Cruz v. United States of America et al
Filing
46
ORDER regarding 45 Joint Motion for Determination of Discovery Dispute. Plaintiff's motion to compel further response to Request for Production No. 15 is denied. Signed by Magistrate Judge David H. Bartick on 2/24/16. (kas)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
SOUTHERN DISTRICT OF CALIFORNIA
10
11
Case No.: 14cv2956-LAB (DHB)
SIRA CRUZ,
Plaintiff,
12
13
14
ORDER REGARDING JOINT
MOTION FOR DETERMINATION
OF DISCOVERY DISPUTE
v.
UNITED STATES OF AMERICA,
NATIONAL STEEL AND
SHIPBUILDING COMPANY, and
PETERSON INDUSTRIAL
SCAFFOLDING, INC.,
15
16
17
[ECF No. 45]
Defendants.
18
19
20
On January 26, 2016, Plaintiff and Defendant National Steel and Shipbuilding
21
Company (“NASSCO”) filed a Joint Motion for Determination of Discovery Dispute.1
22
23
1
24
25
26
27
28
The Court notes that Plaintiff’s counsel refused to provide Plaintiff’s portion of the Joint Motion to
NASSCO’s counsel so that NASSCO could meaningfully prepare an opposition. (ECF No. 45-3 at ¶2.)
Plaintiff’s counsel’s conduct in this Court’s view is at best, inappropriate, and at worst, verges on violating
the Local Rules of Professionalism, which provide counsel must not “serve motions and pleadings on
opposing parties or counsel at a time or in a manner that will unfairly limit their opportunity to respond.”
CivLR 83.4(a)(2)(e). This Court’s Chambers Rules should not have needed to specify that NASSCO be
given an opportunity to view Plaintiff’s portion of the motion in advance of preparing its opposition, as
common sense and professional courtesy should have made this obvious. Nevertheless, the Court has
amended its Chambers Rules to make clear that “the party initiating a joint motion to resolve a discovery
dispute must provide opposing counsel with a complete draft of the joint motion and any exhibits or
1
14cv2956-LAB (DHB)
1
(ECF No. 45.) Having considered the parties’ submissions and supporting exhibits, the
2
Court hereby DENIES Plaintiff’s motion to compel, as outlined below.
3
I. BACKGROUND
4
Plaintiff commenced this action on December 16, 2014, by filing a Complaint
5
alleging that on or about February 20, 2013, she was injured while working as a tank-tester
6
aboard the Navy vessel, USS MAKIN ISLAND, during ship repair operations at the dock
7
in San Diego. (ECF No. 1.) Plaintiff alleges her injuries were, at least partially, due to
8
NASSCO’s negligence in failing to cover an exposed hole in the deck at the bottom of a
9
vertical ladder leading into one of the ship’s tanks. Following the accident, NASSCO
10
employees conducted an investigation and prepared a number of reports. (See ECF No.
11
45-3 at ¶ 4.)
12
On June 23, 2015, Plaintiff propounded her first set of Request for Production of
13
Documents on NASSCO. (ECF No. 45-3 at ¶ 5.) In Request for Production No. 5, Plaintiff
14
demanded “All documents pertaining to all self-critical analyses of subject accident.”
15
(ECF No. 45-4 at 65.)
16
NASSCO responded to the document requests on July 27, 2015. (ECF No. 45-4 at
17
60-71.) NASSCO objected to Request No. 5, stating the requested documents were
18
protected by the attorney-client privilege and work product doctrine. (Id. at 65.)
19
Plaintiff waited approximately two and a half months before initiating the meet and
20
confer process regarding the document requests. On October 13, 2015, Plaintiff sent
21
NASSCO a letter challenging NASSCO’s assertion of the attorney-client and work product
22
privilege. (ECF No. 45-5 at 74-75.)
23
Thereafter, on November 4, 2015, NASSCO produced certain documents as well as
24
a privilege log. (ECF No. 45-3 at ¶ 8; 45-4 at 77-80.) The privilege log indicated that
25
26
27
28
supporting declarations at least five (5) business days prior to the anticipated filing date.” Judge Bartick’s
Civil Chambers Rules IV(C)(3). Plaintiff’s counsel is directed to review the revised Chambers Rules,
which are posted on the Court’s website.
2
14cv2956-LAB (DHB)
1
NASSCO had withheld the following two documents on the basis of privilege: (1)“Email
2
Correspondence with attached Draft Critique Report;” and (2) “Final Critique Report.”
3
(ECF No. 45-4 at 80.)
4
On November 10, 2015, Plaintiff propounded a second set of Request for Production
5
of Documents. (ECF No. 45-3 at ¶ 9.) In Request for Production No. 15, Plaintiff requested
6
“All post-accident Critique Reports prepared by you concerning plaintiff Sira Cruz’s
7
February 20, 2013 accident aboard the USS MAKIN ISLAND which is the subject of this
8
action.” (ECF No. 45-5 at 86.)
9
NASSCO responded to the second set of document requests on December 18, 2015
10
(served on December 22, 2015). (ECF No. 45-3 at ¶ 9.) NASSCO objected to Request
11
No. 15 on grounds of attorney-client privilege and work product protection. (ECF No. 45-
12
4 at 86.) NASSCO further objected that Request No. 15 was “duplicative of prior requests
13
for production of documents, including but not limited to Request for Production No. 5.”
14
(Id.)
15
Following further unsuccessful meet and confer efforts, the parties filed the instant
16
joint motion. (ECF No. 45.) Plaintiff moves to compel NASSCO to produce further
17
documents in response to Request No. 15, and specifically asks the Court to compel
18
NASSCO to produce the “Email Correspondence with attached Draft Critique Report” and
19
“Final Critique Report.” 2 NASSCO argues the motion is untimely, and that the requested
20
documents are protected from disclosure by the attorney-client privilege and work product
21
doctrine.
22
II. ANALYSIS
23
Pursuant to this Court’s Chambers Rules, all discovery motions must be filed “within
24
forty-five (45) days of the date upon which the event giving rise to the dispute occurred.”
25
Judge Bartick’s Civil Chambers Rules IV. For written discovery, the event giving rise to
26
27
2
28
NASSCO indicates that the first document listed on the privilege log was erroneously included, as it
does not refer to Plaintiff’s accident, or any accident. Therefore, NASSCO states it will provide
Plaintiff with an updated privilege log removing the document. See ECF No. 45-3 at ¶ 11.
3
14cv2956-LAB (DHB)
1
the dispute is the date of the service of the initial response. Id. Plaintiff argues the event
2
that triggered the time for filing the joint discovery motion was NASSCO’s response to
3
Request No. 15. The Court disagrees.
4
Request for Production No. 15 is substantially similar to Request for Production No.
5
5. In Request No. 5, Plaintiff broadly asked for all documents regarding “self-critical
6
analyses.” (ECF No. 45-4 at 65.) Then, months after the deadline to move to compel had
7
expired with regard to Request No. 5, Plaintiff propounded Request No. 15, which
8
requested a specific subset of the documents sought by Request No. 5. Indeed, in Request
9
No. 15, Plaintiff seeks the exact documents that NASSCO indicated were responsive to
10
Request No. 5, but withheld due to privilege. (Compare ECF No. 45-4 at 80 (Privilege
11
Log indicating “Draft Critique Report” and “Final Critique Report” were being withheld)
12
with ECF No. 45-5 at 86 (Request No. 15 requesting “Critique Reports”).)
13
Under Federal Rule of Civil Procedure 26(b)(2)(C), the Court must limit discovery
14
that is “unreasonably cumulative or duplicative.” Fed.R.Civ.P. 26(b)(2)(C).
15
Courts in this district routinely reject attempts to end-run around discovery deadlines. See
16
Bird v. PSC Holdings I, LLC, 2013 WL 1120659 (S.D. Cal. Mar. 18, 2013) (stating “any
17
discovery demands which are substantially similar to previous demands will not re-start
18
the clock for filing a discovery motion, and may be grounds for a protective order.”);
19
ViaSat, Inc. v. Space Systems/Loral Inc., 2013 WL 3467413 (S.D. Cal. July 10, 2013) (“The
20
Court is not inclined to indicate to these parties, or any parties, that they will be allowed to
21
do an end run around discovery deadlines that were missed through a party’s own lack of
22
due diligence. The consequences for failing to meet Court deadlines are undermined if the
23
neglectful party is allowed to seek the same information through a different discovery
24
vehicle.”).
Moreover,
25
Here, the Court finds the event giving rise to the dispute was the date NASSCO
26
responded to Request No. 5, which was July 27, 2015. (ECF No. 45-4 at 60-71.) Therefore,
27
the deadline for this discovery motion to be filed was September 9, 2015. Accordingly,
28
4
14cv2956-LAB (DHB)
1
Plaintiff’s motion to compel is untimely.3 The Court rejects Plaintiff’s attempt to revive
2
the filing deadline by propounding Request No. 15.
3
III. CONCLUSION
4
5
For the foregoing reasons, IT IS HEREBY ORDERED that Plaintiff’s motion to
compel further response to Request for Production No. 15 is DENIED.
6
IT IS SO ORDERED.
7
Dated: February 24, 2016
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
3
27
28
Even assuming the 45-day period started to run on November 4, 2015, when NASSCO produced the
privilege log that specifically identified the Final Critique Report, Plaintiff’s motion is still untimely by
more than a month.