10 to 15% loss in compressive strength. In his
12
opinion, that is what happened here. Exhs. 553, 747, 760. The court understood Rothestein to mean
13
that the 6000 psi design may or may not have achieved the desired strength without entrained air.
14
But, with entrained air, it definitely flunked. The court finds this testimony credible and accepts it. 7
In summary, SBS failed to provide conforming 6000 psi concrete as it contracted to do. Its
15
16
problem was it used a mix design that it had not properly qualified, a fact that it concealed.
17
Furthermore, it added an unauthorized admixture to the design that did not belong and which
18
guaranteed that the already very questionable mix design would fail to reach the required
19
compressive strength. SBS was not the third party beneficiary of any contractual obligation that
20
other TEMF project participants had, such as Frazier to KISAQ, or vice versa. SBS’s failures are
21
not excused by any omission of Frazier or other project participants to ferret out and prevent SBS
22
from going off the rails.
23
24
7
25
26
27
28
The entrained air is also why those small, circular delaminations occurred at places on the surface
of the slab as it was being finished. The surface was being “hard troweled” by Frazier people who
did not realize the mix contained entrained air. Hard troweling can cause delaminations if the mix
has entrained air. In any event, the delaminations did not affect compressive strength.
Delaminations also occurred on the slab area designated to receive 4000 psi concrete, but where
Frazier for its convenience had ordered and placed SBS’s 6000 psi mix but without steel fibers.
Those delaminations were repaired, and the ACOE did not require removal and replacement of that
slab area.
12
FINDINGS OF FACT
1
2
3
4
5
6
7
8
For the Northern District of California
United States District Court
9
10
11
12
13
14
15
16
1. SBS is a California corporation operating as a ready-mix concrete manufacturer based in
Hollister, California.
2. Frazier is a California corporation operating as a licensed concrete and masonry
subcontractor in California.
3. KISAQ is a joint venture composed of RQ Construction and KISAQ, LLC. It is
organized under the laws of the State of California and operates as a general contractor.
4. Federal is an Indiana corporation and Western a South Dakota corporation. Both are
qualified to operate as sureties in California.
5. In September 2009, KISAQ entered into a contract with the ACOE to design and build
the TEMF at Fort Hunter Liggett in Jolen, California.
6. As required by the Miller Act, KISAQ obtained from Federal and Western payment and
performance bonds in favor of the United States.
7. KISAQ entered into a written subcontract with Frazier, who was to supply and install the
concrete necessary for the TEMF project.
8. Beginning in the fall of 2011, SBS entered talks with Frazier about furnishing to Frazier
17
the ready-mix concrete needed for the TEMF project. Frazier gave SBS the project’s concrete
18
specifications.
19
9. SBS submitted to Frazier several Proposals as well as concrete mix designs for the
20
different classes of concrete needed for the project. Further, it gave Frazier what it represented were
21
historical data for each mix, including the extra strength 6000 psi concrete. In fact, the data on the
22
6000 psi mix was not historical, and that mix design had never been used on a job before or been
23
properly qualified by careful batch testing. SBS had never done a 6000 psi job before.
24
10. When a ready-mix supplier gives historical data to a potential buyer, it amounts to a
25
representation that the supplier has had previous jobs using the mix in question and that the mix
26
performed as intended.
27
28
13
11. Representatives of Frazier and SBA met on March 30, 2012 and negotiated an
1
2
agreement on the prices per cubic yard that Frazier would pay for the various categories of concrete
3
and other material needed for the project.
12. SBS’s Proposals each contained language: “Quality Assurance Program by Others.”
4
5
SBS now claims that this language meant that someone else would have to design the mixes for the
6
different classes of concrete. The court finds that this language has nothing to do with mix design,
7
and that mix design was SBS’s responsibility.
13. Also on March 30, 2012, Frazier issued a letter of intent to enter into a purchase order
8
For the Northern District of California
United States District Court
9
10
11
with SBS for the project. Its Purchase Order accepting SBS’s offer to sell was sent on July 30,
2012.
14. A portion of the slab floor in the TEMF building was to be extra strong 6000 psi
12
concrete because that area was where the military was going to repair and maintain very heavy
13
equipment, including tanks.
14
15
16
15. Per the project specifications, the 6000 psi concrete was to achieve that degree of
strength after 28 days from the date of placement.
16. SBS was aware of the requirement for 6000 psi concrete, had represented to Frazier it
17
had prior history for this kind of concrete, and knew Frazier was looking to it to design and,
18
ultimately, to batch and supply a mix that would produce it.
19
17. SBS began batching its 6000 psi mix with steel fibers on August 24, 2012. Over the
20
course of hours, SBA delivered 28 truckloads to the site. Frazier’s people placed and finished it.
21
22
23
24
18. As the concrete was being poured from the trucks, SBS took representative samples of
the wet concrete for later testing. KISAQ’s testing laboratory, CTE, also took samples.
19. CTE tested some of its samples after 28 days and determined that compressive strength
was substantially lower than the required 6000 psi.
25
20. SBS tested some of its samples after 28 days, and they too were not close to 6000 psi.
26
21. On September 30, 2012, Frazier notified SBS that it had supplied nonconforming ready-
27
mix concrete and that SBS would be responsible for any costs to remedy.
28
14
1
22. At SBS’s suggestion, Frazier agreed to give the concrete more time and test again at 56
2
days. But, the samples tested at 56 days were only a little better than before, nowhere near the 6000
3
psi they needed.
4
23. SBS hired a concrete expert, Geoffrey Hichborn, who drilled out core samples from the
5
slab and tested them for compressive strength 101 days after placement. Under an accepted industry
6
protocol, if the core samples had averaged at least 85% of the designed strength, with no sample less
7
than 75%, the slab would be acceptable. Hichborn’s core tests achieved an average compressive
8
strength of only 4,210 psi, well less than what was needed.
For the Northern District of California
United States District Court
9
24. CTE also extracted core samples from the slab, and Frazier sent them to David
10
Rothestein, a qualified concrete petrographer, for examination. Rothstein found air by volume of
11
between 6% and 7.4%, significantly higher than the 4% mix design. That increased air caused a 10
12
to 15% loss of compressive strength. Although there was credible evidence of other missteps by
13
SBS with the mix design, with the quality of some of the mix materials, and with the amounts of
14
water added to certain batches at the batch plant, the primary reason for the heavy duty slab not
15
achieving 6000 psi was the excess air.
16
25. This excess air was caused because SBS added entrained air. “Entrained air” is a liquid
17
product that can be introduced to a mix to create microscopic air bubbles in the concrete. The
18
project specifications did not call for entrained air. SBS now says that Frazier orally told them to do
19
it. Frazier denies it, and no contemporaneous record supports SBS’s assertion. No one told SBS to
20
add air. SBS did it on its own volition.
21
26. SBS initially took responsibility for low compressive strength in the heavy duty slab, but
22
changed its story after it became obvious that the passage of time would never bring it up to
23
strength. Then, it placed all the blame on Frazier’s placement and finishing of the concrete. That
24
was coupled with the argument that it had no responsibility for mix design anyway, which should
25
have been done by others.
26
27. Yes, SBS was responsible for mix design, and failed to deliver conforming 6000 psi
27
concrete. No, Frazier’s placement and finishing of the concrete, even to the extent it may have had
28
some flaws, did not contribute to any loss of compressive strength.
15
1
2
3
28. It is not disputed by anyone that the 6000 psi concrete manufactured and delivered by
SBS did not achieve the required 28-day compressive strength by 28, 56, or 101 days.
29. At the direction of the ACOE, KISAQ had Frazier remove and replace the heavy duty
4
area of the slab. SBS did not challenge any item on Frazier’s itemized list of the costs for this work:
5
$312,430.90. This amount was correctly backcharged to SBS.
6
30. SBS has unpaid invoices to Frazier of $303,357.04. From that is to be deducted the
plus sales tax on the taxable items of $2,741.14, total $45,961.30. The net, $257,395.74 is owed by
9
For the Northern District of California
invoices for the non-conforming 6000 psi concrete with steel fibers in the amount of $43,220.16,
8
United States District Court
7
Frazier, and will be offset against Frazier’s recovery from SBS. Subtracting the offset, Frazier’s
10
11
recovery is $55,035.16.
31. SBS tried to find cover for its failures by pointing to alleged missteps of others (i.e.
12
Frazier, KISAQ, the consulting engineer, etc.) in not fulfilling the letter of their contractual
13
obligations. For example, KISAQ did not convene a “preinstallation” conference with all concerned
14
before the pour. Plus, there was the error of not sending the “final” mix design to the ACOE for its
15
formal approval. And, others. But, none of these failures excuses SBS. And, it is nothing but
16
speculation to argue that the outcome would have been any different if others had followed project
17
procedures to the letter.
CONCLUSIONS OF LAW
18
19
1. The sale of concrete is a sale of “goods,” and the California Commercial Code controls.
20
2. SBS contracted to provide 6000 psi concrete to Frazier for the TEMF project, and it failed
21
to do so. This was a material breach of contract and justified Frazier withholding monies otherwise
22
owed to SBS.
23
3. Frazier was justified in removing and replacing the nonconforming concrete. In doing so
24
it incurred reasonable costs in the amount of $312,430.90. Those costs are damages recoverable
25
from SBS.
26
27
4. SBS shall take nothing on its claims for breach of contract and for recovery on the Miller
Act payment bonds. It is entitled payment of its unpaid invoices for conforming concrete and
28
16
1
materials supplied to Frazier. Of the $303,357.07 in unpaid invoices, $45,961.30 were charges for
2
the nonconforming 6000 psi concrete. Therefore, SBS’s net unpaid charges are $257,395.77.
3
5. Deducting $257,395.77 from $312,430.90 brings Frazier’s recovery to $55,035.13.
4
6. Frazier shall have judgment against SBS in the amount of $55,035.13, plus costs and
5
6
7
8
For the Northern District of California
United States District Court
9
10
11
prejudgment interest at the applicable rate.
7. Since SBS recovered nothing against them, KISAQ, Federal, and Western shall also have
judgment in their favor.
8. Any request for an award of attorney fees shall be addressed to the court by noticed
motion.
Dated: January 28, 2015
HOWARD R. LLOYD
UNITED STATES MAGISTRATE JUDGE
12
13
14
Frazier shall prepare a proposed judgment.
15
16
17
18
19
20
21
22
23
24
25
26
27
28
17
1
C13-00469 HRL Notice will be electronically mailed to:
2
Albert Ibrahim
3
Brian S. Case
4
Diana Marie Dron
5
Counsel are responsible for distributing copies of this document to co-counsel who have not
registered for e-filing under the court’s CM/ECF program.
pcornejo@ciclaw.com
bcase@ciclaw.com, aibrahim@ciclaw.com
dron@mmlawyers.com
6
7
8
For the Northern District of California
United States District Court
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
18
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?